Sunrise Powerlink Transmission Project Weekly Monitoring Report No. 01469 From: Through: 02/20/2011 02/26/2011 INTRODUCTION ALL LINKS Alpine RFO: No ground disturbing work conducted. Alpine Construction Yard: Set up of additional field offices initiated. San Luis Rey Substation: Roel completed work for 69 kV line on south side of new circuit breaker. Biological monitor on site. Great Horned Owl nest buffer in place. Work conducted on Sunday, with approval from the City of Oceanside, 2/20/2011. Rough Acres Construction Yard: PAR conducting steel tower assembly and moving their activities to the JVR Yard. TTS-I continues to receive steel deliveries. The Wash Station on site is being used several times daily to prevent the spread of weeds. Driveway improvements conducted. Encina Switchyard: Roel building new control shelter. Foundation in and block work being done. Excavating for gas circuit breaker pads and switch stands. Anderson drilling During the week of 02/20/2011 through 02/26/2011, construction continued at the Alpine RFO, Alpine Construction Yards, San Luis Rey Substation, Encina Switchyard, the Rough Acres Construction Yard Phase I & II Use, the Thomas Yard, Link 4 Underground, Link 3, Suncrest Substation, for NTP No. 13 for Links 1, 2 & 5, non-Federal lands only, and the Imperial Valley Substation. Pre-Construction Activity with appropriate monitors: Monday, 2/21/2011: Five crews verified tower and reference points at EP 106-3, EP 107-3, EP 105-2, EP 109-1, EP 106-3, EP 182, EP 183, EP 184-1, EP 185-1, EP 186-1. Tuesday, 2/22/2011: Four crews verified tower and reference points at EP 143-1, EP 144, EP 145, EP 146, EP 147, BLM Land. Two PAR crews conducted staking at EP 191-2, EP 193-2, EP 243, EP 196-2, EP 197-3 and EP 198-3B. Wednesday, 2/23/2011: Crews conducted existing access road staking at EP 68 to EP 70, EP 67 to EP 70 and EP 71 to EP 79. Two PAR crews conducted staking at EP 83, EP 87-1, EP 88-2, EP 85-2, EP 93, EP 94, EP 95 and EP 96. Thursday, 2/24/2011: Crews conducted existing access road staking at EP 75-2, EP 76-2, EP 78 and EP 79. Two PAR crews conducted staking at EP 102-3, EP 102A-1, EP 103-2, EP 108-2, EP 97, EP 98-1, EP 99-2, EP 101-2. Friday, 2/25/1011: Crews conducted reference point verification at EP 187-2, EP 188-1, EP 200A-1, EP 201-3, EP 173-1, EP 174, EP 175. Two crews set reference points at EP 187-1, EP 188-1, EP 200A-1 and EP 201-3. One crew staked existing access roads at EP 105-2, EP 112-3 to EP 113-4 and EP 116. Two PAR crews conducted staking at EP 113-5, EP 114-2, EP 115-1, EP 116-1, EP 109-1, EP 110-2, EP 111-4, EP 112-3, EP 112A-1. Saturday, 2/26/2011: Two PAR crews conducted staking at EP 121A-1, EP 122-1, EP 123-1, EP 124, EP 117-2, EP 118-2, EP 119-2, EP 121-3. Native American Representatives: The following Representatives monitored during this period at various construction sites: Campo: Dan Mason, Andrea Najera, Albert Quihuis, Frank Salazar. Viejas: Clarence Brown, Frank Brown, Vera Tucker. Cocopah: Alan Hatcher. Jamul: Jesse Pinto. Kumeyaay Native: Dave Elliot Sr., Dave Z. Elliot Jr. Wildlife Reporting: The following listed or Species of Special Concern were found dead in Project construction limits during this period: Yellow-rumped Warbler (Dendroica coronate) During this reporting period, a rain event began on 2/25/2011 with precipitation occurring through 2/26/2011. The following precipitation totals have been recorded for this period: Link 1: 0.4 to 4.0 inches; Link 2: 1.1 inches; Link 3: 1.5 inches; Link 4: 1.5 inches; Link 5: 1.7 to 0.65 inches; Alpine HQ/Yard: 1.5 inches; Rough Acres Yard: 0.4 inches, Encina Switchyard: 0.9 inches. Pre-storm inspections were conducted and maintenance of BMPs was conducted as identified. In Link 2 and Link 3, precipitation of 1.5 inches was recorded in a period of less than 24-hours, causing a breach of BMPs. (A post-storm inspection identified areas where BMP maintenance and improvement was initiated.) Minor leaks and drips from equipment were contained and cleaned. Leaks and drips are also recorded in the SWPPP log along with reporting to appropriate agencies as needed. Summary of Construction Yard activities where monitors were on site for any set-up and ground disturbing activities: JVR: TTS-I yard set-up complete; PAR utilizing the yard. Visual screening fence slatting modifications in progress. Helix: Access road improvements in progress. Hartung: Two active red-tailed hawk nest with buffers in place causing a halt to construction access. Bartlett-Hauser Creek: Field office set up and road improvements in progress. Kreutzkamp: TTS-I yard set-up in progress. SWAT: TTS-I yard set-up and access road improvement in progress. Page 1 of 60 Weekly Monitoring Report f_dr_02c

Upload: lydien

Post on 07-Sep-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

INTRODUCTION

ALL LINKS

Alpine RFO: No ground disturbing work conducted. Alpine Construction Yard: Set up of additional field offices initiated.

San Luis Rey Substation: Roel completed work for 69 kV line on south side of new circuit breaker. Biological monitor on site. Great Horned Owl nest buffer in place. Workconducted on Sunday, with approval from the City of Oceanside, 2/20/2011.

Rough Acres Construction Yard: PAR conducting steel tower assembly and moving their activities to the JVR Yard. TTS-I continues to receive steel deliveries. The WashStation on site is being used several times daily to prevent the spread of weeds. Driveway improvements conducted.

Encina Switchyard: Roel building new control shelter. Foundation in and block work being done. Excavating for gas circuit breaker pads and switch stands. Anderson drilling

During the week of 02/20/2011 through 02/26/2011, construction continued at the Alpine RFO, Alpine Construction Yards, San Luis Rey Substation, Encina Switchyard, theRough Acres Construction Yard Phase I & II Use, the Thomas Yard, Link 4 Underground, Link 3, Suncrest Substation, for NTP No. 13 for Links 1, 2 & 5, non-Federal landsonly, and the Imperial Valley Substation.Pre-Construction Activity with appropriate monitors:Monday, 2/21/2011: Five crews verified tower and reference points at EP 106-3, EP 107-3, EP 105-2, EP 109-1, EP 106-3, EP 182, EP 183, EP 184-1, EP 185-1, EP 186-1.Tuesday, 2/22/2011: Four crews verified tower and reference points at EP 143-1, EP 144, EP 145, EP 146, EP 147, BLM Land. Two PAR crews conducted staking at EP 191-2,EP 193-2, EP 243, EP 196-2, EP 197-3 and EP 198-3B.Wednesday, 2/23/2011: Crews conducted existing access road staking at EP 68 to EP 70, EP 67 to EP 70 and EP 71 to EP 79. Two PAR crews conducted staking at EP 83, EP87-1, EP 88-2, EP 85-2, EP 93, EP 94, EP 95 and EP 96.Thursday, 2/24/2011: Crews conducted existing access road staking at EP 75-2, EP 76-2, EP 78 and EP 79. Two PAR crews conducted staking at EP 102-3, EP 102A-1, EP103-2, EP 108-2, EP 97, EP 98-1, EP 99-2, EP 101-2.Friday, 2/25/1011: Crews conducted reference point verification at EP 187-2, EP 188-1, EP 200A-1, EP 201-3, EP 173-1, EP 174, EP 175. Two crews set reference points at EP187-1, EP 188-1, EP 200A-1 and EP 201-3. One crew staked existing access roads at EP 105-2, EP 112-3 to EP 113-4 and EP 116. Two PAR crews conducted staking at EP113-5, EP 114-2, EP 115-1, EP 116-1, EP 109-1, EP 110-2, EP 111-4, EP 112-3, EP 112A-1.Saturday, 2/26/2011: Two PAR crews conducted staking at EP 121A-1, EP 122-1, EP 123-1, EP 124, EP 117-2, EP 118-2, EP 119-2, EP 121-3.

