sts-61a national space transportation system mission report

Upload: bob-andrepont

Post on 08-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    1/14

    JSC-209

    STS 61-ANational SpaceTransportation SystemMission Report

    March 1986

    N/_ANational Aeronautics andSpace AdministrationLyndon B. Johnson Space CenterHouston, Texas

    IN

    I _

    OC

    I_lk,

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    2/14

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    3/14

    JSC-20956

    STS 61-ANATIONAL SPACE TRANSPORTATION SYSTEM

    MISSION REPORT

    Michael A. Collins, Jr.Manager, Flight Dataand Evaluation Office

    _o_ _ Or_e_aa__'_GFE Projects Office

    A. D. Ald_ffch ,_Man_ger / "i-,,-_'t.National Space _ransportation t_System

    NATIONAL AERONAUTICS AND SPACE ADMINISTRATIONLYNDON B. JOHNSON SPACE CENTER

    HOUSTON, TEXAS 77058

    MARCH 1986

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    4/14

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    5/14

    INTRODUCTION AND MISSION OBJECTIVES

    The STS 61-A National Space Transportation System (STS) Mission Report contains asummary of the major activities and accomplishments of the twenty-second SpaceShuttle mission and the ninth flight of the OV-099 vehicle, Challenger.

    The primary objective of the STS 61-A flight was to successfully operate and returnthe German Spacelab D-I payload. The sequence of events for this mission is shown inTable I, and the Orbiter problem tracking llst is presented In Table II.

    The crew for thls twenty-second flight ot the Space Shuttle was Henry W. Hartsfleld,Jr., Commander; Steven R. Nagel, Lt. Col., U. S. Alr Force, Pilot; James F. Buchll,Col., U. S. Marine Corp., Gulon S. Bluford, Jr., Col., U. S. Alr Force, and Bonnie J.Dunbar, Ph.D., Mission Specialists; and Reinhard Furrer, Ph.D., Ernest Messerschmldt,Ph.D., and Wubbo J. Ockels, Ph.D., Payload Specialists.

    MISSION SUMMARY

    The STS 61-A countdown proceeded very smoothly with no unplanned holds. Llft-offoccurred at 303:17:02:00 G.m.t. (11:02 a.m.e.s.t, on October 30, 1985) from launchcomplex 39A at Kennedy Space Center (KSC). The launch phase was normal and thevehicle was inserted into a 170- by 174-nmi. orbit at the conclusion of the secondorbital maneuvering system (OMS) maneuver.

    Spacelab D-I activation was begun about 3 hours after orbital insertion and wascompleted 2 hours later. Seventy-three of the 76 D-! experiments were successfullyactivated; however, the furnace in the Materials Science Experiment Double rack forExperiment Modules and Apparatus (MEDEA) material processing rack malfunctioned.

    The Orbiter fuel cell ! condenser exlt temperature cycled between 147 deg and 160deg F throughout launch and during the mission. This oscillation had no effect offuel cell operation or impact on the mission.

    At external tank (ET) separation, the right aft reaction control system (RCS)experienced two anomalies. Initial indications showed a failure of the B-legregulator. As a result, the right RCS provided propellants for all aft RCSthrusters. Aside from the minor RCS and fuel cell problems, all Orbiter subsystemsoperated satisfactorily.

    The Global Low Orbiting Mission Relay (GLOMR) satellite was launched at a missionelapsed tlme of 12 hours 34 minutes.

    Spacelab I>-I payload activities during the second day continued satisfactorily wlthbetter results in the areas of llfe sciences than materials science. The Orbitersubsystems and Spacelab experiments continued to operate In a satisfactory mannerduring the third day. Spacelab power usage was about 1.5 kW below predictions forthls point in the mission. A successful inflight maintenance (IFM) procedure wasperformed on the MEDEA furnace pressure sensors, and a lamp change-out was also made.As a result, the MEDEA facility was fully recovered and processing of samples wasinitiated; however, many hours of run-tlme on various samples were lost because ofthe furnace malfunction.

