steaminjection design
TRANSCRIPT
-
7/27/2019 Steaminjection Design
1/88
Harper Steam Injection Scheme
Performance Presentation to ERCB
March 22, 2011
-
7/27/2019 Steaminjection Design
2/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 2
BackgroundSub-Surface
Geology / Geoscience Overview
Drilling and Completions
Instrumentation
Scheme Performance and Monitoring
Surface
Facilities
Environmental
Key Learnings and Future Plans
Agenda
-
7/27/2019 Steaminjection Design
3/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 3
ApplicationApplication #1587764 submitted to ERCB on September, 2008
ApprovalApproval # 11379 received from ERCB on November, 2009
Delay of one year due to cancellation of Harper winter drillingprogram in 2009
Procurement of ServicesSeptember 2010
11-21-95-25W4M Drilling & CompletionsDrilling - December 30th to January 08th
Completions January 8th to January 25th
Steam Cycle
January 28
th
StartFebruary 15th End
Production CycleFebruary 19th Start
March 17th End
Demobilization
Introduction Key Dates
-
7/27/2019 Steaminjection Design
4/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 4
Scheme PurposeConfirm oil mobility through thermal stimulation
Establish a preliminary data set to aid determination of the
applicability and technical feasibility of in-situ thermal recovery
methods as they apply to the Grosmont formation
ChallengesRemoteness
Winter only access
Weather
Terrain
Team Introduction
Introduction Scheme Purpose, Challenges & Team Introductions
-
7/27/2019 Steaminjection Design
5/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 5
Jason HancherukVP, Land & Regulatory Affairs
Trevor DufresneSenior Geologist, Harper Pilot Project Manager
Tony SabelliVP, Drilling and Construction
Tomasz WnorowskiManager, Reservoir Engineering
Presenters
-
7/27/2019 Steaminjection Design
6/88
Sub-Surface Information
-
7/27/2019 Steaminjection Design
7/88Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 7
Geology
-
7/27/2019 Steaminjection Design
8/88
-
7/27/2019 Steaminjection Design
9/88Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 9
Harper Property
Edmonton
Calgary
Ft McMurray
Injection well 11-21-95-24W4
Structural Cross Section A A
2 key wells in area (7-8 & 14-21)
Limited 2D seismic
Harper Property
A
AKey Well
7-8
Key Well
14-21
Injection
Well
11-21
-
7/27/2019 Steaminjection Design
10/88Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 10
Scheme Project Area
Edmonton
Calgary
Ft McMurray
Harper Property
Key Well
7-8
Pilot Area
Pilot Project
Area
Key Well
14-21
Injection
Well
11-21
Small section
pilot area
Injection well drilled
50m to SW of key
well 14-21
-
7/27/2019 Steaminjection Design
11/88
-
7/27/2019 Steaminjection Design
12/88Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 12
Regional Stratigraphy
Pilot Project
Area
-
7/27/2019 Steaminjection Design
13/88Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 13
Regional Grosmont Structural Cross-Section
A
A
-
7/27/2019 Steaminjection Design
14/88Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 14
Reservoir Properties:
Depth: 540m to 571m
Net Pay Thickness: 29m
Avg. Porosity: 18%
Avg. So: 85%
Dol Scale
12% 100 Ohmm
11-21-95-24W4 Open Hole Logs (Steam Injection Well)
-
7/27/2019 Steaminjection Design
15/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 15
11-21 Petrophysical Analysis (Steam Injection Well)
540m
Grosmont C
571m
Base Pay
-
7/27/2019 Steaminjection Design
16/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 16
Reservoir Properties:
Depth: 541m to 566m
Net Pay Thickness: 22.6m
Avg. Porosity: 18%
Avg. So: 85%
Lst Scale
12
%
100 Ohmm
14-21-95-24W4 Open Hole Logs (Offset 50m to NE)
H Hi h R l i Mi I & P h i l
-
7/27/2019 Steaminjection Design
17/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 17
Grosmont C
31m
Reservoir
Thickness
Fractures
Harper: High Resolution Micro-Imager & Petrophysical
Correlation 14-21-95-24W4 Grosmont C
-
7/27/2019 Steaminjection Design
18/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 18
2mm
Thinsection work on 14-21-95-24W4
-
7/27/2019 Steaminjection Design
19/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 19
Reservoir Properties:
Depth: 570m to 596m
Net Pay Thickness: 23.4m
Avg. Porosity: 22%
Avg. So: 85%
Lst Scale
12% 100 Ohmm
7-8-96-24W4 Open Hole Logs (6.1km North)
H Hi h R l ti Mi I & P t h i l
-
7/27/2019 Steaminjection Design
20/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 20
Grosmont C
27m
Reservoir
Thickness
LargeVuggy
Porosity
Harper: High Resolution Micro-Imager & Petrophysical
Correlation 07-08-95-24W4 Grosmont C
-
7/27/2019 Steaminjection Design
21/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 21
Grosmont C Net Pay Map
Legend23.4 m Net Pay Value
20m Net Pay Contours
Grosmont D..Subcrop Edge
Sunshine
Oilsands Land
Pilot Project
Area
-
7/27/2019 Steaminjection Design
22/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 22
Grosmont C Pay Top Structure
Legend
23.4 m Pay Top
...Structure Value