Native American Representatives: The following Representatives monitored during this period at various construction sites: Campo: Dan Mason, Andrea Najera, Albert Quihuis,Frank Salazar. Viejas: Clarence Brown, Frank Brown, Vera Tucker. Cocopah: Alan Hatcher. Jamul: Jesse Pinto. Kumeyaay Native: Dave Elliot Sr., Dave Z. Elliot Jr.

Wildlife Reporting: The following listed or Species of Special Concern were found dead in Project construction limits during this period:Yellow-rumped Warbler (Dendroica coronate)

During this reporting period, a rain event began on 2/25/2011 with precipitation occurring through 2/26/2011. The following precipitation totals have been recorded for thisperiod: Link 1: 0.4 to 4.0 inches; Link 2: 1.1 inches; Link 3: 1.5 inches; Link 4: 1.5 inches; Link 5: 1.7 to 0.65 inches; Alpine HQ/Yard: 1.5 inches; Rough Acres Yard: 0.4inches, Encina Switchyard: 0.9 inches. Pre-storm inspections were conducted and maintenance of BMPs was conducted as identified. In Link 2 and Link 3, precipitation of 1.5inches was recorded in a period of less than 24-hours, causing a breach of BMPs. (A post-storm inspection identified areas where BMP maintenance and improvement wasinitiated.) Minor leaks and drips from equipment were contained and cleaned. Leaks and drips are also recorded in the SWPPP log along with reporting to appropriate agenciesas needed.

Summary of Construction Yard activities where monitors were on site for any set-up and ground disturbing activities:JVR: TTS-I yard set-up complete; PAR utilizing the yard. Visual screening fence slatting modifications in progress. Helix: Access road improvements in progress. Hartung:Two active red-tailed hawk nest with buffers in place causing a halt to construction access. Bartlett-Hauser Creek: Field office set up and road improvements in progress.Kreutzkamp: TTS-I yard set-up in progress. SWAT: TTS-I yard set-up and access road improvement in progress.

Page 1 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011Encina Switchyard: Roel building new control shelter. Foundation in and block work being done. Excavating for gas circuit breaker pads and switch stands. Anderson drillingon site.

Thomas Yard: No ground disturbing work being conducted. The Link Lead monitored for any Burrowing Owls during activity on site.Link 4 Underground:Vaults 2L. Excavation continues at the exit pit to the Hwy 8 Jack and Bore (North Side of I8), V15L, V18L, V8L, V13L, V2L, V9L. Potholing was conducted Alpine Blvd. fromSouth Grade Rd. west for 700¿, from 1850 Alpine Blvd west to Tavern Rd. Drilling/saw cutting was conducted at V7L, V6R, V13L, V3R, V4R, V5R, V19L, V16L, V7R.Trenching was conducted at V7, V15, V14, V18 and East of West Willows Road. Work continues for the Bauer Bridge. BMPs in other areas checked for any neededmaintenance before expected rain. Minor hydraulic fluid leaks were reported and were immediately contained, cleaned up and were not in storm water, waterways or ESAs.Reporting was made to the County of San Diego, Storm Water Hotline.

Link 3 Suncrest Substation and Wilson Yard: Rough grading along the access road and pad. Blasting was conducted on the eastern and western slopes on the pad. Boulderswere moved from the road to the pad. BMP installation maintenance conducted in many areas, as needed. Wilson yard set-up by TTS-I complete. Variance for the water supplypond and secondary entrance has been approved and work is scheduled.Links 1, 2 & 5, NTP No. 13: Note: No work conducted on Monday, 2/21/2011, Holiday. Link 1: Conventional foundations conducted at EP 244, EP 218-1, 217-1, EP 215, EP214, EP 213, EP 211, EP 210 and EP 219-1. Helicopter structure assembly at EP 230-1, EP 245-1, EP 44, EP 238-1, EP 237-1, EP 234-1, EP 233-1, EP 232-1, EP 231A , EP227, EP 199-3, EP 194-2, EP 197-2, EP 195-1. Micropile drilling conducted at EP 238-1, EP 235-1, EP 231A, EP 231-1, EP 229-1, EP 226-1, EP 224-1, EP 223-1, EP 221-Aand EP 230-1. Conventional structure assembly at EP 206-1, EP 203-3, EP 200A, EP 205-2, EP 209-1, EP 204-3, EP 202-3, EP 201-3, EP 208, EP 207, EP 218-1, and EP 217-1.12kV relocation continued on the West side of McCain Valley Road.

Link 2: Installation of a radio communications site at EP 87-1 TSAP. Soil boring at EP 85-2. Erosion repair and BMP maintenance on access roads to EP 84 and EP 85-2.TSAP grading and structure clearing at EP 79, EP 80, EP 81, EP 87. Clearing scheduled but not started because of fly permit at CP 51-2 and CP 45-1 TSAPs.Link 5: Installation of a radio communications site at CP 108 TSAP. Soil boring at CP 20. Access road rough grading at CP 31-2. Conventional foundation installation at CP17-1.

Imperial Valley Substation Upgrade: Foundation work continues for new 500 circuit breaker stands. Drilling conducted for the piers. On February 22, 2011, a small collectionof freshwater mollusks were recovered from the excavated sediments by the Paleontologist. These paleontological discoveries were from the Lake Chuilla sediments. No workwas stopped or diverted.