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    6/14

    Orbiter subsystemscontinued to operate satisfactorily for the remainder of the7-day mission. All Spacelab experiment subsystems also operated satisfactorily forthe remainder of the mission.B_causeof the temporary malfunction of the MEDEAfurnace facility during the earlypart of the mission, discussions were held with the Science community on lengtheningthe mission one day to obtain additional materials processing data. Spacelab power-usage levels could not be reduced enough to provide the required extension day;therefore, the decision was madeto not extend the mission, and instead, to conductsimultaneous materials processing and vestibular sled operations.After completing the final entry preparations, including deactivation of theSpacelab, the 171-second deorbit maneuverwas performed. Entry was normal in allrespects. A 207-degree heading alignment circle (HAC)maneuverwas performed and theOrbiter landed at 310:17:44:51G.m.t., on runway 17 at EdwardsAFB, California.Rollout required 8304 feet and was completed 49 seconds after landing.All Orbiter detailed test objectives (DTO's) assigned to STS61-A were completed. Inaddition, seven speclal-test-condltion DTO's were accomplished either completely, orto a very high degree. Data were also collected on seven data-only DTO's.

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    7/14

    TABLEI. - STS 61-A SEQUENCE OF EVENTSEvent Actual time r G.m.t.

    APU activation (I) 303:16:55:09(2) 303:16:55:10(3) 303:16:55:11

    SRB HPU activation command 303:16:55:29.4MPS start command sequence (engine 3) 303:16:59:53.5SRB ignition command from GPC (llft-off) 303:17:00:00MPS throttle down to 89-percent thrust (engine 3) 303:17:00:18.5MPS throttle down to 65-percent thrust (engine 3) 303:17:00:27.1Maximum dynamic pressure 303:17:00:50MPS throttle up to 104-percent thrust (engine 3) 303:17:00:59.9SRB separation command 303:17:02:05MPS throttle down for 3g acceleration (engine 3) 303:17:08:28.5Main engine cutoff (MECO) 303:17:08:36External tank separation 303:17:08:54OMS-I ignition 303:17:10:35OMS-I cutoff 303:17:12:37APU deactivation (3) 303:17:18:53OMS-2 ignition 303:17:44:44OMS-2 cutoff 303:17:46:56FCS (flight control system) checkout - APU I activation 309:17:31:03APU 1 deactivation 309:17:35:12APU 2 activation 310:16:35:31Deorbit maneuver ignition 310:16:40:30Deorbit maneuver cutoff 310:16:43:21APU I activation 310:17:00:25APU 3 activation 310:17:00:26Entry interface (400,000 ft) 310:17:13:32End blackout 310:17:31:33"Terminal Area Energy Management (TAEM) 310:17:38:26Main landing gear contact (LH) 310:17:44:51Nose landing gear contact 310:17:44:59Wheel stop 310:17:45:50APU deactivation complete 310:18:01:59

    *Engineering approximation

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    8/14

    VEHICLE ASSESSMENT

    SOLID ROCKET BOOSTERS

    All solid rocket booster (SRB) systems performed as expected. The SRB prelaunchcountdown was nominal with no problems noted. Performance of both solid rocketmotors (SRM's) was near predicted values, and well within the allowed envelopes.Propellant burn rates were near predicted values. Preliminary data indicate that theSRB separations occurred 0.2-second early. The SRB recovery system was reported tohave performed nominally. Both SRB's and frustums were floating and recovered.

    EXTERNAL TANK

    All ET systems performed as expected. No launch commit criteria (LCC) orOperational Maintenance Requirements and Specifications Document (OMRSD) violationsoccurred. Propellant loading was accomplished as planned. Some normal frost wasobserved, but weather conditions were not conducive to any appreciable ice/frostformation. No known ET preflight or flight anomalies were noted.

    Liquid oxygen ullage pressure transducer no. I experienced a momentary 10-secondcontrol band dropout approximately 7.5 minutes after llft-off, and this anomaly hadno impact on the flight. All instrumentation performed satisfactorily during thecountdown.

    SPACE SHUTTLE MAIN ENGINES

    All Space Shuttle main engine (SSME) parameters appeared to be normal during theprelaunch countdown and compared well with prelaunch parameters that have beenobserved on previous flights. Preliminary data indicate that SSME performance atstart, malnstage, shutdown, and propellant dump was satisfactory.