20m Pay Top
.Structure Contours
Grosmont D
..Subcrop Edge
Sunshine
Oilsands Land
Pilot Project
Area
-
7/27/2019 Steaminjection Design
23/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 23
Grosmont C Pay Bottom Structure
Legend
23.4 m Pay Bottom
Structure Value
20m Pay Bottom
.Structure Contours
Grosmont D
..Subcrop Edge
Sunshine
Oilsands Land
Pilot Project
Area
-
7/27/2019 Steaminjection Design
24/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 24
Harper Property
Key Well
7-8
Key Well
14-21
Injection
Well
11-21
Pilot Project
Area
Trade Seismic Proprietary Seismic
(Winter 2011)
Harper Property 2D Seismic
-
7/27/2019 Steaminjection Design
25/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 25
Pilot Area
Pilot Project Area
Injection Well
11-21
Reservoir Properties
from 11-21 Injection Well:
Depth: 540m to 571m
Net Pay Thickness: 29m
Avg. Porosity: 18%
Avg. So: 85%
OBIP:~ 17.8 Million Bbls/qtr sec
OBIP=(Phi*h*A*(1-Sw))/FVF
Phi = 18%
h = 29m
A = 64ha
Sw = 15%FVF = 1.005
OBIP for Scheme Area in Harper (1/4 Section)
-
7/27/2019 Steaminjection Design
26/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 26
The Grosmont formation was ultimately sealed by theoverlaying Lower Cretaceous Wabiskaw shales
Caprock injectivity testing shows the Wabiskaw shale fracture
gradient to be 22kpa/m
Maximum surface steam injection pressures were limited to
5,100 kPa to prevent fracturing of the Wabiskaw shales
Actual injection pressures did not exceed 4,000 kPa throughout
the steam injection cycle
Caprock
-
7/27/2019 Steaminjection Design
27/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 27
Drilling and Completions
-
7/27/2019 Steaminjection Design
28/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 28
Scheme Area Location
Edmonton
Calgary
Ft McMurray
Harper Property
Pilot Area
Pilot Area
-
7/27/2019 Steaminjection Design
29/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 29
Well Summary Drilling 11-21-95-24W4
Spud date: December 30, 2010
Surface: Drilled 444mm hole to 145mKBRan 339.7mm X 81.1Kg/m K55 casing, set at 145mKB
Cemented with 20t RFC thermal cement, 2.5m3 returns
Intermediate: Drilled 311mm hole to 536mKB
Ran 244.5mm X 59.3 Kg/m L80 Hydril 603, set @ 536m
Cemented with 24t of RFC thermal cement, 8m3 of cement returns
Main Hole: drilled 200mm hole to 587mKB
Ran 139.7mm X 23.07kg/m J55 slotted liner, set at 587mKB (top @
523mKB)
Not cemented
Drilling losses: 380m3 into the Grosmont formation
Completed drilling operations on January 8th , 2011
-
7/27/2019 Steaminjection Design
30/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 30
Well Summary Completions 11-21-95-24W4
Conducted well completion operation from January 8th to 25th
Ran CBL log from 523mKB to Surface casing
Reviewed CBL log with ERCB
Perforated Intermediate casing from 517-518mKB for remedial
cement Squeeze.
Performed remedial cement operations (squeezed 200 liters of
cement at maximum surface pressure of 3,000kPa)
Drilled out cement and cleaned out to top of liner.
Ran 88.9mm Hydril 503 tubing and PSN, set bottom of tubing @
517.17mKB
Ran 31.75mm Coil tubing c/w fiber optic and thermocouples, set coilbottom at 572mKB
Ran 300X250 RWBFS pump with 10X34mm sinker bars and
56X25.4mm grade D rods
-
7/27/2019 Steaminjection Design
31/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 31
Well Summary Operations 11-21-95-24W4
Completed installation of steam generator and
production tanks from January 8th to 27th
Commenced steam injection - January 28th
Steam soak February 15th to 17th
Production operations initiated on February 18th
Steamer demobilization February 15th to 22nd
Production operations demobilization - March 17th to
22nd
-
7/27/2019 Steaminjection Design
32/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 32
Well Completion
WELL NAME DATE Jan-23-2011
ELEVATIONS (meters)
KB ELEV GL ELEV KB TO THF KB TO SCF KB TO GL PBTD
770.09m 765.79m 3m 4.0m 4.30m 582m
OD (mm) LANDED DEPTH WEIGHT (kg/m Grade
339.7 145 81.1 K-55
244.5 536 59.3 Hydril 603
139.7 523-587 23.07 J-55
139.7 top @ 523
Perf Date Zones Top Shot Bottom Shot SPM Gun Data
Jan-14-11 Grosmount 523.00 587.00 SLOTTED 1/4"slots
1/17/2011 Abandoned perfs 517.00 518.00 13 Cemented off
Intermidiate
Slotted Liner
Liner Hanger Import tools
CASING DESCRIPTION
Downhole Well ProfileSunshine Harper 11-21-095-25w4
Surface Casing
DOWNHOLE DESCRIPTION FROM BOTTOM UP (Tubing String)ITEM # DESCRIPTION LENGTH TOP OF (mKB)
1 145.00 0.00
2 536.00 0.00
3 63.00 523.00
4 1.00 517 mKB
5 517.17 0.00
6 572.00 0.00
7 8.00 509.00
8 509.00 0.00
31.75mm coil tubing c/w fiber optic string & thermocouples
300X250 RWBFC max stroke 3.67m
10 X .34m sinker bars plus 56 X 25.4mm graded rods
339.7mm X 81.1kg/m. K55 sur face casing
244.5mm X 59.3 kg/m. L-80 hydril 603
139.7mm X 23.07 kg/m. J-55
remedial perf orations 517.518 mKB
88.9mm X 13.84 kg/m. hydril 503 L-80 tubing
REMARKS
All items on wellhead are high tempature . Pressure tested wellhead before steam injections 6 mpa.