ENVIRONMENTAL MONITORS

LINK: 1

ASM Affiliates, Inc. Adam Giacinto

ASM Affiliates, Inc. Daniel Ryan McCarthy

ASM Affiliates, Inc. Isabell Cordova

ASM Affiliates, Inc. Patrick Hadel

ASM Affiliates, Inc. Shelby Gunderman

ASM Affiliates, Inc. Thomas Taylor

Burns & McDonnell Rebecca Carson

Chambers Group Ana Hernandez

Chambers Group Andy Steyers

Page 2 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL MONITORS

LINK: 1

Chambers Group Brett Bergman

Chambers Group Brian Lohstroh

Chambers Group Brant Primrose

Chambers Group Brent Riemer

Chambers Group Ben Rosenbaum

Chambers Group Chris Bugbee

Chambers Group Caesara Brungraber

Chambers Group Carina Weber

Chambers Group David Flietner

Chambers Group Erik Strods

Chambers Group Gerhard Bombe

Chambers Group Garrett Huffman

Chambers Group John Dicus

Chambers Group John Kanlund

Chambers Group Kari Kerwin

Chambers Group Laurie Gorman

Chambers Group Melanie Dicus

Chambers Group Michael W. Klein

Chambers Group Robert Thompson

Chambers Group Sean Han

Chambers Group Saraiah Skidmore

Chambers Group Tamara Bryant

Chambers Group Tyler Sears

Pangea Biological Amanda Castro

Pangea Biological Don Spires

Pangea Biological Eric Piehel

Pangea Biological Mark V. Bahn

Pangea Biological Steve Ehrilich

Page 3 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL MONITORS

LINK: 1

Pangea Biological Tim Cass

LINK: 2

ASM Affiliates, Inc. Stephen Rochester

ASM Affiliates, Inc. Thomas Taylor

Burns & McDonnell Randy Burke

Burns & McDonnell Rosina Gallego

Chambers Group Ana Hernandez

Chambers Group Andy Steyers

Chambers Group Brian Arnold

Chambers Group Brant Primrose

Chambers Group Chris Bugbee

Chambers Group Darin Busby

Chambers Group Drew Engstrom

Chambers Group Gretchen Cummings

Chambers Group Jennifer Edwards

Chambers Group Michael W. Klein

Chambers Group Ryan Quilley

Chambers Group Robert Thompson

Chambers Group Seth Reimers

Chambers Group Saraiah Skidmore

Chambers Group Shane Valiere

LINK: 3

ASM Affiliates, Inc. Brian Williams

ASM Affiliates, Inc. Lucas Piek

Pangea Biological Mark Meridith

TRC Solutions, Inc. Alicia Hill

TRC Solutions, Inc. Randy Blake

Page 4 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL MONITORS

LINK: 4

ASM Affiliates, Inc. Daniel Ryan McCarthy

ASM Affiliates, Inc. Jessica Hennessey

ASM Affiliates, Inc. Jason Kjolsing

ASM Affiliates, Inc. Thomas Taylor

Burns & McDonnell Jeff Smith

Burns & McDonnell Ken Katsuda

Chambers Group Ben Rosenbaum

TRC Solutions, Inc. Katherine Vittum

TRC Solutions, Inc. Michael Scaffidi

TRC Solutions, Inc. Nina Allmendinger

LINK: 5

Chambers Group Ben Rosenbaum

Chambers Group Chris Bugbee

Chambers Group Jennifer Edwards

Chambers Group Melanie Dicus

Chambers Group Shane Valiere

Chambers Group Tamara Bryant

Chambers Group Tyler Sears

LINK: ALL

Chambers Group Caesara Brungraber

Chambers Group Jennifer Edwards

Chambers Group Linette Lina

LINK: NA

ASM Affiliates, Inc. Isabell Cordova

ASM Affiliates, Inc. Meagan Papp

Burns & McDonnell Jim Gibson

Chambers Group Brent Riemer

Chambers Group Chris Bugbee

Page 5 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1AQ-APM-4

EP 24402/22/2011 Y Carpooled with the Native American monitor toand from the work site.Remarks: Work was in compliance.

Mitigation Measure in Compliance? Y

B-1cEP24302/21/2011 Y All work in compliance

Remarks: Verified bird surveys with Chambersnesting monitors.biomonitoring

Mitigation Measure in Compliance? Y

ENVIRONMENTAL MONITORS

LINK: NA

Chambers Group Carina Weber

Chambers Group Fern Hoffman

Chambers Group Jacqueline Boudreau

Chambers Group Melanie Dicus

Chambers Group Michael W. Klein

Chambers Group Seth Reimers

Chambers Group Shane Valiere

Chambers Group Tamara Bryant

San Diego Natural History Museum Bradford O. Riney

San Diego Natural History Museum Gino Calvano

San Diego Natural History Museum Patrick J. Sena

TRC Solutions, Inc. Lauralyn Jensen

TRC Solutions, Inc. Okorie Puryear

Page 6 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

EP21302/22/2011 Y Contractors in compliance with general andbiological mitigation measures includingremaining within approved footprint, outside ofESAs, no fluids leaks from equipment andvehicles. No sensitive wildlife species harmed.Remarks: Contractor (MacTec) inspected rebarcages for tower footings.

Mitigation Measure in Compliance? Y

EP21302/22/2011 Y All work performed by contractor was incompliance and all mitigation measures weremet

Mitigation Measure in Compliance? Y

EP-209,EP-214

02/22/2011 Y A crew smoothed out sand berms along twoentrances to the ROW and the entrance toRough Acres Ranch with no environmentalimpacts.

Mitigation Measure in Compliance? Y

EP-21502/22/2011 Y Provided biological monitoring for rebardelivery at EP-213. Provided biologicalmonitoring for eco-pan delivery at EP-215. Allwork done was in compliance. Site was leftclean.

bio.monitoringMitigation Measure in Compliance? Y

EP231-102/22/2011 Y Monitored micropile drilling.Remarks: Work was in compliance.

biomonitorMitigation Measure in Compliance? Y

EP224-102/22/2011 Y All work in compliance. Activities at the siteincluded drilling at to leg "B", which wasfinished at the end of the day (6 piles).Biomonitor

Mitigation Measure in Compliance? Y

238-102/22/2011 Y Micropile work in compliance.Remarks: All work in compliance

biomonitorMitigation Measure in Compliance? Y

Page 7 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

EP 221-A02/22/2011 Y The Par/Baxter crews cleared soil andjackhammered rock around the leg structures atEP 221-A and EP 230-1 in preparation for themicropile crew. The crew was reminded theyhad to keep all construction activity inside thepermanent work area, not trim any vegetation,and create a soil ramp at the low edge of anexcavation to prevent the entrapment of animals.Remarks: Crews in compliance

Compliance metMitigation Measure in Compliance? Y

ROUGHACRESRANCH-(RAR)

02/22/2011 Y Remarks: Rough Acres Ranch (RAR)- Tuesday,Feb 22, 2011. Contractors-Par, TTSI, Maxim,Nordic Rentals. TTSI- organized steel andmaterials. Maxim- organized wire reels, wait forreels. Nordic Rentals- Delivered water to Bakertanks. PAR- QA/QC tower structures.

complianceMitigation Measure in Compliance? Y

JacumbaValleyRanchYard

02/22/2011 Y Remarks: Conducted biological monitoring foractivities at the Jacumba Valley Ranchconstruction yard. This included: Par personnelcontinued constructing fly towers. Four cranesand four skylifts were used throughout the dayerecting towers and loading helicopter. Airoperations included one heavy lift helicopter andseveral smaller helicopters. There wereapproximately thirty to forty people working atJacumba Valley Ranch yard.

Mitigation Measure in Compliance? Y

221A, 224,226, 229,230-1,231-A, 238

02/22/2011 Y Oversight & management of monitoring. PAR 1)EP218, conventional drilling. 2) EP217,conventional drilling. 3) EP220, access road. 4)EP243, rebar delivery. 5) EP215, 12kvrelocation.

oversightMitigation Measure in Compliance? Y

EP24402/22/2011 Y Bio monitor was present throughoutconstruction activities and all work was incompliance.Remarks: All work in compliance.

Bio monitoringMitigation Measure in Compliance? Y

Page 8 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

THOMASYARD

02/22/2011 Y Remarks: All mitigation measures met duringtower assembly.Mitigation Measure in Compliance? Y

RoughAcresRanch

02/22/2011 Y A crew cleaned and maintained the entrance toRough Acres Ranch and checked on SWPPPBMP's. No environmental impacts occurred.

Mitigation Measure in Compliance? Y

EP-217-1102/22/2011 Y Compliance met biological monitor on-site.Remarks: Compliance met; biological monitoron-site. PAR and URS crews on-site drillingEP-217-1 structural legs a,b,c and d.

BiomonitoringMitigation Measure in Compliance? Y

EP22002/22/2011 Y All observed work was environmentallycompliant

biomonitoringMitigation Measure in Compliance? Y

EP 21902/22/2011 Y Monitored drilling operations at structure siteEP 219. All activities were kept within thedesignated work area and all environmentalmitigation measures were followed.BioMonitor

Mitigation Measure in Compliance? Y

EP 229-102/22/2011 Y Biological monitor completed pre-activitysweep of area including 500-foot buffer. Noactive nests, etc. were observed. Monitorobserved crew excavating micropiles forsoutheastern foot of tower. Crew remainedwithin flagged work limits and otherwiseavoided and minimized impacts.Remarks: Monitor was present throughout day;no impacts occurred.

Bio MonitoringMitigation Measure in Compliance? Y

EP213,215, 217,220

02/22/2011 Y Oversight of monitoring efforts for EP213, 215,217, 220,.Remarks: All drilling/rebar crews were incompliance.

biomonitoringMitigation Measure in Compliance? Y

Page 9 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

EP-21502/22/2011 Y Machine graded road between EP-214 andEP-215.Remarks: All was compliantGeneral

Mitigation Measure in Compliance? Y

DesertRoseRanchRoad

02/23/2011 Y Remarks: Desert Rose Ranch Road mobile homedecon. Crews segmented mobile home intosections then sealed exposed edges with plastictarp, and installed wheels on bottom fortransport at a later date, in presence ofbiological monitor. All mitigation measures infull compliance.

