study on model and tests of sheet pile wall with a relieving...
TRANSCRIPT
Research ArticleStudy on Model and Tests of Sheet Pile Wall with aRelieving Platform
Ming Zhang1 Wei Wang 2 Ronghua Hu3 and Ziyi Wang4
1Institute of Civil Engineering Henan University of Engineering Xianghe Rd 1 Zhengzhou 451191 China2College of Architecture and Urban Planning Beijing University of Technology Pingleyuan Rd 100 Beijing 100124 China3Amer International Group Co Ltd West Hongli Rd 8133 Shenzhen 518040 China4College of Architecture and Civil Engineering Beijing University of Technology Pingleyuan Rd 100 Beijing 100124 China
Correspondence should be addressed to Wei Wang ieewwbjuteducn
Received 4 June 2020 Revised 23 August 2020 Accepted 6 September 2020 Published 18 September 2020
Academic Editor Hui Yao
Copyright copy 2020 Ming Zhang et al +is is an open access article distributed under the Creative Commons Attribution Licensewhich permits unrestricted use distribution and reproduction in any medium provided the original work is properly cited
A new type of retaining wall the sheet pile wall with a relieving platform is introduced in this paper Based on the prototyperetaining wall with a height of 12 meters the model tests with a geometric similarity ratio of 7 are designed and we focus on themodel production and analysis on the test results Some comparative analyses between the measured values and the calculationvalues by using the theoretical calculation method and finite difference method are carried out including Earth pressure behindthe wall prepile resistance force the bending moment and the deformation of rib pillars in the retaining wall +e results showthat Earth pressure behind the wall has a linear increase with the depth and lies between Rankine Earth pressure and Earthpressure at rest Moreover the prepile resistance force can be approximated by the m method and the bending moment can bealso used for approximate calculation by the mmethod and is larger than the results calculated by the finite differencemethod It isalso observed that there is a zero-displacement point on the pile bottom and the Earth pressure above the point behind the piledevelops from Earth pressure at rest to the active Earth pressure the Earth pressure under the point behind the pile develops fromEarth pressure at rest to the passive Earth pressure +erefore the Earth pressure behind the bottom wall is larger than thecalculated value by the Rankine theory Finally the displacement of the rib pillars is greater than the calculated results using thefinite differencemethod and exceeds the standard requirements owing to the failure of the retaining wall and the unloading boardneeds to be constructed to improve the retaining wallrsquos behaviour +ese findings verify the modelrsquos credibility and provide anunderpinning for studying the behavior of the retaining wall
1 Introduction
Currently the standard methods that have been used to in-vestigate and analyze the interaction between retaining structureand soil include model tests centrifugal tests field tests ana-lytical methods and numerical analysis Compared with theother tests such as centrifugal tests and field tests the modeltests have the advantages of excellent repeatability strong op-erability and unconstrained field conditions +us they aresuitable for studying the various influencing factors on theretaining structure and their complex mechanisms In additionthe model tests can adjust test parameters or change testconditions and investigate one or several factors intensively toreveal the nature of the problem of retaining structural
engineering +erefore model testing is considered as the mostimportant means to study complex engineering problemsparticularly in the areas of the new retaining structure [1 2]
With regard to the reinforced soil retaining wall (RSW) ithas become one of the Earthrsquos retaining structures that can beseen in geotechnical engineering since 1963 +e RSW securesstructural stability through the frictional force between thefoundation and the reinforcement by installing reinforcementsand walls simultaneously with the foundations [3] A series ofmodel tests have been conducted to investigate the failurephenomenon [4ndash7] the deformation behavior [3 7ndash9] andEarth pressure distributions [9 10] of the RSW Inclined Earthretaining (IER) structure is developed in order to improve themechanical properties of the existing Earth retaining method
HindawiAdvances in Civil EngineeringVolume 2020 Article ID 8894601 16 pageshttpsdoiorg10115520208894601
IER consists of three main structures front support backsupport and head binding and the back support is very effectivefor the reduction of the Earth pressure acting on the frontsupport and the lateral displacement of IER which has beenconfirmed by model tests [11 12] Assembled Earth Retainingwall (AER-wall) using back pile has been developed at PusanNational University Both cost and time have been significantlyreduced because AER-wall can be fabricated in a shop Also itsstability has been improved with a back-supporting beam re-ducing Earth pressure which has been confirmed by laboratorymodel tests and the lateral displacement of AER-wall signifi-cantly decreases with both inclined wall and back-supportingbeams [13] +e field model tests of AER-wall have beenperformed to confirm that the Earth pressure is considerablyreduced compared with the L-shaped retaining wall [14] Aprecast concrete double wall (PCDW) system is developed toimprove the productivity of conventional retaining wall [15]+e ARE-wall is composed of the PCDW system and retainingwall system which can contribute to securing integrity re-ducing the delay in construction and improving quality Anoverall process for themember design and construction stage ofthe ARE-wall system has been proposed and its improvementeffects are examined regarding various aspects in comparison tothe reinforced concrete method However no experimentalmethod has been used to determine the performance of theARE-wall
+e distribution of Earth pressure behind the cantileverretaining walls subjected to line loads has been predicted by acomparison between the conventional theories of Earthpressure and the finite element method [16] +e magnitudeand distribution of lateral Earth pressure of the cantileverretaining walls resting on clayey soil are studied by a series oftwo-dimensional plane-strain analyses and the finite ele-ment method [17] However the cantilever retaining wallcan be the most economical solution by adding relievingplatforms on the backfill side of the wall +e relievingplatforms have advantages of decreasing the lateral Earthpressure and increasing the overall stability of the retainingwall +e retaining wall is not a new type of construction incountries such as China Korea India and Russia Modeltests have been performed to determine the distribution ofthe Earth pressure and confirm the effect of decreasing thelateral Earth pressure on the retaining wall with relievingplatform [18ndash20] From the model tests comparisons be-tween the retaining wall with relieving platform and thecantilever retaining wall show that the reduction of thelateral Earth pressure and deformation of wall are indicatedclearly on the retaining wall with a relieving platform andthe overall stability is increased by the relieving platform[21] +e length and the location of the platform are the keyfactors influencing the lateral Earth pressure A sheet pileretaining wall is composed of a pile a retaining plate and arib pillar Its advantages include a small space for ar-rangement and no limitation on bearing capacity of thefoundation structure +e behavior of the contiguous boredpile retaining wall supporting system has been investigatedusing a physical model [22] and a series of plane-strainsmall-scale model tests on a piled retaining wall embeddedin sand under axial loads are performed in the laboratory
and the influence of the penetration depth pile stiffness andsand relative density on both ultimate axial capacity anddeformation behavior of the piled system has been evaluated[23]
Combining the advantages of the retaining wall withrelieving platforms and the sheet pile retaining wall thesheet pile wall with a relieving platform (shown in Figure 1)has been successfully used in various slope managementprojects in China +e retaining wall has the followingadvantages
(1) It has the advantages of the sheet pile retaining wallincluding a small space for arrangement good safetyand reliability and good durability
(2) +e Earth pressure behind the wall under theunloading board is reduced through the unloadingeffect of the unloading board
(3) +e unloading board provides a reverse bendingmoment to the rib pillars and piles therefore theinternal force distribution of the retaining wall tendsto be reasonable and the mechanical deformationcharacteristics of the retaining wall are optimized
(4) Due to the unloading effect of the unloading boardand its inverse bending moment to the wall theretaining wall is applicable to higher slope than thecantilever sheet pile retaining wall
(5) Compared with the reinforced soil retaining wall(RSW) the excavation space behind the wall is re-duced which has good adaptability to the site andhigh safety for long-term use
Currently both Chinese and international scholars andengineers have used simplified theoretical calculationmethods and numerical analysis to determine some pa-rameters and analyze the mechanical deformation prop-erties of the retaining structure+eoretical analysis has beenused to obtain the ratio between the reasonable unloadingboard buried depth and board width as well as the ratio ofheight between the upper wall and lower wall [24] Hu et al[25] developed the computational formula of the range valuefor unloading board width and computational formula of theminimum pile length Meanwhile the validity and credi-bility of computational formula for the minimum pile lengthwere verified through the data and example analysis Huet al [26] divided the sheet pile wall with a relieving platforminto loaded segment and anchored segment and developed aFEM numerical model to calculate the inner force anddeformation of the sheet pile with relieving platform and theeffectiveness of the calculation model was confirmed byusing FEM model and fielding monitoring data Hu et al[27] deduced the analytical formula for the deformation ofthe retaining wall based on elastic foundation beam methodand analyzed the influence of the diameter and length of pilethe proportional coefficient of foundation soil resistancecoefficient and the internal friction angle of the backfill onthe structural deformation +eir studies show that thelength of the unloading board has significant effective lowerand upper limit value
2 Advances in Civil Engineering
However there is no comprehensive and accurate cal-culation theory or method for the retaining wall structure+us this research conducted a model test study on the sheetpile wall with a relieving platform and provided a basis forthe design principles and calculation method of the retainingwall In this study the model pile box and the modelstructure of the sheet pile wall with a relieving platform weremade A test scheme was developed after determining themodel material model structure and size model loadingequipment and measurement system +is study found aseries of test results such as the Earth pressure behind thewall prepile resistance force the bending moment and thedeformation of rib pillars in the retaining wall +e analysisof the findings verified the credibility of the test model testdata and the test instrument A credibility test method wasthus provided for studying the mechanical and deformationcharacteristics of the sheet pile wall with a relieving platform
2 General Structure of Sheet Pile Wall with aRelieving Platform
Currently in China the sheet pile walls with the relievingplatform are generally used for retaining engineering andthey are ranging between 80m and 150m Figure 2 showsthe sheet pile wall structure with a relieving platform used inthe project with 12m support +is wall structure is used asthe prototype of the model testing +e mechanical pa-rameters of the retaining wall and characteristic parametersof the retaining wall structure are shown in Tables 1 and 2respectively
3 Similarity Coefficient of the Model
Using three similar theorems to calculate the similaritycoefficient λx of the same physical quantity in the prototypeand the model of the sheet pile wall with a relieving platform[28ndash32]
λx Xp
Xm (1)
In equation (1) x is any physical quantity the subscriptsldquoprdquo and ldquomrdquo represent the prototype and the model
respectively According to the catalogue of scaling laws [33]the theory of elasticity the theory of soil strength and a loadof sheet pile wall with a relieving platform and the similarrelationship of the main physical quantities are shown inTable 3 (the results are derived from Iai [34]) +e geometricsimilarity coefficient λ is 7 in this test Iai [34] studied thesimilarity relationship of each physical quantity in modeltest and the results showed that only the geometric simi-larity coefficient λ density similarity coefficient λρ andstrain similarity coefficient λε were independent in thephysical quantities in Table 3
4 Construction of the Test Model
41 Model Materials When soil materials are being se-lected the similarity coefficient λc of the soil specificgravity is made close to 1 in the prototype that is the
Counterfort
Pile foundation
Unloading board
Wall surface plate
Top beam
Figure 1 3D schematic diagram of the sheet pile wall with arelieving platform
Wall top or groundUpper wall plate
Lower wall column (plate)
39m
50m
70m
08m
90m
-12
0m
14m
Pile
Ground
Unloading board
Figure 2 +e cross section of sheet pile wall with a relievingplatform in a project
Table 1 Mechanical parameters of the sheet pile wall with therelieving platform
Items E (MPa) Μ ρ (kgm3) c (kPa) φ (deg)Pile foundation 280000 020 25000 mdash mdashTop beam 280000 020 25000 mdash mdashRib pillar 280000 020 25000 mdash mdashWall surface plate 280000 020 25000 mdash mdashUnloading board 280000 020 25000 mdash mdashFill soil (stone powder) 800 028 24000 10 350Soil between piles 300 030 18000 280 160
Advances in Civil Engineering 3
similarity coefficient λE of the elastic modulus is madeclose to 7 and the medium-coarse sand is selected as thefill soil and soil between piles in the model test A series ofphysical and mechanical tests including specific gravitytest the maximum and minimum dry density test directshear test particle separation test and water content testare completed in the geotechnical laboratory of CivilEngineering Department of Shenzhen University inChina +e physical and mechanical parameters of themedium-coarse sand are as shown in Table 4 +e gradingcurve is shown in Figure 3
Steel polymethyl methacrylate (PMMA) gypsum andfine-aggregate reinforced concrete are considered when themodel material for the retaining wall is selected +estructural material of the prototype retaining wall is thereinforced concrete as it is in an elastic state under normalworking conditions Owing to its characteristic of being easyto produce and simulate a steel is chosen as the modelmaterial for the retaining wall Corresponding to each part ofthe prototype structure the circular steel pipe pile is usedwhile the square steel pipe is applied in the pillar ribs +echannel steel and steel plates are applied in the unloadingboard
42 Model Structure Size
421 Size and Construction of the Model Test Box +eprototype retaining wall is 12m high the piles have 3m
