gde report from snowmass to a baseline barry barish ilcsc meeting daegu, korea 27-aug-05
TRANSCRIPT
27-Sept-05 ILCSC - Daegu, KOREA 2
GDE MembersChris Adolphsen, SLACJean-Luc Baldy, CERNPhilip Bambade, LAL, OrsayBarry Barish, CaltechWilhelm Bialowons, DESYGrahame Blair, Royal HollowayJim Brau, University of OregonKarsten Buesser, DESYElizabeth Clements, FermilabMichael Danilov, ITEPJean-Pierre Delahaye, CERN, Gerald Dugan, Cornell UniversityAtsushi Enomoto, KEKBrian Foster, Oxford UniversityWarren Funk, JLABJie Gao, IHEPTerry Garvey, LAL-IN2P3Hitoshi Hayano, KEKTom Himel, SLACBob Kephart, FermilabEun San Kim, Pohang Acc LabHyoung Suk Kim, Kyungpook Nat’l UnivShane Koscielniak, TRIUMFVic Kuchler, FermilabLutz Lilje, DESY
Tom Markiewicz, SLACDavid Miller, Univ College of LondonShekhar Mishra, FermilabYouhei Morita, KEKOlivier Napoly, CEA-SaclayHasan Padamsee, Cornell UniversityCarlo Pagani, DESYNan Phinney, SLACDieter Proch, DESYPantaleo Raimondi, INFNTor Raubenheimer, SLACFrancois Richard, LAL-IN2P3Perrine Royole-Degieux, GDE/LALKenji Saito, KEKDaniel Schulte, CERNTetsuo Shidara, KEKSasha Skrinsky, Budker InstituteFumihiko Takasaki, KEKLaurent Jean Tavian, CERNNobu Toge, KEKNick Walker, DESYAndy Wolski, LBLHitoshi Yamamoto, Tohoku UnivKaoru Yokoya, KEK
49 members
Americas 16 Europe 21 Asia 12
27-Sept-05 ILCSC - Daegu, KOREA 3
main linacbunchcompressor
dampingring
source
pre-accelerator
collimation
final focus
IP
extraction& dump
KeV
few GeV
few GeVfew GeV
250-500 GeV
Starting Point for the GDE
Superconducting RF Main Linac
The GDE Plan and Schedule 2005 2006 2007 2008 2009 2010
Global Design Effort Project
Baseline configuration
Reference Design
ILC R&D Program
Technical Design
Expression of Interest to Host
International Mgmt
LHCPhysics
CLIC
27-Sept-05 ILCSC - Daegu, KOREA 5
From Snowmass to a Baseline
August September October November December
2005Snowmass
WW/GG summaries
Response to list of 40+ decisions
All documented ‘recommendations available on ILC Website (request community feedback)
Review by BCD ECBCD EC publishes‘strawman’ BCD
PublicReview Frascati
GDE meeting
BCD Executive Committee:BarishDugan, Foster, Takasaki Raubenheimer, Yokoya, Walker
27-Sept-05 ILCSC - Daegu, KOREA 6
Baseline Configuration Document Review Process
• BCD executive committee will monitor BCD progress– Review WG/GG summary write-ups (recommendations)– Review each question on the list of 40+ decisions
• BCD EC will identify and solicit needed additional input– additional expertise from ILC / GDE community
• Strawman BCD available mid-November• Presentation of strawman BCD at Frascati GDE meeting
(Dec. 10-12)
• Final agreed BCD to be documented by end of 2005• Final BCD becomes property of ‘change control board’ in
early 2006• Begin the Reference Design to be completed by end of 2006
27-Sept-05 ILCSC - Daegu, KOREA 7
Review of Snowmass
670 Scientists attended two week
workshopat
Snowmass
27-Sept-05 ILCSC - Daegu, KOREA 8
Self Organization following Technology Decision
• 1st ILC workshop at KEK November 2005• ILCSC forms 5 technical WG + 1 communications
and outreach WG• WG1 Parameters & General Layout• WG2 Main Linac• WG3 Injectors• WG4 Beam Delivery & MDI• WG5 High gradient SCRF• WG6 Communications
27-Sept-05 ILCSC - Daegu, KOREA 9
Evolution by Snowmass
• WG1 Parms & layout• WG2 Linac• WG3 Injectors• WG4 Beam Delivery• WG5 High Grad. SCRF• WG6 Communications
• WG1 LET beam dynamics• WG2 Main Linac• WG3a Sources• WG3b Damping Rings• WG4 Beam Delivery• WG5 SCRF Cavity Package• WG6 Communications
Birth of the GDEand Preparation for Snowmass
27-Sept-05 ILCSC - Daegu, KOREA 10
Enter the GDE - Snowmass
• WG1 Parms & layout• WG2 Linac• WG3 Injectors• WG4 Beam Delivery• WG5 High Grad. SCRF• WG6 Communications
• WG1 LET beam dynamics• WG2 Main Linac• WG3a Sources• WG3b Damping Rings• WG4 Beam Delivery• WG5 SCRF Cavity Package• WG6 Communications• GG1 Parameters & Layout• GG2 Instrumentation• GG3 Operations & Reliability• GG4 Cost Engineering• GG5 Conventional Facilities• GG6 Physics Options
Birth of the GDEand Preparation for Snowmass
Introduction of Global Groupstransition workshop → project
27-Sept-05 ILCSC - Daegu, KOREA 11
GDE Organization for Snowmass
•W
G1
LE
T b
dy
n.