    One anomaly was recorded for main engine-I at 5 minutes 13 seconds after llft-off.The high pressure oxidizer turbopump (HPOTP) discharge pressure measurement, which isonly a maintenance parameter, failed the reasonableness test. This had no effect onengine performance.

    MAIN PROPULSION SYSTEM

    Overall performance of the main propulsion system (MPS) was excellent. Liquid oxygenand liquid hydrogen loads were very close to the inventory loads. There were noMPS-related leaks of any significance. Ascent performance appeared to be normal.

    ORBITER

    Right Reaction Control System Helium Regulators FailedDuring the prelaunch reaction control system (RCS) pressurization operations, therlght-RCS A-leg fuel regulators failed in the open position, and this resulted in arupture of the downstream burst disc. A retest of the A and B fuel-regulator legsverified acceptable performance, although the A-leg regulators were operatingsluggishly.

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    9/14

    At 303:19:00 G.m.t. after ET separation, the right RCS fuel-tank pressure was reading274 psia, indicating that a primary regulator had failed in the open position. Thecrew closed the right RCS helium pressure A-leg to prevent a possible overpressurecondition. After the right RCS helium pressure A-leg was closed, the fuel ullagepressure decayed to about 215 psla, thus indicating that the right RCS regulatorB-leg had failed closed. The crew reopened the right RCS regulator A-leg torepressurize the system. The right fuel-tank pressure rose above secondary lockuppressure, reaching 290 psla.

    A special on-orblt test of the right RCS fuel regulator A-leg was conducted tosimulate the entry propellant flow rates and obtain the main poppit valve openingcharacteristics. The test was performed at 309:18:53 G.m.t., and the capability ofthe right RCS fuel regulators to support entry primary flow requirements wasverified.

    Fuel Cell I Condenser Exit Temperature Cycling

    The fuel cell I condenser exit temperature cycled beyond the normal control range of145 deg F to 160 deg F during prelaunch hlgh-load operations. Analysis showed thiscondition was acceptable for launch and flight. The cycles damped during ascent andtemperature cycling returned to the normal control band during flight.

    This was the first flight for this fuel cell since it was rebuilt and stored dryfor approximately 1 year. A records review Showed that the coolant flow controlcartridge was marginally acceptable based on flow/gain characteristics duringcomponent-level bench testing. However, other valves with similar flow/gaincharacteristics have not shown a tendency to become unstable. Postfllght acceptancetest procedure operations for this fuel cell showed behavior similar to flightperformance, with a tendency toward mlno_ytllng of 3 to 4 deg F with load changes,indicative of marginally high coolant flow control valve gain. The fuel cell hasbeen removed and replaced.

    SPACELAB D-l

    The Spacelab D-1 had 76 experiments of whlch 73 operated properly and the datareceived was well beyond the experimenters" expectations. The Germans" response tothe success was stated as "an extremely challenging mission with outstandingresults." Data reduction and evaluation is in progress. Five minor problemsoccurred in addition to the three experiments that were lost. None of these fiveproblems had a significant impact on the conduct of infllght experiments. Overall,the Spacelab D-I mission must be viewed as an outstanding success.

    DETAILED TEST OBJECTIVES

    All Shuttle DTO's assigned to this flight were accomplished. The following DTO'srequired special test conditions or crew activity.

    External Tank Thermal Protection System Performance (DTO 0312) - This DTO required a+X translation after ET separation to photograph the ET thermal protection system.