spacing and the filling height is 12m +e horizontal widthof the prototype retaining wall is 125m Accordingly themodel test box is 20m wide and 4 piles are simulated +elongitudinal length of the test box is determined by thespatial dimension calculated using the sliding plane of theactive Earth pressure and the passive Earth pressure +erelationship between the prototype size and model size isshown in Table 5 and Figure 4
In this study the size of the model test box is 65m(length) times 20m (width) times 40m (height) +e real figure ofthe model test box is shown in Figure 5 Due to the highstructural model of the retaining wall the model box is fixedfirmly into the ground for easy testing and operation Fouranchor fixing bolts are prescrewed into the top of the modeltest box to secure the reaction frame
422 Size of Model Structure and Production According tothe characteristic parameters of the retaining wall in Table 2and the similarity relationship in Table 3 the characteristicparameters of the retaining wall structure are shown inTable 6
In the equivalent calculation several aspects should bestated [35]
(1) Assume that (EI)p and (EI)m are the actual stiffnessesof the prototype structure and model structure re-spectively while (EI)acutep and (EI)acutem are the stiffnessesof unit width in the prototype structure and model
Table 2 Characteristic parameters of the sheet pile wall with the relieving platform
Components Concreteno
Sectiondimension
(m)
Sectionmoment ofinertia (m4)
Stiffness(Nmiddotm2) (E)
Stiffness inunit width(Nmiddotm2m)
Calculativewidth (m) Remarks
Pilefoundation C25 Pile diameter
14 021 499 163E9 3Reinforcement ratio is
considered as the calculatingmoment of inertia
Rib pillar C25 08times11 005 149 467E8 3Upper base multiplied by thelower base for equivalent
calculationUnloadingboard C25 05times 30 003125 8758 292E8 3 +ickness multiplied by the
width
Top beam C25 16times 08 00683 1919 mdash mdash Rectangle length multipliedby the height
Wall surfaceplate C25 12times 03 00027 7568 252E8 3 Rectangle height multiplied
by the thickness
Table 3 +e similar relationship of the main physical quantities
Symbols Physical quantity Similarity relation (prototype model) Test valuel Length (geometry size) Λe 7ρ Density λρ 1q Load (area force) λλρ 7ε Strain λε 1σ Stress λλρ 7s Displacement λλε 7EI Flexural rigidity with unit width λ4λρλε 2401M Bending moment with unit width λ3λρ 343φ Internal friction angle of soil λφ 1
4 Advances in Civil Engineering
structure respectively +e following equation isshown in Table 3
(EI)primem (EI)primep
ρconcreteρsteel( 1113857λ41113872 1113873 (2)
(2) +e unit width of the model is 17 of the prototypewidth that is 3m7asymp 043m In order to expand themeasurement displacement and facilitate the
generating of the structural model the pile spacing inthe model is 06 meters
(3) +e unit width stiffness of a 5mm thick steel plate isnegligible compared to the unit width stiffness of thechannel steel
(4) In the equivalent calculation of the retainingplate the parameters of the wooden board are asfollows [36] Eboard 275 GPa and ρboard 600 kgm3
0
10
20
30
40
50
60
70
80
90
100
000100100100100010000Particle size (mm)
Soil
part
icle
qua
lity
perc
enta
gepa
ssin
g a p
artic
le si
ze
Sample ASample BSample C
Figure 3 Grading curve
Table 4 Physical and mechanical parameters of the medium-coarse sand
Items E (MPa) Μ ρd (kgm3) φ (deg) Specificgravity
Moisturecontent ()
Coefficient ofuniformity Cu Coefficient of curvature Cc
Medium-coarse sand 15 030 15910 358 2653 12 286 092
Table 5 +e relationship between the prototype size and model size
ItemsPile
length(m)
Height of theretaining wall
(m)
Horizontalwidth (m)
Longitudinal length(m)
RemarksLengthbeforethe pile
Lengthafter thepile
Prototype 120 120 125 (width of 4piles) mdash mdash +e longitudinal length of the model is calculated and
determined by the sand parametersModel 170 170 20 (width of 4piles) 375 275
Advances in Civil Engineering 5
+e front elevation drawing and profile drawing of themodel structure are shown in Figure 6 while the realfigure of the model structure is illustrated in Figure 7
43 Loading Equipment and MeasurementSystem of the Test Model
431 Loading Equipment of the Test Model In the modeltests the air pressure load is used to simulate the load on thetop of the wall +e loading equipment is shown in Figure 8+e test is undertaken among five levels from 10 kPa to50 kPa with each level increasing by 10 kPa
It is found that the air pressure load has two advantages(1) When the load is unloaded the load transmission isconsistent and continuous without impact (2) Its airpressure valve can be adjusted to maintain the load stabilityof each stage load +e magnitude of the change can becontrolled within the range of plusmn01 kPa
432 Measurement System +e layout of the selected Earthpressure measuring equipment is shown in Figure 9
+e test data present the Earth pressure in the upper andlower walls It is found that the measured Earth pressurebefore and after the pile foundation is the Earth pressure onthe pile not the average Earth pressure in the two piles +e
Wall height 4000
300
2000
300
300 3003750 2750
Wall height 2000
(a)
300
2000
1700
Top of sandfilling
P
Sand filling
Active failure surface
Top of sand fillingModel channel boundary
Passive failure surface
ψ = 358deg
45deg + ψ2
45deg ndash ψ2Model channel boundary
2000 17
0030
0
Model channel boundary42791 332209
D le 200189339 85661-D
3750 2750
ψ = 358deg
(b)
Figure 4 +e dimension of model test box (a) Planar graph (b) Profile drawing (the unit of the dimension is mm)
Anchor fixing bolts Anchor fixing bolts
Figure 5 +e real figure of model test box
6 Advances in Civil Engineering
conversion equation (3) is used to transform the measuredvalue
P1 P0d
b (3)
In equation (3) P0 is the measured Earth pressure beforeand after the pile P1 is the average Earth pressure in the twopiles d is the pile diameter and b is the pile spacing
+e strain gauges are set up in the maximal internal forceside of the pile and rib pillar in the retaining wall+e layoutsof strain gauges are shown in Figure 10 After measuring thestrain the moment at each measurement point of the pile iscalculated [37]
Mxz EIεy
(d2) (4)
In equation (4) εy is the compressive (tensile) strain atthe measurement point E is the elastic modulus of the pileand I is the moment of inertia of the cross section of the pile+e directions represented by x y and z are shown inFigure 11
By using the displacement measurement the dial indicatorwith a range of 30mm and an accuracy of 001mm is selectedWith the finite element method the maximum displacement ofthe top of the retaining wall is 208mm when it is in the mostunsafe environment (without the unloading board) Assumingthat the pile bottom is fixed the maximum displacement at the
Table 6 Characteristic parameters of retaining wall model structure
Components
Required flexuralrigidity with unitwidth (Nmiddotm2m)
(E)
Calculationwidth (m)
Sectionproperty ofmaterials
Sectiondimension ofmaterials (mm)
Selected flexuralrigidity with unit
width (Nmiddotm2m) (E)Remarks
Pile 6795 06 Circular steelpipe 159times 5 7205 Outer
diametertimes thickness
Rib pillar 1945 06 Square steelpipe 100times 25 2155 Outer
diametertimes thickness
Unloadingboard 1225 06
Channel steeland steelplate
Channel10 + 5mm steel
plate1025 Small stiffness of channel
steel
Top beam 8195 mdash Square steelpipe 250times 5 9815 mdash
Retainingplate 1055 06 Wooden
board +ickness 36 1155+ickness 18mmoverlapped wooden
board
Square steel pipe100 times 25
10
Slot
Steel plate thickness 5
Wooden board thickness 18
Welding plate thickness 10
Continuous connectionSquare steel pipe 250 times 5
Steel pipe 159 times 5
530
300
300
350
300
300
1650
250
1500
100 600 600 600 1002000
(a)
700
100
850
250
150017
5034
0016
50
Support baseboardthickness 5
Square steel pipe100 times 25
2M16
Steel pipe159 times 5
Square steel pipe 250 times 5 Continuous connection
Support baseboard thickness 8Wooden board thickness 18
Welding plate
Steel plate thickness 5
10Equal leg angle steel 100 times 5
(b)
Figure 6 Front elevation drawing and profile drawing of model structure (a) Front elevation drawing (b) Profile drawing (the unit of thedimension mm)
Advances in Civil Engineering 7
top of the retaining wall is calculated as 144mm It is consistentwithin an environment with only one supported beam+erefore the meter of the dial gauge has a full scale of 30mm+e dial indicator is fixed by using the magnetic gauge seat andensuring that the extendable rods are tipped on the square steeltubular It is found that the retaining wall is deflected with theincreasing thickness of the sand layer Moreover the dial in-dicator can be used tomeasure the displacement of the retainingwall simultaneously At the time of testing there are ten hor-izontal displacement measuring points on the rib pillar Ten dialindicators are installed to measure the horizontal displacementof the retaining wall +e layout and number of displacementmeasurement points are shown in Figure 12
433 Data Acquisition and Processing System Earth pres-sure and strain data acquisition are equipped with the au-tomatic acquisition of artificial guards Moreover theautomatic collection box is equipped with an accumulatorand a module that automatically controls the measurementof the sensor within a specified time +e measurementresults are first saved in the vibrating wire sensor (as shownin Figure 13) which is connected to an external data col-lection box +en the automatic dynamic monitoring of thenetwork is implemented Finally the data acquisition system
software is used to aggregate data collected in various modesinto a database and further display and process taskswitching Measurement data is saved in an Excel spread-sheet for subsequent analysis and processing +e schematicdiagram of data transmission collection and processingswitching work is shown in Figure 14
5 Test Scheme
A total of 28 grouping model tests are conducted one grouptest without the unloading board 18 group comparison testswithout external loading and 9 group external load com-parison tests +e combination of tests is shown in Table 7and the parameters are shown in Figure 15
A retaining wall model test without the unloading boardis performed firstly +e test has four purposes First it isused to verify the validity and reliability of the test instru-ment Second it is known that the structure of the retainingwall without the unloading board is relatively simple +usthe accuracy of the measurement data of the retaining wallmodel is verified by comparing them with the results fromother theories +ird in comparison with the results of thetest model of the unloading board retaining wall theunloading effect of the unloading board is analyzed that is
Rib pillar
Top beam
Pile
(a)
Unloading board(channel steel + steel plate)
(b)
Figure 7 Real figure of model structure (a) Real figure 1 (b) Real figure 2
Reducingvalve
Inlet valve
PipeSnuffle valve
Air pressure gauge
Pressurized air bags
Airpressure
gauge
Reactionwoodenboard
Anchor fixing boltReaction frame (channel steel)
Aircompressor
Figure 8 Schematic diagram of air pressure loading
8 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
IER consists of three main structures front support backsupport and head binding and the back support is very effectivefor the reduction of the Earth pressure acting on the frontsupport and the lateral displacement of IER which has beenconfirmed by model tests [11 12] Assembled Earth Retainingwall (AER-wall) using back pile has been developed at PusanNational University Both cost and time have been significantlyreduced because AER-wall can be fabricated in a shop Also itsstability has been improved with a back-supporting beam re-ducing Earth pressure which has been confirmed by laboratorymodel tests and the lateral displacement of AER-wall signifi-cantly decreases with both inclined wall and back-supportingbeams [13] +e field model tests of AER-wall have beenperformed to confirm that the Earth pressure is considerablyreduced compared with the L-shaped retaining wall [14] Aprecast concrete double wall (PCDW) system is developed toimprove the productivity of conventional retaining wall [15]+e ARE-wall is composed of the PCDW system and retainingwall system which can contribute to securing integrity re-ducing the delay in construction and improving quality Anoverall process for themember design and construction stage ofthe ARE-wall system has been proposed and its improvementeffects are examined regarding various aspects in comparison tothe reinforced concrete method However no experimentalmethod has been used to determine the performance of theARE-wall
+e distribution of Earth pressure behind the cantileverretaining walls subjected to line loads has been predicted by acomparison between the conventional theories of Earthpressure and the finite element method [16] +e magnitudeand distribution of lateral Earth pressure of the cantileverretaining walls resting on clayey soil are studied by a series oftwo-dimensional plane-strain analyses and the finite ele-ment method [17] However the cantilever retaining wallcan be the most economical solution by adding relievingplatforms on the backfill side of the wall +e relievingplatforms have advantages of decreasing the lateral Earthpressure and increasing the overall stability of the retainingwall +e retaining wall is not a new type of construction incountries such as China Korea India and Russia Modeltests have been performed to determine the distribution ofthe Earth pressure and confirm the effect of decreasing thelateral Earth pressure on the retaining wall with relievingplatform [18ndash20] From the model tests comparisons be-tween the retaining wall with relieving platform and thecantilever retaining wall show that the reduction of thelateral Earth pressure and deformation of wall are indicatedclearly on the retaining wall with a relieving platform andthe overall stability is increased by the relieving platform[21] +e length and the location of the platform are the keyfactors influencing the lateral Earth pressure A sheet pileretaining wall is composed of a pile a retaining plate and arib pillar Its advantages include a small space for ar-rangement and no limitation on bearing capacity of thefoundation structure +e behavior of the contiguous boredpile retaining wall supporting system has been investigatedusing a physical model [22] and a series of plane-strainsmall-scale model tests on a piled retaining wall embeddedin sand under axial loads are performed in the laboratory
and the influence of the penetration depth pile stiffness andsand relative density on both ultimate axial capacity anddeformation behavior of the piled system has been evaluated[23]
Combining the advantages of the retaining wall withrelieving platforms and the sheet pile retaining wall thesheet pile wall with a relieving platform (shown in Figure 1)has been successfully used in various slope managementprojects in China +e retaining wall has the followingadvantages
(1) It has the advantages of the sheet pile retaining wallincluding a small space for arrangement good safetyand reliability and good durability
(2) +e Earth pressure behind the wall under theunloading board is reduced through the unloadingeffect of the unloading board
(3) +e unloading board provides a reverse bendingmoment to the rib pillars and piles therefore theinternal force distribution of the retaining wall tendsto be reasonable and the mechanical deformationcharacteristics of the retaining wall are optimized
(4) Due to the unloading effect of the unloading boardand its inverse bending moment to the wall theretaining wall is applicable to higher slope than thecantilever sheet pile retaining wall
(5) Compared with the reinforced soil retaining wall(RSW) the excavation space behind the wall is re-duced which has good adaptability to the site andhigh safety for long-term use
