status of lhc operations

35
Status of LHC Operations R. Assmann for the LHC commissioning team and LHC teams & groups LPCC 23.4.2010

Upload: veata

Post on 24-Feb-2016

38 views

Category:

Documents


0 download

DESCRIPTION

Status of LHC Operations. R. Assmann for the LHC commissioning team and LHC teams & groups LPCC 23.4.2010. Commissioning Strategy Last Weeks. Mike Lamont et al. Outline. The squeeze story: Getting all 4 IR’s squeezed to 2m IR1 and IR5 IR8 IR2 All 4 IR’s at once - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Status of LHC Operations

Status of LHC Operations

R. Assmannfor the LHC commissioning team and LHC teams & groups

LPCC 23.4.2010

Page 2: Status of LHC Operations

LPCC, R. Assmann 2

Commissioning Strategy Last Weeks

23.4.2010

Mike Lamont et al

Page 3: Status of LHC Operations

LPCC, R. Assmann 3

Outline

The squeeze story: Getting all 4 IR’s squeezed to 2m IR1 and IR5 IR8 IR2 All 4 IR’s at once Qualification tests for machine protection

Higher intensity Storing 10 bunches at injection Storing nominal bunch charge

Feedbacks, emittance and operational issues Feedbacks “Hunt the Hump” Multiple beam-induced quench

Conclusion

23.4.2010

Page 4: Status of LHC Operations

LPCC, R. Assmann 4

PART I – Squeeze IP Beam Size @3.5 TeV

23.4.2010

… a long story but with a happy ending…

This is one of the most complex stages of operation!

Change of beam optics to reduce beam size at the interaction points.

Goal for 2010 beam size reduction: factor ~2.2 for each plane(factor 5 in IP beta):

factor 5 higher luminosity

This is a change in b* by a factor ~5! Complex control of all IR power converters plus precision corrections.

At the same time the beam size at the triplets around the experiments increases significantly:

triplets become aperture bottlenecks

Protection of triplets and experiments against beam loss must be carefully verified before stable beams.

Page 5: Status of LHC Operations

LPCC, R. Assmann 5

Step 1: Squeezing and correcting IR1 & IR5

b-beat for Beam1 @ b * = 2m after correction using IR5 Q2:

Rogelio Tomas et al23.4.2010

Page 6: Status of LHC Operations

LPCC, R. Assmann 6

Example: CMS Luminosity Optimization

23.4.2010S. White

Page 7: Status of LHC Operations

LPCC, R. Assmann 7

ATLAS and CMS Improvement

23.4.2010

M. Ferro-Luzzi

Increase after squeeze: Factor 4-4.5 (to be compared with expected factor 5)

Luminosity up to 5×1027 cm-2 s-1.

Page 8: Status of LHC Operations

LPCC, R. Assmann 8

Step 2: Squeezing and correcting IR8

b-beat for Beam1 after squeeze and @ b * = 2m in IR8 after correction of Q5:

Rogelio Tomas et al23.4.2010

Page 9: Status of LHC Operations

LPCC, R. Assmann 9

Step 3: Squeezing and correcting IR2 b-beat for Beam1 at b* = 2m in IR2 (all other IPS at b * = 2m):

Rogelio Tomas et al

23.4.2010

Page 10: Status of LHC Operations

Problem Example I: Too steep current requests

RQS.A78B2 (17/04) tripped 3 times due to steep current-ramp requests. RQS.A56B2 (16/04) tripped once for the same reason QPS inductive compensation does not have time to react. V_REF translates directly into U_RES which goes above threshold. Functions need to be adjusted / smoothened.

Fixed as found… Thanks to crucial help from MP3 team on shift!

LPCC, R. Assmann23.4.2010 10

Page 11: Status of LHC Operations

Problem Example II: Discontinuities after incorporation

Fixed by new software

Page 12: Status of LHC Operations

LPCC, R. Assmann 12

Problem Example III: Leftover trims incorporated

Fixed by procedure…

Many small issues that require to be found and fixed. Each little issue costs 5-6 hours!

23.4.2010

Page 13: Status of LHC Operations

LPCC, R. Assmann 13

Step 4: Squeezing and correcting all 4 IR’s

23.4.2010

Mike LamontGabriel MullerMarek StrzelczykStefano RedaelliXavier

21 optics steps!

Rogelio Tomas et al

Page 14: Status of LHC Operations

LPCC, R. Assmann 14

Squeeze now starts working smoothly!

23.4.2010

Look at 4 most recent fills in last 48 hours!

All these fills made it to 3.5 TeV and 2m b*!

First two still affected by bugs (intensity loss) but used for qualification study!

Last two fills without any problem, very smooth! Used for provoked loss tests in preparation for stable beams!

Page 15: Status of LHC Operations

LPCC, R. Assmann 15

Provoked vertical beam loss on beam 1

23.4.2010

IR8 IR1IR2 IR5

Mom

entu

m C

lean

ing

Dum

p P

rote

ctio

n C

ol.

2m optics exposes IR’s as expected! Protected by tertiary collimators.

Collimation Team

Page 16: Status of LHC Operations

LPCC, R. Assmann 16

Zoom (vertical loss beam 1)

23.4.2010

factor 1,000

factor 4,000

Betatron Cleaning

IR8factor 600,000

OK for stable beams from collimation!Collimation Team

Page 17: Status of LHC Operations

LPCC, R. Assmann 17

Provoked asynchronous beam dump

1e-3 leakage to tertiary collimators in IR’s

OK for stable beams from beam dump!

Brennan Goddard et al

23.4.2010

Page 18: Status of LHC Operations

LPCC, R. Assmann 18

Status and Outlook Squeeze

Squeeze to 2m for all 4 IR’s established. All IR’s steered into collision. Golden orbit established. All 16 tertiary collimators adjusted. Squeezed optics fully qualified for protection.

