stochastic unit commitment with topology control recourse...

52
Stochastic Unit Commitment with Topology Control Recourse for Renewables Integration Jiaying Shi and Shmuel Oren University of California , Berkeley IPAM, January 2016 1

Upload: others

Post on 08-Aug-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Stochastic Unit Commitment with Topology Control Recourse for Renewables

Integration

Jiaying Shi and Shmuel OrenUniversity of California , Berkeley

IPAM, January 2016

1

Page 2: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

33% RPS - Cumulative expected VERs build-out through 2020

Source: CAISO

Page 3: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

All Rights Reserved to Shmuel Oren

Page 4: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Negative Correlation with Load

0

50

100

150

200

250

win

d po

wer

out

put (

MW

)

24 48 72 96 120 144 168 3000

4000

5000

6000

7000

8000

load

(MW

)

hour

wind power

load

4

Page 5: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Introduction

Integration of Renewable Generation Challenge for energy system operations

Renewable Generation:Supply with Uncertainty

Goal:Demand = Supply

How to ensure

reliable and economical operations?

5

Page 6: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Integration of Renewable Generation

Flexibility

Goal:

n nD t S t

Storage

Flexible Generation

Flexible Transmission

(TopologyControl)

Demand = Supply with Uncertainty

6

Demand Response

Page 7: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Conventional Solution

Source: CAISO

Page 8: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Background

Topology Control Topology control has been studied to: Relieve abnormal conditions[1]

Reduce system loss[2]

Reduce operating cost (Optimal Transmission Switching)[3]

Utilize existing assets required by normal operating conditions. No additional cost other than the wear of breakers is incurred.

[1] A. G. Bakirtzis and A. P. Sakis Meliopoulos, “Incorporation of switching operations in power system corrective control computations,” IEEE Transactions on Power Systems, vol. PWRS-2, no. 3, pp. 669–675, 1987.[2] R. Bacher and H. Glavitsch, “Loss reduction by network switching,” IEEE Transactions on Power Systems, vol. 3, no. 2, pp. 447–454, 1988.[3] E. Fisher, R. O’Neill, and M. Ferris, “Optimal transmission switching,” IEEE Transactions on Power Systems, pp. 1–10, 2008.

8

Page 9: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

National Directives

9

• Federal Energy Regulatory Commission (FERC) Order 890– Improve the economic operations of the electric

transmission grid• Energy Policy Act of 2005

– Sec.1223.a.5 of the US Energy Policy Act of 2005– “encourage… deployment of advanced transmission

technologies” – “optimized transmission line configuration”

• Energy Independence and Security Act of 2007– Title 13, Smart Grid:– “increased use of … controls technology to improve

reliability, stability, and efficiency of the grid”– “dynamic optimization of grid operations and resources”

Page 10: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

10

How?

Original Optimal Cost: $20,000 (A=180MW,B=30MW, C=40MW)

Open Line A-B, Optimal Cost: $15,000 (A=200MW, B=50MW)

120MW

80MW

Original Feasible Set

150MW 180MW 200MW

Gen B

Gen A

30MW

Feasible set with Line A-B switched off

50MW

Page 11: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

11

(Does Topology Control Always Degrade Reliability: Counter Example

Page 12: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

12

Generator Info

• Operational costs, startup costs, shutdown costs, min & max operating levels, ramp rates

• N-1 is enforced– System must have adequate 10 minute spinning reserve online

to respond to any contingency (line or generator)

Page 13: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

13

Optimal Solutions & Impact on Reliability

• Optimal N-1 compliant solution with static topology:– Solution cannot handle loss of generators 3 and 4

• Optimal N-1 compliant solution with smart switching (line A-C open)– Solution can handle loss of generators 3 and 4

Page 14: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Superstorm Sandy• PJM lost 82 bulk electric facilities

– 6 500kV transmission assets; 3 345kV transmission assets ; 39 230kV transmission assets; 25 138kV transmission assets

• Caused extremely high voltage on the system during low load levels

• “We were dealing with extremely high voltage on the system but a switching plan was developed to help alleviate these conditions.”

• Per Andy Ott, VP of PJM: several 500kV lines were switched out to mitigate over voltage concerns during these low load level periods

14

Page 15: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Topology Control as Recourse

Topology Control In deterministic unit commitment, topology

control can reduce the generation cost[4] and mitigate post contingency violations

In stochastic unit commitment, topology control as a recourse action may leverage the grid controllability and mitigate the variability of renewable generation.

[4] K. Hedman and M. Ferris, and et al. “Co-optimization of generation unit commitment and transmission switching with N-1 reliability,” IEEE Transactions on Power Systems vol. 25, no. 2, pp. 1052–1063, 2010.