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    10/14

    Waste and Supply Water Dumps(DTO0325) - Three test conditions were performed fromthe DTO'sset of required tests. All tests were waste water dumps, starting at anozzle temperature of I00 degrees. The first was a warm-attitude dumpwhich wasstopped at 50 percent. The second and third test conditions were combined into asingle dumpat a cold attitude, which was stopped at 66-percent remaining.MPSVacuumDumpTest (DTO0411) - This test required dumpingMPSoxygen through thefill and drain valves. It was a repeat of the test performed on STS51-J and wascompleted as planned.NoseWheel Steering Evaluation (DTO0515) - This test was performed during thelanding rollout. Real-time data and physical track data indicated nominal systemperformance. Crewcommentsand evaluation are required.Cabin Air Monitoring (DTO0623) - This test required sampling the cabin air with asolid sorbent sampler. This DTOis required on all Spacelab flights.Radiator Performance (DTO0624) - Onetest condition was performed from this DTO'sset of required tests. This was an evaluation of radiator performance in a -ZLVattitude with the radiators stowed followed by an evaluation of performance with theradiators deployed.Gravity Gradient Attitude Control (DTO0816) - Five test conditions were performedfrom this DTO's set of required tests. Each test required entry into gravity-gradient modeusing vernier reaction control system thrusters and all appear to havebeen successful.The following DTO's required no special test or crew activity other than thefunctioning of operational Instrumentation/modular auxiliary data system (OI/MADS)instrumentation and recorders.

    DTO No. Title

    0301030303070308031103190758

    Ascent Structural Capability EvaluationReinforced Carbon Carbon Life EvaluationEntry Structural CapabilityVibration and Acoustic EvaluationLongitudinal Oscillation (POGO) Stability PerformanceShuttle/Payload Low Frequency EnvironmentPayload Flight Control System (FCS) Dynamics Measurements

    Postflight analysis of data from these DTO's will be required. A MADS pulse codemodulation (PCM) master built-in test equipment (BITE) failed inflight and this mayindicate problems with the PCM data.

    ACIP data were recorded during OMS maneuvers to gather data on what the crew call"rough starts". Also, data were taken for DTO 0327, Waste Control System AirflowMeasurements, although the DTO itself was not assigned to this flight.

    NASA-JSC

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    11/14

    _ r/

    _J$C 20956 $T$ 61- ,t HLasto_ IIo_nt Distribution:

    NIOA HeedQunrter8 _:_ (oontinued)DE/ll. I t. Sohu lz e P2/L. Jenklne _lltan Stando_d/r_OSL6-4/G. L. Roth [P/C. A. Vou oh nLB-4/$. I. Mebster ZS/D. . Vide Hr. Vi1111 H. HavkLneHC8/H. Goeoer IrS/P. C. Glynn Sonlor AdvisorHO/[. Horkleroed (2) r_12/v. G. HoNullen (2) _kheed Conpo.otio.MP1-5/M. Hamby F.SO/J. &. kith P.O. Box 551HY/M. Frondnen r_3/L. D. Polaep _, CA 91529

    035/t. L. J_'mot.onQodd_rd 5pioe Flilht Center F.q6/R. 6alalunia _. Iliohaltd H. BstttnIlOO/V. [olthley [36/11. Jovoa (2) Aseoiloto _partae.t HoedqOO/L L, B4tmann [Z/V. . Chandlm" Charleo Stork Draper l_otow_, I04.?O0/J. H. Boookol I[ZID. H. G_wenohiolds 555 TeahnololW 5qmmo7lOft, E. Hubav F&/R. L. Berny Cmbriddo, Kt 0 2139730/E. I. Powers F&/J. R. Oomon731/E. M. Travis FD/$. 14. I[eathley Lt, Gen. Lolihtme_ T. Davis731/J. P. Touns FDIR. t. iqelbt_ul[Ee US/,F Clot,)7]lO/J. Bar_oklar_ (6) F04/C. F. Helen4 72 (] StolLeaoioh ]load, Four HIllo300/A, E. Joneo F96/5. llo_ris &lbuquo_que, BH 87123302/V. F, l_nl_lU Ftb'E. C. Lineberry, Jr. (8)750.2/_. E. rnegon lq(/E. It. Sahiosoav [_, Herbo_t [. Grloe313/Jt. 14u_riott Flt/[. N. NoRem-y Consultant313/J. Pe_k FO/J. [. Ha_er (2) 2223 Avonida do lo PloFo

    OA/A. D. Aldrich Suite 30_iOk/t. H. [ohro La Jolla, C1 92037-_q-D/$oopooltoey (_) _rlj. Presno11Jl_/LlbNmy (3) It". Zr_ GPant Hed_iQk

