Project Progress – 29th Mar 2014
BLOCK 1&2 BASEMENT-2 ROOF SLAB COMPLETED, BASEMENT-1 COLUMNS COMPLETED SLAB SHUTTERING IN PROGRESS
BLOCK-1 BLOCK-2
BLOCK-1 BASEMENT-1 ROOF SLAB SHUTTERING DONE & STEEL FIXING IN PROGRESS
BLOCK-1 BASEMENT-1 SHUTTERING DONE TOP VIEW
BASEMENT-1 LIFT AREA & STAIRCASE AREA BLOCK-1 TOP VIEW TOWARDS NORTH SIDE
BLOCK-2 BASEMENT-1 COLUMNS COMPLETED,SOUTH SIDE VIEW
BLOCK-2 BASEMENT-1 COLUMNS COMPLETED, NORTH SIDE VIEW
BLOCK-3 TOP VIEW SOUTH SIDE
BLOCK-3 COMPACTION DONE FOR DEEP BEAM, SOUTH -WEST CORNER
BLOCK-3 BACKFILLING IN PROGRESS FOR DEEP BEAM, NORTH –WEST CORNER
BLOCK-3 BALANCE COLUMNS IN PROGRESS FOR DEEP BEAM, SOUTH SIDE
BLOCK-4 STUB COLUMNS IN PROGRESS –SOUTH SIDE VIEW
BLOCK-4 STUB COLUMNS IN PROGRESS –SOUTH EAST CORNER
BLOCK-4 TIE BEAM IN PROGRESS-NORTH SIDE VIEW
BLOCK 19 SOUTH SIDE COLUMNS FOR BASEMENT-2 ROOF SLAB IN PROGRESS.
BLOCK 19 SOUTH SIDE TOP VIEW COLUMNS IN PROGRESS.
BLOCK 19 NORTH SIDE TOP VIEW COLUMNS IN PROGRESS.
BLOCK -20 SOUTH SIDE GRADE SLAB GRID(K-J-H-G) COMPLETED
BLOCK -20 SOUTH SIDE SLAB DONE & BALANCE PORTION BACKFILLING DONE COMPACTION IN PROGRESS FOR GRADE SLAB
BLOCK -20 SOUTH SIDE BALANCE PART BACKFILLING & COMPACTION IN PROGRESS FOR GRADE SLAB
BLOCK 17 NORTH SIDE VIEW FOOTINGS IN PROGRESS
BLOCK 17 SOUTH SIDE VIEW FOOTINGS DONE & COLUMNS IN PROGRESS
BLOCK 17 SOUTH SIDE VIEW FOOTINGS DONE & COLUMNS IN PROGRESS
BLOCK 5 & 6 IN PROGRESS
BLOCK 15 & 16 IN PROGRESS
BLOCK 7 &8 IN PROGRESS
BLOCK 13&14 IN PROGRESS
BLOCK 9 &10 IN PROGRESS
BLOCK 11 &12 WORK IN PROGRESS