Currently both Chinese and international scholars andengineers have used simplified theoretical calculationmethods and numerical analysis to determine some pa-rameters and analyze the mechanical deformation prop-erties of the retaining structure+eoretical analysis has beenused to obtain the ratio between the reasonable unloadingboard buried depth and board width as well as the ratio ofheight between the upper wall and lower wall [24] Hu et al[25] developed the computational formula of the range valuefor unloading board width and computational formula of theminimum pile length Meanwhile the validity and credi-bility of computational formula for the minimum pile lengthwere verified through the data and example analysis Huet al [26] divided the sheet pile wall with a relieving platforminto loaded segment and anchored segment and developed aFEM numerical model to calculate the inner force anddeformation of the sheet pile with relieving platform and theeffectiveness of the calculation model was confirmed byusing FEM model and fielding monitoring data Hu et al[27] deduced the analytical formula for the deformation ofthe retaining wall based on elastic foundation beam methodand analyzed the influence of the diameter and length of pilethe proportional coefficient of foundation soil resistancecoefficient and the internal friction angle of the backfill onthe structural deformation +eir studies show that thelength of the unloading board has significant effective lowerand upper limit value
2 Advances in Civil Engineering
However there is no comprehensive and accurate cal-culation theory or method for the retaining wall structure+us this research conducted a model test study on the sheetpile wall with a relieving platform and provided a basis forthe design principles and calculation method of the retainingwall In this study the model pile box and the modelstructure of the sheet pile wall with a relieving platform weremade A test scheme was developed after determining themodel material model structure and size model loadingequipment and measurement system +is study found aseries of test results such as the Earth pressure behind thewall prepile resistance force the bending moment and thedeformation of rib pillars in the retaining wall +e analysisof the findings verified the credibility of the test model testdata and the test instrument A credibility test method wasthus provided for studying the mechanical and deformationcharacteristics of the sheet pile wall with a relieving platform
2 General Structure of Sheet Pile Wall with aRelieving Platform
Currently in China the sheet pile walls with the relievingplatform are generally used for retaining engineering andthey are ranging between 80m and 150m Figure 2 showsthe sheet pile wall structure with a relieving platform used inthe project with 12m support +is wall structure is used asthe prototype of the model testing +e mechanical pa-rameters of the retaining wall and characteristic parametersof the retaining wall structure are shown in Tables 1 and 2respectively
3 Similarity Coefficient of the Model
Using three similar theorems to calculate the similaritycoefficient λx of the same physical quantity in the prototypeand the model of the sheet pile wall with a relieving platform[28ndash32]
λx Xp
Xm (1)
In equation (1) x is any physical quantity the subscriptsldquoprdquo and ldquomrdquo represent the prototype and the model
respectively According to the catalogue of scaling laws [33]the theory of elasticity the theory of soil strength and a loadof sheet pile wall with a relieving platform and the similarrelationship of the main physical quantities are shown inTable 3 (the results are derived from Iai [34]) +e geometricsimilarity coefficient λ is 7 in this test Iai [34] studied thesimilarity relationship of each physical quantity in modeltest and the results showed that only the geometric simi-larity coefficient λ density similarity coefficient λρ andstrain similarity coefficient λε were independent in thephysical quantities in Table 3
4 Construction of the Test Model
41 Model Materials When soil materials are being se-lected the similarity coefficient λc of the soil specificgravity is made close to 1 in the prototype that is the
Counterfort
Pile foundation
Unloading board
Wall surface plate
Top beam
Figure 1 3D schematic diagram of the sheet pile wall with arelieving platform
Wall top or groundUpper wall plate
Lower wall column (plate)
39m
50m
70m
08m
90m
-12
0m
14m
Pile
Ground
Unloading board
Figure 2 +e cross section of sheet pile wall with a relievingplatform in a project
Table 1 Mechanical parameters of the sheet pile wall with therelieving platform
Items E (MPa) Μ ρ (kgm3) c (kPa) φ (deg)Pile foundation 280000 020 25000 mdash mdashTop beam 280000 020 25000 mdash mdashRib pillar 280000 020 25000 mdash mdashWall surface plate 280000 020 25000 mdash mdashUnloading board 280000 020 25000 mdash mdashFill soil (stone powder) 800 028 24000 10 350Soil between piles 300 030 18000 280 160
Advances in Civil Engineering 3
similarity coefficient λE of the elastic modulus is madeclose to 7 and the medium-coarse sand is selected as thefill soil and soil between piles in the model test A series ofphysical and mechanical tests including specific gravitytest the maximum and minimum dry density test directshear test particle separation test and water content testare completed in the geotechnical laboratory of CivilEngineering Department of Shenzhen University inChina +e physical and mechanical parameters of themedium-coarse sand are as shown in Table 4 +e gradingcurve is shown in Figure 3
Steel polymethyl methacrylate (PMMA) gypsum andfine-aggregate reinforced concrete are considered when themodel material for the retaining wall is selected +estructural material of the prototype retaining wall is thereinforced concrete as it is in an elastic state under normalworking conditions Owing to its characteristic of being easyto produce and simulate a steel is chosen as the modelmaterial for the retaining wall Corresponding to each part ofthe prototype structure the circular steel pipe pile is usedwhile the square steel pipe is applied in the pillar ribs +echannel steel and steel plates are applied in the unloadingboard
42 Model Structure Size
421 Size and Construction of the Model Test Box +eprototype retaining wall is 12m high the piles have 3m
spacing and the filling height is 12m +e horizontal widthof the prototype retaining wall is 125m Accordingly themodel test box is 20m wide and 4 piles are simulated +elongitudinal length of the test box is determined by thespatial dimension calculated using the sliding plane of theactive Earth pressure and the passive Earth pressure +erelationship between the prototype size and model size isshown in Table 5 and Figure 4
In this study the size of the model test box is 65m(length) times 20m (width) times 40m (height) +e real figure ofthe model test box is shown in Figure 5 Due to the highstructural model of the retaining wall the model box is fixedfirmly into the ground for easy testing and operation Fouranchor fixing bolts are prescrewed into the top of the modeltest box to secure the reaction frame
422 Size of Model Structure and Production According tothe characteristic parameters of the retaining wall in Table 2and the similarity relationship in Table 3 the characteristicparameters of the retaining wall structure are shown inTable 6
In the equivalent calculation several aspects should bestated [35]
(1) Assume that (EI)p and (EI)m are the actual stiffnessesof the prototype structure and model structure re-spectively while (EI)acutep and (EI)acutem are the stiffnessesof unit width in the prototype structure and model
Table 2 Characteristic parameters of the sheet pile wall with the relieving platform
Components Concreteno
Sectiondimension
(m)
Sectionmoment ofinertia (m4)
Stiffness(Nmiddotm2) (E)
Stiffness inunit width(Nmiddotm2m)
Calculativewidth (m) Remarks
Pilefoundation C25 Pile diameter
14 021 499 163E9 3Reinforcement ratio is
considered as the calculatingmoment of inertia
Rib pillar C25 08times11 005 149 467E8 3Upper base multiplied by thelower base for equivalent
calculationUnloadingboard C25 05times 30 003125 8758 292E8 3 +ickness multiplied by the
width
Top beam C25 16times 08 00683 1919 mdash mdash Rectangle length multipliedby the height
Wall surfaceplate C25 12times 03 00027 7568 252E8 3 Rectangle height multiplied
by the thickness
Table 3 +e similar relationship of the main physical quantities
Symbols Physical quantity Similarity relation (prototype model) Test valuel Length (geometry size) Λe 7ρ Density λρ 1q Load (area force) λλρ 7ε Strain λε 1σ Stress λλρ 7s Displacement λλε 7EI Flexural rigidity with unit width λ4λρλε 2401M Bending moment with unit width λ3λρ 343φ Internal friction angle of soil λφ 1
4 Advances in Civil Engineering
structure respectively +e following equation isshown in Table 3
(EI)primem (EI)primep
ρconcreteρsteel( 1113857λ41113872 1113873 (2)
(2) +e unit width of the model is 17 of the prototypewidth that is 3m7asymp 043m In order to expand themeasurement displacement and facilitate the
generating of the structural model the pile spacing inthe model is 06 meters
(3) +e unit width stiffness of a 5mm thick steel plate isnegligible compared to the unit width stiffness of thechannel steel
(4) In the equivalent calculation of the retainingplate the parameters of the wooden board are asfollows [36] Eboard 275 GPa and ρboard 600 kgm3
0
10
20
30
40
50
60
70
80
90
100
000100100100100010000Particle size (mm)
Soil
part
icle
qua
lity
perc
enta
gepa
ssin
g a p
artic
le si
ze
Sample ASample BSample C
Figure 3 Grading curve
Table 4 Physical and mechanical parameters of the medium-coarse sand
Items E (MPa) Μ ρd (kgm3) φ (deg) Specificgravity
Moisturecontent ()
Coefficient ofuniformity Cu Coefficient of curvature Cc
Medium-coarse sand 15 030 15910 358 2653 12 286 092
Table 5 +e relationship between the prototype size and model size
ItemsPile
length(m)
Height of theretaining wall
(m)
Horizontalwidth (m)
Longitudinal length(m)
RemarksLengthbeforethe pile
Lengthafter thepile
Prototype 120 120 125 (width of 4piles) mdash mdash +e longitudinal length of the model is calculated and
determined by the sand parametersModel 170 170 20 (width of 4piles) 375 275
Advances in Civil Engineering 5
+e front elevation drawing and profile drawing of themodel structure are shown in Figure 6 while the realfigure of the model structure is illustrated in Figure 7
43 Loading Equipment and MeasurementSystem of the Test Model
431 Loading Equipment of the Test Model In the modeltests the air pressure load is used to simulate the load on thetop of the wall +e loading equipment is shown in Figure 8+e test is undertaken among five levels from 10 kPa to50 kPa with each level increasing by 10 kPa
It is found that the air pressure load has two advantages(1) When the load is unloaded the load transmission isconsistent and continuous without impact (2) Its airpressure valve can be adjusted to maintain the load stabilityof each stage load +e magnitude of the change can becontrolled within the range of plusmn01 kPa
432 Measurement System +e layout of the selected Earthpressure measuring equipment is shown in Figure 9
+e test data present the Earth pressure in the upper andlower walls It is found that the measured Earth pressurebefore and after the pile foundation is the Earth pressure onthe pile not the average Earth pressure in the two piles +e
Wall height 4000
300
2000
300
300 3003750 2750
Wall height 2000
(a)
300
2000
1700
Top of sandfilling
P
Sand filling
Active failure surface
Top of sand fillingModel channel boundary
Passive failure surface
ψ = 358deg
45deg + ψ2
45deg ndash ψ2Model channel boundary
2000 17
0030
0
Model channel boundary42791 332209
D le 200189339 85661-D
3750 2750
ψ = 358deg
(b)
Figure 4 +e dimension of model test box (a) Planar graph (b) Profile drawing (the unit of the dimension is mm)
Anchor fixing bolts Anchor fixing bolts
Figure 5 +e real figure of model test box
6 Advances in Civil Engineering
conversion equation (3) is used to transform the measuredvalue
P1 P0d
b (3)
In equation (3) P0 is the measured Earth pressure beforeand after the pile P1 is the average Earth pressure in the twopiles d is the pile diameter and b is the pile spacing
+e strain gauges are set up in the maximal internal forceside of the pile and rib pillar in the retaining wall+e layoutsof strain gauges are shown in Figure 10 After measuring thestrain the moment at each measurement point of the pile iscalculated [37]
Mxz EIεy
(d2) (4)
In equation (4) εy is the compressive (tensile) strain atthe measurement point E is the elastic modulus of the pileand I is the moment of inertia of the cross section of the pile+e directions represented by x y and z are shown inFigure 11
By using the displacement measurement the dial indicatorwith a range of 30mm and an accuracy of 001mm is selectedWith the finite element method the maximum displacement ofthe top of the retaining wall is 208mm when it is in the mostunsafe environment (without the unloading board) Assumingthat the pile bottom is fixed the maximum displacement at the
Table 6 Characteristic parameters of retaining wall model structure
Components
Required flexuralrigidity with unitwidth (Nmiddotm2m)
(E)
Calculationwidth (m)
Sectionproperty ofmaterials
Sectiondimension ofmaterials (mm)
Selected flexuralrigidity with unit
width (Nmiddotm2m) (E)Remarks
Pile 6795 06 Circular steelpipe 159times 5 7205 Outer
diametertimes thickness
Rib pillar 1945 06 Square steelpipe 100times 25 2155 Outer
diametertimes thickness
Unloadingboard 1225 06
Channel steeland steelplate
Channel10 + 5mm steel
plate1025 Small stiffness of channel
steel
Top beam 8195 mdash Square steelpipe 250times 5 9815 mdash
Retainingplate 1055 06 Wooden
board +ickness 36 1155+ickness 18mmoverlapped wooden
board
Square steel pipe100 times 25
10
Slot
Steel plate thickness 5
Wooden board thickness 18
Welding plate thickness 10
Continuous connectionSquare steel pipe 250 times 5
Steel pipe 159 times 5
530
300
300
350
300
300
1650
250
1500
100 600 600 600 1002000
(a)
700
100
850
250
150017
5034
0016
50
Support baseboardthickness 5
Square steel pipe100 times 25
2M16
Steel pipe159 times 5
Square steel pipe 250 times 5 Continuous connection
Support baseboard thickness 8Wooden board thickness 18
Welding plate
Steel plate thickness 5
10Equal leg angle steel 100 times 5
(b)
Figure 6 Front elevation drawing and profile drawing of model structure (a) Front elevation drawing (b) Profile drawing (the unit of thedimension mm)
Advances in Civil Engineering 7
top of the retaining wall is calculated as 144mm It is consistentwithin an environment with only one supported beam+erefore the meter of the dial gauge has a full scale of 30mm+e dial indicator is fixed by using the magnetic gauge seat andensuring that the extendable rods are tipped on the square steeltubular It is found that the retaining wall is deflected with theincreasing thickness of the sand layer Moreover the dial in-dicator can be used tomeasure the displacement of the retainingwall simultaneously At the time of testing there are ten hor-izontal displacement measuring points on the rib pillar Ten dialindicators are installed to measure the horizontal displacementof the retaining wall +e layout and number of displacementmeasurement points are shown in Figure 12
433 Data Acquisition and Processing System Earth pres-sure and strain data acquisition are equipped with the au-tomatic acquisition of artificial guards Moreover theautomatic collection box is equipped with an accumulatorand a module that automatically controls the measurementof the sensor within a specified time +e measurementresults are first saved in the vibrating wire sensor (as shownin Figure 13) which is connected to an external data col-lection box +en the automatic dynamic monitoring of thenetwork is implemented Finally the data acquisition system