15

Page 16: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Scope

Include the uncertainty of wind generation in the model of power system day-ahead scheduling.

Examine whether the operation cost can be reduced in stochastic unit commitment when topology control is introduced in the recourse.

16

Page 17: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Formulation17

Two-stage Stochastic Programming Objective : minimize the operating cost Decision variables:

Commitment of Slow Generators

Commitment of Fast Generators,

Dispatch of Generation

&Transmission

Switching

Renewable Generation

1ST Stage 2nd StageUncertainty

Page 18: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Startup of slow units

Uncertainty(Multiple

Scenarios)

Scenarios of• Load • Wind power outpu• contingenciest

Start of fast units,Output level of fast

and slow units, Line switching

,

18

Decision Structure

Page 19: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Formulation19

Constraints System-wide constraints Market clearing DC power flow Line capacity Number of lines that can be switched off

Generator constraints Generation capacity Ramping up/down Min up/down time On/off transition

, , , , , , , , , ,

max max, , , , , ,

M 1 M 1ij ij t s ij t s ij i t s j t s ij ij t s

ij t s ij ij t s ij t s ij

r F B r

r F F r F

Page 20: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Formulation20

, , , , , , , , , , , ,

, , , , , , ,t , ,s ,

bus bus bus

min .

. .

g g t g g t s g g t s g g t s g g t s g g t s i i t st T g GS s S g GF g GS i N

ij t s ki t s g t s g g t i ti N k N g GF g GS g Wj N i N g on i g on i g on i

s u s u c P c P L

s t F F P P W D

, , 0, , ,i t sL i N t T s S

min max, , , , , ,

min max, , ,

, , , 1,

, 1, , ,

, , ,

, ,

, , , 1,

, , , 1,

g g t s g t s g g t s

g g t g t g g t

ug t s g t s g

dg t s g t s g

P u P P u g GF t T s S

P u P P u g GS t T

P P R g GF t T t s S

P P R g GF t T t s S

, , , 1,

, 1, , ,

, , , , , 1,

, , , 1

, , , 1

, , , 1

, , , 1,

, , , 1

ug t s g t s g

dg t s g t s g

g t s g t s g t s

g t g t g t

P P R g GS t T t

P P R g GS t T t

s u u g GF t T t s S

s u u g GS t T t

, , , , , , , , , ,

max max, , , , , ,

, , , , ,

, ,

M 1 M 1 , , , ,

, , , ,

( 0,1 , , 0,1 , 0,1 for ), ,

( 0,1

ij ij t s ij t s ij i t s j t s ij ij t s

ij t s ij ij t s ij t s ij

ij t s g t s g t

g t s

r F B r i j N t T s S

r F F r F i j N t T s S

r i j N u for g GF u g GS t T s S

s for g G

,, 0,1 for ), ,g tF s g GS t T s S

Page 21: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Case

IEEE 118 system

118 buses186 lines19 conventional generators

21

Page 22: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Wind Modeling

Wind Generation Simulation In our test, wind speed and wind power data of three

locations in Wyoming are obtained from NREL Western Wind Resources Dataset .

1000 wind generation scenarios are generated using the method described in [5].

To reduce the computational complexity, we adopt the scenario reduction technique introduced in [6].

[5] A. Papavasiliou and S. S. Oren, “Multiarea stochastic unit commitment for high wind penetration in a transmission constrained network,” Operations Research, vol. 61, no. 3, pp. 578–592, 2013.[6] N Growe-Kuska, H Heitsch and W Romisch, “Scenario Reduction and Scenario Tree Construction for Power Management Problems”. IEEE Power Tech Conference, Bologna 2003.

22

Page 23: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Wind Speed Scenario Generation

Page 24: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Power Curve24

Page 25: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Wind Speed Modeling and Calibration

Page 26: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Autoregressive Model

Page 27: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Scenario Generation

Page 28: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Preliminary Test Results

Solving the problem—Branch and Bound 48,336 binary variables, 80,352 continuous

variables. The problem is solved on a laptop: 2.6GHz CPU,

12G RAM. When the MIP gap tolerance is 5%, using the

default setting of CPLEX the program does not terminate after 8 hours.

The automatic tuning tool of CPLEX does not work for this problem. Appropriate parameters are not found after over 8 hours.

28

Page 29: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Warm Starts

Solving the problem—Branch and Bound Using CPLEX MIP warm-start

Stochastic Unit Commitment without

Topology Control

Optimal Transmission

Switching for 1 Hour with the Heaviest Net

Load

Warm-Start Solution Solver

29

Page 30: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Warm Start Heuristic

Solving the problem—Branch and Bound Using CPLEX MIP Unit Commitment Decisions

The warm-start values for unit commitment decisions are obtained from solving a stochastic unit commitment problem with no topology control recourse.

