Welcome to the new Reading Branch Library
![Page 2: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/2.jpg)
Ground was broken on April 21, 2014.
![Page 3: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/3.jpg)
In June, 2014, work officially began. The first job was to drill the geothermal well.
![Page 4: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/4.jpg)
July, 2014 ‒ Workers install reinforcing bars for the branch foundation.
![Page 5: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/5.jpg)
Glass containers were unearthed at the site including (left to right) a 1920 Nu-Grape soda bottle, a WT Wagner bottle, and a cottage cheese container.
![Page 6: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/6.jpg)
August, 2014 ‒ The foundations are finished and the under slab electric and plumbing are nearly complete.
![Page 7: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/7.jpg)
September, 2014 ‒ Steel columns are installed and cranes are used to lift the frame into place.
![Page 8: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/8.jpg)
October, 2014 ‒ Exterior stud walls are installed and sheathing is attached.
![Page 9: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/9.jpg)
November, 2014‒ Masons begin to install brick and stone on the exterior facade.
![Page 10: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/10.jpg)
January, 2015 ‒ The interior walls are taking shape.
![Page 11: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/11.jpg)
February, 2015‒ More
finishing touches are
added to the interior,
including paint, tile and
flooring.
![Page 12: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/12.jpg)
March, 2015 ‒ Glass installation begins and the branch gets new fountains and a refillable water
bottle station.
![Page 13: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/13.jpg)
April, 2015 ‒ The interior is taking shape and work begins on the sidewalks and parking lot.
![Page 14: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/14.jpg)
April, 2015‒ Final touches are made to the drive-thru and book drop area.
![Page 15: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/15.jpg)
May, 2015 ‒ The branch gets carpeting and a sliding glass entry door.
![Page 16: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/16.jpg)
June 18, 2015 ‒ Last minute preparations are made before the opening.
![Page 17: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/17.jpg)
June 18, 2015 ‒ Last minute preparations are made before the opening.
![Page 18: Step-by-Step Look At How We Built The New Reading Branch Library](https://reader030.vdocument.in/reader030/viewer/2022032504/55c3bc66bb61eb62188b466d/html5/thumbnails/18.jpg)
Welcome to the new Reading Branch Library! Please explore the building and enjoy complimentary