software is used to aggregate data collected in various modesinto a database and further display and process taskswitching Measurement data is saved in an Excel spread-sheet for subsequent analysis and processing +e schematicdiagram of data transmission collection and processingswitching work is shown in Figure 14
5 Test Scheme
A total of 28 grouping model tests are conducted one grouptest without the unloading board 18 group comparison testswithout external loading and 9 group external load com-parison tests +e combination of tests is shown in Table 7and the parameters are shown in Figure 15
A retaining wall model test without the unloading boardis performed firstly +e test has four purposes First it isused to verify the validity and reliability of the test instru-ment Second it is known that the structure of the retainingwall without the unloading board is relatively simple +usthe accuracy of the measurement data of the retaining wallmodel is verified by comparing them with the results fromother theories +ird in comparison with the results of thetest model of the unloading board retaining wall theunloading effect of the unloading board is analyzed that is
Rib pillar
Top beam
Pile
(a)
Unloading board(channel steel + steel plate)
(b)
Figure 7 Real figure of model structure (a) Real figure 1 (b) Real figure 2
Reducingvalve
Inlet valve
PipeSnuffle valve
Air pressure gauge
Pressurized air bags
Airpressure
gauge
Reactionwoodenboard
Anchor fixing boltReaction frame (channel steel)
Aircompressor
Figure 8 Schematic diagram of air pressure loading
8 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
However there is no comprehensive and accurate cal-culation theory or method for the retaining wall structure+us this research conducted a model test study on the sheetpile wall with a relieving platform and provided a basis forthe design principles and calculation method of the retainingwall In this study the model pile box and the modelstructure of the sheet pile wall with a relieving platform weremade A test scheme was developed after determining themodel material model structure and size model loadingequipment and measurement system +is study found aseries of test results such as the Earth pressure behind thewall prepile resistance force the bending moment and thedeformation of rib pillars in the retaining wall +e analysisof the findings verified the credibility of the test model testdata and the test instrument A credibility test method wasthus provided for studying the mechanical and deformationcharacteristics of the sheet pile wall with a relieving platform
2 General Structure of Sheet Pile Wall with aRelieving Platform
Currently in China the sheet pile walls with the relievingplatform are generally used for retaining engineering andthey are ranging between 80m and 150m Figure 2 showsthe sheet pile wall structure with a relieving platform used inthe project with 12m support +is wall structure is used asthe prototype of the model testing +e mechanical pa-rameters of the retaining wall and characteristic parametersof the retaining wall structure are shown in Tables 1 and 2respectively
3 Similarity Coefficient of the Model
Using three similar theorems to calculate the similaritycoefficient λx of the same physical quantity in the prototypeand the model of the sheet pile wall with a relieving platform[28ndash32]
λx Xp
Xm (1)
In equation (1) x is any physical quantity the subscriptsldquoprdquo and ldquomrdquo represent the prototype and the model
respectively According to the catalogue of scaling laws [33]the theory of elasticity the theory of soil strength and a loadof sheet pile wall with a relieving platform and the similarrelationship of the main physical quantities are shown inTable 3 (the results are derived from Iai [34]) +e geometricsimilarity coefficient λ is 7 in this test Iai [34] studied thesimilarity relationship of each physical quantity in modeltest and the results showed that only the geometric simi-larity coefficient λ density similarity coefficient λρ andstrain similarity coefficient λε were independent in thephysical quantities in Table 3
4 Construction of the Test Model
41 Model Materials When soil materials are being se-lected the similarity coefficient λc of the soil specificgravity is made close to 1 in the prototype that is the
Counterfort
Pile foundation
Unloading board
Wall surface plate
Top beam
Figure 1 3D schematic diagram of the sheet pile wall with arelieving platform
Wall top or groundUpper wall plate
Lower wall column (plate)
39m
50m
70m
08m
90m
-12
0m
14m
Pile
Ground
Unloading board
Figure 2 +e cross section of sheet pile wall with a relievingplatform in a project
Table 1 Mechanical parameters of the sheet pile wall with therelieving platform
Items E (MPa) Μ ρ (kgm3) c (kPa) φ (deg)Pile foundation 280000 020 25000 mdash mdashTop beam 280000 020 25000 mdash mdashRib pillar 280000 020 25000 mdash mdashWall surface plate 280000 020 25000 mdash mdashUnloading board 280000 020 25000 mdash mdashFill soil (stone powder) 800 028 24000 10 350Soil between piles 300 030 18000 280 160
Advances in Civil Engineering 3
similarity coefficient λE of the elastic modulus is madeclose to 7 and the medium-coarse sand is selected as thefill soil and soil between piles in the model test A series ofphysical and mechanical tests including specific gravitytest the maximum and minimum dry density test directshear test particle separation test and water content testare completed in the geotechnical laboratory of CivilEngineering Department of Shenzhen University inChina +e physical and mechanical parameters of themedium-coarse sand are as shown in Table 4 +e gradingcurve is shown in Figure 3
Steel polymethyl methacrylate (PMMA) gypsum andfine-aggregate reinforced concrete are considered when themodel material for the retaining wall is selected +estructural material of the prototype retaining wall is thereinforced concrete as it is in an elastic state under normalworking conditions Owing to its characteristic of being easyto produce and simulate a steel is chosen as the modelmaterial for the retaining wall Corresponding to each part ofthe prototype structure the circular steel pipe pile is usedwhile the square steel pipe is applied in the pillar ribs +echannel steel and steel plates are applied in the unloadingboard
42 Model Structure Size
421 Size and Construction of the Model Test Box +eprototype retaining wall is 12m high the piles have 3m
spacing and the filling height is 12m +e horizontal widthof the prototype retaining wall is 125m Accordingly themodel test box is 20m wide and 4 piles are simulated +elongitudinal length of the test box is determined by thespatial dimension calculated using the sliding plane of theactive Earth pressure and the passive Earth pressure +erelationship between the prototype size and model size isshown in Table 5 and Figure 4
In this study the size of the model test box is 65m(length) times 20m (width) times 40m (height) +e real figure ofthe model test box is shown in Figure 5 Due to the highstructural model of the retaining wall the model box is fixedfirmly into the ground for easy testing and operation Fouranchor fixing bolts are prescrewed into the top of the modeltest box to secure the reaction frame
422 Size of Model Structure and Production According tothe characteristic parameters of the retaining wall in Table 2and the similarity relationship in Table 3 the characteristicparameters of the retaining wall structure are shown inTable 6
In the equivalent calculation several aspects should bestated [35]
(1) Assume that (EI)p and (EI)m are the actual stiffnessesof the prototype structure and model structure re-spectively while (EI)acutep and (EI)acutem are the stiffnessesof unit width in the prototype structure and model
Table 2 Characteristic parameters of the sheet pile wall with the relieving platform
Components Concreteno
Sectiondimension
(m)
Sectionmoment ofinertia (m4)
Stiffness(Nmiddotm2) (E)
Stiffness inunit width(Nmiddotm2m)
Calculativewidth (m) Remarks
Pilefoundation C25 Pile diameter
14 021 499 163E9 3Reinforcement ratio is
considered as the calculatingmoment of inertia
Rib pillar C25 08times11 005 149 467E8 3Upper base multiplied by thelower base for equivalent
calculationUnloadingboard C25 05times 30 003125 8758 292E8 3 +ickness multiplied by the
width
Top beam C25 16times 08 00683 1919 mdash mdash Rectangle length multipliedby the height
Wall surfaceplate C25 12times 03 00027 7568 252E8 3 Rectangle height multiplied
by the thickness
Table 3 +e similar relationship of the main physical quantities
Symbols Physical quantity Similarity relation (prototype model) Test valuel Length (geometry size) Λe 7ρ Density λρ 1q Load (area force) λλρ 7ε Strain λε 1σ Stress λλρ 7s Displacement λλε 7EI Flexural rigidity with unit width λ4λρλε 2401M Bending moment with unit width λ3λρ 343φ Internal friction angle of soil λφ 1
4 Advances in Civil Engineering
structure respectively +e following equation isshown in Table 3
(EI)primem (EI)primep
ρconcreteρsteel( 1113857λ41113872 1113873 (2)
(2) +e unit width of the model is 17 of the prototypewidth that is 3m7asymp 043m In order to expand themeasurement displacement and facilitate the
generating of the structural model the pile spacing inthe model is 06 meters
(3) +e unit width stiffness of a 5mm thick steel plate isnegligible compared to the unit width stiffness of thechannel steel
(4) In the equivalent calculation of the retainingplate the parameters of the wooden board are asfollows [36] Eboard 275 GPa and ρboard 600 kgm3
0
10
20
30
40
50
60
70
80
90
100
000100100100100010000Particle size (mm)
Soil
part
icle
qua
lity
perc
enta
gepa
ssin
g a p
artic
le si
ze
Sample ASample BSample C
Figure 3 Grading curve
Table 4 Physical and mechanical parameters of the medium-coarse sand
Items E (MPa) Μ ρd (kgm3) φ (deg) Specificgravity
Moisturecontent ()
Coefficient ofuniformity Cu Coefficient of curvature Cc
Medium-coarse sand 15 030 15910 358 2653 12 286 092
Table 5 +e relationship between the prototype size and model size
ItemsPile
length(m)
Height of theretaining wall
(m)
Horizontalwidth (m)
Longitudinal length(m)
RemarksLengthbeforethe pile
Lengthafter thepile
Prototype 120 120 125 (width of 4piles) mdash mdash +e longitudinal length of the model is calculated and
determined by the sand parametersModel 170 170 20 (width of 4piles) 375 275
Advances in Civil Engineering 5
+e front elevation drawing and profile drawing of themodel structure are shown in Figure 6 while the realfigure of the model structure is illustrated in Figure 7
43 Loading Equipment and MeasurementSystem of the Test Model
431 Loading Equipment of the Test Model In the modeltests the air pressure load is used to simulate the load on thetop of the wall +e loading equipment is shown in Figure 8+e test is undertaken among five levels from 10 kPa to50 kPa with each level increasing by 10 kPa
It is found that the air pressure load has two advantages(1) When the load is unloaded the load transmission isconsistent and continuous without impact (2) Its airpressure valve can be adjusted to maintain the load stabilityof each stage load +e magnitude of the change can becontrolled within the range of plusmn01 kPa
432 Measurement System +e layout of the selected Earthpressure measuring equipment is shown in Figure 9
+e test data present the Earth pressure in the upper andlower walls It is found that the measured Earth pressurebefore and after the pile foundation is the Earth pressure onthe pile not the average Earth pressure in the two piles +e
Wall height 4000
300
2000
300
300 3003750 2750
Wall height 2000
(a)
300
2000
1700
Top of sandfilling
P
Sand filling
Active failure surface
Top of sand fillingModel channel boundary
Passive failure surface
ψ = 358deg
45deg + ψ2
45deg ndash ψ2Model channel boundary
2000 17
0030
0
Model channel boundary42791 332209
D le 200189339 85661-D
3750 2750
ψ = 358deg
(b)
Figure 4 +e dimension of model test box (a) Planar graph (b) Profile drawing (the unit of the dimension is mm)
Anchor fixing bolts Anchor fixing bolts
Figure 5 +e real figure of model test box
6 Advances in Civil Engineering
conversion equation (3) is used to transform the measuredvalue
P1 P0d
b (3)
In equation (3) P0 is the measured Earth pressure beforeand after the pile P1 is the average Earth pressure in the twopiles d is the pile diameter and b is the pile spacing
+e strain gauges are set up in the maximal internal forceside of the pile and rib pillar in the retaining wall+e layoutsof strain gauges are shown in Figure 10 After measuring thestrain the moment at each measurement point of the pile iscalculated [37]
Mxz EIεy
(d2) (4)
In equation (4) εy is the compressive (tensile) strain atthe measurement point E is the elastic modulus of the pileand I is the moment of inertia of the cross section of the pile+e directions represented by x y and z are shown inFigure 11
By using the displacement measurement the dial indicatorwith a range of 30mm and an accuracy of 001mm is selectedWith the finite element method the maximum displacement ofthe top of the retaining wall is 208mm when it is in the mostunsafe environment (without the unloading board) Assumingthat the pile bottom is fixed the maximum displacement at the
Table 6 Characteristic parameters of retaining wall model structure
Components
Required flexuralrigidity with unitwidth (Nmiddotm2m)
(E)
Calculationwidth (m)
Sectionproperty ofmaterials
Sectiondimension ofmaterials (mm)
Selected flexuralrigidity with unit
width (Nmiddotm2m) (E)Remarks
Pile 6795 06 Circular steelpipe 159times 5 7205 Outer
diametertimes thickness
Rib pillar 1945 06 Square steelpipe 100times 25 2155 Outer
diametertimes thickness
Unloadingboard 1225 06
Channel steeland steelplate
Channel10 + 5mm steel
plate1025 Small stiffness of channel
steel
Top beam 8195 mdash Square steelpipe 250times 5 9815 mdash
Retainingplate 1055 06 Wooden
board +ickness 36 1155+ickness 18mmoverlapped wooden
board
Square steel pipe100 times 25
10
Slot
Steel plate thickness 5
Wooden board thickness 18
Welding plate thickness 10
Continuous connectionSquare steel pipe 250 times 5
Steel pipe 159 times 5
530
300
300
350
300
300
1650
250
1500
100 600 600 600 1002000
(a)
700
100
850
250
150017
5034
0016
50
Support baseboardthickness 5
Square steel pipe100 times 25
2M16
Steel pipe159 times 5
Square steel pipe 250 times 5 Continuous connection
Support baseboard thickness 8Wooden board thickness 18
Welding plate
Steel plate thickness 5
10Equal leg angle steel 100 times 5
(b)
Figure 6 Front elevation drawing and profile drawing of model structure (a) Front elevation drawing (b) Profile drawing (the unit of thedimension mm)
Advances in Civil Engineering 7
top of the retaining wall is calculated as 144mm It is consistentwithin an environment with only one supported beam+erefore the meter of the dial gauge has a full scale of 30mm+e dial indicator is fixed by using the magnetic gauge seat andensuring that the extendable rods are tipped on the square steeltubular It is found that the retaining wall is deflected with theincreasing thickness of the sand layer Moreover the dial in-dicator can be used tomeasure the displacement of the retainingwall simultaneously At the time of testing there are ten hor-izontal displacement measuring points on the rib pillar Ten dialindicators are installed to measure the horizontal displacementof the retaining wall +e layout and number of displacementmeasurement points are shown in Figure 12