    _D I1_. L. |oineo Preoldontiol /_olstent fotpIleopooltory (30) NA/L. T. 5penne C_npon|_ ToohnoloEy[L611J. led',iil (S) Irl_'J. H. Levies Grummm AerOllpa_.e Corpo_stio_ID_3/P. _ (5) I_Y. J. idmm SethJ_e, MY 1171_Fk31/$. P. Ssu_hl_- S&/J. P. I[erw_nJAOI/J. A. Dopey S_D/S. L. PoOl Dr, 54_lour C. HImN1Sa25/O. [. _enaon _3/J. Onw_lol 12700 Lak* lvenue

    _I/M. lnteo_ dt501[_I_I [IOy l lole*rah Center SE/V. H. ;tuoh Lakevood, O_ lllllO_

    /Hail Stop _/. D. Porner CO)TO/L, S. ll_hol_oe Hr. John F. M_ormldTAI J. Hon e1 _m tt Yioe Peuid_nt-Toeh_lul Se_vlo_JRookvell-Oovnoy TJ_I. L. B1o_mt Tigeeie, Zoo.

    FA91,'Dota Nanqieat (90) TC2fll. Lambe_ (S) ]K)00Tor.th lo]rbou_.n ArmTC12/I. . httey Burbm_, CA 91505

    |o_mell-Houstoe T_/L. G. VllliemZC01/$. Stein (5) TI[JJ. F. GOPS4 Dr. _Oh_ 0. _tet_Z001/1. lrllleP 1_q/L. E. $ell Norther. oTri_ or Plan( mdZCOI/V. [, kith lq[q/A, Jool ]m Eu4letZ01/ D. Coro_edo 11(/A. a. Bild_op Te_emsee Volle7 iutbo_ty

    TK2tJ. hone [69_C 112 /L. [ o#H_ _00 Corn &venue S. Huntooo YO/D. . S_bultz ][nozvllle. 111 _7002[/A. Cohen VA/I. &. Colonn4J_. [. _a_losvorth Vl/t. V. Noor*b*_d l. Btm_tJUO/L, . Dun_itJ_ VI[/I. [. llotola Io_J 10/,23P_. alt_ (_) _. H. Teylor General Elo_tnil CO.LPq/N. [ewm_m 1Z3/P, N. DeaM _ Oivi_toe _ '_ . A. Setwil t_/N. i. Collin_. Jp. P.O. _oz $$55Bl_q/Hiotory Ofriee (2) VF2/V. J. Gsylm- Ph_laOelpl_Lt, PA 19101CMG. W. 3. lbb_7 W2/It. M. i _e toke (25)C&/I. L. C_ppen t72/a. JohnsonC_/J. v. Tounl F2/. Ceit_ Houston, 1_ 77058ClS/H. V. ao_tatLeld (8) tT_/J. [. Neohela7 itto: . Peto_CWI[. Colpn W'3/I. J. Hoed_&/[. F. I_eno _Fq/H. 6onn*au S. H447043JD. F. Fuddy 1r515. N. kad_b 6510 Te_t Vi_/2)6D&alJ. V. O'$olll fPI. N*collouah (3) Ir_ &FB. C& 9_S_3D_LS/_r. I. Loe I rPI 2_N. b_Lndl e_DAS/$. J. Sunean IrP3/N. . Coody D. NeCu_dyDAO)LI_ TIt/V. B. Milton Noil Stop q63DE/P. $. hrn*o ZR1/COZ. Op_on7 X. tilth Lan_le 7 tesoo_h ComtorDr6/D. hlsoe ' Zll/llaJ. Bsl L. honer Bampton. IM 23665OGLE. [. Hob Z]II/Lt. Col. Be Rm_lviek (2)UqAt. D. &nTdop Z112/_. Cobb (2) I_e_lquarte_l, Spl_e DlviolO_Deq/Z. B. PLppe_ BUB/P. _nett ()) &tt_: SDIGeCTDBqlJ. F. Haito17 _D/YOn Lt, J, Hablin8DM/J. C. B_pold Lo_ kngeles iF S_4_lm_/C. F. belto_i_ P.O. lloz 92960Dl6/ ll a_mmxl h lsoa MoPldmq Poe tal Cootor$C/V. e. 6u_r Los knples. CA goGOgI[C3_r. H. 8m_mski (2) D_. J. J. BunterI_.A/L. O. Caee]r Setl_l Ao_tt_l EMod)li_memtED3/L hi'ran iatt_mal Re_em_eh Coueoil of Cmmdem[/L $. Smr/_ Otteva, Conedo I[1A OR6EE/J. B. Jobnmm_/D. L. [nlsht Ja4m V4.111mm_/0. L, 8_s_,dt 1995 Fe_ndale PlmIDr_/. J. Stokep lhouund8 Oiul. CA 91)60D'II. N. [urtonD3Jl[. I. Nm_fiold D_. [. H. _t_abIDL_. J. Coo Uotlomtl io_t1[_ll btobllo/_mmtEHIO/R. 1. L_nd8 letional loseL'_ah Or Cam_k_EHIJZ. $. Chevmm Ottmm, Conedo El& Or6im2/p. C. _me_E]i]/S. Nu_eay (2) I_yl StpioklandeuO/D. Gilbert 3609 &nnedaie LanealSIJ. E, Teo lpt 112_/H. J. Bel _ne lul korammto, CA 9M21_P51. I. Gib_0_