Next: intensity from 2e10/beam to 3.5e10/beam Next: Stable beams with 10 times luminosity:

1028 cm-2 s-1 in reach

Still a lot to go but first steps are most difficult!

23.4.2010

Page 19: Status of LHC Operations

LPCC, R. Assmann 19

PART II – Increasing Intensity at 450 GeV

23.4.2010

… will be a long story but so far very happy…

This will be the challenge of LHC!

Goal: Factor 10 at injection.

Page 20: Status of LHC Operations

20

Increase Intensity: Number of Bunches

LPCC, R. Assmann

Dump of the 10 bunches

T factor 10

Brennan Goddard et al

23.4.2010

Page 21: Status of LHC Operations

LPCC, R. Assmann 21

Increasing bunch intensity

23.4.2010

factor 10

Major success for LHC: Nominal bunch charge at 450 GeV! 25 hours beam lifetime!

Means: No single bunch show stoppers from dynamic aperture, instabilities, …

Page 22: Status of LHC Operations

22

Increase Intensity: Over-Injection

LPCC, R. Assmann

Example of over-injection of 1E11 – 40 us integration

Losses from over-injectionLosses from TL

collimators (X-talk)

TDI

Brennan Goddard et al

23.4.2010

Page 23: Status of LHC Operations

LPCC, R. Assmann 23

Tunnel View

Collimation Team

23.4.2010

Transfer line collimator

Ring magnets with beam loss monitors

Page 24: Status of LHC Operations

LPCC, R. Assmann 24

Increase Intensity: Emittance

Emittances versus bunch intensity:

factor 10beyond 1e10 pilot

Injection team

23.4.2010

Page 25: Status of LHC Operations

LPCC, R. Assmann 25

Increase Intensity: Tune Shift Beam 1

23.4.2010

DQv = 0.0015

DQh = 0.0005

Injection team

Page 26: Status of LHC Operations

LPCC, R. Assmann 26

Tune shift: Measured versus Expected

B1 meas B2 meas ExpectedQh tune shift 5e-4 1.5e-3

Qv tune shift 1.5e-3 2.0e-3 4.5e-4

23.4.2010

for 1e10 to 1e11 p

Elias Metral et al

to be studied systematically:

impedance vs. collimator settingsother source?

Page 27: Status of LHC Operations

LPCC, R. Assmann 27

PART III – Feedbacks, Emittance & OP Issues

23.4.2010

…the cure, some issues…

Page 28: Status of LHC Operations

LPCC, R. Assmann 28

Tune Feedback in Operation

Tune feedback during ramp: Ralph Steinhagen et al

23.4.2010

Page 29: Status of LHC Operations

LPCC, R. Assmann 29

Orbit Feedback in Operation

23.4.2010

Ralph Steinhagen et al

Maximum orbit change during energy ramp: 0.08 mm

Page 30: Status of LHC Operations

LPCC, R. Assmann 30

Transv. Damper: Damping Beam Excitations

OFF ON

Crucial device to keep emittance

growth under control!

Wolfgang Hoefle et al

23.4.2010

Page 31: Status of LHC Operations

LPCC, R. Assmann 31

0

10

20

30

40

50

60

70

80

90

100

0

0.5

1

1.5

2

2.5

3

3.5

3:36 4:48 6:00 7:12 8:24 9:36 10:48 12:00 13:12 14:24 15:36

LHC_

BRAN

B_4L8

e_no

rm

Time

B1H

B1V

B2H

B2V

Lumi_LHCb

Ram

p st

art

Ram

p fin

ish

Bum

ps c

olla

psed

VE

LO in

LHC

b lu

mi-s

can

CM

S lu

mi-s

can

ATLA

S lu

mi-

scan

LHC

b 2nd

lum

i-sc

an

Emittance Growth: Still a Problem

Mirko Pojer23.4.2010

factor 3

Emitt

ance

Time

Page 32: Status of LHC Operations

32

Lifetime Drops with “Quiet” Beam Our friend the hump on the lifetime - ~ 7 minute period

LPCC, R. Assmann

Hunt the Hump!The hump is a vertical excitation on the beam that has a fast frequency component (therefore visible as “hump” in the tune spectrum and a slow moving frequency component (7 min).

23.4.2010

Page 33: Status of LHC Operations

LPCC, R. Assmann 33

4 Magnet Quench from Injected Pulse Losses in Sector12 at 450 GeV injection (1e10 p):

Debugging of operational procedures…

First injection into machine with some magnets mis-powered.

First injection always with pilot beam to exclude damage.

Collimation cannot protect for strong local kicks!

23.4.2010

Page 34: Status of LHC Operations

LPCC, R. Assmann 34

Conclusion Our “baby” (the LHC) learns walking surprisingly fast:

Routine ramps with 2e10 p to 3.5 TeV (just below safe beam limit). Squeeze in all 4 IR’s to 2m b* starts to run smoothly (smallest 2010). Squeezed optics fully qualified for protection IR’s protected by

collimation as foreseen. Tonight/tomorrow:

Stable beams: unsafe 3.5 TeV beam, all IR’s squeezed to 2m b*.Luminosity at 1028 cm-2 s-1.

In parallel important progress towards higher intensities: Stored nominal bunch intensity at 450 GeV with excellent lifetimes. Multiple bunches stored. Various feedbacks running. Instrumentation, RF, cryo, … very good! Seeing and addressing issues: emittance growth, hump, thresholds,

impedance, operational issues, … Remember, LHC is still a baby (for beam). So we try to guide

it carefully the first steps… (we do not want to fall)23.4.2010

Page 35: Status of LHC Operations

LPCC, R. Assmann 35

Thank you for your attention!

23.4.2010