status of lhc operations
DESCRIPTION
Status of LHC Operations. R. Assmann for the LHC commissioning team and LHC teams & groups LPCC 23.4.2010. Commissioning Strategy Last Weeks. Mike Lamont et al. Outline. The squeeze story: Getting all 4 IR’s squeezed to 2m IR1 and IR5 IR8 IR2 All 4 IR’s at once - PowerPoint PPT PresentationTRANSCRIPT
Status of LHC Operations
R. Assmannfor the LHC commissioning team and LHC teams & groups
LPCC 23.4.2010
LPCC, R. Assmann 2
Commissioning Strategy Last Weeks
23.4.2010
Mike Lamont et al
LPCC, R. Assmann 3
Outline
The squeeze story: Getting all 4 IR’s squeezed to 2m IR1 and IR5 IR8 IR2 All 4 IR’s at once Qualification tests for machine protection
Higher intensity Storing 10 bunches at injection Storing nominal bunch charge
Feedbacks, emittance and operational issues Feedbacks “Hunt the Hump” Multiple beam-induced quench
Conclusion
23.4.2010
LPCC, R. Assmann 4
PART I – Squeeze IP Beam Size @3.5 TeV
23.4.2010
… a long story but with a happy ending…
This is one of the most complex stages of operation!
Change of beam optics to reduce beam size at the interaction points.
Goal for 2010 beam size reduction: factor ~2.2 for each plane(factor 5 in IP beta):
factor 5 higher luminosity
This is a change in b* by a factor ~5! Complex control of all IR power converters plus precision corrections.
At the same time the beam size at the triplets around the experiments increases significantly:
triplets become aperture bottlenecks
Protection of triplets and experiments against beam loss must be carefully verified before stable beams.
LPCC, R. Assmann 5
Step 1: Squeezing and correcting IR1 & IR5
b-beat for Beam1 @ b * = 2m after correction using IR5 Q2:
Rogelio Tomas et al23.4.2010
LPCC, R. Assmann 6
Example: CMS Luminosity Optimization
23.4.2010S. White
LPCC, R. Assmann 7
ATLAS and CMS Improvement
23.4.2010
M. Ferro-Luzzi
Increase after squeeze: Factor 4-4.5 (to be compared with expected factor 5)
Luminosity up to 5×1027 cm-2 s-1.
LPCC, R. Assmann 8
Step 2: Squeezing and correcting IR8
b-beat for Beam1 after squeeze and @ b * = 2m in IR8 after correction of Q5:
Rogelio Tomas et al23.4.2010
LPCC, R. Assmann 9
Step 3: Squeezing and correcting IR2 b-beat for Beam1 at b* = 2m in IR2 (all other IPS at b * = 2m):
Rogelio Tomas et al
23.4.2010
Problem Example I: Too steep current requests
RQS.A78B2 (17/04) tripped 3 times due to steep current-ramp requests. RQS.A56B2 (16/04) tripped once for the same reason QPS inductive compensation does not have time to react. V_REF translates directly into U_RES which goes above threshold. Functions need to be adjusted / smoothened.
Fixed as found… Thanks to crucial help from MP3 team on shift!
LPCC, R. Assmann23.4.2010 10
Problem Example II: Discontinuities after incorporation
Fixed by new software
LPCC, R. Assmann 12
Problem Example III: Leftover trims incorporated
Fixed by procedure…
Many small issues that require to be found and fixed. Each little issue costs 5-6 hours!
23.4.2010
LPCC, R. Assmann 13
Step 4: Squeezing and correcting all 4 IR’s
23.4.2010
Mike LamontGabriel MullerMarek StrzelczykStefano RedaelliXavier
21 optics steps!
Rogelio Tomas et al
LPCC, R. Assmann 14
Squeeze now starts working smoothly!
23.4.2010
Look at 4 most recent fills in last 48 hours!
All these fills made it to 3.5 TeV and 2m b*!
First two still affected by bugs (intensity loss) but used for qualification study!
Last two fills without any problem, very smooth! Used for provoked loss tests in preparation for stable beams!
LPCC, R. Assmann 15
Provoked vertical beam loss on beam 1
23.4.2010
IR8 IR1IR2 IR5
Mom
entu
m C
lean
ing
Dum
p P
rote
ctio
n C
ol.
2m optics exposes IR’s as expected! Protected by tertiary collimators.
Collimation Team
LPCC, R. Assmann 16
Zoom (vertical loss beam 1)
23.4.2010
factor 1,000
factor 4,000
Betatron Cleaning
IR8factor 600,000
OK for stable beams from collimation!Collimation Team
LPCC, R. Assmann 17
Provoked asynchronous beam dump
1e-3 leakage to tertiary collimators in IR’s
OK for stable beams from beam dump!
Brennan Goddard et al
23.4.2010
LPCC, R. Assmann 18
Status and Outlook Squeeze
Squeeze to 2m for all 4 IR’s established. All IR’s steered into collision. Golden orbit established. All 16 tertiary collimators adjusted. Squeezed optics fully qualified for protection.
