SUBMITTAL PACKAGE/ITEM COMMENT AND STAMP SHEET

Fortis Construction Pte. Ltd.'s Comment and/or Stamp

Consultant's Comment and/or Stamp

Syahrizan.Selamat
Text Box
This rev 1 copy is after internal review. Separate RA/SWP/ITP/SD and IFC to refer for the actual works
Syahrizan.Selamat
SGA Stamp
Craig Watkins Aedas
Microsoft Word - B_Stamp
Craig Watkins Aedas
Text Box
07.06.21

METHOD OF STATEMENT FOR FLOOR SCREEDING AND HARDENER WORKS FOR PROJECT SGA-EXTERNAL SERVICES BUILDINGS AND STRUCTURES

Rev.no 0

PROJECT TITLE: PROJECT SGA

EXTERNAL SERVICES BUILDINGS

AND

STRUCTURES

METHOD OF STATEMENT FOR FLOOR SCREEDING AND HARDENER WORKS FOR PROJECT SGA-EXTERNAL SERVICES BUILDINGS AND STRUCTURES

Rev.no 0

METHOD STATEMENT

FOR

FLOOR SCREEDING AND HARDENER WROKS

(Architectural)

Doc.

Rev

No.

Date Remarks/Description of Revision /

Status

Prepared

by

Checked

by Approved by

Reviewed

by

0

24 FEB 21

Initial Submission Aung Muhammad Song

TOP PAVE PTE LTD

Maureen
Text Box
WORKS

METHOD OF STATEMENT FOR FLOOR SCREEDING AND HARDENER WORKS FOR PROJECT SGA-EXTERNAL SERVICES BUILDINGS AND STRUCTURES

Rev.no 0

Content

Contents

1. Introduction ....................................................................................... 4

2. Scope of Works ................................................................................. 4

3. Construction Resources .................................................................... 4

4. Construction Methodology of Floor Screeding ................................... 4

4.1. Preparation Work ......................................................................... 4

4.1.1. Clearances ................................................................. 4

4.1.2. Level Checking ........................................................... 4

4.1.3. Cleaning ..................................................................... 5

4.1.4. Mixing ......................................................................... 5

4.2. Application of E-Mix Screed Eco .................................................. 5

5. Construction Methodology of Floor Hardener .................................... 6

5.1. Preparation Work ......................................................................... 6

5.1.1. Surface Preparation ................................................... 6

5.2. Application ................................................................................... 6

6. Curing ............................................................................................... 6

METHOD OF STATEMENT FOR FLOOR SCREEDING AND HARDENER WORKS FOR PROJECT SGA-EXTERNAL SERVICES BUILDINGS AND STRUCTURES

Rev.no 0

1. Introduction

The methodology outlines the sequence of works for the proposed installation of Floor Screeding and

Hardener Works as the part of the Construction of Contract.

2. Scope of Works

1. To deliver approved materials in pallets form to respective work areas including proper designated covered storage area.

2. To do setting out based on given dimension in approved drawings. 3. To mix the E-Mix Easi screed cement sand mortar evenly with water in mixer prior to spreading

the mix onto the existing floor. 4. To mix the Nitroflor Hardtop hardener evenly with water in mixer prior to spreading the mix onto

the existing floor. 5. Housekeeping and periodic cleaning.

3. Construction Resources

Index Plant and Equipment

1 Electrical Mixer

2 Wooden / Steel Float

3 Spade

4 Laser Pointer

5 Yellow Plastic Pail

6 Trowel

7 Measuring Container

8 Measurement Tape

9 Wheel Barrow

4. Construction Methodology of Floor Screeding

4.1. Preparation Work

4.1.1. Clearances

1. Ensure that structural and MEP clearances are obtained prior to proceeding with works

4.1.2. Level Checking

1. Before commencing with any works, to conduct the setting out & check reference points. 2. Ensure supervisor to have a set of approved shop drawings showing the levels such as FFL /

SFL.

Maureen
Text Box
With Reference to approved: Submittal #03 35 00-2 Revision 0: SGA0_033500_Sbmtl_Site_ScreedProduct https://app.procore.com/503376/project/submittal_logs/20157091 & Submittal #03 35 00-3 Revision 1: SGA0_03 35 00_Sbmtl_Site_Concrete Hardeners and Sealers https://app.procore.com/503376/project/submittal_logs/22120715
Maureen
Text Box
Ensure that necessary preceding architectural works (example: waterproofing) had been done, inspected, tested and accepted
Hugo
Text Box
IFC
Hugo
Line
Hugo
Text Box
AED: To indicate whether any control joint/dividing strip is required & what is the spacing requirements before carrying out screed works

METHOD OF STATEMENT FOR FLOOR SCREEDING AND HARDENER WORKS FOR PROJECT SGA-EXTERNAL SERVICES BUILDINGS AND STRUCTURES

Rev.no 0

3. Ensure to check the levels that has given and marked on site with approved shop drawing. If the levels are same, proceed to start the works.

