successful workface planning - groupasi.netgroupasi.net/conferencelibrary/2014/awpc 2014 - bentley -...

26
Successful WorkFace Planning 10% Technology, 90% Sociology

Upload: others

Post on 11-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

Successful WorkFace Planning10% Technology, 90% Sociology

Page 2: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

2 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated2 | WWWWW.WWWW.BEBEBEBEBEB NTNTNTNTN LEY.COM | ©©©© © ©© 2222220101010101222 Bentley SySyststemmmemems,s,s,s,s,sss IIIIncncncncncororppop rar ted2 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Robin M. Mikaelsson PMP

Senior Construction ConsultantQuick Bio:• Over 20 years in the construction industry• Started as a tradesman in the field• In 2000 Completed education in process pipe engineering (SAIT and University of

Houston)• Worked as a engineering design lead for several years• In 2003 completed education in Project Management and obtained PMP credentials

(PMI)• Returned to the field in construction management• Helped develop the original WFP model• Worked as WFP manager on many major industrial projects from 3million to 20billion• Continues to work with industry bodies to further develop the WFP philosophy

(Committee member with both COAA and CII)• Joined Bentley in 2009 and has a global roll in working with clients to further their

WFP implementations in order to better utilize ConstructSim• Now lives with his wife and two children on Skeleton Lake in northern Alberta (Lower

area of the Alberta Oil Sands)

Page 3: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

3 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated3 | WWWWW.WWWW.BEBEBEBEBEB NTNTNTNTN LEY.COM | ©©©© © ©© 2222220101010101222 Bentley SySyststemmmemems,s,s,s,s,sss IIIIncncncncncororppop rar ted3 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Page 4: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

4 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

The Need For Innovation• Success in construction is elusive

• Independent Project Analysis (IPA) study of 318 projects > $2B:

• 65% of projects FAILED, experiencing either:• > 25% cost overrun

• > 25% schedule slip

• Significant underperformance of the asset once constructed

Page 5: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

5 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

What is the Answer?

Improve Visibility & Predictability!

Adoption of WFP Principles in Heavy Industrial Construction

Page 6: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

6 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

But….

Page 7: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

7 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

• Many stove pipe systems for data and processes – nosingle point of truth

• Data flow between engineering, fabricators, construction and commissioning typically not connected

• No change management technology in place to support change processes

• Work packages – Manually created versus assembled and published– Readiness or completeness managed by spreadsheets– Lack alignment with work processes – No consistency & poor integration with project controls

Challenges to Visibility, Risk Reduction

Page 8: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

8 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

• Leverage our core competencies in engineering & information management– Modular and scalable

• Our system comprises of:– Construction business process management services– Graphical and non-graphical work packaging, look ahead planning,

status visualization and reporting tools– Connections to other enterprise systems

• Built on enterprise proven products– eB platform– ConstructSim platform– Bentley’s open enterprise interoperability strategy

Build “off the shelf software”…

Page 9: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

9 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Bentley Construction Solution

Connecting Project Data…

ININ IN IN ININININ

Models MaterialsSchedule Cost Plan EquipmentManyothersERPResources

Enabling

Work packagemanagement

Engineering model & data management

Field based QA/QC

Dashboards & reports

Field based work progressing

Status visualisation, Look ahead

planningChange management

Page 10: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

10 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Technology is out there…

Page 11: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

11 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Instant Updates From The Field

Page 12: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

12 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Bentley Mobile AppsField Supervisor Create personalized views into project data sources on an

iPadInspectTech Collector Mobile Inspect transportation assets, capture photos, and create

reports on an iPadMap Mobile View Bentley Map information models on Andriod devices

Navigator Mobile Review 3D models and documents on an iPad

Navigator Pano Review Review 3D design models on an iPad

ProjectWise Explorer Mobile Create, browse, and view ProjectWise documents on an iPad

Structural Synchronizer View View structural models on an iPad

Page 13: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

13 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Making it Work

M || ©©© © 222010101110 2 2 22 BeBentleeeeeeeey y y SySySySySySySyststss emememmemmmss,sss,,s, IIIIIIIncnncnncncncoororrrrrooorrrrorrrorppppoooopppoooooorararaarateeeeetteted

Page 14: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

14 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated14 | WWWWWWW.W.W.W.W.W BEBEBEBEBENTNNN LEY.COMM || © © © © ©© © 22220101000 2 Bentley y SySyststtemmmememmmms,s,s,ss,s,s IIIncncnnn ororo poorated14 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Silent Killers

Page 15: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

15 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

10) Alignment of Rates and Rules of Credit (ROC)

• ROCs need to align with IWPs• ROCs need to be flexible in separation of

code groupings• ROC must be structured to allow single

crew completion of IWP

Page 16: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

16 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

9) Complete work procedures• Detailed outline for dept. operation• Training and onboarding• Work Package content• Clear deliverables of stake holders

Page 17: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

17 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

8) Regular monitoring and audits• Use of cold eyes reviews• Third party auditors• Required standards • Established metrics

Page 18: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

18 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

7) Appropriately staffed positions• Planners need to have skills specific to the

area of planning• Managers need to have a working

knowledge of the Best Practice Model• Administrators of WFP/AWP systems

require specific skill sets

Page 19: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

19 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

6) Management buy in and understanding• All management needs to support planning

efforts• Staffing requirements need to be protected• Supply of required resources• Understanding the difference between

Planners and Schedulers

Page 20: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

20 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

5) Material management alignment with WP content and process

• CWP/IWP boundaries need to be established in material system

• Ability to request at component level• Appropriate level of tracking into

construction

Page 21: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

21 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

4) Support of all phases for WPs• Engineering following standard on EWPs

based on CWP boundaries• Construction completion of CWPs• IWP aligned to hierarchy• Path of construction supported by

deliverables

Page 22: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

22 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

3) IWP Constraint management• IWPs need to be controlled by priority• IWP release plans need to be followed• Look ahead plans must be in place• Physical constraints must be satisfied• Feedback loop must be in place

Page 23: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

23 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

2) A time and place for everything• Planners need to be located near and

embedded with the construction craft • EWPs / CWPs need to be completed well

ahead of the IWPs• FIWP release plan need to be complete

based in the CWPs• IWPs need to be completed ahead of time

but not to far in advance to lose the influence of the field

Page 24: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

24 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Best Practice Lessons Learned

1) Contractual alignment• Expectations of stakeholders• Process standards• Required data specification• Reporting intervals• Required deliverables• JV integration and interface management• Ownership and accountability

Page 25: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

25 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated25 | WWWWWWW.W.W.W.W.W BEBEBEBEBENTNNN LEY.COMM || © © © © ©© © 22220101000 2 Bentley y SySyststtemmmememmmms,s,s,ss,s,s IIIncncnnn ororo poorated25 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Question & Answer

Page 26: Successful WorkFace Planning - groupasi.netgroupasi.net/conferencelibrary/2014/AWPC 2014 - Bentley - Successf… · PMP Senior Construction Consultant Quick Bio: ... • In 2003 completed

26 | WWW.BENTLEY.COM | © 2012 Bentley Systems, Incorporated

Thank you!Senior Construction Consultant

Robin M. Mikaelsson PMP

Bentley SystemsSkeleton Lake, Alberta

Canada+1 587 777 0407

[email protected]