    B. 1. Alk@_o_lotionll loronootie_l [otebliihe_nt|otlo_OI loaoonah Counoil OF _edoOttave, CAnado [li 016T. V. Uoshav (2)_PU ieroopone Limited1700 0mont Dr.Veoton. Tononto, Ontm_io. CAnedo HgEJ. N_ddloton_ll le_oopl@l Limited825 Colindonlo Ic_edTorero, Ontavio, Cineda N6B )Z8II, Pomt5907 Sunrll_e D_lveFilly, llol&ll Il. lotireorJH*ll Stop 818-5IUnnespol is - Honeyv411Aviooias Oivioi_13350 _ 19Cloavvet_m, In. 335_6C, Mlltm (k)Nell Stop 2q_-lqCede/O leaior_h Cento_No_rett Field, C A 9q015

    aq., IFTEC[lrklm_d _FB, l. Mix. 87117Ul_/OL-OF (2)Potpiok AFB, I_ ]2925ierolpine Cowpo_otiaeI. O. BOl 929S?_o a bp ln e, ca 90009Join: M. [, Haith, NSnltI k_ ene ll Doui loI -Houl to_D2J14. D. Pi p_mTOL/I. D. HookonbunyD. Ho lp a_il _totion 135-._M1Tlrd S_i tene1 _eoe Pe_,kledor_lo i. CA 90278[.. n. _kLM/Haii C4xle _36Zm _de.1322 Spane P ick _ivoBouatOno 1I 77054Jmene I. MmsnekMOO Oek Gpovo DmivePisedo,',% CA 91109T. _#ersI/ot4m leahr_lolly, lnl.13766 So. Hm*th_ne Bled.a_0 CA 90250I._b_avienZBN kil Co4e 0212I_22 3p_* Foul _lveliouotou. Tooas '_OS_D_. David ION Oletwe10 Eone Geovenamm EenkSkol_nene, Llmmluhiml|n|lm4

    IJk_& Ir,_,opnem le_oNmtotii_e/e _mm I_ul_m_yA_O I_v To_k, lit 097?7ll_ leoldlnt ll41t Of_lneilnneiIooedvtJk '1114 letlm_lindlJ, !, C_lt/, 6123/_1 (2)Loak_ a-t_autlne Divloloe&atline _nO. lnlomnetiae ContomP. O. bx 3SO_&dnn_le, CA 94088C_Snl _slU. $. k_q Lo$iotlu Coet_it to: iTCS_-PS/COl. Ser_qelFt. Lee, Vi 2,,38001-,6000

    Iotif_f _r2/l. V. ierl _ (rlr_-6353) of .my iorYeoti_ml, sdditioel. _ dlletlor_l to this Ult.

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    12/14

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    13/14

  • 8/7/2019 STS-61A National Space Transportation System Mission Report

    14/14