•W
G2
Ma
in L
ina
c
•W
G3
a S
ou
rces
•W
G3
b D
R
•W
G4
BD
S
•W
G5
Ca
vity• GG1 Parameters• GG2 Instrumentation• GG3 Operations & Reliability• GG4 Cost & Engineering• GG5 Conventional Facilities• GG6 Physics Options
Technical sub-systemWorking Groups
Global Group
Provide input
27-Sept-05 ILCSC - Daegu, KOREA 12
Goals of the Snowmass Workshop
• Recommendations for the Baseline Configuration
• Identify - Alternative Configurations
• Identify R&D– To support the baseline– To develop the alternatives
• Priorities for detector R&D
27-Sept-05 ILCSC - Daegu, KOREA 13
Guidance for Baseline Configuration
Baseline: A forward looking configuration which we are reasonably confident can achieve the required performance and can be used to give a reasonably accurate cost estimate by mid-end 2006 in a “Reference Design Report.”
27-Sept-05 ILCSC - Daegu, KOREA 14
What are Alternatives and Why?
Alternates: Technologies or concepts, which may provide a significant cost reduction, improved performance (or both), but which will not be mature enough to used in baseline by end 2006
Alternatives will be part of the RDR, will form an important element in the R&D program and are the key to evolving the design
27-Sept-05 ILCSC - Daegu, KOREA 15
Baseline Configuration Document
• Our ‘Deliverable’ by the end of 2005
• A structured electronic document– Documentation (reports, drawings etc)– Technical specs.– Parameter tables– …
• A ‘printable / readable’ summary document (~100 pages)
27-Sept-05 ILCSC - Daegu, KOREA 16
Structure of the BCD
Summary-like overview for those who want to understand the choice and the why
Technical documentation of the baseline, for engineers and acc. phys. making studies towards RDR
27-Sept-05 ILCSC - Daegu, KOREA 18
Design Approach• Create a baseline configuration for the machine
– Document a concept for ILC machine with a complete layout, parameters etc. defined by the end of 2005
– Make forward looking choices, consistent with attaining performance goals, and understood well enough to do a conceptual design and reliable costing by end of 2006.
– Technical and cost considerations will be an integral part in making these choices.
– Baseline will be put under “configuration control,” with a defined process for changes to the baseline.
– A reference design will be carried out in 2006. I am proposing we use a “parametric” design and costing approach.
– Technical performance and physics performance will be evaluated for the reference design
27-Sept-05 ILCSC - Daegu, KOREA 19
Parametric Approach
• Parametric approach to design– machine parameters : a space to optimize the machine
– Trial parameter space, being evaluated by subsystems
– machine design : incorporate change without redesign; incorporates value engineering, trade studies at each step to minimize costs
27-Sept-05 ILCSC - Daegu, KOREA 20
Approach to ILC R&D Program
• Proposal-driven R&D in support of the baseline design. – Technical developments, demonstration experiments,
industrialization, etc.
• Proposal-driven R&D in support of alternatives to the baseline– Proposals for potential improvements to the baseline,
resources required, time scale, etc.
• Develop a prioritized DETECTOR R&D program aimed at technical developments needed to reach combined design performance goals
27-Sept-05 ILCSC - Daegu, KOREA 21
The Key Decisions
Critical choices: luminosity parameters & gradient
27-Sept-05 ILCSC - Daegu, KOREA 22
Making Choices – The Tradeoffs
Many decisions are interrelated and require input from several WG/GG groups
27-Sept-05 ILCSC - Daegu, KOREA 23
Gradient
• Baseline recommendation for cavity - Standard TESLA 9-cell
• Alternatives: – Low-loss,– Re-entrant – superstructure
27-Sept-05 ILCSC - Daegu, KOREA 24
Gradient
Gradient recommendation (WG5)• 8km @ 31.5 MV/m → 250 GeV• +7km @ 36 MV/m → 500 GeV
Tunnel length for one 500 GeV linac (8+7)/0.7 21km
27-Sept-05 ILCSC - Daegu, KOREA 27
Results from KEK-DESY collaboration
must reduce spread (need more statistics)
sin
gle
-cell m
easu
rem
en
ts (
in n
ine-c
ell c
avit
ies) TESLA Cavity - Gradient Status
27-Sept-05 ILCSC - Daegu, KOREA 32
Cavity R&D
Fabrication from large grain Nb discs
May remove the need for electropolishing
( cost!)
27-Sept-05 ILCSC - Daegu, KOREA 33
Since Snowmass
• Summaries from Working Groups and Global Groups are posted on the ILC Website
• Analysis and Recommendations of the 40+ Decisions posted on the ILC Website
• GDE Executive Committee met at SLAC 22-Sept to assess Snowmass results, make plans to produce a “strawman” baseline by mid-November
• Planning done in the context of organizational approach and structures for next year to produce the RDR
27-Sept-05 ILCSC - Daegu, KOREA 34
RDR Matrix
22.09.2005
e- source e+ source Damping Rings RTML Main Linac BDS
Vacuum systems X X X X X X
Warm magnet systems X X X X (X) X
Cryomodule X X (X) X X (X)
Cavity Package X X (X) X X (X)
RF Power X X (X) X X (X)
Cryogenics X X X X X X
Accelerator Physics X X X X X X
Operations & Reliability X X X X X X
Instrumentation X X X X X X
Controls X X X X X X
Systems integration X X X X X X
CF&S X X X X X X
Cost X X X X X X
27-Sept-05 ILCSC - Daegu, KOREA 35
Other Issues for ILCSC
• Appointment letters have been sent to the three Regional Directors with terms through RDR
• Machine Advisory Committee needed early 2006. Propose to ask three senior accelerator physicists to attend Frascati meeting and review the BCD.
• Plans to proceed past RDR to a TDR– Anticipated transition from ILCSC to FALC for
management and oversight of GDE (see Takeuchi letter to FALC Resource Board)
– Expresssions of Intererest for Siting? Stategy / When ?– Plans toward an International Management Structure for
the ILC