In practice, system operators can use the commitment decisions of previous days with similar loading conditions to construct warm-up values for commitment decisions.

30

Page 31: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Warm Start Heuristic

Solving the problem—Branch and Bound Using CPLEX MIP Topology Control Decisions

Topology control warm-up values are obtained from solving an optimal transmission switching problem for the highest load hour (no wind).

The warm-start values for switching decisions are the same for different hours and scenarios.

31

Page 32: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Results

Start Switching Solutions We conducted 9 numerical tests “x” in “TCSUC-x” stands for the maximum number of

lines that can be switched off. ( )Case Start switching solution

TCSUC-1 132TCSUC-2 132,136TCSUC-3 132,136,153TCSUC-4 132,136,153,162TCSUC-5 132,136,151,153,163TCSUC-6 132,136,148,153,161,162TCSUC-7 63,132,136,148,153,161,162TCSUC-10 126, 132, 136, 146, 151, 153, 157, 165

TCSUC-∞1, 10, 14, 25, 28, 31, 57, 63, 66, 77, 79, 86, 96, 103, 110, 111, 132, 136, 146, 151, 153, 161, 165, 184

J x

32

Page 33: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Results

Improvement over SUC with no switching33

Cost Reduction: percentage of savingTime limit: 30minMaximum value of optimality gap: 7.88%

Gap:7.88%

Gap:3.66%

Page 34: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Results

Results analysis Why cost can be reduced with transmission

switching in the recourse? Reduction of production cost Reduction of start-up cost Reduction of no-load cost Reduction of load shedding

34

Page 35: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Results

Why cost can be reduced with transmission switching in the recourse? Reduction of production cost

35

Page 36: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Results

Why cost can be reduced with transmission switching in the recourse? Reduction of start-up cost (STC6<STC8)

36

Page 37: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Results

Why cost can be reduced with transmission switching in the recourse? Reduction of no-load cost

37

Page 38: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Preliminary Test Results

Why cost can be reduced with transmission switching in the recourse? Reduction of load shedding

38

Page 39: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Solving the problem39

Progressive Hedging For problem

The algorithm proceeds as follows:Step-0:Step-1: Step-2: For each :

Step-3: If has not converged, go to Step-1.

min , : ,s s s ss S

f x p g x y x y Q

,0, 0, arg min , : ,k ks x y s sk x f x g x y x y Q w

s

1; 1; k k ks s s s s

s Sp x k k w w x

,

2

arg min ,

1 : ,2

k ks x y s s

s

x f x g x y w x

x x y Q

x

Page 40: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Solving the problem40

Progressive Hedging For stochastic unit commitment with topology control,

all first stage variables are 0-1 variables. Quadratic terms in Step-2 can be expressed as :

since . Step-2 can be implemented in parallel.

21 1 12 2 2

T Tx x x Tx x x

Page 41: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Solving the problem41

Warm-up Solution to Iteration k:Solution to Iteration k-1

Iteration k

Warm-up Solution to Iteration k+1:Solution to Iteration k

Step-1:Calculate ,

Calculate

1k k

ksx

Scenario 1s

Scenario s n

Calculate ksx

Calculate ksx

Step-2

Page 42: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Solving the Problem42

The optimality gap for each sub-problem is set to be 4% and the time limit for each sub-problem is set to be 6 minutes.

The algorithm converges after 7 iterations. The estimated time for solving the problem in parallel is 42 minutes.

The cost is reduced by 10.1% with topology control recourse.

Page 43: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Progressive Hedging Results43

L1-norm error of first-stage decisions in each iteration:

Page 44: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Switching Results44

Switching solution for different scenarioScenario Switching solution of Hour 18 (Lines are off)

1 40, 94,109, 132, 136, 146, 151, 153, 157, 1652 48, 88, 126, 132, 136, 146, 151, 153, 157, 1653 116, 126, 132, 136, 153, 1654 94, 96, 124, 132, 136, 146, 151, 153, 157, 1655 39, 40, 63, 84, 122, 132, 136, 151, 153, 1656 1, 83, 126, 132, 16. 146, 151, 153, 157, 1657 45, 118, 126, 132, 136, 146, 151, 153, 157, 1658 63, 96, 109, 124, 127, 132, 153, 163, 1689 21, 42, 79, 132, 136, 146, 151, 153, 157, 162

10 37, 42, 59. 103, 132, 136, 146, 151, 153, 157

Page 45: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Evaluation

Evaluate the robustness of the solution that was based on a reduced scenario set, under a richer uncertainty representation.