433 Data Acquisition and Processing System Earth pres-sure and strain data acquisition are equipped with the au-tomatic acquisition of artificial guards Moreover theautomatic collection box is equipped with an accumulatorand a module that automatically controls the measurementof the sensor within a specified time +e measurementresults are first saved in the vibrating wire sensor (as shownin Figure 13) which is connected to an external data col-lection box +en the automatic dynamic monitoring of thenetwork is implemented Finally the data acquisition system
software is used to aggregate data collected in various modesinto a database and further display and process taskswitching Measurement data is saved in an Excel spread-sheet for subsequent analysis and processing +e schematicdiagram of data transmission collection and processingswitching work is shown in Figure 14
5 Test Scheme
A total of 28 grouping model tests are conducted one grouptest without the unloading board 18 group comparison testswithout external loading and 9 group external load com-parison tests +e combination of tests is shown in Table 7and the parameters are shown in Figure 15
A retaining wall model test without the unloading boardis performed firstly +e test has four purposes First it isused to verify the validity and reliability of the test instru-ment Second it is known that the structure of the retainingwall without the unloading board is relatively simple +usthe accuracy of the measurement data of the retaining wallmodel is verified by comparing them with the results fromother theories +ird in comparison with the results of thetest model of the unloading board retaining wall theunloading effect of the unloading board is analyzed that is
Rib pillar
Top beam
Pile
(a)
Unloading board(channel steel + steel plate)
(b)
Figure 7 Real figure of model structure (a) Real figure 1 (b) Real figure 2
Reducingvalve
Inlet valve
PipeSnuffle valve
Air pressure gauge
Pressurized air bags
Airpressure
gauge
Reactionwoodenboard
Anchor fixing boltReaction frame (channel steel)
Aircompressor
Figure 8 Schematic diagram of air pressure loading
8 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
similarity coefficient λE of the elastic modulus is madeclose to 7 and the medium-coarse sand is selected as thefill soil and soil between piles in the model test A series ofphysical and mechanical tests including specific gravitytest the maximum and minimum dry density test directshear test particle separation test and water content testare completed in the geotechnical laboratory of CivilEngineering Department of Shenzhen University inChina +e physical and mechanical parameters of themedium-coarse sand are as shown in Table 4 +e gradingcurve is shown in Figure 3
Steel polymethyl methacrylate (PMMA) gypsum andfine-aggregate reinforced concrete are considered when themodel material for the retaining wall is selected +estructural material of the prototype retaining wall is thereinforced concrete as it is in an elastic state under normalworking conditions Owing to its characteristic of being easyto produce and simulate a steel is chosen as the modelmaterial for the retaining wall Corresponding to each part ofthe prototype structure the circular steel pipe pile is usedwhile the square steel pipe is applied in the pillar ribs +echannel steel and steel plates are applied in the unloadingboard
42 Model Structure Size
421 Size and Construction of the Model Test Box +eprototype retaining wall is 12m high the piles have 3m
spacing and the filling height is 12m +e horizontal widthof the prototype retaining wall is 125m Accordingly themodel test box is 20m wide and 4 piles are simulated +elongitudinal length of the test box is determined by thespatial dimension calculated using the sliding plane of theactive Earth pressure and the passive Earth pressure +erelationship between the prototype size and model size isshown in Table 5 and Figure 4
In this study the size of the model test box is 65m(length) times 20m (width) times 40m (height) +e real figure ofthe model test box is shown in Figure 5 Due to the highstructural model of the retaining wall the model box is fixedfirmly into the ground for easy testing and operation Fouranchor fixing bolts are prescrewed into the top of the modeltest box to secure the reaction frame
422 Size of Model Structure and Production According tothe characteristic parameters of the retaining wall in Table 2and the similarity relationship in Table 3 the characteristicparameters of the retaining wall structure are shown inTable 6
In the equivalent calculation several aspects should bestated [35]
(1) Assume that (EI)p and (EI)m are the actual stiffnessesof the prototype structure and model structure re-spectively while (EI)acutep and (EI)acutem are the stiffnessesof unit width in the prototype structure and model
Table 2 Characteristic parameters of the sheet pile wall with the relieving platform
Components Concreteno
Sectiondimension
(m)
Sectionmoment ofinertia (m4)
Stiffness(Nmiddotm2) (E)
Stiffness inunit width(Nmiddotm2m)
Calculativewidth (m) Remarks
Pilefoundation C25 Pile diameter
14 021 499 163E9 3Reinforcement ratio is
considered as the calculatingmoment of inertia
Rib pillar C25 08times11 005 149 467E8 3Upper base multiplied by thelower base for equivalent
calculationUnloadingboard C25 05times 30 003125 8758 292E8 3 +ickness multiplied by the
width
Top beam C25 16times 08 00683 1919 mdash mdash Rectangle length multipliedby the height
Wall surfaceplate C25 12times 03 00027 7568 252E8 3 Rectangle height multiplied
by the thickness
Table 3 +e similar relationship of the main physical quantities
Symbols Physical quantity Similarity relation (prototype model) Test valuel Length (geometry size) Λe 7ρ Density λρ 1q Load (area force) λλρ 7ε Strain λε 1σ Stress λλρ 7s Displacement λλε 7EI Flexural rigidity with unit width λ4λρλε 2401M Bending moment with unit width λ3λρ 343φ Internal friction angle of soil λφ 1
4 Advances in Civil Engineering
structure respectively +e following equation isshown in Table 3
(EI)primem (EI)primep
ρconcreteρsteel( 1113857λ41113872 1113873 (2)
(2) +e unit width of the model is 17 of the prototypewidth that is 3m7asymp 043m In order to expand themeasurement displacement and facilitate the
generating of the structural model the pile spacing inthe model is 06 meters
(3) +e unit width stiffness of a 5mm thick steel plate isnegligible compared to the unit width stiffness of thechannel steel
(4) In the equivalent calculation of the retainingplate the parameters of the wooden board are asfollows [36] Eboard 275 GPa and ρboard 600 kgm3
0
10
20
30
40
50
60
70
80
90
100
000100100100100010000Particle size (mm)
Soil
part
icle
qua
lity
perc
enta
gepa
ssin
g a p
artic
le si
ze
Sample ASample BSample C
Figure 3 Grading curve
Table 4 Physical and mechanical parameters of the medium-coarse sand
Items E (MPa) Μ ρd (kgm3) φ (deg) Specificgravity
Moisturecontent ()
Coefficient ofuniformity Cu Coefficient of curvature Cc
Medium-coarse sand 15 030 15910 358 2653 12 286 092
Table 5 +e relationship between the prototype size and model size
ItemsPile
length(m)
Height of theretaining wall
(m)
Horizontalwidth (m)
Longitudinal length(m)
RemarksLengthbeforethe pile
Lengthafter thepile
Prototype 120 120 125 (width of 4piles) mdash mdash +e longitudinal length of the model is calculated and
determined by the sand parametersModel 170 170 20 (width of 4piles) 375 275
Advances in Civil Engineering 5
+e front elevation drawing and profile drawing of themodel structure are shown in Figure 6 while the realfigure of the model structure is illustrated in Figure 7
43 Loading Equipment and MeasurementSystem of the Test Model
431 Loading Equipment of the Test Model In the modeltests the air pressure load is used to simulate the load on thetop of the wall +e loading equipment is shown in Figure 8+e test is undertaken among five levels from 10 kPa to50 kPa with each level increasing by 10 kPa
It is found that the air pressure load has two advantages(1) When the load is unloaded the load transmission isconsistent and continuous without impact (2) Its airpressure valve can be adjusted to maintain the load stabilityof each stage load +e magnitude of the change can becontrolled within the range of plusmn01 kPa
432 Measurement System +e layout of the selected Earthpressure measuring equipment is shown in Figure 9
+e test data present the Earth pressure in the upper andlower walls It is found that the measured Earth pressurebefore and after the pile foundation is the Earth pressure onthe pile not the average Earth pressure in the two piles +e
Wall height 4000
300
2000
300
300 3003750 2750
Wall height 2000
(a)
300
2000
1700
Top of sandfilling
P
Sand filling
Active failure surface
Top of sand fillingModel channel boundary
Passive failure surface
ψ = 358deg
45deg + ψ2
45deg ndash ψ2Model channel boundary
2000 17
0030
0
Model channel boundary42791 332209
D le 200189339 85661-D
3750 2750
ψ = 358deg
(b)
Figure 4 +e dimension of model test box (a) Planar graph (b) Profile drawing (the unit of the dimension is mm)
Anchor fixing bolts Anchor fixing bolts
Figure 5 +e real figure of model test box
6 Advances in Civil Engineering
conversion equation (3) is used to transform the measuredvalue
P1 P0d
b (3)
In equation (3) P0 is the measured Earth pressure beforeand after the pile P1 is the average Earth pressure in the twopiles d is the pile diameter and b is the pile spacing
+e strain gauges are set up in the maximal internal forceside of the pile and rib pillar in the retaining wall+e layoutsof strain gauges are shown in Figure 10 After measuring thestrain the moment at each measurement point of the pile iscalculated [37]
Mxz EIεy
(d2) (4)
In equation (4) εy is the compressive (tensile) strain atthe measurement point E is the elastic modulus of the pileand I is the moment of inertia of the cross section of the pile+e directions represented by x y and z are shown inFigure 11
By using the displacement measurement the dial indicatorwith a range of 30mm and an accuracy of 001mm is selectedWith the finite element method the maximum displacement ofthe top of the retaining wall is 208mm when it is in the mostunsafe environment (without the unloading board) Assumingthat the pile bottom is fixed the maximum displacement at the
Table 6 Characteristic parameters of retaining wall model structure
Components
Required flexuralrigidity with unitwidth (Nmiddotm2m)
(E)
Calculationwidth (m)
Sectionproperty ofmaterials
Sectiondimension ofmaterials (mm)
Selected flexuralrigidity with unit
width (Nmiddotm2m) (E)Remarks
Pile 6795 06 Circular steelpipe 159times 5 7205 Outer
diametertimes thickness
Rib pillar 1945 06 Square steelpipe 100times 25 2155 Outer
diametertimes thickness
Unloadingboard 1225 06
Channel steeland steelplate
Channel10 + 5mm steel
plate1025 Small stiffness of channel
steel
Top beam 8195 mdash Square steelpipe 250times 5 9815 mdash
Retainingplate 1055 06 Wooden
board +ickness 36 1155+ickness 18mmoverlapped wooden
board
Square steel pipe100 times 25
10
Slot
Steel plate thickness 5
Wooden board thickness 18
Welding plate thickness 10
Continuous connectionSquare steel pipe 250 times 5
Steel pipe 159 times 5
530
300
300
350
300
300
1650
250
1500
100 600 600 600 1002000
(a)
700
100
850
250
150017
5034
0016
50
Support baseboardthickness 5
Square steel pipe100 times 25
2M16
Steel pipe159 times 5
Square steel pipe 250 times 5 Continuous connection
Support baseboard thickness 8Wooden board thickness 18
Welding plate
Steel plate thickness 5
10Equal leg angle steel 100 times 5
(b)
Figure 6 Front elevation drawing and profile drawing of model structure (a) Front elevation drawing (b) Profile drawing (the unit of thedimension mm)
Advances in Civil Engineering 7
top of the retaining wall is calculated as 144mm It is consistentwithin an environment with only one supported beam+erefore the meter of the dial gauge has a full scale of 30mm+e dial indicator is fixed by using the magnetic gauge seat andensuring that the extendable rods are tipped on the square steeltubular It is found that the retaining wall is deflected with theincreasing thickness of the sand layer Moreover the dial in-dicator can be used tomeasure the displacement of the retainingwall simultaneously At the time of testing there are ten hor-izontal displacement measuring points on the rib pillar Ten dialindicators are installed to measure the horizontal displacementof the retaining wall +e layout and number of displacementmeasurement points are shown in Figure 12
433 Data Acquisition and Processing System Earth pres-sure and strain data acquisition are equipped with the au-tomatic acquisition of artificial guards Moreover theautomatic collection box is equipped with an accumulatorand a module that automatically controls the measurementof the sensor within a specified time +e measurementresults are first saved in the vibrating wire sensor (as shownin Figure 13) which is connected to an external data col-lection box +en the automatic dynamic monitoring of thenetwork is implemented Finally the data acquisition system
software is used to aggregate data collected in various modesinto a database and further display and process taskswitching Measurement data is saved in an Excel spread-sheet for subsequent analysis and processing +e schematicdiagram of data transmission collection and processingswitching work is shown in Figure 14
5 Test Scheme
A total of 28 grouping model tests are conducted one grouptest without the unloading board 18 group comparison testswithout external loading and 9 group external load com-parison tests +e combination of tests is shown in Table 7and the parameters are shown in Figure 15
A retaining wall model test without the unloading boardis performed firstly +e test has four purposes First it isused to verify the validity and reliability of the test instru-ment Second it is known that the structure of the retainingwall without the unloading board is relatively simple +usthe accuracy of the measurement data of the retaining wallmodel is verified by comparing them with the results fromother theories +ird in comparison with the results of thetest model of the unloading board retaining wall theunloading effect of the unloading board is analyzed that is
Rib pillar
Top beam
Pile
(a)
Unloading board(channel steel + steel plate)
(b)
Figure 7 Real figure of model structure (a) Real figure 1 (b) Real figure 2
Reducingvalve
Inlet valve
PipeSnuffle valve
Air pressure gauge
Pressurized air bags
Airpressure
gauge
Reactionwoodenboard
Anchor fixing boltReaction frame (channel steel)
Aircompressor
Figure 8 Schematic diagram of air pressure loading
8 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
structure respectively +e following equation isshown in Table 3
(EI)primem (EI)primep
ρconcreteρsteel( 1113857λ41113872 1113873 (2)
(2) +e unit width of the model is 17 of the prototypewidth that is 3m7asymp 043m In order to expand themeasurement displacement and facilitate the
generating of the structural model the pile spacing inthe model is 06 meters
(3) +e unit width stiffness of a 5mm thick steel plate isnegligible compared to the unit width stiffness of thechannel steel
(4) In the equivalent calculation of the retainingplate the parameters of the wooden board are asfollows [36] Eboard 275 GPa and ρboard 600 kgm3
0
10
20
30
40
50
60
70
80
90
100
000100100100100010000Particle size (mm)
Soil
part
icle
qua
lity
perc
enta
gepa
ssin
g a p
artic
le si
ze
Sample ASample BSample C
Figure 3 Grading curve
Table 4 Physical and mechanical parameters of the medium-coarse sand
Items E (MPa) Μ ρd (kgm3) φ (deg) Specificgravity
Moisturecontent ()
Coefficient ofuniformity Cu Coefficient of curvature Cc
Medium-coarse sand 15 030 15910 358 2653 12 286 092
Table 5 +e relationship between the prototype size and model size