Home DeconstrucMitigation Measure in Compliance? Y

EP 229-102/23/2011 Y All micropile work was in compliance.Remarks: Biological monitor conductedpre-clearance sweep and monitored constructionactivities at EP 229-1 throughout the day.

Bio MonitoringMitigation Measure in Compliance? Y

EP21702/23/2011 Y Foundation crew performed all work withinenvironmental complianceRemarks: No environmental issues observed. Allmitigation measures met

Bio MonitoringMitigation Measure in Compliance? Y

THOMASYARD

02/23/2011 Y Remarks: All mitigation measures met duringtower assembly.Mitigation Measure in Compliance? Y

EP213 andRoughAcresRanchdriveway.

02/23/2011 Y Bio monitor was present throughoutconstruction activities and all work was incompliance.Remarks: All work in compliance during BMPinstallation.

Bio monitoringMitigation Measure in Compliance? Y

EP-224-102/23/2011 Y Micropile drilling, dust was kept at a minimum.All was compliant with mitigation.Remarks: All was compliantMicropile

Mitigation Measure in Compliance? Y

EP231-102/23/2011 Y All work in compliance during drilling for guywires and micropile operations.Remarks: In ComplianceBiomonitoring

Mitigation Measure in Compliance? Y

Page 10 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

EP 21902/23/2011 Y All activities met mitigation requirements.Remarks: Monitored drilling operations atstructure site EP 219 and escorted equipment toEP 215. All activities were kept within thedesignated work area and all environmentalmitigation measures were followed.

BioMonitorMitigation Measure in Compliance? Y

EP 21402/23/2011 Y All mitigation measures are metRemarks: Area is in compliance during drillingholes for structure base.MMs met

Mitigation Measure in Compliance? Y

EP231-102/23/2011 Y Monitored micropile drilling at EP231-1Remarks: Crew was in compliance. No majorissues arose.

Mitigation Measure in Compliance? Y

EP 238-102/23/2011 Y Work in compliance during micropileoperations.Remarks: Site was kept clean and free of debris.

Mitigation Measure in Compliance? Y

EP-214102/23/2011 Y Compliance met bio-monitor present andon-site.Remarks: PAR crews noted as in compliance forall applicable mitigation measures. PAR movedfrom site 217 to 214 to work on digging holesfor structure legs. Equipment not left on-sitedue to the drainage adjacent to the pad site at214.

Compliance metMitigation Measure in Compliance? Y

EP224,226, 229,231-1, 238

02/23/2011 Y Oversight & management of micropile drillingEP224, 226, 229, 231-1 & 238

oversightMitigation Measure in Compliance? Y

EP21702/23/2011 Y All drilling and concrete work in compliance.Remarks: Monitored inspectors on overheadsites along McCain Valley Rd. All incompliance.

biomonitoringMitigation Measure in Compliance? Y

Page 11 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

EP22002/23/2011 Y Contractors in compliance with general andbiological mitigation measures includingremaining within approved footprint, outside ofESAs, no fluids leaks from equipment andvehicles. No sensitive wildlife species harmed.Remarks: Air drilling contractor worked ontower footing excavation preparation at EP220.

Mitigation Measure in Compliance? Y

JacumbaValleyRanchYard

02/23/2011 Y Remarks: Assembling fly towers and helicopteroperations. Par and Crux were the majorcontractors on site. The newly formed pondswere checked for animals. The yard waschecked for signs of new bird nests.

Mitigation Measure in Compliance? Y

EP21702/23/2011 Y All observed work was environmentallycompliant.Remarks: Monitored foundation pouring atEP217.

biomonitoringMitigation Measure in Compliance? Y

EP21902/24/2011 Y All mitigation measures were met.Remarks: All ground and steel work incompliance.biomonitoring

Mitigation Measure in Compliance? Y

EP21102/24/2011 Y Contractors in compliance with general andbiological mitigation measures includingremaining within approved footprint, outside ofESAs, no fluids leaks from equipment andvehicles. No sensitive wildlife species harmed.Remarks: Rebar foundation cages delivered toEP211.

Mitigation Measure in Compliance? Y

EP 21502/24/2011 Y All activities met mitigation requirements.

BioMonitorMitigation Measure in Compliance? Y

EP238-102/24/2011 Y Remarks: Drilling was in compliance.Mitigation Measure in Compliance? Y

Page 12 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

DesertRose Road

02/24/2011 Y Work was in compliance.Remarks: Construction crew at Desert RoseRoad mobile home prepared house for transportby cutting the house into smaller sections, andthen putting wheels under those segments, inpresence of biological monitor. All mitigationmeasures in compliance.

House DeconMitigation Measure in Compliance? Y

EP224,226, 229,231-1,235-1, 238

02/24/2011 Y Oversight & management of monitors for:CRUX micropile drilling: EP224, 229, 231-1,235-1, 238. CRUX micropile grouting:EP231-ARemarks: All work in compliance.

oversightMitigation Measure in Compliance? Y

ThomasYard

02/24/2011 Y Remarks: Monitored PAR at the Thomas Yard.Par has been constructing a tower at thislocation for practice to trouble shoot and takenotes on any manufacturer problems. PARfinished the tower today so the manufacturercame out to get a copy of the notes and look atthe issues.

Mitigation Measure in Compliance? Y

EP 231-102/24/2011 Y Remarks: Crux crew 2 finished up at tower legA of STR EP 231-1 and moved the rig over toleg B. All work performed in compliance.Compliance Met

Mitigation Measure in Compliance? Y

EP-214102/24/2011 Y Compliance met; biologist present and on-sitemonitoring PAR work crews while theycontinued backfilling holes and pumping outgroundwater.Remarks: Chambers Group bio-monitor on-site.Bio-monitors worked with all crews on-site toremain in compliance.

Compliance metMitigation Measure in Compliance? Y

JacumbaYard

02/24/2011 Y Area in compliance with APM'sMitigation Measure in Compliance? Y

Page 13 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

EP8402/24/2011 Y Remarks: Monitored Crux with URS at EP84.Crux conducted a soil test drill at a depth ofabout 50 feet. URS collected core samples.

Mitigation Measure in Compliance? Y

RoughAcresRanch

02/24/2011 Y All work was within limits, no vehicle idlingwas observed.Remarks: All work was in compliance. TTSIaccepted steel and organized loads. UnitedContractors picked up steel posts andtransported to Bartlett yard. PAR picked upsteel posts and transported to Bartlett yard.Maxim Cranes unloaded cable reels. NordicEquipment Rental filled baker tanks with water.

Mitigation MetMitigation Measure in Compliance? Y

12KV02/24/2011 Y Three poles framed and set for 12KV line.Remarks: All was compliant

GeneralMitigation Measure in Compliance? Y

EP 224-102/24/2011 Y All mitigation measures are metRemarks: Area is in compliance

MMs metMitigation Measure in Compliance? Y

EP21702/24/2011 Y All work performed within environmentalcompliance. All mitigation measures have beenmetRemarks: Monitored breakdown of concreteform supports by Par crew at EP217

Bio MonitoringMitigation Measure in Compliance? Y

EP 238-102/24/2011 Y Work in compliance during micropileoperations.Remarks: Site was kept clean and free of debris.

Mitigation Measure in Compliance? Y

EP231a -Jacumba

02/24/2011 Y Biological monitoring for grout foundation wrkRemarks: All Construction Work was incompliance with the MMCRPBio Monitoring

Mitigation Measure in Compliance? Y

Page 14 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

EP235-102/24/2011 Y Remarks: Crews were in compliance duringdrilling operations.Mitigation Measure in Compliance? Y

EP229-102/24/2011 Y Biological monitor completed pre-activitysweep of area including 500-foot buffer. Noactive nests, etc. were observed. Monitorobserved crew complete excavation of southeastfooter and began work on northeast footer.Crew remained within flagged work limits andotherwise avoided and minimized impacts.Remarks: Biological monitor was present atEP229-1 throughout the day. Crew compliedwith all migitation measures.