Liner top is @523MKB Its a import oil tools liner hanger 177mm X 139.7mm
Perfs f rom 517 to 518mKB Where cemented off and pressure tested to 2 mpa w ith 0% leak off after 15 min
1
2
3
4
56
7
8
-
7/27/2019 Steaminjection Design
33/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 33
Artificial Lift PerformanceMaximum SPM: 6
Maximum Fluid Production:
98m3
/dayActual Production Rates: 70-85m3/day
87% efficiencies achieved
Downhole Rod Insert Pump
-
7/27/2019 Steaminjection Design
34/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 34
Wellhead Configuration and Schematic
WELL HEAD DESCRIPTION
ITEM # DESCRIPTION SERIAL # MWP SIZE
1 FMC Casing bow l 21.00 279.4mm
2 FMC Side angle entr y spool 21.00 279.4 x 179mm
complete w ith tbg hanger spool
slips installed in sideangle hanger
w ith 1.25 inch coil installed
3 FMC Flow tee w ith 1.25" radigans 21.00 179.4 x 94.5mm
rams and 50mm flow tee
ll i ll i . ll i i .
i i I i il l li i . .
i l i
-
7/27/2019 Steaminjection Design
35/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 35
Instrumentation
-
7/27/2019 Steaminjection Design
36/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 36
Fiber Optic string installed in the 11-21-95-24W4 pilot wellfrom surface to 572m
Continuous temperature monitoring during injection and
production cycles
Two thermocouples inside coil tubing string to verify fiber optic
performance and for calibration
Depths of 532m and 542m
Fiber Optic Monitoring
-
7/27/2019 Steaminjection Design
37/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 37
Fiber optics inside coil
tubing string
Coil tubing string installed
independently outside of
tubing
Two thermocouples addedinside coil string to
evaluate fiber optic
accuracy
Allows for temperature
monitoring of steam
injection and produced
fluids
Fiber Optic Deployment
-
7/27/2019 Steaminjection Design
38/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 38
Production Performance andMonitoring
-
7/27/2019 Steaminjection Design
39/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 39
The pilot design consists of threeelements:
Steam injection
Maintain Nitrogen blanket in annulus
above Grosmont formation
Three day steam soakProduction
Harper Pilot Test Design
Soaking
-
7/27/2019 Steaminjection Design
40/88
-
7/27/2019 Steaminjection Design
41/88
-
7/27/2019 Steaminjection Design
42/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 42
Average Steam Quality: 80%Average Daily Injection Rates: 245m3/d
Steam Generation Pressures: 2,000 - 4,000 kPa
Well Head Pressures: 2,000 3,000 kPa
No risks identified due to the low injection pressures and no
potential for fracturing of the formation or the cap rock
Fiber optic temperature string monitored for any unexpected
uphole temperature changes
Pressure fluctuations during steam injection cycle may be due to
heterogeneous fractured and vuggy nature of the Grosmont Cformation
Injection Operations Summary
-
7/27/2019 Steaminjection Design
43/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 43
Fiber Optic Monitoring - Start of Injection
Initial Reservoir Temperature Gradient
Grosmont Reservoir Temperature: 19C
-
7/27/2019 Steaminjection Design
44/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 44
Fiber Optic Monitoring - Injection Cycle
Injection Interval 523m-587m
Steam Temperatures: >200C
Nitrogen Blanket 0-520m
Temperature: ~170C
-
7/27/2019 Steaminjection Design
45/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 45
Fiber Optic Monitoring - Injection Interval
Heating Across Grosmont
Injection Interval 523m-587m
Steam Temperatures: >200C
-
7/27/2019 Steaminjection Design
46/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 46
0
1000
2000
3000
4000
5000
6000
1/27/2011 0:00 2/1/2011 0:00 2/6/2011 0:00 2/11/2011 0:00 2/16/2011 0:00 2/21/2011 0:00
P
r
e
s
s
u
r
e
Date/Time
Detailed Pressure Plot
S te am Di sc har ge P re ss W el lh ead Pr es su re N2 / Cs g P re ss F ee d W ate r Inl et P re ss
Steam Injection Period Pressure Monitoring
Steam Generator Start Up Following Electrical Failure
2 Days of Down Time Jan 30-31, 2011
-
7/27/2019 Steaminjection Design
47/88
-
7/27/2019 Steaminjection Design
48/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 48
No seismic surveys at this time due to the limited span of this
project and only one CSS injection cycle
Long term pilot will require steam chamber growth and
surface monitoring including consideration of 4D seismic to
aid evaluation of reservoir conformance
Seismic
-
7/27/2019 Steaminjection Design
49/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 49
Production Cycle
-
7/27/2019 Steaminjection Design
50/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 50
Operating Temperature Range: 60-180 C