ItemsPile
length(m)
Height of theretaining wall
(m)
Horizontalwidth (m)
Longitudinal length(m)
RemarksLengthbeforethe pile
Lengthafter thepile
Prototype 120 120 125 (width of 4piles) mdash mdash +e longitudinal length of the model is calculated and
determined by the sand parametersModel 170 170 20 (width of 4piles) 375 275
Advances in Civil Engineering 5
+e front elevation drawing and profile drawing of themodel structure are shown in Figure 6 while the realfigure of the model structure is illustrated in Figure 7
43 Loading Equipment and MeasurementSystem of the Test Model
431 Loading Equipment of the Test Model In the modeltests the air pressure load is used to simulate the load on thetop of the wall +e loading equipment is shown in Figure 8+e test is undertaken among five levels from 10 kPa to50 kPa with each level increasing by 10 kPa
It is found that the air pressure load has two advantages(1) When the load is unloaded the load transmission isconsistent and continuous without impact (2) Its airpressure valve can be adjusted to maintain the load stabilityof each stage load +e magnitude of the change can becontrolled within the range of plusmn01 kPa
432 Measurement System +e layout of the selected Earthpressure measuring equipment is shown in Figure 9
+e test data present the Earth pressure in the upper andlower walls It is found that the measured Earth pressurebefore and after the pile foundation is the Earth pressure onthe pile not the average Earth pressure in the two piles +e
Wall height 4000
300
2000
300
300 3003750 2750
Wall height 2000
(a)
300
2000
1700
Top of sandfilling
P
Sand filling
Active failure surface
Top of sand fillingModel channel boundary
Passive failure surface
ψ = 358deg
45deg + ψ2
45deg ndash ψ2Model channel boundary
2000 17
0030
0
Model channel boundary42791 332209
D le 200189339 85661-D
3750 2750
ψ = 358deg
(b)
Figure 4 +e dimension of model test box (a) Planar graph (b) Profile drawing (the unit of the dimension is mm)
Anchor fixing bolts Anchor fixing bolts
Figure 5 +e real figure of model test box
6 Advances in Civil Engineering
conversion equation (3) is used to transform the measuredvalue
P1 P0d
b (3)
In equation (3) P0 is the measured Earth pressure beforeand after the pile P1 is the average Earth pressure in the twopiles d is the pile diameter and b is the pile spacing
+e strain gauges are set up in the maximal internal forceside of the pile and rib pillar in the retaining wall+e layoutsof strain gauges are shown in Figure 10 After measuring thestrain the moment at each measurement point of the pile iscalculated [37]
Mxz EIεy
(d2) (4)
In equation (4) εy is the compressive (tensile) strain atthe measurement point E is the elastic modulus of the pileand I is the moment of inertia of the cross section of the pile+e directions represented by x y and z are shown inFigure 11
By using the displacement measurement the dial indicatorwith a range of 30mm and an accuracy of 001mm is selectedWith the finite element method the maximum displacement ofthe top of the retaining wall is 208mm when it is in the mostunsafe environment (without the unloading board) Assumingthat the pile bottom is fixed the maximum displacement at the
Table 6 Characteristic parameters of retaining wall model structure
Components
Required flexuralrigidity with unitwidth (Nmiddotm2m)
(E)
Calculationwidth (m)
Sectionproperty ofmaterials
Sectiondimension ofmaterials (mm)
Selected flexuralrigidity with unit
width (Nmiddotm2m) (E)Remarks
Pile 6795 06 Circular steelpipe 159times 5 7205 Outer
diametertimes thickness
Rib pillar 1945 06 Square steelpipe 100times 25 2155 Outer
diametertimes thickness
Unloadingboard 1225 06
Channel steeland steelplate
Channel10 + 5mm steel
plate1025 Small stiffness of channel
steel
Top beam 8195 mdash Square steelpipe 250times 5 9815 mdash
Retainingplate 1055 06 Wooden
board +ickness 36 1155+ickness 18mmoverlapped wooden
board
Square steel pipe100 times 25
10
Slot
Steel plate thickness 5
Wooden board thickness 18
Welding plate thickness 10
Continuous connectionSquare steel pipe 250 times 5
Steel pipe 159 times 5
530
300
300
350
300
300
1650
250
1500
100 600 600 600 1002000
(a)
700
100
850
250
150017
5034
0016
50
Support baseboardthickness 5
Square steel pipe100 times 25
2M16
Steel pipe159 times 5
Square steel pipe 250 times 5 Continuous connection
Support baseboard thickness 8Wooden board thickness 18
Welding plate
Steel plate thickness 5
10Equal leg angle steel 100 times 5
(b)
Figure 6 Front elevation drawing and profile drawing of model structure (a) Front elevation drawing (b) Profile drawing (the unit of thedimension mm)
Advances in Civil Engineering 7
top of the retaining wall is calculated as 144mm It is consistentwithin an environment with only one supported beam+erefore the meter of the dial gauge has a full scale of 30mm+e dial indicator is fixed by using the magnetic gauge seat andensuring that the extendable rods are tipped on the square steeltubular It is found that the retaining wall is deflected with theincreasing thickness of the sand layer Moreover the dial in-dicator can be used tomeasure the displacement of the retainingwall simultaneously At the time of testing there are ten hor-izontal displacement measuring points on the rib pillar Ten dialindicators are installed to measure the horizontal displacementof the retaining wall +e layout and number of displacementmeasurement points are shown in Figure 12
433 Data Acquisition and Processing System Earth pres-sure and strain data acquisition are equipped with the au-tomatic acquisition of artificial guards Moreover theautomatic collection box is equipped with an accumulatorand a module that automatically controls the measurementof the sensor within a specified time +e measurementresults are first saved in the vibrating wire sensor (as shownin Figure 13) which is connected to an external data col-lection box +en the automatic dynamic monitoring of thenetwork is implemented Finally the data acquisition system
software is used to aggregate data collected in various modesinto a database and further display and process taskswitching Measurement data is saved in an Excel spread-sheet for subsequent analysis and processing +e schematicdiagram of data transmission collection and processingswitching work is shown in Figure 14
5 Test Scheme
A total of 28 grouping model tests are conducted one grouptest without the unloading board 18 group comparison testswithout external loading and 9 group external load com-parison tests +e combination of tests is shown in Table 7and the parameters are shown in Figure 15
A retaining wall model test without the unloading boardis performed firstly +e test has four purposes First it isused to verify the validity and reliability of the test instru-ment Second it is known that the structure of the retainingwall without the unloading board is relatively simple +usthe accuracy of the measurement data of the retaining wallmodel is verified by comparing them with the results fromother theories +ird in comparison with the results of thetest model of the unloading board retaining wall theunloading effect of the unloading board is analyzed that is
Rib pillar
Top beam
Pile
(a)
Unloading board(channel steel + steel plate)
(b)
Figure 7 Real figure of model structure (a) Real figure 1 (b) Real figure 2
Reducingvalve
Inlet valve
PipeSnuffle valve
Air pressure gauge
Pressurized air bags
Airpressure
gauge
Reactionwoodenboard
Anchor fixing boltReaction frame (channel steel)
Aircompressor
Figure 8 Schematic diagram of air pressure loading
8 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
+e front elevation drawing and profile drawing of themodel structure are shown in Figure 6 while the realfigure of the model structure is illustrated in Figure 7
43 Loading Equipment and MeasurementSystem of the Test Model
431 Loading Equipment of the Test Model In the modeltests the air pressure load is used to simulate the load on thetop of the wall +e loading equipment is shown in Figure 8+e test is undertaken among five levels from 10 kPa to50 kPa with each level increasing by 10 kPa
It is found that the air pressure load has two advantages(1) When the load is unloaded the load transmission isconsistent and continuous without impact (2) Its airpressure valve can be adjusted to maintain the load stabilityof each stage load +e magnitude of the change can becontrolled within the range of plusmn01 kPa
432 Measurement System +e layout of the selected Earthpressure measuring equipment is shown in Figure 9
+e test data present the Earth pressure in the upper andlower walls It is found that the measured Earth pressurebefore and after the pile foundation is the Earth pressure onthe pile not the average Earth pressure in the two piles +e
Wall height 4000
300
2000
300
300 3003750 2750
Wall height 2000
(a)
300
2000
1700
Top of sandfilling
P
Sand filling
Active failure surface
Top of sand fillingModel channel boundary
Passive failure surface
ψ = 358deg
45deg + ψ2
45deg ndash ψ2Model channel boundary
2000 17
0030
0
Model channel boundary42791 332209
D le 200189339 85661-D
3750 2750
ψ = 358deg
(b)
Figure 4 +e dimension of model test box (a) Planar graph (b) Profile drawing (the unit of the dimension is mm)
Anchor fixing bolts Anchor fixing bolts
Figure 5 +e real figure of model test box
6 Advances in Civil Engineering
conversion equation (3) is used to transform the measuredvalue
P1 P0d
b (3)
In equation (3) P0 is the measured Earth pressure beforeand after the pile P1 is the average Earth pressure in the twopiles d is the pile diameter and b is the pile spacing
+e strain gauges are set up in the maximal internal forceside of the pile and rib pillar in the retaining wall+e layoutsof strain gauges are shown in Figure 10 After measuring thestrain the moment at each measurement point of the pile iscalculated [37]
Mxz EIεy
(d2) (4)
In equation (4) εy is the compressive (tensile) strain atthe measurement point E is the elastic modulus of the pileand I is the moment of inertia of the cross section of the pile+e directions represented by x y and z are shown inFigure 11
By using the displacement measurement the dial indicatorwith a range of 30mm and an accuracy of 001mm is selectedWith the finite element method the maximum displacement ofthe top of the retaining wall is 208mm when it is in the mostunsafe environment (without the unloading board) Assumingthat the pile bottom is fixed the maximum displacement at the
Table 6 Characteristic parameters of retaining wall model structure
Components
Required flexuralrigidity with unitwidth (Nmiddotm2m)
(E)
Calculationwidth (m)
Sectionproperty ofmaterials
Sectiondimension ofmaterials (mm)
Selected flexuralrigidity with unit
width (Nmiddotm2m) (E)Remarks
Pile 6795 06 Circular steelpipe 159times 5 7205 Outer
diametertimes thickness
Rib pillar 1945 06 Square steelpipe 100times 25 2155 Outer
diametertimes thickness
Unloadingboard 1225 06
Channel steeland steelplate
Channel10 + 5mm steel
plate1025 Small stiffness of channel
steel
Top beam 8195 mdash Square steelpipe 250times 5 9815 mdash
Retainingplate 1055 06 Wooden
board +ickness 36 1155+ickness 18mmoverlapped wooden
board
Square steel pipe100 times 25
10
Slot
Steel plate thickness 5
Wooden board thickness 18
Welding plate thickness 10
Continuous connectionSquare steel pipe 250 times 5
Steel pipe 159 times 5
530
300
300
350
300
300
1650
250
1500
100 600 600 600 1002000
(a)
700
100
850
250
150017
5034
0016
50
Support baseboardthickness 5
Square steel pipe100 times 25
2M16
Steel pipe159 times 5
Square steel pipe 250 times 5 Continuous connection
Support baseboard thickness 8Wooden board thickness 18
Welding plate
Steel plate thickness 5
10Equal leg angle steel 100 times 5
(b)
Figure 6 Front elevation drawing and profile drawing of model structure (a) Front elevation drawing (b) Profile drawing (the unit of thedimension mm)
Advances in Civil Engineering 7
top of the retaining wall is calculated as 144mm It is consistentwithin an environment with only one supported beam+erefore the meter of the dial gauge has a full scale of 30mm+e dial indicator is fixed by using the magnetic gauge seat andensuring that the extendable rods are tipped on the square steeltubular It is found that the retaining wall is deflected with theincreasing thickness of the sand layer Moreover the dial in-dicator can be used tomeasure the displacement of the retainingwall simultaneously At the time of testing there are ten hor-izontal displacement measuring points on the rib pillar Ten dialindicators are installed to measure the horizontal displacementof the retaining wall +e layout and number of displacementmeasurement points are shown in Figure 12
433 Data Acquisition and Processing System Earth pres-sure and strain data acquisition are equipped with the au-tomatic acquisition of artificial guards Moreover theautomatic collection box is equipped with an accumulatorand a module that automatically controls the measurementof the sensor within a specified time +e measurementresults are first saved in the vibrating wire sensor (as shownin Figure 13) which is connected to an external data col-lection box +en the automatic dynamic monitoring of thenetwork is implemented Finally the data acquisition system
software is used to aggregate data collected in various modesinto a database and further display and process taskswitching Measurement data is saved in an Excel spread-sheet for subsequent analysis and processing +e schematicdiagram of data transmission collection and processingswitching work is shown in Figure 14
5 Test Scheme
A total of 28 grouping model tests are conducted one grouptest without the unloading board 18 group comparison testswithout external loading and 9 group external load com-parison tests +e combination of tests is shown in Table 7and the parameters are shown in Figure 15
A retaining wall model test without the unloading boardis performed firstly +e test has four purposes First it isused to verify the validity and reliability of the test instru-ment Second it is known that the structure of the retainingwall without the unloading board is relatively simple +usthe accuracy of the measurement data of the retaining wallmodel is verified by comparing them with the results fromother theories +ird in comparison with the results of thetest model of the unloading board retaining wall theunloading effect of the unloading board is analyzed that is
Rib pillar
Top beam
Pile
(a)
Unloading board(channel steel + steel plate)
(b)
Figure 7 Real figure of model structure (a) Real figure 1 (b) Real figure 2
Reducingvalve
Inlet valve
PipeSnuffle valve
Air pressure gauge
Pressurized air bags
Airpressure
gauge
Reactionwoodenboard
Anchor fixing boltReaction frame (channel steel)
Aircompressor
Figure 8 Schematic diagram of air pressure loading
8 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
conversion equation (3) is used to transform the measuredvalue
P1 P0d
b (3)
In equation (3) P0 is the measured Earth pressure beforeand after the pile P1 is the average Earth pressure in the twopiles d is the pile diameter and b is the pile spacing
+e strain gauges are set up in the maximal internal forceside of the pile and rib pillar in the retaining wall+e layoutsof strain gauges are shown in Figure 10 After measuring thestrain the moment at each measurement point of the pile iscalculated [37]
Mxz EIεy
(d2) (4)
In equation (4) εy is the compressive (tensile) strain atthe measurement point E is the elastic modulus of the pileand I is the moment of inertia of the cross section of the pile+e directions represented by x y and z are shown inFigure 11