Bio MonitoringMitigation Measure in Compliance? Y

DesertRoseRanch Rd

02/25/2011 Y Remarks: Crews at Desert Rose Ranch Rdfinished installation of plastic tarp on exposededges of home segments in preparation of stormin presence of biological monitor. All mitigationmeasures in compliance.

Home DeconstrucMitigation Measure in Compliance? Y

EP-21502/25/2011 Y Provided bio monitoring for the installation of arock dip section just north of EP-215. All workwas in compliance. Site was left clean.bio. monitoring

Mitigation Measure in Compliance? Y

EP 221-202/25/2011 Y Remarks: Drilling in compliance.Mitigation Measure in Compliance? Y

EP21502/25/2011 Y Contractors in compliance with general andbiological mitigation measures includingremaining within approved footprint, outside ofESAs, no fluids leaks from equipment andvehicles. No sensitive wildlife species harmed.

Mitigation Measure in Compliance? Y

EP21102/25/2011 Y All work performed within environmentalcompliance and mitigation measures met.Remarks: Delivery of (2)foundation re-bar cagesto site.

Bio MonitoringMitigation Measure in Compliance? Y

Page 15 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

EP21502/25/2011 Y All mitigation measures met.Remarks: Drilling, relocation of 12kV line andrebar inspection in compliance.biomonitoring

Mitigation Measure in Compliance? Y

EP231-Aand 226-1

02/25/2011 Y Work was in complianceRemarks: Crew began grout and finished twolegs.

Mitigation Measure in Compliance? Y

EP221-2,224, 226,231-1,231-A,235-1, 238

02/25/2011 Y Oversight and management of the monitoring:CRUX micropile drilling: EP224, 229, 231-1,235-1, 238 CRUX grouting: EP231-A, 226-1PAR micropile preparation: EP221-2oversight

Mitigation Measure in Compliance? Y

RoughAcresRanch

02/25/2011 Y All work was within limits, no vehicle idlingwas observed.Remarks: All work was in compliance.Mitigation Met

Mitigation Measure in Compliance? Y

EP 21902/25/2011 Y All activities met mitigation requirements.Remarks: Monitored drilling operations atstructure site EP 219. All activities were keptwithin the designated work area and allenvironmental mitigation measures werefollowed.

BioMonitorMitigation Measure in Compliance? Y

EP224-102/25/2011 Y All work completed by micropiling crew was incompliance.Mitigation Measure in Compliance? Y

EP 224-102/25/2011 Y All mitigation measures are metRemarks: Area is in compliance

MMs metMitigation Measure in Compliance? Y

EP 231-1and EP231-A

02/25/2011 Y Remarks: Crux crew 2 finished up at tower legB of STR EP 231-1 and moved the rig over toleg C. A separate grouting crew was workingover at tower EP 231-A. All work incompliance.

Compliance MetMitigation Measure in Compliance? Y

Page 16 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

JacumbaYard

02/25/2011 Y Area in compliance with APM'sMitigation Measure in Compliance? Y

12kVRelocation,E. ofMcCainValley Rd.

02/25/2011 Y Framed and set one pole. Strung wire from eachpole site. Placed and hung transformer.Remarks: All was compliantGeneral

Mitigation Measure in Compliance? Y

EP-211,EP-214102/25/2011 Y PAR crews on-site bio-monitor present. Thecrews worked on backfilling the holes with fillfrom EP-217 and from EP-214. Constructioncrews continued working on access roads on theROW. Fill was removed from EP-211 to use forEP-214.Remarks: Mitigation measures in compliance.Bio-monitor on-site.

Compliance metMitigation Measure in Compliance? Y

EP235-102/25/2011 Y Remarks: In compliance

biomonitorMitigation Measure in Compliance? Y

EP 229-102/25/2011 Y Work was in compliance.Remarks: Biological monitor conductedpre-activity sweep of work area and 500-footbuffer and monitored micropile excavationthroughout the day.

Bio MonitoringMitigation Measure in Compliance? Y

EP226-102/26/2011 Y Monitored grouting at EP226-1. All work incomplianceMitigation Measure in Compliance? Y

EP235-102/26/2011 Y Monitored micorpile drilling at EP235-1. Allwork in compliance.

BioMonitorMitigation Measure in Compliance? Y

Page 17 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-1c

JacumbaYard

02/26/2011 Y Remarks: PAR cancelled activity due toinclement weather. CRUX and helicopteroperations continued until noon.

Mitigation Measure in Compliance? Y

EP224-102/26/2011 Y Monitored micropile drilling at EP224-1Remarks: All work in compliance.

BioMonitorMitigation Measure in Compliance? Y

EP224-102/26/2011 Y Monitored micropile drilling at EP224-1. Allwork in compliance.

BioMonitorMitigation Measure in Compliance? Y

EP21902/26/2011 Y All work performed by contractor was inenvironmental compliance and all mitigationmeasures were metRemarks: Monitored Par Electrical drill crew atEP219.

Bio MonitoringMitigation Measure in Compliance? Y

RoughAcres Yard

102/26/2011 Y Bio-monitor on-site compliance met.Complications due to weather impacted PARcrews and only 1 crew was working on theROW. CRUX crews accepted deliveries from ElCentro yard to be taken to Link 5.Remarks: All applicable monitors were presentfor work activities.

Compliance metMitigation Measure in Compliance? Y

EP 231-102/26/2011 Y Monitored micropile drilling. All work incompliance

BioMonitorMitigation Measure in Compliance? Y

EP224,EP226,EP229,EP231-1,EP235,EP238

02/26/2011 Y Oversight & management of monitoring ofCRUX micropile drilling: EP224, 229, 231-1,235-1, 238; CRUX micropile grouting: 226-1Oversight

Mitigation Measure in Compliance? Y

Page 18 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-2a

EP21702/23/2011 Y All work performed within complianceRemarks: Foundation work performed withindesignated boundaries. Eco-pans utilized bycontractor

Bio MonitoringMitigation Measure in Compliance? Y

EP 238-102/23/2011 Y Remarks: All micropile construction occurredwithin approved limits.Mitigation Measure in Compliance? Y

EP 238-102/24/2011 Y Remarks: All micropile construction occuredwithin approved limits.Mitigation Measure in Compliance? Y

EP 221-202/25/2011 Y Remarks: Construction limits staked andflagged.Mitigation Measure in Compliance? Y

B-5aEP22002/22/2011 Y Sticky Geraea Special status plant populations were staked or

flagged.biomonitoringMitigation Measure in Compliance? Y

B-7iEP 230-102/22/2011 N No Quino Checkerspot observed

Remarks: QCB-permitted biologist present inQCB-occupied habitat during construction.QCB Habitat

Mitigation Measure in Compliance? Y

EP226-102/22/2011 N QuinoCheckerspotButterfly

No QCB observed todayRemarks: Cold day, few nectar sourcesflowering, no primary host plant observed

QCB, few nectMitigation Measure in Compliance? Y

Page 19 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1B-7i

EP 229-102/23/2011 N Monitor examined buffer area surrounding workarea for QCB larval host plants. No larval hostplants were identified; seedlings are emergingand difficult to identify. Weather conditions atthe site are too cold for adult QCB activity.Remarks: Monitor holding QCB permit ispresent at EP 299-1, within QCB critical habitat.

QCB monitoringMitigation Measure in Compliance? Y

EP229-102/24/2011 N QCB-permit holding monitor was present onsite. No adult QCB activity was observed.Remarks: QCB-permitted biologist was presentthroughout day.