Next: intensity from 2e10/beam to 3.5e10/beam Next: Stable beams with 10 times luminosity:
1028 cm-2 s-1 in reach
Still a lot to go but first steps are most difficult!
23.4.2010
LPCC, R. Assmann 19
PART II – Increasing Intensity at 450 GeV
23.4.2010
… will be a long story but so far very happy…
This will be the challenge of LHC!
Goal: Factor 10 at injection.
20
Increase Intensity: Number of Bunches
LPCC, R. Assmann
Dump of the 10 bunches
T factor 10
Brennan Goddard et al
23.4.2010
LPCC, R. Assmann 21
Increasing bunch intensity
23.4.2010
factor 10
Major success for LHC: Nominal bunch charge at 450 GeV! 25 hours beam lifetime!
Means: No single bunch show stoppers from dynamic aperture, instabilities, …
22
Increase Intensity: Over-Injection
LPCC, R. Assmann
Example of over-injection of 1E11 – 40 us integration
Losses from over-injectionLosses from TL
collimators (X-talk)
TDI
Brennan Goddard et al
23.4.2010
LPCC, R. Assmann 23
Tunnel View
Collimation Team
23.4.2010
Transfer line collimator
Ring magnets with beam loss monitors
LPCC, R. Assmann 24
Increase Intensity: Emittance
Emittances versus bunch intensity:
factor 10beyond 1e10 pilot
Injection team
23.4.2010
LPCC, R. Assmann 25
Increase Intensity: Tune Shift Beam 1
23.4.2010
DQv = 0.0015
DQh = 0.0005
Injection team
LPCC, R. Assmann 26
Tune shift: Measured versus Expected
B1 meas B2 meas ExpectedQh tune shift 5e-4 1.5e-3
Qv tune shift 1.5e-3 2.0e-3 4.5e-4
23.4.2010
for 1e10 to 1e11 p
Elias Metral et al
to be studied systematically:
impedance vs. collimator settingsother source?
LPCC, R. Assmann 27
PART III – Feedbacks, Emittance & OP Issues
23.4.2010
…the cure, some issues…
LPCC, R. Assmann 28
Tune Feedback in Operation
Tune feedback during ramp: Ralph Steinhagen et al
23.4.2010
LPCC, R. Assmann 29
Orbit Feedback in Operation
23.4.2010
Ralph Steinhagen et al
Maximum orbit change during energy ramp: 0.08 mm
LPCC, R. Assmann 30
Transv. Damper: Damping Beam Excitations
OFF ON
Crucial device to keep emittance
growth under control!
Wolfgang Hoefle et al
23.4.2010
LPCC, R. Assmann 31
0
10
20
30
40
50
60
70
80
90
100
0
0.5
1
1.5
2
2.5
3
3.5
3:36 4:48 6:00 7:12 8:24 9:36 10:48 12:00 13:12 14:24 15:36
LHC_
BRAN
B_4L8
e_no
rm
Time
B1H
B1V
B2H
B2V
Lumi_LHCb
Ram
p st
art
Ram
p fin
ish
Bum
ps c
olla
psed
VE
LO in
LHC
b lu
mi-s
can
CM
S lu
mi-s
can
ATLA
S lu
mi-
scan
LHC
b 2nd
lum
i-sc
an
Emittance Growth: Still a Problem
Mirko Pojer23.4.2010
factor 3
Emitt
ance
Time
32
Lifetime Drops with “Quiet” Beam Our friend the hump on the lifetime - ~ 7 minute period
LPCC, R. Assmann
Hunt the Hump!The hump is a vertical excitation on the beam that has a fast frequency component (therefore visible as “hump” in the tune spectrum and a slow moving frequency component (7 min).
23.4.2010
LPCC, R. Assmann 33
4 Magnet Quench from Injected Pulse Losses in Sector12 at 450 GeV injection (1e10 p):
Debugging of operational procedures…
First injection into machine with some magnets mis-powered.
First injection always with pilot beam to exclude damage.
Collimation cannot protect for strong local kicks!
23.4.2010
LPCC, R. Assmann 34
Conclusion Our “baby” (the LHC) learns walking surprisingly fast:
Routine ramps with 2e10 p to 3.5 TeV (just below safe beam limit). Squeeze in all 4 IR’s to 2m b* starts to run smoothly (smallest 2010). Squeezed optics fully qualified for protection IR’s protected by
collimation as foreseen. Tonight/tomorrow:
Stable beams: unsafe 3.5 TeV beam, all IR’s squeezed to 2m b*.Luminosity at 1028 cm-2 s-1.
In parallel important progress towards higher intensities: Stored nominal bunch intensity at 450 GeV with excellent lifetimes. Multiple bunches stored. Various feedbacks running. Instrumentation, RF, cryo, … very good! Seeing and addressing issues: emittance growth, hump, thresholds,
impedance, operational issues, … Remember, LHC is still a baby (for beam). So we try to guide
it carefully the first steps… (we do not want to fall)23.4.2010
LPCC, R. Assmann 35
Thank you for your attention!
23.4.2010