1
10
100
1000
10000
100000
1000000
10000000
100000000
0 20 40 60 80 100 120 140 160 180 200 220 240
Estimated Bitumen Viscosity for Harper
Viscosity
,mPa.s
Temperature, C
Produced Oil Viscosity Range of 20-10,000cp
P d d Fl id Vi it d D it T t
-
7/27/2019 Steaminjection Design
51/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 51
Produced Fluid Viscosity and Density Test
Produced
Bitumen
Produced
Water
-
7/27/2019 Steaminjection Design
52/88
P d d Bit Vi it A l i
-
7/27/2019 Steaminjection Design
53/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 53
Produced Bitumen Viscosity Analysis
P d ti O ti
-
7/27/2019 Steaminjection Design
54/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 54
Daily fluid production 70-85m3/d maximizing pump
performance
No gas production
Constant fluid levels of 110-130m above pump
1-3% oil cuts throughout the production cycle
Total oil volumes to be verified once the production tanks are
cleaned
Production Operations
Fib O ti M it i P d ti
-
7/27/2019 Steaminjection Design
55/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 55
Fiber Optic Monitoring Production
Operations: Feb 23
Temperature gradient during production operationsTemperature gradient during production operations
Transition Zone
Top of Steam Column Bottom of Steam Column
Transition Zone
Emulsion
D/H pump set @ 520m
~100oC at 101 kPaa
Residual N2 Mixture
Production Cycle
-
7/27/2019 Steaminjection Design
56/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 56
Production Cycle
0
10
20
30
40
50
60
70
80
90
100
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
2/16 2/21 2/26 3/3 3/8 3/13 3/18 3/23
ater/oilcuts(
)
productionrate(m
3/d)
Date
Fluid Production
Daily PRD Oil
Cut%
Water
Cut%
P d ti C l T t
-
7/27/2019 Steaminjection Design
57/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 57
Production Cycle - Temperatures
0
10
20
30
40
50
60
70
80
90
100
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
2/16 2/21 2/26 3/3 3/8 3/13 3/18 3/23
ater/oilcuts(
)
productionrate(m
3/d)
Date
Fluid Production
Daily PRD Oil
Cut%
Water
Cut%
Reservoir cooling at ~5oC/d
Cumulative Fluid Production vs Temperature Loss
-
7/27/2019 Steaminjection Design
58/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 58
Cumulative Fluid Production vs. Temperature Loss
0
20
40
60
80
100
120
140
0
500
1000
1500
2000
2500
3000
3500
0 10 20 30 40 50 60
e
pC
Days
VolumeM3
Volume Vrs BHT
c umul ati ve vol ume the rmo te mp Li ne ar (c umul ati ve vol ume ) Expon. (the rmo te mp)
Mar.08 Mar.18
March 17th Scheduled shut
down of production operations
Expected Produced Volume:
~2,000m3 , 50% recovery of
injected volume
Expected BHT: ~59oC
-
7/27/2019 Steaminjection Design
59/88
Surface Information
-
7/27/2019 Steaminjection Design
60/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 60
Scheme Facilities
Injection Facilities Plot Plan
-
7/27/2019 Steaminjection Design
61/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 61
Injection Facilities Plot Plan
Production Facilities Plot Plan
-
7/27/2019 Steaminjection Design
62/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 62
Production Facilities Plot Plan
Steam Injection Flow Diagram
-
7/27/2019 Steaminjection Design
63/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 63
Steam Injection Flow Diagram
Production Operations Flow Diagram
-
7/27/2019 Steaminjection Design
64/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 64
Production Operations Flow Diagram
Discussion of Measurement & Reporting
-
7/27/2019 Steaminjection Design
65/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 65
Injection volumes measured by reading daily steam injection
volumes (roots meter)
Injected volumes verified through trucked water volumes and
water balance
Production volumes measured daily by monitoring field tanklevels
Production volumes verified through trucked volumes
Total produced oil volume to be verified upon cleaning of tanks
The water cuts measured through wellhead fluid sampling and
separation with centrifuge
Discussion of Measurement & Reporting
Discussion of Measurement & Reporting
-
7/27/2019 Steaminjection Design
66/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 66
Production accounting department submissions to
Petroleum Registry of Alberta
Injected volumes based on water balance
Delivered oil production volumes as allocated at
approved drop off facilities
Water production volumes based on the production
fluid balance
Discussion of Measurement & Reporting
Fluid Trucking
-
7/27/2019 Steaminjection Design
67/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 67
Produced fluids trucked off site to approved facilities
Newalta, Red Earth
CCS, Slave Lake
Legacy, Wabasca
