UNIVERSITY OF FLORIDATHE J.W. REITZ UNION
Site Survey Final ReportRobert G. Chronic, P.E., LEED
®AP
E M C ENGINEERS, INC.
OVERALL SCOPE
EMC performed a survey of the JWRU facility to ascertain the physical and general operating condition of the following systems :
Mechanical Systems Plumbing systems Electrical systems Building envelope and roofing systems Identified structural components
SURVEY INTENT
Document the various systems’ current condition Provide cost estimates for major repairs Assign priority level to the findings Provide an executive summary report Provide a searchable database
COST ESTIMATES
The cost estimates contained in this presentation and in the executive summary report are based upon the following factors:
Cost estimates are construction costs only No general condition fees, A/E fees, or other fees
are included Costs are based on 2009 costs with no yearly
escalation
CRITICAL ISSUES TO BE ADDRESSED
• Observed asbestos in heating hot water piping in the hotel fan coil units ~ $30,000
• Additional asbestos abatement of the plumbing systems ~ $53,688
• Non-functioning duct smoke detectors ~ $150,000
• Non-functioning refrigerant detection systems ~ $20,000
• Overheating of the main building medium voltage distribution transformer and replacement switchgear ~ $375,000
• Potential additional site work of ~ $50,000 to $100,000
• Cost of Critical Issues: ~ $708,688 (est. total project cost = $1,771,720)
UF E M C
ASBESTOSSIXTH FLOOR ABOVE ROOM 605 ASBESTOS
Asbestos abatement of the plumbing systems Additional to the asbestos findings at the hotel
Estimated cost ~ $53,688 2009
REFRIGERANT DETECTION SYSTEMS
Non-functioning refrigerant detection systems
Estimated Cost ~ $20,000 2009
NON-FUNCTIONING REFRIGERANT MONITORING SYSTEMS
THESE MONITORING SYSTEMS MUST BE ACTIVE IN ORDER TO PROVIDE A SAFE WORKING ENVIRONMENT
OVERHEATING OF THE MAIN BUILDING MEDIUM VOLTAGE DISTRIBUTION TRANSFORMER
ESTIMATED COST ~ $375,000
Surface coil insulation temperatures exceeding recommended limits
Potential additional site work ~ $50,000 to $100,000
MECHANICAL DIVISION
EMC completed a survey of:
chilled water condenser water heating hot water steam and condensate systems air distribution and air handling systems
ADDITIONAL MAJOR ISSUES TO BE ADDRESSED ESTIMATED COST TIMEFRAME
• Lack of a fully functioning automation system generating energy waste ~ $1,050,000 to $1,750,000 2010
PAYBACK of 6.3 to 10.5 years and ENERGY SAVINGS of $170,000 per year
• Functionality of the chiller plant ~ $2,000,000 2014 – 2019
• Heating hot water system ~ $300,000 2010
• Air handling systems ~ $ 825,000 2009
• Ductwork Renovations ~ $3,500.000 or $10.00 per square foot
UF E M C
CONTROL SYSTEMS
• Monitors the chiller plant, the Welcome Center air handling units (AHU-PL-1, AHU-PL-2, AHU-G-4, AHU-G-6, AHU-G-7, AHU-G-8 , AHU-G-9, and AHU-1-4), the CRC air handling unit (AHU-G-4), and the Grand Ballroom air handling units (AHU-3-11, AHU-3-12, AHU-3-13, and AHU-3-14)
• Text-based system
• Archaic and difficult to use
• Monitors AHU-4-1, AHU-4-2, AHU-4-3 and AHU-5-2 in the main building
• Automatic system
• In good working order, but is under-utilized
Johnson Controls (JCI) Automated Logic
All remaining air handling units are not being monitored
CHILLED AND CONDENSER WATER SYSTEMLOAD & CAPACITY
• 730 Tons – Original Load
• 800 Tons – Original Capacity
• Original chilled water system
consisted of two 400 ton Trane units with condenser water provided by
groundwater wells.