QCB monitoringMitigation Measure in Compliance? Y

EP 229-102/25/2011 N Conditions for adult QCB flight not met.Remarks: QCB monitor present on sitethroughout day.QCB monitoring

Mitigation Measure in Compliance? Y

BIO-APM-3EP21302/22/2011 Y Contractor in compliance with dust control

measures by use of water truck on access roads.Mitigation Measure in Compliance? Y

EP-217-102/22/2011 Y Water truck on-site watering roads.Remarks: Compliance met; water truck waswatering access roads to EP-217-1.Biomonitoring

Mitigation Measure in Compliance? Y

JacumbaValleyRanchYard

02/22/2011 Y All areas of the yard were watered well enoughto prevent dust.Remarks: many contractors using the facilitydust compliance

Mitigation Measure in Compliance? Y

EP21302/22/2011 Y All work performed by contractor was incompliance and all mitigation measures weremet. Dust was adequately controlled duringwork activities.

Mitigation Measure in Compliance? Y

EP226-102/22/2011 Y Water buffalo onsite and used during drillingRemarks: Drilling in compliance

DustMitigation Measure in Compliance? Y

Page 20 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1BIO-APM-3

JacumbaValleyRanchYard

02/23/2011 Y Soil watered frequently to control dust.Mitigation Measure in Compliance? Y

EP21102/24/2011 Y Contractor in compliance with dust controlmeasures by use of water truck.Mitigation Measure in Compliance? Y

JacumbaYard

02/24/2011 Y Water truck keeping dust downMitigation Measure in Compliance? Y

EP21502/25/2011 Y Contractor in compliance with dust controlmeasures by use of water truck.Mitigation Measure in Compliance? Y

EP21302/25/2011 Y All work performed within complianceRemarks: Delivery of (2)Eco-pans to EP213

Bio MonitoringMitigation Measure in Compliance? Y

EP238-102/25/2011 Y Micropile drilled with regular watering tominimize fugitive dust.Remarks: Work was in compliance.

Mitigation Measure in Compliance? Y

JacumbaYard

02/25/2011 Y Water truck kept dust downMitigation Measure in Compliance? Y

BIO-APM-4EP 21402/23/2011 Y Construction area limits in compliance

Remarks: Construction activities restrictedwithin predetermined area limitsWork limits

Mitigation Measure in Compliance? Y

EP 224-102/24/2011 Y Construction area limits in complianceRemarks: Construction activities restrictedwithin predetermined area limitsWork limits

Mitigation Measure in Compliance? Y

Page 21 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1C-1e

EP-21402/22/2011 Y Remarks: All road grading was monitored by acultural monitor and a Native Americanmonitor. No new cultural artifacts were found.cultural

Mitigation Measure in Compliance? Y

EP 24402/22/2011 Y The crew was compliant with allowing thearchaeologist and Native American monitor toobserve the placement of the BMPs and siftthrough the soil. Two artifacts that were foundin the work area were removed by thearchaeologist and Native American monitor andplaced outside the work area.

Mitigation Measure in Compliance? Y

McCainValley Rd /WuestProperty

02/23/2011 Y All work observed by Archaeological andNative American Monitors was in compliance

CulturalMitigation Measure in Compliance? Y

Tower 7902/23/2011 Y PAR cleared brush from tower location 79Remarks: No new cultural material wasobserved today.Cultural

Mitigation Measure in Compliance? Y

McCainValley Rd /WuestProperty

02/24/2011 Y All work observed by Archaeological andNative American Monitors was in compliance

CulturalMitigation Measure in Compliance? Y

IVSubstationaccessroadd

02/24/2011 Y Remarks: All digging for mph signage wasmonitored by a cultural monitor and performedin compliance.cultural

Mitigation Measure in Compliance? Y

BartlettYard andRoughAcres

02/24/2011 Y Remarks: Conducted archaeological montioringof locations EP 220 and EP 215. Both requiredBMP work, as they had been impacted by theprevious weekend's rather substantial rain andlight snow. Work was completed at EP 215, andall activites were found to be in compliance.Grading of Potrero Truck Trail was notcompleted. The activity at this location was alsoin compliance.

In complianceMitigation Measure in Compliance? Y

Page 22 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1C-1e

RoughAcres/ EP215

02/25/2011 Y Remarks: Cultural Monitoring took place in twolocations associated with the structure EP 215area. The first, involved the disturbance ofground for a rock filled drainage on the accessroad just north of EP 215. The second, involvedstringing line and other activities associated withthe relocation of the 12 kv segment east ofMcCain Valley road. No previously recordedESAs were impacted, all activities were incompliance.

In ComplianceMitigation Measure in Compliance? Y

EP21902/25/2011 Y All work observed by Archaeological andNative American Monitor was in compliance

CulturalMitigation Measure in Compliance? Y

C-3aEP-21502/24/2011 Y Remarks: No cultural resources observed during

drilling for the replacement pole for the 12kVline.drilling EP 215

Mitigation Measure in Compliance? Y

CR-APM-3EP 214 andEP 211

02/25/2011 Y Remarks: Ground disturbance monitored at EP214 and EP 211. In compliance.Mitigation Measure in Compliance? Y

N-1aEP-217-102/23/2011 N Compliance met, PAR crews monitored by

bio-monitor.Remarks: Compliance met bio-monitor presentand on-site and vehicle idle time reduced whenfeasible.

Compliance metMitigation Measure in Compliance? Y

EP-214102/25/2011 N PAR reduced idle time when feasible.Remarks: Vehicle idle time was reduced whenfeasible. Large trucks reduced idle time on-site.Compliance met

Mitigation Measure in Compliance? Y

Page 23 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 1WQ-APM-13

JacumbaYard

Notified LinkLead

02/25/2011 Y Hydrocarbon sheen noticed at fueling station,floating on top of the rainwater collected in therubber basin. Absorbent pads were used toremove hydrocarbon sheen to the extentpossible. The liquid was pumped out into awater truck.

Mitigation Measure in Compliance? Y

EP235-102/26/2011 Y Remarks: Small hydraulic fluid leak, both linklead and SWPPP monitor modified. Visqueenused to catch additional drips; leak was fixed;contaminated soil was placed in trash bag andlabeled as hazardous material for transport offsite.

fluid leakMitigation Measure in Compliance? Y

LINK: 2B-1c

BartlettConstructionYard

02/20/2011 Y Inspected condition of Bartlett construction yardfollowing a 4.5 inch rain event over the previous48 hours. A temporarily installed sand bagcheck dam and repaired sand bag retaining wallprevented sediment from flowing off SE cornerof site during Saturday evening's rain event.Scheduled to monitor 900 MHz communicationvault work within yard, however, no crews wereon site. Inspected area around communicationvault to ensure that no ground nesting birds,reptiles, amphibians, or burrowing mammalswere present within the vicinity of thecommunication vault, should crews arrive tocomplete this work later in the day. No grounddisturbance would be necessary for this work,which involves only electrical wiring.

Mitigation Measure in Compliance? Y

Page 24 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 2B-1c

Bartlett/HauserConst.Yard

Notified LinkLead

32.65139,-116.50543902/21/2011 Y Prairie Falcon Remarks: While waiting for crew to arrive, aprairie falcon (Falco mexicanus) was spotted onthe top of a wooden pole adaject toBarlett/Hauser construction yard access road.Individual was observed alone and no activenest was seen.

Bio MonitorMitigation Measure in Compliance? Y

EP85-202/22/2011 Y Biological Monitors were onsite duringconstruction activities. All work was incompliance.

Mitigation Measure in Compliance? Y

EP85-202/22/2011 Y Contractors remained in compliance of allbiological mitigation measures.

CompliantMitigation Measure in Compliance? Y

BartlettYard

02/22/2011 Y Compliance metRemarks: Hankins installed rumble plates onBig Protero Truck Trail, (the access road toBartlett Yard). Pro Tool graded NW area ofBartlett yard and received 3 office trailers. AreaWest repaired blown down fence at north end ofyard. PAR steel delivery.