When required for drilling operations, water was trucked to 06-14-097-24W4 and 14-03-096-24W4
Prevented additional water withdrawals that would have been
required during drilling with losses
Fluid Trucking
-
7/27/2019 Steaminjection Design
68/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 68
Environmental
-
7/27/2019 Steaminjection Design
69/88
-
7/27/2019 Steaminjection Design
70/88
Compliance
-
7/27/2019 Steaminjection Design
71/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 71
ERCB Approvals
Commercial Scheme Approval # 11379 November 27, 2009Facility License # F42557 December 10, 2010
Class IV Injection Well (D51) Approval # 24 January 25, 2011
Sustainable Resource Development Approvals
Surface Approval MSL 082313/LOC 080480 October 24, 2008
Caribou Protection Plan #NEB2-045-10/11-Harper November
3, 2010
Alberta Environment ApprovalsTDL 00280101-00-00 (20,000 m3) November 1, 2010
TDL 00280141-00-00 (30,000 m3) November 1, 2010
Compliance
-
7/27/2019 Steaminjection Design
72/88
Reclamation Activities
-
7/27/2019 Steaminjection Design
73/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 73
The Pad site will have topsoil and subsoil re-contoured to mimic
surrounding landscape
Course woody debris will be re-spread evenly over disturbed areas
and the lease will be left to naturally re-vegetate
On-going monitoring for weeds, erosion, and re-vegetation
performance will occur until a Reclamation Certificate has been
obtained
Sunshine Oil Sands Ltd confirms, to the best of its knowledge, that
all operations are in compliance with all conditions and approvals
related to the Harper CSS Pilot Project
Reclamation Activities
-
7/27/2019 Steaminjection Design
74/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 74
Key Learnings and Future Plans
Key Learnings
-
7/27/2019 Steaminjection Design
75/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 75
Grosmont C bitumen is thermally mobile
Successful in mobilizing and producing bitumen during this steam pilot
Grosmont C has high injectivity due to excellent permeability
Could not pressure up the formation
Maximum steam injection rates of 250m3/d CWE
High well deliverability, unable to draw down the fluid levels
Fiber optic temperature sensor has good resolution, allowing observations onfluid levels and downhole conditions
Can conclude injection and production to the lower porosity interval dueto uniform heating of fiber optic string
Able to see temperature changes in the wellbore, N2 blanket visible
Potential fluid level monitoring although highly interpretive
N2 blanket successfully insulated wellbore above steam injection interval
Key Learnings
Potential Design Improvements
-
7/27/2019 Steaminjection Design
76/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 76
Reservoir Heterogeneity
Reservoir non-conformance challenges were indicated when there was no
pressure build-up during injection operations and was likely due to highlypermeable fractures and vugs
Shorter cycles might be required to optimize the thermal stimulation and
production cycles
Artificial Lift
Due to pre-production delays, production operations were only able to recover~50% of injected CWE volume from the formation
Maximum pump volumes of ~85m3/day were insufficient to draw down
wellbore fluid levels
Operating Improvements
Pre-steam production test to understand reservoir fluid dynamics
Cost effective water disposal required
Real time surface and down-hole pressure and temperature monitoring
Flow meters for all fluids including fuel
More time required for CSS cycles
Potential Design Improvements
Future Plans
-
7/27/2019 Steaminjection Design
77/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 77
Evaluating options to produce remainder of injected water back next winter
Determine if there is a mobile water phase in the Grosmont formation
Evaluating potential for future cycles at the Harper Pilot location
Shorter injection cycles with a more aggressive production strategy
Amendment of current application and extension of pilot operations are required if
another cycle is to be executed at the 11-21-95-24W4 pilot location
Current steam flood experiments of Grosmont C 11-21-95-24W4 core will provide
greater understanding of potential recovery factors and residual oil saturations
Impacts of vugs and fractures on recoveries to be determined through CT scans
before and after steam flood tests
Future pilot projects experimenting with modern enhanced oil recovery techniques will
be evaluated
Future Plans
Contact Information
-
7/27/2019 Steaminjection Design
78/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 78
Sunshine Oilsands Ltd.
Jason Hancheruk VP, Land & Regulatory Affairs
Suite 1400, 700 - 4th Avenue S.W.