By using the displacement measurement the dial indicatorwith a range of 30mm and an accuracy of 001mm is selectedWith the finite element method the maximum displacement ofthe top of the retaining wall is 208mm when it is in the mostunsafe environment (without the unloading board) Assumingthat the pile bottom is fixed the maximum displacement at the
Table 6 Characteristic parameters of retaining wall model structure
Components
Required flexuralrigidity with unitwidth (Nmiddotm2m)
(E)
Calculationwidth (m)
Sectionproperty ofmaterials
Sectiondimension ofmaterials (mm)
Selected flexuralrigidity with unit
width (Nmiddotm2m) (E)Remarks
Pile 6795 06 Circular steelpipe 159times 5 7205 Outer
diametertimes thickness
Rib pillar 1945 06 Square steelpipe 100times 25 2155 Outer
diametertimes thickness
Unloadingboard 1225 06
Channel steeland steelplate
Channel10 + 5mm steel
plate1025 Small stiffness of channel
steel
Top beam 8195 mdash Square steelpipe 250times 5 9815 mdash
Retainingplate 1055 06 Wooden
board +ickness 36 1155+ickness 18mmoverlapped wooden
board
Square steel pipe100 times 25
10
Slot
Steel plate thickness 5
Wooden board thickness 18
Welding plate thickness 10
Continuous connectionSquare steel pipe 250 times 5
Steel pipe 159 times 5
530
300
300
350
300
300
1650
250
1500
100 600 600 600 1002000
(a)
700
100
850
250
150017
5034
0016
50
Support baseboardthickness 5
Square steel pipe100 times 25
2M16
Steel pipe159 times 5
Square steel pipe 250 times 5 Continuous connection
Support baseboard thickness 8Wooden board thickness 18
Welding plate
Steel plate thickness 5
10Equal leg angle steel 100 times 5
(b)
Figure 6 Front elevation drawing and profile drawing of model structure (a) Front elevation drawing (b) Profile drawing (the unit of thedimension mm)
Advances in Civil Engineering 7
top of the retaining wall is calculated as 144mm It is consistentwithin an environment with only one supported beam+erefore the meter of the dial gauge has a full scale of 30mm+e dial indicator is fixed by using the magnetic gauge seat andensuring that the extendable rods are tipped on the square steeltubular It is found that the retaining wall is deflected with theincreasing thickness of the sand layer Moreover the dial in-dicator can be used tomeasure the displacement of the retainingwall simultaneously At the time of testing there are ten hor-izontal displacement measuring points on the rib pillar Ten dialindicators are installed to measure the horizontal displacementof the retaining wall +e layout and number of displacementmeasurement points are shown in Figure 12
433 Data Acquisition and Processing System Earth pres-sure and strain data acquisition are equipped with the au-tomatic acquisition of artificial guards Moreover theautomatic collection box is equipped with an accumulatorand a module that automatically controls the measurementof the sensor within a specified time +e measurementresults are first saved in the vibrating wire sensor (as shownin Figure 13) which is connected to an external data col-lection box +en the automatic dynamic monitoring of thenetwork is implemented Finally the data acquisition system
software is used to aggregate data collected in various modesinto a database and further display and process taskswitching Measurement data is saved in an Excel spread-sheet for subsequent analysis and processing +e schematicdiagram of data transmission collection and processingswitching work is shown in Figure 14
5 Test Scheme
A total of 28 grouping model tests are conducted one grouptest without the unloading board 18 group comparison testswithout external loading and 9 group external load com-parison tests +e combination of tests is shown in Table 7and the parameters are shown in Figure 15
A retaining wall model test without the unloading boardis performed firstly +e test has four purposes First it isused to verify the validity and reliability of the test instru-ment Second it is known that the structure of the retainingwall without the unloading board is relatively simple +usthe accuracy of the measurement data of the retaining wallmodel is verified by comparing them with the results fromother theories +ird in comparison with the results of thetest model of the unloading board retaining wall theunloading effect of the unloading board is analyzed that is
Rib pillar
Top beam
Pile
(a)
Unloading board(channel steel + steel plate)
(b)
Figure 7 Real figure of model structure (a) Real figure 1 (b) Real figure 2
Reducingvalve
Inlet valve
PipeSnuffle valve
Air pressure gauge
Pressurized air bags
Airpressure
gauge
Reactionwoodenboard
Anchor fixing boltReaction frame (channel steel)
Aircompressor
Figure 8 Schematic diagram of air pressure loading
8 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
top of the retaining wall is calculated as 144mm It is consistentwithin an environment with only one supported beam+erefore the meter of the dial gauge has a full scale of 30mm+e dial indicator is fixed by using the magnetic gauge seat andensuring that the extendable rods are tipped on the square steeltubular It is found that the retaining wall is deflected with theincreasing thickness of the sand layer Moreover the dial in-dicator can be used tomeasure the displacement of the retainingwall simultaneously At the time of testing there are ten hor-izontal displacement measuring points on the rib pillar Ten dialindicators are installed to measure the horizontal displacementof the retaining wall +e layout and number of displacementmeasurement points are shown in Figure 12
433 Data Acquisition and Processing System Earth pres-sure and strain data acquisition are equipped with the au-tomatic acquisition of artificial guards Moreover theautomatic collection box is equipped with an accumulatorand a module that automatically controls the measurementof the sensor within a specified time +e measurementresults are first saved in the vibrating wire sensor (as shownin Figure 13) which is connected to an external data col-lection box +en the automatic dynamic monitoring of thenetwork is implemented Finally the data acquisition system
software is used to aggregate data collected in various modesinto a database and further display and process taskswitching Measurement data is saved in an Excel spread-sheet for subsequent analysis and processing +e schematicdiagram of data transmission collection and processingswitching work is shown in Figure 14
5 Test Scheme
A total of 28 grouping model tests are conducted one grouptest without the unloading board 18 group comparison testswithout external loading and 9 group external load com-parison tests +e combination of tests is shown in Table 7and the parameters are shown in Figure 15
A retaining wall model test without the unloading boardis performed firstly +e test has four purposes First it isused to verify the validity and reliability of the test instru-ment Second it is known that the structure of the retainingwall without the unloading board is relatively simple +usthe accuracy of the measurement data of the retaining wallmodel is verified by comparing them with the results fromother theories +ird in comparison with the results of thetest model of the unloading board retaining wall theunloading effect of the unloading board is analyzed that is
Rib pillar
Top beam
Pile
(a)
Unloading board(channel steel + steel plate)
(b)
Figure 7 Real figure of model structure (a) Real figure 1 (b) Real figure 2
Reducingvalve
Inlet valve
PipeSnuffle valve
Air pressure gauge
Pressurized air bags
Airpressure
gauge
Reactionwoodenboard
Anchor fixing boltReaction frame (channel steel)
Aircompressor
Figure 8 Schematic diagram of air pressure loading
8 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
the unloading effect is established +e effect of theunloading board has mechanical and deformation charac-teristics +e retaining wall is analyzed at the end of the testFourth by analyzing all the issues involved in the test theexperience of conducting the test is reflected and summa-rized Based upon these the subsequent tests are completed+e test process is shown in Figure 16
6 Test Results and Discussion
61 Distribution of Earth Pressure +e Earth pressure be-hind the retaining wall and prepile resistance force withoutthe unloading board25 are shown in Figures 17 and 18Figure 17 shows that there is a linear increasing tendencywith the depth in the measured Earth pressure behind the
A bus (six cores)
ty08
ty09ty10
ty11ty12
ty13ty01ty02
ty03ty04ty05ty06
ty07
ty14ty15
ty16
Sand filling
ty17 ty18
1650
1750
90 310
380
450
120
250
250
250
150
310
160
160
200
170
500
1150
3400
250
250
440
130
630
50
Sand filling
Earth pressure cellData processor
Automatic collecting system
Computer
Data line
Data bus
Statements1 When the length of plate changes the layout of earth pressure cell position is not affected on some
plates (ty17 ty18)When the plate position changes earth pressure cell position change didnrsquot affect the upper lowerand pile bottom unloading boarde dimension unit in the figure is mm
2
3
50
Figure 9 +e layout of Earth pressure cell
Strain gauge before pileStrain gauge aer pileData processor
Automatic collectingsystemComputer
Data lineData bus
1650
1750
220
280 50
011
5025
034
0015
00
980
240
280
300
350
500
250
420
220
360
500
yb06
yb09yb10
yb07
yb08
yb01yb02
yb03
yb04
500yb05
yb01
yb06 yb16yb17yb09yb18yb10
yb19yb20
yb07
yb08
100 600 6002000
600 100
yb02
yb03
yb04
yb11yb12
yb13
yb14 Sandfilling
1650
1500
250
Statements1 Strain gauge position layout when plate length changed didnrsquot affect the plate (yb05)
Strain gauge position change when the plate position changed didnrsquot affect the upperlower and pile bottom unloading boarde dimension unit in the figure is mm
2
3
Figure 10 Strain gauge layout
Advances in Civil Engineering 9
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
retaining wall Moreover the measured Earth pressure be-hind the wall lies between Rankine Earth pressure and Earthpressure at rest showing that the soil behind the wall is keptin the progressive active failure state +e measured Earthpressure at the bottom of retaining wall is 133 times thecalculation value by Rankine theory and 082 times Earthpressure at rest
Figure 18 shows that the measured prepile resistanceforce tends to increase first and then decrease afterwardswith the depth It is found that the measured prepile re-sistance force at the bottom of retaining wall is close to zero(this is much less than theoretical calculation value byRankinersquos theory) +e measured prepile resistance force ofthe upper wall (above 06m depth) is close to CoulombrsquosEarth pressure +is indicates that the upper wall remains ina progressive passive limit state +e measured prepile re-sistance force of the lower wall (below 06m depth) is foundto be much less than the calculation value by Rankine Earthpressure +e measured prepile resistance force is close tothe calculation value by m method in ldquoJGJ 120ndash2012 J1412ndash2012 Technical Specifications for Retaining andProtection of Building Foundation Excavationsrdquo (Ministryof Housing and Urban-Rural Development of the PeoplersquosRepublic of China 2010) It indicates that the prepile re-sistance force can be approximated by using the m method
oprime
o y
x
z
Strain gaugeMxz
Figure 11 +e directions represented by x y and z
400
400
400
400
50
bf01
bf02
bf03
bf04
bf05
Sand filling
Sand filling
γ
γ
γ
γ
γ
Dial indicator
(a)
bf01bf02
bf03
bf04bf05
bf06bf07
bf08
bf09
bf10
Sandfilling
Sandfilling
1650
250
1500
100 600 6002000
600 100
(b)
Figure 12 External displacement measurement point layout of retaining wall (unit mm) (a) Side view drawing (b) Front elevationdrawing
Figure 13 +e vibrating wire sensor
10 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
+e present study found that the Earth pressure distri-bution measured before and behind the wall has a certainregularity+e reason is shown in Figure 19 In Figure 19 It isfound that there is a turning point on the position of thebottom of retaining wallrsquos pile foundation that is a zero-displacement point With the development of deformationwith the retaining wall structure the Earth pressure above thezero-displacement point behind the pile develops from thestatic Earth pressure to the active Earth pressure showing agradual active limit state Moreover the Earth pressure underthe zero-displacement point behind the pile develops fromstatic Earth pressure to passive Earth pressure +erefore the
Earth pressure measured by the Earth pressure cell H is thepassive Earth pressure and the Earth pressure measured bythe Earth pressure cell H is larger than the calculated value bythe Rankine theory +e Earth pressure above the zero-dis-placement point before the pile develops from static Earthpressure to passive Earth pressure showing a progressivelypassive limit state +e Earth pressure under the zero-dis-placement point before the pile changes from static Earthpressure to active Earth pressure In addition during theprocess of the turning of the pile it is found that the de-formation of the right sand at the bottom of the pile is smallor the deformation of the right sand cannot grasp the turning
Collection sowareprocessing data
Automaticcollection box Data processor
Surface concrete strain gauge (n)Earth pressure cell (n)
Figure 14 Schematic diagram of data transmission collection and processing switching work
Hprime = 175
H = 17
L
h
B
Sand filling
20
20
Air bag reservation
Square steel pipeLock beam
275375
Circular steel pipePile
Channel steelUnloading board
Square steel pipeColumn
Statement the dimension in the figure is m
Top of sand filling
Top of model box
Sand filling
Figure 15 Parameters figure for the combination of tests
Advances in Civil Engineering 11
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
deformation of the pile In other words there is a loosecontact between the pile and the sand resulting in a smallmeasurement of the Earth pressure unit N
62 Internal Force Distribution of the Retaining Wall +einternal force change of the retaining wall is largely reflectedin the bending moment of the retaining wall structure +ebending moment distribution curve of the retaining wall isshown in Figure 20 In Figure 20 it is found that the
measured bending moment value approximates the calcu-lated value by the m method and is larger than the bendingmoment value calculated by the finite difference methodDuring the model test the sand is layered 6 times in total Itis found that when the sand surface is flat the external loadgenerated by the human bodyrsquos own weight increasescausing the measured strain value to be greater than thestrain value calculated by the finite difference method+erefore the measuredmoment value is found to be greater
Table 7 Combination of tests
Grouping number H (m) B (m) H (m) BH hH Load at wall top q (kPa)1 170 0 170 0 mdash 02 170 04 06 024 035 03 170 04 09 024 053 04 170 04 12 024 070 05 170 05 06 030 035 06 170 05 09 030 053 07 170 05 12 030 070 08 170 06 06 035 035 09 170 06 09 035 053 010 170 06 12 035 070 011 170 08 06 047 035 012 170 08 09 047 053 013 170 08 12 047 070 014 170 10 06 059 035 015 170 10 09 059 053 016 170 10 12 059 070 017 170 12 06 070 035 018 170 12 09 070 053 019 170 12 12 070 070 020 170 04 06 024 035 102030405021 170 04 09 024 053 102030405022 170 04 12 024 070 102030405023 170 06 06 035 035 102030405024 170 06 09 035 053 102030405025 170 06 12 035 070 102030405026 170 10 06 059 035 102030405027 170 10 09 059 053 102030405028 170 10 12 059 070 1020304050Notes the meanings of B and h in the table are shown in Figure 15
Install retaining wallstructure model
Arrange the lowermeasurement instrument
Measure the initial value ofthe instrument
Instrument debugging andcalibration Fill sand to the ground
elevation
Arrange the upper measurement instrument andread the initial value of the instrument
Fill sand to the designelevation
