Weekly Activity Submission Form
ABERDEEN BUSINESS SCHOOL
Master of Science in Project Management (Distance Learning)
Weekly Activity Submission Form
Name:
Murat Islam
Email:
Course: MSc Project Management (Distance Learning)
Module:
Project Commercial Integrity
(SUM104)
Assignment and
Title:
Activity No: 6
Activity Title: Introduction to Planning Software:
Microsoft Project
Date:
27 March 2015
For the attention
of the Module
Coordinator
(SUM104):
Toni Fisher
Number of pages
in submission:
Read nos: (a) &
(b) below
Agree to both (a) & (b): Insert your Signature/Confirm
by writing your full name here: Ivan Messaggi
Before submitting ensure:
(a) That the work undertaken for this assignment is entirely your own and
that you have not made use of any unauthorised assistance;
(b) That the sources of all references material have been properly
acknowledged.
BY SUBMITTING THIS DOCUMENT YOU ARE CONFIRMING STATEMENTS (a)
AND (b) ABOVE
Schedule 0
Baseline Constraints: Work between 8am-12pm and 1pm-5pm
Schedule 1
Additional Constraints to Previous Schedule: Work between 8am-12am and 1pm-5pm and Stop on Fridays at 4pm
Schedule 2
Additional Constraints to Previous Schedule: Christmas holidays: 25-26 Dec 14 and 1-2 Jan 15
Schedule 3
Additional Constraints to Previous Schedule: Trades holiday, 2nd week in August (11-15 Aug 14)
Schedule 4
Additional Constraints to Previous Schedule: Resource X cannot work in period 22-31 Dec 14 and 1-4 Jan 15
Resource Levelling 1
Levelling Approach for the above constrained Schedule: Float only & Fixed Units
Resource Levelling 2
Levelling Approach for the above constrained Schedule: Adjusted Task Assignments
Resource Levelling 3
Levelling Approach for the above constrained Schedule: Adjusted Task Assignments and Priorities
Selected Project Schedule based on the Levelled Resources
Resource Levelling 3 with further adjustments: Adjusted Task Assignments and Priorities
An additional for Resource X (100%) to be hired and working on weekends are allowed only for Resource X at a Rate
of 1.5 x Normal Rate (£22.5/hr) between 26/11/2014 – 22/01/2015. Task K and L are based on a Weekend Calendar.
RESULT: £11,100 cost and 1week lead time increase based on the over allocated resource case. 1st and 2nd levelling
options haven’t been selected due to excessive lead time or resource allocation requirements.
Updates to Above Levelled Baseline
A As schedule B Started 2days late
C As schedule D As schedule E Finished 1 wk late
F As schedule G Finished 1 day early
H As schedule I As schedule J Started 2 days early
K 75% complete L 25% complete
M As schedule N ----
O 75% complete