Calgary, Alberta, Canada
T2P 3J4
Tel: +1 (403) 984-5144
Fax: +1 (403) 455-7674
Website: www.sunshineoilsands.com
Contact Information
-
7/27/2019 Steaminjection Design
79/88
Harper Steam Injection SchemePerformance Review
March 22, 2011
Appendix
-
7/27/2019 Steaminjection Design
80/88
Appendix B: Water Source
-
7/27/2019 Steaminjection Design
81/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 81
pp
Appendix C: Trucked Fluids
-
7/27/2019 Steaminjection Design
82/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 82
ppLocation Volume m
Trucking Ticket PO. Fluid Hauled In Hauled Out
Date Company Number Number Type Transfered From Transfered To Oil Water Other Oil Water Other
28-Jan Black Gold 27034 Water 11-21 14-3-96-24 18.0
29-Jan Black Gold 27264 Water 11-21 14-3-96-24 18.0
2-Feb Clean Harbours Water 11-21 14-3-96-24 45.0
4-Feb Casper 2527 Water 11-21 14-3-96-24 44.0
7-Feb Casper 2530 Water 11-21 14-3-96-24 22.0
9-Feb Casper 2651 Water 11-21 14-3-96-24 1.0
11-Feb Casper 2652 Water 11-21 14-3-96-24 20.015-Feb Casper 2654 Water 11-21 14-3-96-24 2.0
16-Feb Casper Water 11-21 14-3-96-24 61.0
17-Feb Casper 2657 Water 11-21 14-3-96-24 10.0
22-Feb Gibson 597055 Water 11-21 6-14-97-24 30.0
22-Feb Black Gold 27532 Water 11-21 6-14-97-24 10.0
23-Feb Gibson 6027977 Water 11-21 Newalta 25.0
23-Feb Casper 2626 Water 11-21 6-14-97-24 10.0
23-Feb Clean Harbours CH124728 Water 11-21 6-14-97-24 15.0
24-Feb Gibson 6027979 Water 11-21 Newalta 25.0
25-Feb Gibson 6288391 Water 11-21 Legacy 25.0
25-Feb Gibson 6288391 Water 11-21 Legacy 25.0
25-Feb Gibson 6027980 Water 11-21 Legacy 25.0
26-Feb Gibson 6027981 Water 11-21 Legacy 25.0
26-Feb Gibson 6288392 Water 11-21 Legacy 25.0
26-Feb Gibson 6288493 Water 11-21 Legacy 28.0
27-Feb Gibson 6288393 Water 11-21 Legacy 25.0
27-Feb Gibson 6027982 Water 11-21 Legacy 27.0
27-Feb Gibson 6288494 Water 11-21 Legacy 28.0
28-Feb Gibson 6178523 Water 11-21 Legacy 25.0
28-Feb Gibson 6288498 Water 11-21 Legacy 28.0
28-Feb Gibson 6288394 Water 11-21 Legacy 25.0
1-Mar Gibson 6288395 Water 11-21 CCS Slave Lake 25.0
1-Mar Gibson 6178524 Water 11-21 CCS Slave Lake 25.0
1-Mar Gibson 6288499 Water 11-21 CCS Slave Lake 28.0
3-Mar Gibson 6178526 Water 11-21 Legacy 25.0
3-Mar Gibson 6288396 Water 11-21 Legacy 25.0
3-Mar Gibson 6288501 Water 11-21 Legacy 28.0
4-Mar Gibson 6117228 Water 11-21 Legacy 25.0
4-Mar Gibson 6288502 Water 11-21 Legacy 28.0
4-Mar Gibson 6169548 Water 11-21 Legacy 25.0
4-Mar Gibson 6178527 Water 11-21 Legacy 25.0
5-Mar Gibson 6169550 Water 11-21 Legacy 25.0
5-Mar Gibson 6117226 Water 11-21 Legacy 25.05-Mar Gibson 6288503 Water 11-21 Legacy 26.0
6-Mar Gibson 6178530 Water 11-21 Legacy 25.0
6-Mar Gibson 6117229 Water 11-21 Legacy 25.0
6-Mar Gibson 6178670 Water 11-21 Legacy 25.0
6-Mar Gibson 6169551 Water 11-21 Legacy 25.0
7-Mar Gibson 6288504 Water 11-21 Legacy 26.0
7-Mar Gibson 6178531 Water 11-21 Legacy 25.0
8-Mar Gibson 6288505 Water 11-21 Legacy 26.0
8-Mar Gibson 6178532 Water 11-21 Legacy 25.0
8-Mar Gibson 6178673 Water 11-21 Legacy 25.0
19-Mar Black Gold 27348 Water 11-21 CCS Slave Lake 0.6
19-Mar Black Gold 27348 Solids 11-21 CCS Slave Lake 0.1
19-Mar Black Gold 27348 Oil 11-21 CCS Slave Lake 0.3
19-Mar Black Gold 28002 Water 11-21 CCS Slave Lake 4.4