Mitigation Measure in Compliance? Y

EP12402/22/2011 Y Loska crew surveying reference points for LaPosta Truck Trail access road.Mitigation Measure in Compliance? Y

SWATConstructionYard

02/22/2011 Y All in compliance during fencing operations andBMP installation.Remarks: All construction activities were incompliance.

Mitigation Measure in Compliance? Y

Page 25 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 2B-1c

EP 86-1,EP79

02/23/2011 Y Crew was in compliance throughout the day atboth sites.Remarks: Once at each site, a laborer found awood rat midden (Neotoma spp.) in vegetationto be cleared. It was pulled slowly apart with arake to ensure no wildlife was injured duringvegetation clearing. Crew was given direction toavoid ESA, which was in close proximity toclearing at EP 79

Bio MonitorMitigation Measure in Compliance? Y

EP36-102/23/2011 Y During the assignment no sensitive species wereobserved and all activities were in compliance.The crew staked the center line (orange) for theaccess road to EP 39-1 and staked thepermanent (green) and temporary impact (blue)zone limits of EP 39-1.

Mitigation Measure in Compliance? Y

BartlettYard

02/23/2011 Y Compliance metRemarks: Hankins installed rumble plates onBig Protero Truck Trail, (the access road toBartlett Yard). Pro Tool graded NW area ofBartlett yard and received 3 office trailers. AreaWest repaired blown down fence at north end ofyard. PAR steel delivery.

Mitigation Measure in Compliance? Y

EP12402/23/2011 Y Loska crew surveying edge-of-road for La PostaTruck Trail access road.Mitigation Measure in Compliance? Y

RoughAcresentrance toEP-214

02/23/2011 Y All work was within limits, no vehicle idlingwas observed.Remarks: All work was in compliance duringthe loading of steel.

Mitigation MetMitigation Measure in Compliance? Y

EP85-202/23/2011 Y All road grading activity and straw wattleinstallation on the access road leading intoEP85-2 was in compliance with the Project'smitigation measures and the bio APMs.compliance

Mitigation Measure in Compliance? Y

Page 26 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 2B-1c

EP87-102/23/2011 Y All work was in compliance with all APMs andMitigation Measures. There were no impactsoutside of footprint nor environmental issuesrequiring attention.

Mitigation Measure in Compliance? Y

EP34 andEP33

02/24/2011 Y Remarks: All activities in compliance duringESA markouts.Mitigation Measure in Compliance? Y

EP 79 andEP 86

02/24/2011 Y Monitored the installation of two temporaryplatforms: one at EP79 and one at EP86.

Bio MonitorMitigation Measure in Compliance? Y

BartlettYard

02/24/2011 Y Compliance met. South driveway entrance toBartlett Yard staked with ESA signs and bufferestablished due to Spotted Towhee nest. Buffercreated to prevent access to southern portion ofdriveway entrance. Crews were notified ofchanges verbally and instructed to use northentrance instead.Remarks: Pro Tool renovated and installed 3office trailers. Area West repaired blown downfence at north end of yard. PAR steel deliveryand tower assembly. SDGE and PAR helicopteractivity throughout day. PRO Tool assembledtemporary TSAP.installed rumble plates on BigProtero Truck Trail, (the access road to BartlettYard). Pro Tool graded NW area of Bartlettyard and received 3 office trailers. Area Westrepaired blown down fence at north end of yard.PAR steel delivery.

Mitigation Measure in Compliance? Y

EP 80, EP81

02/24/2011 Y Crew was in compliance throughout the day.Remarks: At EP 80, a bird nest fragment wasfound on the ground prior to vegetation clearing.No birds were observed in the immediate areaand the cause of nest destruction was determinedto be natural.

Bio MonitorMitigation Measure in Compliance? Y

Page 27 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 2B-1c

SWATYard

02/24/2011 Y Remarks: Many people were touring the SWATYard deciding where different contractors willbe based. Crews continued building the fence atthe SWAT Yard. All posts are in the groundand half of the chain link is installed.

Mitigation Measure in Compliance? Y

EP12502/24/2011 Y Loska crew surveying edge-of-road for La PostaTruck Trail access road.Mitigation Measure in Compliance? Y

KreutzkampYard

02/25/2011 Y Remarks: Monitored TTSI while they installederosion control devices and removed cattle fencein the Kreutskamp Yard. Walked the yardlooking for new active nests. No active nestswere observed.

Mitigation Measure in Compliance? Y

EP85-202/25/2011 Y Biological Monitors were onsite duringconstruction activities. All work was incompliance.

Mitigation Measure in Compliance? Y

SWATYard

02/25/2011 Y Remarks: The crew finished installing the fenceat SWAT Yard. Barbed wire is approximatelyhalf finished.

Mitigation Measure in Compliance? Y

ThomasYard

02/25/2011 Y Remarks: Monitored PAR at the Thomas Yard.Par has been constructing a tower at thislocation for practice to trouble shoot and takenotes on any manufacturer problems. PARfinished the tower today so the manufacturercame out to get a copy of the notes and look atthe issues.

Mitigation Measure in Compliance? Y

EP8402/25/2011 Y Remarks: Monitored Crux with URS at EP84.Crux conducted a soil test drill at a depth ofabout 50 feet. URS collected core samples.

Mitigation Measure in Compliance? Y

EP36-1DeerhornValley

02/25/2011 Y Remarks: Surveyors were in compliance withthe MMCRP when staking boundaries.

Bio MonitoringMitigation Measure in Compliance? Y

Page 28 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 2B-1c

Accessroad toEP85-2

02/25/2011 Y Remarks: The BMP installation activities werein compliance with all mitigation measures.

In ComplianceMitigation Measure in Compliance? Y

BartlettYard

02/25/2011 Y Compliance metRemarks: Pro Tool renovated and installed stairsfor 3 office trailers. Area West repaired fence.PAR steel delivery and tower assembly. SDGEand PAR helicopter activity in morning.Geosyntec came by to enhance BMP's. NationalElectric Works worked on Bartlett Yard powerline at yard entrance.

Mitigation Measure in Compliance? Y

EP26 andEP27

02/25/2011 Y Remarks: ESA flagging was completed to advisepersonnel of Hermes Copper Butterfly hostplants (Spiny Redberry). No sensitive specieswere observed and all mitigation measures werein compliance.

Mitigation Measure in Compliance? Y

Bartlett/HauserCreekConstructionYard

02/26/2011 Y Work detail (tower assembly and materialdeliveries) was cancelled due to adverseweather.Biomonitor

Mitigation Measure in Compliance? Y

B-3aSWATYard

02/25/2011 Y All vehicles with caked on mud were cleaned.The crew used weed wash station #8.Mitigation Measure in Compliance? Y

BIO-APM-15BartlettYard

Sedimentsstabilized orerosion controlsinstalled

BartlettYard

02/26/2011 Y Monitored the installation of BMPs forstormwater and sediment control. Theseincluded additional sand bag check dams andstraw wattles. Installation of these additionalBMPs was at the recommendation of GeosyntecSWPPP monitors, because the previouslyinstalled BMPs were breeched.

Mitigation Measure in Compliance? Y

Page 29 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 2BIO-APM-3

SWATYard

02/24/2011 Y Vehicles were kept below speed limitMitigation Measure in Compliance? Y

C-1eEP85-202/23/2011 Y EP85-2 At the previously constructed access

road leading to EP85-2 from Lake MorenaDrive, Colwell was sent to re-grade a road toprevent further erosion and fix the erosioncaused by the previous winter storm. Monitoredthe bulldozer pulling dirt from the road to fix theerosion spots, no artifacts were noted. Somemodern trash was seen in the road (e.g. roofingtile, mortar, rubber tire pieces), but all of thatwas very recent. EP84 Sent to repair theaccess road to EP84, but were unable to accessthe portions needing repair due to standingwater under the advice of both the bio monitorand the SWPPP monitor that bringing in themachinery needed might cause complianceissues.