• 1346 Tons – Present Load
844 – Main Building
77 – CRC
224 – Welcome Center
• 1200 Tons – Present Capacity
89% diversity factor
ORIGINAL PRESENT
However, the piping configuration with two chillers in series and one in parallel does not appear to allow the total capacity to be utilized.
Current Drawings do not reflect the field installation of this system.
Estimated Cost ~ $2,000,000 2014 - 2019
HEATING HOT WATER SYSTEMS LOAD & CAPACITY
• Original heating hot water load for the main building was approx. 5,245 MBH.
• The presently installed and original heat exchanger is sized to deliver 5,500 MBH.
• The current heating load is approx. 8,112 MBH: Main building plus the
CRC,
Welcome Center, and
Grand Ballroom additions
68% diversity factor
very low system is undersized.
ORIGINAL PRESENT
Estimated Cost ~ $300,000 2010
STEAM - CONDENSATE SYSTEMS LOAD & CAPACITY
EMC has the steam load on this branch as 8,112 MBH for the heat exchanger, 1,550 MBH for both domestic water heaters, 608 MBH for AHU-B-4 and 1,115MBH for AHU-B-5.
This gives a total steam load for this branch of 11,385 MBH or approx. 11,385 lbs per hour.
The pressure reducing valve associated with this branch is indicated per the 1967 documents as 8,000 lbs per hour.
a diversity of 70%. This is a very low diversity factor and indicates the system is undersized.
The present steam pressure reducing valve configuration is a single pressure reducing valve with a manual bypass. For a building of this size, typically a 1/3 pressure reducing valve, a 2/3 pressure reducing valve and a manual bypass are installed. Thus, under part-load conditions, the 1/3 valve would handle the steam load and under full-load conditions the 2/3 valve would open to increase steam flow.
This configuration provides a finer degree of control.
UNIT COOLING COILS AND DRAIN PANS ARE IN POOR CONDITION ATTEMPTS HAVE BEEN MADE TO KEEP CLEAN UTILIZING BIO-TABLETS
THE AIR DISTRIBUTION SYSTEM IS COMPRISED OF SEVERAL
DIFFERENT METHODOLOGIES:
Supply Air PlenumsReturn Air PlenumsDucted Supply with Lined InsulationDucted Supply with External InsulationDucted Return with Lined InsulationDucted Return with no insulationDucted Exhaust
THE ORIGINAL BUILDING CONTAINS A MIXTURE OF ALL METHODOLOGIES
PLUMBING DIVISION
EMC completed a survey of:
domestic water water and vent building storm drainage systems all floors of the original main building CRC addition Welcome Center and Bookstore addition
The life expectancy of its plumbing system is approximately 20 – 40 years. Cast iron pipe life expectancy is 35 – 45 years. Copper pipe life expectancy is 20 – 40 years.
ADDITIONAL MAJOR ISSUES TO BE ADDRESSED ESTIMATED COST TIMEFRAME
• Complete demo and replacement of the waste lines and domestic water lines serving the kitchen areas ~ $199,178 2009
• Complete demo and replacement of the waste lines and domestic water lines serving the entire main building (excluding the kitchen above)~ $852,918 2010
• Plumbing renovations ~$4.50 per square foot for the main building
UF E M C
ELECTRICAL DIVISION
EMC completed a survey of:
primary distribution equipment
luminaires and lamp technologies
physical condition systems & general illumination
ADDITIONAL MAJOR ISSUES TO BE ADDRESSED ESTIMATED COST TIMEFRAME
MAIN DISTRIBUTION SWITCHBOARDS & PANELBOARDS IN THE MAIN BUILDING
overall existing switchboards ~ $525,000
all original lighting & appliance panels ~ $1,250,000
original equipment exceeded expected life span
time frame 2009 - 2010
MINIMAL TO NONE – OUTDATED LIGHTING CONTROLS
new & replacement upgrades ~ $3.00 per square foot
time frame 2009-2010
UF E M C
MAIN DISTRIBUTION SWITCHBOARDS
PANELBOARDS IN THE MAIN BUILDING