19-Mar Black Gold 28002 Solids 11-21 CCS Slave Lake 0.4
19-Mar Black Gold 28002 Oil 11-21 CCS Slave Lake 3.2
Appendix D: Production Cycle
-
7/27/2019 Steaminjection Design
83/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 83
pp y
Date TimeWater
Cut%
Total
BS&W%
Oil
Cut%
Wellhead
Temp C
Thermo
Couple
Temp C
Pump
SPM
Fluid On
Pump M
Joints to Fluid
9.6m/jt
Fluid
Level
m
Tank 1
VOL
Tank 2
VOL
Tank 3
VOL
Tank 4
VOL
2/17/2011 8:00 -5 110 0 0 0 0
2/17/2011 12:00 10 107.3 47.8 46 441.8
2/17/2011 16:00 15 158.7 38.24 47 451.4
2/17/2011 20:00
2/17/2011 0:00
2/17/2011 4:00
2/18/2011 8:00 -38 122.4 105.16 40 384.4 0 0 0 0
2/18/2011 10:00 5 115.8 105.16 40
2/18/2011 15:00 65 156.5 114.72 39
2/18/2011 18:30 60 60 40 70 173.4 143.4 36
2/18/2011 0:00
2/18/2011 4:00
2/19/2011 8:00 60 60 40 70 173.2 2.75 124.28 38 365.3 0 26 0 0
2/19/2011 12:00 60 60 40 70 174.8 2.75
2/19/2011 16:00 60 60 40 70 173.1 2.75
2/19/2011 20:00 60 60 40 80 174 2.75 114.72 39
2/19/2011 0:00
2/19/2011 4:00
2/20/2011 8:00 80 80 20 70 169.2 2.75 114.72 39 374.9 0 57 0 0
2/20/2011 12:00 95 95 5 83 168.8 3.5
2/20/2011 16:00 96 96 4 80 167.7 3.5 133.84 37
2/20/2011 20:00 80 165.8 3.5
2/20/2011 0:00
2/20/2011 4:00
2/21/2011 8:00 95 95 5 83 160.5 3.5 124.28 38 365.3 0 76 32 0
2/21/2011 12:00 96 96 4 93 160.2 3.75
2/21/2011 16:00 96 96 4 90 156.4 3.75
2/21/2011 20:00 96 96 4 84 155.8 3.5
2/21/2011 0:00
2/21/2011 4:00
Appendix D: Production Cycle
-
7/27/2019 Steaminjection Design
84/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 84
pp y
Date TimeWater
Cut%
Total
BS&W%
Oil
Cut%
Wellhead
Temp C
Thermo
Couple
Temp C
Pump
SPM
Fluid On
Pump M
Joints to Fluid
9.6m/jt
Fluid
Level
m
Tank 1
VOL
Tank 2
VOL
Tank 3
VOL
Tank 4
VOL
2/22/2011 8:00 96 96 4 82 152.3 3.5 133.84 37 355.8 0 98 24 0
2/22/2011 12:00 95 95 5 87 150.2 4
2/22/2011 16:00 96 96 4 89.4 149.1 4
2/22/2011 20:00 96 96 4 87 147.4 4
2/22/2011 0:00
2/22/2011 4:00
2/23/2011 8:00 97 97 3 91 143.4 4 133.84 37 355.8 0 100 24 0
2/23/2011 12:00 97 97 3 91.7 141.2 4.5
2/23/2011 16:00 97 97 3 91.4 140.1 5
2/23/2011 20:00 97 97 3 91.6 139.1 5
2/23/2011 0:00
2/23/2011 4:00
2/24/2011 8:00 97 97 3 90.8 134 5 133.84 37 355.8 0 112 90 02/24/2011 12:00 97 97 3 91.2 132.2 5.5
2/24/2011 16:00 97 97 3 90.5 129.7 5.5
2/24/2011 20:00 97 97 3 89.5 129.7 5.5
2/24/2011 0:00
2/24/2011 4:00
2/25/2011 8:00 97 97 3 89.5 129.7 5.5 133.84 37 355.8 0 112 90 0
2/25/2011 12:00 97 97 3 91.7 124.9 6
2/25/2011 16:00 97 97 3 92.6 123.3 6
2/25/2011 20:00 97 97 3 93.1 122.3 6
2/25/2011 0:00
2/25/2011 4:00
2/26/2011 8:00 97 97 3 79.9 120.9 4 133.84 37 355.8 0 112 90 0
2/26/2011 12:00 97 97 3 87.8 118.4 5
2/26/2011 16:00 97 97 3 88 117 5.5
2/26/2011 20:00 97 97 3 86.3 116.4 5.5
2/26/2011 0:00
2/26/2011 4:00
-
7/27/2019 Steaminjection Design
85/88
Appendix D: Production Cycle
-
7/27/2019 Steaminjection Design
86/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 86
pp y
3/4/2011 8:00 97 97 3 78 93 5.5 114.72 39 374.9 0 113 116 0
3/4/2011 12:00 98 98 2 77 92 5.5
3/4/2011 16:00 98 98 2 77 92 5.5
3/4/2011 20:00 98 98 2 77 91 5.5
3/4/2011 0:00
3/4/2011 4:00
3/5/2011 8:00 98 98 2 75 89 5.5 114.72 39 374.9 0 105 116 0
3/5/2011 12:00 98 98 2 73 89 5.5
3/5/2011 16:00 98 98 2 72 88 5.5