Install unloading board andfill in sand to full load
Measure data until stabledata
Start the next test
Discharge sand and cleanthe model box
Figure 16 Flow chart of test
12 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
than the moment value calculated by the finite differencemethod
63 Deformation of the Retaining Wallrsquos Rib PillarsFigure 21 shows that the deformation measurements aremade on the two rib pillars of the retaining wall (pillar A ison the right side and pillar B is on the left side) It is foundthat the field measurement conditions limit the measure-ment resulting in the fact that only the measured values of
the left and right rib pillars are measured +e amount ofdeformation of the rib pillars on the retaining wall and thecalculated value of the finite difference method are shown inFigure 22
Figure 22 presents the following important findings
(1) +e entire retaining wall structure is externally in-clined +e ratio between the displacement of theretaining wallrsquos upper rib pillar at the top ∆x and ribpillar height H is 2512mm1650mm 152 +isvalue is greater than the value of sheet pile retaining
20 40 60 80 100 120 140 160 180Prepile resistance force (kPa)
Measured prepile resistance forceCalculated value by m methodRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
18
16
14
12
10
08
06
04
02
000
Dep
th (m
)
Figure 18+e prepile resistance force of the retaining wall withoutthe unloading board
35
30
25
20
15
10
05
00 0 5 10 15 20 25Earth pressure behind the wall (kPa)
Dep
th (m
)
Earth pressure behind the wallRankine earth pressureCoulombrsquos earth pressureEarth pressure at rest
17Ground line
Figure 17 Earth pressure behind the retaining wall without theunloading board
Earth pressure cell
Statements A B C hellip N are the number of Earth pressure cells
A
B
N H
G
F
E
D
C
IJ
LK
M
Sand filling
Wall turning point
Active Earth pressure area
Dividing line between active Earth pressure andpassive Earth pressure areas
Passive Earth pressure area
Passive Earth pressure area
Active Earth pressure area
Sand filling
Figure 19 Interpretation drawing of Earth pressure distribution ofthe retaining wall
35
30
25
20
15
10
05
00
Dep
th (m
)
Moment value calculated by measured strainMoment value calculated by m methodMoment value calculated by finite difference method
Moment (kNm)0 1 2 3 4 5 6 7 8
Figure 20 Bending moment distribution curve of the retainingwall
Advances in Civil Engineering 13
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
wallrsquos displacement however it is less than 1 ofretaining wallrsquos cantilever length required by ldquoTB10025ndash2006 J 127ndash2006 Code for Design onRetaining Structures of Railway Subgraderdquo (Ministryof Railways of the Peoplersquos Republic of China 2006)namely ∆xHle 10 +is results in a failedretaining wall In summary this finding indicatesthat when the upper part of the retaining wall has nounloading board the entire retaining wall structurefails
(2) +e deformation of pillar A is slightly larger than thatof pillar B which indicates that numerous buriedinstrument wires below pillar A force the sand fillingof pillar A to be loose In addition it is found that theexternal displacement of pillar A is greater than thedisplacement of pillar B
(3) Owing to the 6 times (in total) of layers of sand in themodel test the measured deformation in the retainingwallrsquos upper rib pillar is greater than the calculatedresults using the finite difference method +e sum ofthe incremental results of the six times monitoring isconsidered as the total displacement (the external load
has to be generated by the bodyrsquos self-weight each timeand the sand surface is flattened) +is total displace-ment is then calculated by using the finite differencemethod from the start to the equilibrium increment foraccurate measurement +erefore it is found that thedisplacement is greater than the displacement calculatedby the finite difference method
7 Conclusions
Based on the studies presented in this study the credibilityand validity of the self-made model of the retaining wall thetest instrument and the test data are verified and the fol-lowing five contributions to the field can be extracted
(1) +e measured Earth pressure behind the sheet pilewall with relieving platform without the unloadingboard has a strong linear correlation with its depth+is value lies between the values of Rankine Earthpressure and Earth pressure at rest and the soil behindthe wall remains in a progressive active failure state
(2) +e measured prepile resistance force of the upperwall (above 06m depth) is close to the CoulombrsquosEarth pressure and that of the lower wall (below06m depth) is much less than the calculation valueby Rankine Earth pressure Moreover the measuredprepile resistance force can be used for approximatecalculation by the m method
(3) +ere is a zero-displacement point on the pilebottom of the retaining wall with the develop-ment of deformation with the retaining wallstructure the front and back zones of the pile aredivided into the passive Earth pressure zone andactive Earth pressure zone by the zero-displace-ment point
(4) +e measured moment value of the sheet pile wallwith relieving platform without the unloading boardis close to the value calculated by the m method andthe m method can be used for the approximatecalculation
(5) +e ratio between the displacement of the upper ribpillars in the retaining wall and its height is greaterthan the corresponding standard requirement in-dicating that the retaining wall without theunloading board has failed +us the unloadingboard should be installed to exert the unloadingeffect and improve the stress and deformationcharacteristics of the retaining wall
Nomenclature
E Elastic modulus of the material in the retainingwall structure
μ Poissonrsquos ratio of the material in the retaining wallstructure
ρ Natural density of the material in the retainingwall structure
c Cohesive force of soil
Pillar B Pillar A
Figure 21 Position of pillar A and pillar B and embedded linediagram of the instrument
20
18
16
14
12
10
08
06
04
02
00
24 22 20 18 16 14 12 10Deformation of rib pillar (mm)
Hei
ght o
f rib
pill
ar (m
)
Measured deformation value of pillar AMeasured deformation value of pillar BCalculated value by finite difference method
Figure 22 +e deformation curve of the retaining wallrsquos upper ribpillar
14 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
φ Internal friction angle of soilρd Dry density of the medium-coarse sandλ Similarity coefficient of the same physical
quantity in the prototype and model of theretaining wall
xp Any physical quantity in the prototype of theretaining wall
xm Any physical quantity in the model of theretaining wall
λε Similarity coefficient of the strain of the materialλρ Similarity coefficient of the natural density of the
materialλc Similarity coefficient of material specific gravity or
bulk densityλφ Similarity coefficient of the internal friction angle
of the materialε Strain of the structureq Area force at wall topσ Stress of the structures Displacement of the structureEI Unit flexural stiffness of the structureCu Coefficient of uniformity of the soilCc Coefficient of curvature of the soil(EI)p Actual stiffness of the prototype structure(EI)m Actual stiffness of the model structure(EI)rsquop Stiffness of unit width in the prototype structure(EI)rsquom Stiffness of unit width in the model structureρSoilρSand
Natural density of the soil and sand
ρConcrete Natural density of the concrete materialρSteel Natural density of the steel materialEboard Elastic modulus of the wooden board in themodel
structureρboard Natural density of the wooden board in the model
structureP0 Measured Earth pressure before and after the pileP1 Average Earth pressure within two pilesd Pile diameterb Pile spacingM Moment at each measurement point of the pileεy Compressive (tensile) strain at the measurement
pointI Moment of inertia of cross section of the pileH Height of the retaining wall or rib pillarh Buried depth of the unloading boardB Width of the unloading boardx Displacement of the retaining wallrsquos upper rib
pillar at the top
Data Availability
+e data and figures used to support the findings of thisstudy are included within the article
Conflicts of Interest
+e authors declare that they have no conflicts of interest
Acknowledgments
+is work was supported by the National Natural ScienceFoundation of China (no 51678017) the National Key RampDProgram of China (no 2018YFD1100902-1) and the KeyScientific Research Projects of Henan Provincial Collegesand Universities (no 17A560002) in China +e authorswould like to express their gratitude to these financialsupports
References
[1] G M Sabnis H G Harris R N White et al ldquoStructuralmodeling and experimental techniquesrdquo Journal of DynamicSystems Measurement and Control vol 105 no 7 Article ID307 1983
[2] J J Yang Similarity eory and Structural Modeling Exper-iment Wuhan University of Technology Press WuhanChina 2005
[3] J K Young S J Hyuk and J L Yong ldquoBehaviour analysis ofreinforced soil retaining wall according to laboratory scaletestrdquo Applied Sciences vol 10 no 3 Article ID 901 2020
[4] K S Wong B B Broms and B Chandrasekaran ldquoFailuremodes at model tests of a geotextile reinforced wallrdquo Geo-textiles and Geomembranes vol 13 no 6-7 pp 475ndash4931994
[5] C S Yoo H S Jung S S Jeon et al ldquoFailure mechanism ofgeosynthetic reinforced segmental retaining wall in tieredconfiguration using reduced-scale model testsrdquo Journal of theKorean Geotechnical Society vol 21 pp 65ndash77 2005
[6] R H Chen and Y M Chiu ldquoModel tests of geocell retainingstructuresrdquo Geotextiles and Geomembranes vol 26 no 1pp 56ndash70 2008
[7] C Z Xiao Q Q Chen and J Han ldquoExperimental study ofperformance of geogrid-reinforced retaining wall subjected toload from strip foundation at the top surface of wallrdquo Rockand Soil Mechanics vol 34 no 6 pp 1586ndash1592 2013
[8] J S Ki W H Rew S K Kim and B S Chun ldquoA behavior ofcurve section of reinforced retaining wall by model testrdquoJournal of e Korean Society of Civil Engineers vol 32no 6C pp 249ndash257 2012
[9] L H Li C D Yu H L Xiao et al ldquoExperimental study on thereinforced fly ash and sand retaining wall under static loadrdquoConstruction and Building Materials vol 248 no 10 ArticleID 118678 2020
[10] H Wang G Yang Z Wang and W Liu ldquoStatic structuralbehavior of geogrid reinforced soil retaining walls with adeformation buffer zonerdquo Geotextiles and Geomembranesvol 48 no 3 pp 374ndash379 2020
[11] D-U Jeong J-C Im J-W Yoo M-S Seo Y-M Koo andS-J Kim ldquoAn experimental study on the inclined earthretaining structure in clayrdquo Journal of the Korean GeotechnicalSociety vol 29 no 6 pp 63ndash75 2013
[12] M-S Seo J-C Im D-U Jeong J-W Yoo Y-M Koo andG-H Kim ldquoAn experimental study on the stability of inclinedearth retainingrdquo Journal of the Korean Geotechnical Societyvol 28 no 12 pp 99ndash110 2012
[13] J-W Yoo J-C Im S-P Hwang C-Y Kim J-H Choi andH-S Kim ldquoAn experimental study on the stability of as-sembled earth retaining wall in sandy groundrdquo Journal of theKorean Geotechnical Society vol 32 no 2 pp 43ndash52 2016
[14] H Kim J-C Im J Choi and M Seo ldquoMechanical effects ofback supporting beam of assembled earth retaining wall on
Advances in Civil Engineering 15
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering
field model tests resultsrdquo Journal of the Korean Society of CivilEngineers vol 37 no 2 pp 343ndash355 2017
[15] S Kim D E Lee Y Kim et al ldquoDevelopment and applicationof precast concrete double wall system to improve produc-tivity of retaining wall constructionrdquo Sustainability vol 12no 8 Article ID 3454 2020
[16] F A Salman M Y Fattah S M Shirazi et al ldquoComparativestudy on earth pressure distribution behind retaining wallssubjected to line loadsrdquo Scientific Research and Essays vol 6pp 2228ndash2244 2011
[17] F A Salman M Y Fattah and D K Sabre ldquoLong termbehaviour of a retaining wall resting on clayey soilrdquo Inter-national Journal of the Physical Sciences vol 6 pp 730ndash7452011
[18] W-K Yoo B-I Kim I-J Moon and Y-S Park ldquoCom-parison of the lateral earth pressure on the retaining wall withthe relieving platform by model test and numerical analysisrdquoJournal of the Korea Academia-Industrial Cooperation Societyvol 13 no 5 pp 2382ndash2389 2012
[19] I-J Moon B-I Kim W-K Yoo and Y-S Park ldquoModel testsfor measurement of lateral earth pressure on retaining wallwith the relieving platform using jumoonjin sandrdquo Journal ofthe Korea Academia-Industrial Cooperation Society vol 14no 11 pp 5923ndash5929 2013
[20] H F Shehata ldquoUse of retaining walls with relief shelves as aneconomic solutionrdquo in Proceedings of the Advances in Nu-merical and Experimental Analysis of Transportation Geo-materials and Geosystems for Sustainable InfrastructureFourth Geo-China International Conference ASCE Shan-dong China pp 82ndash90 July 2016
[21] I Kim W K Yoo M R Yang et al ldquoModel test study on theearth pressure of the retaining wall with the relieving plat-formrdquo Journal of Korean Society of Civil Engineers vol 32no 1 pp 27ndash35 2012
[22] A Eslami and J Bazaz ldquoStudy of bored pile retaining wallusing physical modelingrdquo International Journal Civil Envi-ronmental Structure Construction Architecture Engineeringvol 9 no 1 pp 15ndash18 2015
[23] W R Azzam and A Z Elwakil ldquoPerformance of axiallyloaded-piled retaining wall experimental and numericalanalysisrdquo International Journal of Geomechanics vol 17no 2 Article ID 04016049 2017
[24] Y C Liu ldquo+emodel test research on pile-supported relievingretaining wallrdquo MS +esis China Academy of RailwaySciences Beijing China 2010
[25] R H Hu G N Liu and X H Pan ldquoParameters determi-nation of unloading board and pile length of sheet pile wallwith relieving platformrdquo Railway Engineering vol 11pp 74ndash77 2011
[26] Y L Hu G N Liu and Y M Zhao ldquoCalculation method ofdeformation and inner force of a sheet pile wall with relievingplatformrdquo in e Proceeding of Fourth International Con-ference on Transportation Engineering 2013 (ICTE 2013)ASCE Chengdu China pp 172ndash179 2013
[27] Y L Hu G N Liu and Y M Zhao ldquoCalculation on internalforce and deformation of sheet pile wall with relievingplatformrdquo Subgrade Engineering vol 4 pp 70ndash75 2013
[28] X H Chen Structural Modeling Experiment of Brittle Ma-terial China Water amp Power Press Beijing China 1984
[29] J H Cui Geomechanical Model Test Method and Applicationof High Arch Dam China Water amp Power Press BeijingChina 2008
[30] X S Liu Model Test and Dynamic Analysis of Large ShakingTable for Concrete Face Dam China Water amp Power PressBeijing China 2005
[31] W Z Yuan Similarity eory and Statical Mode TestSouthwest Jiaotong University Press Chengdu China 1998
[32] H Heinz Model Analysis of Structures Van NostrandReinhold Company New York NY USA 1974
[33] J Garnier C Gaudin S M Springman et al ldquoCatalogue ofscaling laws and similitude questions in geotechnical cen-trifugemodellingrdquo International Journal of Physical Modellingin Geotechnics vol 7 no 3 pp 01ndash23 2007
[34] S Iai ldquoSimilitude for shaking table tests on soil-structure-fluidmodel in 1g gravitational fieldrdquo Soils and Foundations vol 29no 1 pp 105ndash118 1989
[35] R H Hu ldquoStudy on the mechanical behavior and failuremechanism for sheet pile wall with relieving platformrdquo PhD+esis China Academy of Railway Sciences Beijing China2011
[36] G Y Li Y S He Y Q Tao et al Latest Practical HardwareManual (Revised Edition) Guangdong Science and Tech-nology Press Beijing China 2011
[37] X F Sun Material Mechanics China Science Publishing ampMedia Ltd Beijing China 2009
16 Advances in Civil Engineering