Estimated Cost ~ $1,775,000 2009 – 2010
ARCHITECTURAL DIVISION
EMC’s Consultant Firm W & A completed a survey:
Documenting the general condition of theexterior envelope construction of the various buildings
Specific focus given to the water infiltration performance of the exterior envelope building components
Allowing future remediation to be best scheduled and budgeted
ADDITIONAL MAJOR ISSUES TO BE ADDRESSED ~ ESTIMATED COST TIMEFRAME
• Active water intrusion Evaluating/Testing ~ $25,000 2010 Repairs ~ $200,000 - $250,000 Scheduled as needed
• Bat infestation ~ budgetary cost by a qualified extraction/clean-up contractor 2009
• Exterior precast handrails in poor condition Level 1 – Walkway 2009
Replacement of the level 1 walkway handrails ~ $200,000 Correction of waterproofing beneath the handrails & concrete repairs ~ $200,000 - $250,000
Levels 4 – 6 – Hotel Balconies 2009
Private balcony handrails ~ $200,000 Balcony repairs & brick removal ~ $200,000 - $250,000
• Window and door assemblies at the original Student Center in poor overall condition, including water infiltration protection and lack of energy efficiency ~ $1,500,000
• Roof replacements of the original Student Center roof areas & the Colonnade addition roof area ~ need budgetary consideration 1-5 years
• Specific repairs are recommended to be budgeted for roof areas at the CRC/Ballroom addition & Ballroom/Welcome Center to prolong life expectancy ~ $900,000
UF E M C – W&A
ACTIVE WATER INTRUSION
MAJORITY OCCURRING AT:
Bookstore/Welcome Center addition at building expansion joints
Faulty curtainwall-to-brick wall installations
Certain throughwall flashing conditions and conditions within the related garage
SHOULD BE GIVEN TOP PRIORITY
ACTIVE LEAK LOCATION WITHIN THE BOOKSTORE STORAGE AREA WHICH EXISTS
BENEATH THE RELATED ROOF EXPANSION JOINT OPENING ABOVE
PRECAST / CAST STONE HANDRAIL NOT PROVIDED WITH EXPANSION JOINT OPENINGS
AT LOCATIONS OF RELATED BUILDING EXPANSION JOINTS
WINDOW & DOOR ASSEMBLIES IN POOR CONDITION & WASTING ENERGY
• air & water infiltration
• operational use
• safety
• single pane glass
• non-thermal frames
exterior temperature
to transfer to the
interior of the facility
• non-thermal frames
• single-pane glass
• air gaps between
the operable and
fixed door panels
• unsafe condition at level 2 (two noted locations)
• little resistance to
exterior weather
WINDOW ASSEMBLIES DOOR ASSEMBLIES
Estimated Cost ~ $1,500,000 2009
ALUMINUM FRAMED WINDOW
SINGLE PANE GLASS & NON-THERMALLY IMPROVED FRAMES
resulting in exterior temperature conditions to transfer to the interior of the facility
STRUCTURAL DIVISION
EMC’s Consultant Firm BSA completed a survey of the following structural elements:
Feasibility of adding floor level(s) above the Colonnade Second Floor
Feasibility of adding floor level(s) above the Third Floor – Ballroom
Evaluation of specific areas noted by JWRU
ADDITIONAL MAJOR ISSUES TO BE ADDRESSED
UF E M C – BSA
Feasibility of adding floor level(s) above the existing Colonnade Second Floor
It appears feasible
Further investigation should be conducted ~ projected to be
$40,000
Feasibility of adding floor level(s) above the existing Third Floor Ballroom
Does not appear to be feasible
OVERALL PRIORITY / COST TIMELINE
2009 $2,004,447.452010 $368,700.002011 $240,800.002012 $156,250.002013 $0.002014 $7,264,688.662015 $13,707.422016 $63,950.002017 $127,885.452018 $0.002019 $0.002020 $1,000.002021 $0.002022 $0.002023 $101,212.732024 $1,007.50Various Costs included in other renovations as they occur
$5,444,486.50
TOTAL COST OF ALL NOTED ITEMS
Total construction cost to correct all items
~ $17,000,000
Total project cost to the Reitz Union
~ $42,500,000