The commitment of slow generators are fixed as the slow generators commitment solution of TCSUC-10.

The line switching decisions are optimized for each of the simulation scenarios bot constrained to the union of lines switched in TCSUC-10 for the 10 optimization scenarios.

1000 wind generation scenarios produced using Monte Carlo simulation are used in the evaluation.

Both unit commitment and unit commitment with transmission switching are implemented to compare the cost.

45

Page 46: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Results46

Line switching solution for scenario 1(12.8%)

tline

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

126 1 0 1 0 1 1 1 1 1 0 1 1 0 0 1 0 0 0 1 0 0 0 1 1

132 1 0 1 0 0 0 1 0 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0 1

136 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0

146 1 0 1 1 1 1 1 1 1 1 0 0 1 0 0 0 0 0 0 0 0 1 1 1

151 1 1 1 1 1 1 1 1 1 1 0 0 0 1 1 0 0 1 0 0 0 0 1 1

153 0 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1

157 0 0 1 1 1 1 1 1 1 1 0 0 1 1 0 0 0 1 0 0 1 1 1 1

165 0 1 0 1 1 0 1 1 1 1 0 0 0 0 1 0 0 0 0 0 0 0 0 1

Page 47: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Test Results47

Line switching solution for scenario 2 (13.6%) t

line

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

126 1 0 1 1 1 1 1 1 1 0 1 1 0 1 1 1 0 0 0 0 1 0 1 1132 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1136 1 1 0 1 1 1 1 1 1 0 1 0 0 0 1 1 0 0 0 0 1 1 0 1146 1 1 1 0 0 0 1 1 1 0 0 1 0 0 0 1 0 0 0 0 1 1 1 0151 1 0 1 0 0 1 1 1 1 0 0 1 1 1 0 0 0 0 1 1 1 0 1 0153 0 0 1 1 1 1 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1157 1 1 1 1 1 1 1 1 1 0 0 1 0 0 1 1 0 0 0 0 1 1 1 1165 0 0 0 0 0 1 1 1 1 0 0 1 1 1 0 0 0 0 1 1 0 0 0 0

Page 48: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Evaluation48

In all 1000 tests, when there is transmission switching in the recourse, the total cost is less than when there is no transmission switching.

The average total cost is reduced by 12.9% with transmission switching in the recourse.

The simulation provides a lower bound of the cost reduction for the case where there is no restriction on the lines that can be switched.

Page 49: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Conclusion49

We have developed a two-stage stochastic programming model with topology control recourse for power systems with wind generation.

We proposed a method to find a warm-start for the problem which helps reduce the solution time significantly.

Numerical test results shown for the IEEE 118 system demonstrate that with topology control recourse, the operation cost will be reduced.

To achieve good cost reduction, only a small fraction of lines need be switched off.

For future research directions, we will study efficient algorithms that solve the problem for commercial-scale systems.

Page 50: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Future Work

Conduct test on European system with over 600 buses and over 1000 transmission lines.

Find a scalable method that can solve stochastic unit commitment with topology recourse efficiently.

50

Page 51: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Thank You!

51

Page 52: Stochastic Unit Commitment with Topology Control Recourse ...helper.ipam.ucla.edu/publications/enec2016/enec2016_12632.pdf · Background Topology Control Topology control has been

Reference

[1] A. G. Bakirtzis and A. P. Sakis Meliopoulos, “Incorporation of switching operations in power system corrective control computations,” IEEE Transactions on Power Systems, vol. PWRS-2, no. 3, pp. 669–675, 1987.[2] R. Bacher and H. Glavitsch, “Loss reduction by network switching,” IEEE Transactions on Power Systems, vol. 3, no. 2, pp. 447–454, 1988.[3] E. Fisher, R. O’Neill, and M. Ferris, “Optimal transmission switching,” IEEE Transactions on Power Systems, pp. 1–10, 2008.[4] K. Hedman and M. Ferris, and et al. “Co-optimization of generation unit commitment and transmission switching with N-1 reliability,” IEEE Transactions on Power Systems vol. 25, no. 2, pp. 1052–1063, 2010.[5] A. Papavasiliou and S. S. Oren, “Multiarea stochastic unit commitment for high wind penetration in a transmission constrained network,” Operations Research, vol. 61, no. 3, pp. 578–592, 2013.[6] N Growe-Kuska, H Heitsch and W Romisch, “Scenario Reduction and Scenario Tree Construction for Power Management Problems”. IEEE Power Tech Conference, Bologna 2003.

52