4. Upon completion of the level checking, start to build level pegs as per required and approved levels. If finishing floor is purely screed, level pegs will be at the height of the approved levels reflected within shop drawing. At areas where a gradient in the finished floor is required, varying screed level peg height will be prepared accordingly.

5. In the event floor finishes are tiled, height of level pegs will have to deduct thickness of tile and tiling adhesive.

6. Level peg shall be installed at proper intervals.

4.1.3. Cleaning

1. The substrates must be clean and sound, free from dust and loose particles. 2. Ensure that the MEP openings on the slab such as floor drains are provided with temporary

protection, so as to prevent clogging when screed is laid. Protection is to be by the respective MEP contractors

3. Cement laitance, oil, grease mould release oil or curing compound must be removed from concrete surfaces.

4. Voids underneath should be avoided. 5. A layer of slurry (cement with water ratio 1:6) to apply to the concrete surface to enhance the

bonding properties.

4.1.4. Mixing

1. Add 40 bag of E-mix screed eco with approximately 5.0 – 6.4 liters of clean water into a clean site stir/mix with a low speed side facing mini barrel type concrete mixer until a desired homogeneous mix is achieved by approximately 3 to 5 minutes.

2. A measuring container is used to measure 6 liters of water required for each mix and use the yellow pail of 6 liters in volume is used.

4.2. Application of E-Mix Screed Eco

1. Prior to screed work, apply bonding agent onto the floor surface when necessary. (No bonding agent is applied to areas where there is geotextile membrane)

2. Apply E-Mix Easi Screed Eco onto the substrate using a wooden/steel float or trowel. 3. A maximum thickness of 10-40 mm can be applied per application. 4. For screed with thickness of 50-100 mm, it is recommended to apply in multiple coats. 5. For screed with thickness more than 50mm, wire mesh will be required to be installed. 6. The first coat should act as textured key for subsequent coat to improve adhesion. 7. Textured key should be done using a wire scratcher. In during that period, shall be

compaction the screed by the vibrator (Air compressor). 8. Under-laying layer should be cured for at least 12 hours before application of new layer. 9. E-Mix Floor Screed should be cured for at least 24 hours prior to any floor tiling or floor

granite works. 10. Once the screeding has completed, must have to check the levelling as per the approved

shop drawing. 11. Ensure to make M&W specs finishes, as on the floor finishing levels.

Maureen
Text Box
slurry bond coat (consider adding bonding agent)
Maureen
Text Box
As per approved material manufacturer's recommendations:
Maureen
Text Box
(non-oxidizing metal mesh)
Maureen
Text Box
(refer to the approved material technical data)
Maureen
Text Box
The area should be protected from foot traffic immediately after completion until the screed has set. Provision of barricade is recommended.
Hugo
Text Box
AED: To indicate how bonding agent is being applied : To ensure floor should not have any water ponding while applying bonding agent

METHOD OF STATEMENT FOR FLOOR SCREEDING AND HARDENER WORKS FOR PROJECT SGA-EXTERNAL SERVICES BUILDINGS AND STRUCTURES

Rev.no 0

5. Construction Methodology of Floor Hardener

5.1. Preparation Work

5.1.1. Surface Preparation

1. Surface to be treated with Nitoflor Hardtop must be structurally sound and free from loose

materials. 2. Cracks or holes can be repaired using a recommended Fosroc repair material that should be

allowed to cure prior to start work. 3. Oil and grease contaminated surfaces should be treated with suitable chemical de-greaser

followed by washing with clean water and allowed to dry. 4. Any laitance or existing coating must be removed prior to application by mop, as this will

prevent Nitoflor Hardtop from penetrating. 5. If the concrete surface is dusty, dilution of Nitoflor Hardtop at 1:1 ratio with water is

recommended as first coat so as to allow the low viscosity solution penetrates into the pores of the concrete and get absorbed.

6. Subsequent coats without dilution are required.

5.2. Application

1. Ensure the surface to be treated is dry and apply the mixed Nitoflor Hardtop at a rate approximately 1 litre to every 10 m² using a soft broom or brush.

2. Allow the solution to be absorbed into the floor for a period of up to 2 hours, any solution not absorbed after this period should be removed. Failure to do so will result in the formation of weak, glossy surface film following the drying.

3. Normally two to three coat application is recommended for complete treatment. 4. For a very dense, well-trowelled surfaces such as granolithic toppings, power floated or

vacuum dewatered concrete will generally require only a single coat. 5. If a second coat is necessary, reapply the solution after 24 hours ensuring that the floor is dry.

6. Curing

1. Covered the floor screed and hardener with polyethylene sheet for at least 7 days to prevent drying out.

2. Floor screeding is to be protected against damages, wear and contamination.

---END---

Maureen
Text Box
As per approved material manufacturer's recommendations:
Maureen
Text Box
please include illustrations or photos on what to expect for item 6 and for all the rest of the items, as applicable.
Hugo
Text Box
AED: Also check for hollowness
Hugo
Text Box
AED: To indicate the timing after completion of screed before applying the hardener?