status of ilc barry barish caltech / gde 17-aug-07

27
Status of ILC Status of ILC Barry Barish Caltech / GDE 17-Aug-07

Upload: sandra-rice

Post on 27-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

Status of ILCStatus of ILC

Barry BarishCaltech / GDE

17-Aug-07

Page 2: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

The GDE Plan and Schedule

2005 2006 2007 2008 2009 2010

Global Design Effort Project

Baseline configuration

Reference Design

ILC R&D Program

Engineering Design

Expression of Interest to Host

International Mgmt

LHCPhysics

Page 3: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 3

Parameters for the ILC

• Ecm adjustable from 200 – 500 GeV

• Luminosity ∫Ldt = 500 fb-1 in 4 years

• Ability to scan between 200 and 500 GeV

• Energy stability and precision below 0.1%

• Electron polarization of at least 80%

• The machine must be upgradeable to 1 TeV

Page 4: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 4

main linacbunchcompressor

dampingring

source

pre-accelerator

collimation

final focus

IP

extraction& dump

KeV

few GeV

few GeVfew GeV

250-500 GeV

Designing a Linear Collider

Superconducting RF Main Linac

Page 5: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 5

– 11km SC linacs operating at 31.5 MV/m for 500 GeV– Centralized injector

• Circular damping rings for electrons and positrons• Undulator-based positron source

– Single IR with 14 mrad crossing angle– Dual tunnel configuration for safety and availability

RDR ILC Schematic

Page 6: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 6

Reference Design and Plan

Producing Cavities

Cavity Shape

Obtaining Gradientsingle cells

Page 7: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 7

4th generation prototype ILC cryomodule

Cryomodules

TESLA cryomodule

Page 8: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 8

The Main Linac

• Costs have been estimated regionally and can be compared. – Understanding differences require detail comparisons –

industrial experience, differences in design or technical specifications, labor rates, assumptions regarding

quantity discounts, etc.

Page 9: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 9

– Three RF/cable penetrations every rf unit– Safety crossovers every 500 m– 34 kV power distribution

Main Linac Double Tunnel

Page 10: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 10

Conventional Facilities

72.5 km tunnels ~ 100-150 meters underground

13 major shafts > 9 meter diameter

443 K cu. m. underground excavation: caverns, alcoves, halls

92 surface “buildings”, 52.7 K sq. meters = 567 K sq-ft total

Page 11: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 11

Reference Design and Plan

Making Positrons

6km Damping Ring

10MW Klystrons

Beam Delivery and Interaction Point

Page 12: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 12

Technically Driven Timeline

August

BCD Construction Startup

2006 2010 2014 2018

RDR EDRBeginConst

EndConst

EngineerDesign

Page 13: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 13

Civil Construction Timeline

Page 14: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 14

CMS assembly approach:• Assembled on the surface in parallel with underground work• Allows pre-commissioning before lowering• Lowering using dedicated heavy lifting equipment• Potential for big time saving• Reduces size of required underground hall

On-surface Detector Assembly CMS approach

Page 15: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 15

Technically Driven Timeline

August

BCD

All regions require ~ 5 yrs

Construction Startup

Siting Plan being Developed

2006 2010 2014 2018

RDR EDRBeginConst

EndConst

EngineerDesign

Site Prep

Site Select

Page 16: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 16

~ 5.5 km

~ 5.5 km

Central Area fits inside the Fermilab boundary

Site Characterization of the Central Area can be done

~ Boundary of Fermilab

Preconstruction Plan: Fermilab

Page 17: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 17

Technically Driven Timeline

August

BCD

All regions ~ 5 yrs

Construction Startup

Siting Plan being Developed

2006 2010 2014 2018

RDR EDRBeginConst

EndConst

EngineerDesign

Site Prep

Site Select

R & D -- Industrialization

Page 18: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 18

Module Test – Results

DESY

Page 19: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 19

E Cloud – Results

SLAC

Page 20: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 20

Schedule in Graphical Form2009 2012 2015 2018

ConstructionSchedule

CryomoduleProduction

RF System Tests

Page 21: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 21

Technically Driven Timeline

August

BCD

All regions ~ 5 yrs

Construction Startup

Siting Plan being Developed

2006 2010 2014 2018

RDR EDRBeginConst

EndConst

EngineerDesign

Site Prep

Site Select

R & D -- Industrialization

Gradient

e-CloudCryomoduleFull Production

System Tests

& XFEL

Detector Install

Detector Construct

Page 22: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 22

Detector Concepts

Page 23: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 23

Detector Performance Goals

• ILC detector performance requirements and comparison to the LHC detectors:○ Inner vertex layer ~ 3-6 times closer to IP

○ Vertex pixel size ~ 30 times smaller

○ Vertex detector layer ~ 30 times thinner

Impact param resolution Δd = 5 [μm] + 10 [μm] / (p[GeV] sin 3/2θ)

○ Material in the tracker ~ 30 times less

○ Track momentum resolution ~ 10 times better

Momentum resolution Δp / p2 = 5 x 10-5 [GeV-1] central region

Δp / p2 = 3 x 10-5 [GeV-1] forward region

○ Granularity of EM calorimeter ~ 200 times better

Jet energy resolution ΔEjet / Ejet = 0.3 /√Ejet

Forward Hermeticity down to θ = 5-10 [mrad]

Page 24: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 24

detectorB

may be accessible during run

accessible during run Platform for electronic and

services (~10*8*8m). Shielded (~0.5m of concrete) from five sides. Moves with detector. Also provide vibration isolation.

Concept: one IR - two detectors

The concept is evolving and details being worked out

detectorA

Page 25: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 25

Technically Driven Timeline

August

BCD

All regions ~ 5 yrs

Construction Startup

Siting Plan being Developed

2006 2010 2014 2018

RDR EDRBeginConst

EndConst

EngineerDesign

Site Prep

Site Select

R & D -- Industrialization

Gradient

e-CloudCryomoduleFull Production

System Tests

& XFEL

Detector Install

Detector Construct

Pre-Operations

Page 26: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 26

Conclusions - Technical

• The ILC design is proceeding toward an engineering design by 2010. (Goal: Ready to propose construction when LHC results justify).

• R&D program is being globally coordinated to determine gradient, electron cloud, industrialization, mass production. (Resources are regional, by country and laboratory).

• Detector R&D also very important to be able to fully exploit the ILC (e.g. spatial & energy resolution) (Needs improved coordination, better regional balance).

Page 27: Status of ILC Barry Barish Caltech / GDE 17-Aug-07

17-Aug-07 LP07 Daegu, Korea Global Design Effort 27

Achieving our ILC Timeline“The other issues”

• We need to begin a campaign to prepare the way for submitting a winning proposal in about 2010.– Science Motivation is very strong, but we need LHC results for

validation (~2010)

– Must convince broader HEP and science communities on the ILC

– Must engage the global governments to take ownership and develop international governance

– Must develop a siting strategy

• The key to maintaining our timeline will be working these issues in parallel with developing an engineering design and completing the R&D