3/5/2011 20:00 98 98 2 72 88 5.5
3/5/2011 0:00
3/5/2011 4:00
3/6/2011 8:00 85 0 114.72 39 374.9 0 80 80 03/6/2011 12:00 86 0
3/6/2011 16:00 86 0
3/6/2011 20:00 99 99 1 68 87 5.5
3/6/2011 0:00
3/6/2011 4:00
3/7/2011 8:00 99 99 1 70 83 5.5 114.72 39 374.9 0 121 79 0
3/7/2011 12:00 99 99 1 69 5.5
3/7/2011 16:00 99 99 1 69 5.5
3/7/2011 20:00 99 99 1 67 5.5
3/7/2011 0:00
3/7/2011 4:00
3/8/2011 8:00 99 99 1 66 81 5.5 114.72 39 374.9 0 126 79 0
3/8/2011 12:00 99 99 1 66 81 5.5
3/8/2011 16:00 99 99 1 66 80 5.5
3/8/2011 20:00 99 99 1 66 80 5.5
3/8/2011 0:00
3/8/2011 4:00
Date TimeWater
Cut%
Total
BS&W%
Oil
Cut%
Wellhead
Temp C
Thermo
Couple
Temp C
Pump
SPM
Fluid On
Pump M
Joints to Fluid
9.6m/jt
Fluid
Level
m
Tank 1
VOL
Tank 2
VOL
Tank 3
VOL
Tank 4
VOL
Appendix D: Production Cycle
-
7/27/2019 Steaminjection Design
87/88
Sunshine Oilsands Ltd. Harper Pilot Resource Update March 2011 87
pp y
Date TimeWater
Cut%
Total
BS&W%
Oil
Cut%
Wellhead
Temp C
Thermo
Couple
Temp C
Pump
SPM
Fluid On
Pump M
Joints to Fluid
9.6m/jt
Fluid
Level
m
Tank 1
VOL
Tank 2
VOL
Tank 3
VOL
Tank 4
VOL
3/9/2011 8:00 99 99 1 67 78 5.5 114.72 39 374.9 0 109 79 0
3/9/2011 12:00 99 99 1 66 78 5.5
3/9/2011 16:00 99 99 1 63 77 5.5
3/9/2011 20:00 99 99 1 61 77 5.5
3/9/2011 0:00
3/9/2011 4:00
3/10/2011 8:00 99 99 1 63 76 5.5 114.72 39 0 107 65 0
3/10/2011 12:00 99 99 1 62 75 5.5
3/10/2011 16:00 99 99 1 59 75 5.5
3/10/2011 20:00 99 99 1 58 74 5.5
3/10/2011 0:00
3/10/2011 4:00
3/11/2011 8:00 99 99 1 58 73 5.5 114.72 39 374.9 0 114 65 0
3/11/2011 12:00 99 99 1 58 73 5.5
3/11/2011 16:00 99 99 1 58 72 5.5
3/11/2011 20:00 99 99 1 58 72 5.5
3/11/2011 0:00
3/11/2011 4:00
3/12/2011 8:00 99 99 1 62 71 5.5 114.72 39 374.9 0 84 20 0
3/12/2011 12:00 99 99 1 62 73 1.5
3/12/2011 16:00 99 99 1 62 73 1.5
3/12/2011 20:00 99 99 1 61 71 5.5
3/12/2011 0:00
3/12/2011 4:00
3/13/2011 8:00 99 99 1 58 69 5.5 124.28 38 365.3 0 112 0 0
3/13/2011 12:00 99 99 1 58 69 5.5
3/13/2011 16:00 99 99 1 57 68 5.5
3/13/2011 20:00 99 99 1 57 68 5.5
3/13/2011 0:00
3/13/2011 4:00
3/14/2011 8:00 99 99 1 53 67 5.5 114.72 39 374.9 0 117 0 0
3/14/2011 12:00 99 99 1 54 67 5.5 114.72
3/14/2011 16:00 99 99 1 53 67 5.5 114.72
3/14/2011 20:00 99 99 1 53 66 5.5 114.72
3/14/2011 0:00
3/14/2011 4:00
Appendix D: Production Cycle
-
7/27/2019 Steaminjection Design
88/88
pp y
Date TimeWater
Cut%
Total
BS&W%
Oil
Cut%
Wellhead
Temp C
Thermo
Couple
Temp C
Pump
SPM
Fluid On
Pump M
Joints to Fluid
9.6m/jt
Fluid
Level
m
Tank 1
VOL
Tank 2
VOL
Tank 3
VOL
Tank 4
VOL
3/15/2011 8:00 99 99 1 57 65 5.5 114.72 39 374.9 0 124 0 0
3/15/2011 12:00 99 99 1 56 65 5.5
3/15/2011 16:00 99 99 1 56 65 5.5
3/15/2011 20:00 99 99 1 54 65 5.5
3/15/2011 0:00
3/15/2011 4:00
3/16/2011 8:00 99 99 1 53 64 5.5 114.72 39 374.9 0 129 0 0
3/16/2011 12:00 99 99 1 51 63 5.5
3/16/2011 16:00 99 99 1 50 63 5.5
3/16/2011 20:00 99 99 1 50 63 5.5
3/16/2011 0:00
3/16/2011 4:00
3/17/2011 8:00 99 99 1 51 62 5.5 114.72 39 374.9 0 79 0 0
3/17/2011 12:00
3/17/2011 16:00
3/17/2011 20:00
3/17/2011 0:00
3/17/2011 4:00
3/18/2011 8:00 65 114.72 39 374.9 0 11 0 0
3/18/2011 12:00
3/18/2011 16:00
3/18/2011 20:00
3/18/2011 0:00
3/18/2011 4:00
3/19/2011 8:00 65 105.16 40 384.4 0 0 0 0
3/19/2011 12:00
3/19/2011 16:00
3/19/2011 20:00