ArchaeologyMitigation Measure in Compliance? Y

EP8502/25/2011 Y Colwell installed BMPs along the access road totower EP85

CulturalMitigation Measure in Compliance? Y

LINK: 3B-1c

SuncrestSubstation

02/22/2011 Y Biological monitoring took place at Suncrestsubstation during dirt disturbance activities andbrush chipping in order to minimize impacts tothe wildlife. No sensitive species were impactedas a result of today's activities. No nesting birdbehavior was observed by the biological monitornor any nests were found.

Bio monitoringMitigation Measure in Compliance? Y

Page 30 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 3B-1c

Suncrestsubstation

02/22/2011 Y Rough grading and erosion control installationactivities remained within approved workboundaries.

Mitigation Measure in Compliance? Y

SuncrestsubstationPad

02/22/2011 Y A biologist was present during vegetationrelocation and cleanup work on the SuncrestSubstation pad and ROWBiological

Mitigation Measure in Compliance? Y

SuncrestSubstation

02/23/2011 Y Biological monitoring took place at Suncrestsubstation during dirt disturbance activities andbrush chipping in order to minimize impacts tothe wildlife. No sensitive species were impactedas a result of today's activities. No nesting birdbehavior was observed by the biological monitornor any nests were found.

Bio monitoringMitigation Measure in Compliance? Y

SuncrestsubstationROW

02/23/2011 Y A biologist was present during temporarydrainage repair and road grading on the ROW.

BiologicalMitigation Measure in Compliance? Y

SuncrestsubstationPad

02/23/2011 Y A biologist was present during dirt work on theSuncrest Substation pad.

BiologicalMitigation Measure in Compliance? Y

Suncrestsubstation

02/23/2011 Y Biological monitors were present and observedgrading activities.Mitigation Measure in Compliance? Y

SuncrestSubstationPad

02/24/2011 Y A biologist was present during dirt work on theSuncrest Substation pad.

BiologicalMitigation Measure in Compliance? Y

SuncrestSubstationROW

02/24/2011 Y A biologist was present during road grading onthe ROW.

BiologicalMitigation Measure in Compliance? Y

Page 31 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 3B-1c

SuncrestSubstation

02/24/2011 Y Biological monitoring took place at Suncrestsubstation during dirt disturbance activities inorder to minimize impacts to the wildlife. Nosensitive species were impacted as a result oftoday's activities. No nesting bird behavior wasobserved by the biological monitor nor any nestswere found.

Bio monitoringMitigation Measure in Compliance? Y

SuncrestsubstationPad

02/25/2011 Y A biologist was present during dirt work on theSuncrest Substation pad.

BiologicalMitigation Measure in Compliance? Y

Suncrestsubstation

02/25/2011 Y All required monitors were on site duringground disturbing activities.Mitigation Measure in Compliance? Y

SuncrestSubstation

02/25/2011 Y Biological monitoring took place at Suncrestsubstation during dirt disturbance activities inorder to minimize impacts to the wildlife. Nosensitive species were impacted as a result oftoday's activities..The biological monitor walkedthe first 3rd of the access road in search of nestsand nesting behavior. Several bird species wereobserved which included: Western scrub jay,common raven, red tailed hawk, Americankestrel, merlin, oak titmouse, wrentit, Westernbluebird, California towhee, dark eyed junco,acorn woodpecker, and white crowned sparrow.No nesting bird behavior was observed by thebiological monitor nor any nests were found.

Bio monitoringMitigation Measure in Compliance? Y

B-3aSuncrestsubstationaccessroad

02/22/2011 Y Vehicles observed along the ROW had beenwashed before coming to the job site and werewashed leaving job site.biological

Mitigation Measure in Compliance? Y

Page 32 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 3B-3a

Suncrestsubstationaccessroad

02/23/2011 Y Vehicles observed along the ROW had beenwashed before coming to the job site and werewashed leaving job site.biological

Mitigation Measure in Compliance? Y

Suncrestsubstationaccessroad

02/24/2011 Y Vehicles observed along the ROW had beenwashed before coming to the job site.

biologicalMitigation Measure in Compliance? Y

Suncrestsubstationaccessroad

02/25/2011 Y Vehicles observed along the ROW had beenwashed before coming to the job site.

biologicalMitigation Measure in Compliance? Y

B-8aSuncrestsubstationPad

02/22/2011 Y Observed ravens, california towhee, say'sphoebe, and a red-tailed hawk. Biologistobserved no active nests during monitoring ofconstruction.Biological

Mitigation Measure in Compliance? Y

Suncrestsubstationaccessroad

02/25/2011 Y A biologist conducted nest sweep alongSuncrest substation access road. Observedravens, red-tailed hawk, merlin, and acornwoodpecker. No nesting activity observed.Biological

Mitigation Measure in Compliance? Y

BIO-APM-3SuncrestsubstationPad

02/22/2011 Y No vehicles were observed by biologistexceeding 15mph.

BiologicalMitigation Measure in Compliance? Y

SuncrestsubstationPad

02/23/2011 Y No vehicles were observed by biologistexceeding 15mph.

BiologicalMitigation Measure in Compliance? Y

Suncrestsubstation

02/24/2011 Y Fugitive dust was controlled by regularapplication of water from trucks.Mitigation Measure in Compliance? Y

Page 33 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 3BIO-APM-3

SuncrestSubstationPad

02/24/2011 Y No vehicles were observed by biologistexceeding 15mph.

BiologicalMitigation Measure in Compliance? Y

SuncrestsubstationPad

02/25/2011 Y No vehicles were observed by biologistexceeding 15mph.

BiologicalMitigation Measure in Compliance? Y

C-1eSuncrestsubstation

02/22/2011 Y ESA cultural resource boundaries remainedundisturbed during work activityRemarks: Suncrest Substation grading and BellBluff Truck Trail expansion

culturalMitigation Measure in Compliance? Y

Suncrestsubstation

02/23/2011 Y ESA cultural resource boundaries remainedundisturbed during work activityRemarks: Suncrest Substation grading and BellBluff Truck Trail expansion

culturalMitigation Measure in Compliance? Y

Suncrestsubstation

02/24/2011 Y The cultural ESA boundaries were not impactedby contractor activity throughout the day.Remarks: Suncrest Substation grading and BellBluff Truck Trail expansion

culturalMitigation Measure in Compliance? Y

Suncrestsubstation

02/25/2011 Y Artifacts were recovered from two sitesRemarks: Suncrest Substation and Bell BluffTruck Trail expansioncultural

Mitigation Measure in Compliance? Y

Suncrestsubstation

02/26/2011 Y No artifacts were recovered due to rain event.Remarks: Suncrest Substation grading

culturalMitigation Measure in Compliance? Y

LINK: 4AQ-APM-4

AlpineBlvd, vault9

02/22/2011 Y Carpooled to the site location with the biologicalmonitor from TRC.

CulturalMitigation Measure in Compliance? Y

Page 34 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 4AQ-APM-4

AlpineBlvd

02/23/2011 Y Carpooled to and from the site location with thebiological monitors from TRC.

CulturalMitigation Measure in Compliance? Y

Vault 2L02/23/2011 Y Carpooled with the Native American monitor toand from the work site.Mitigation Measure in Compliance? Y

AlpineBlvd

02/24/2011 Y Carpooled to and from the site location withother monitors.

CulturalMitigation Measure in Compliance? Y

BauerProperty

02/24/2011 Y Carpooled with the other Archaeologicalmonitor to and from the work sites.Mitigation Measure in Compliance? Y

BauerProperty

02/25/2011 Y Carpooled with the other Archaeologicalmonitor to and from the work sites.Mitigation Measure in Compliance? Y

B-1cBauerBridge

02/21/2011 Y Remarks: Due to the holiday no constructionactivities occurred on Link 4. BMPs functionedas intended at Bauer Bridge.

Mitigation Measure in Compliance? Y

Vault 9,10, 11, 13

02/22/2011 Y Monitored PAR crews while trenching andpotholing. All excavations filled properly andtopped with asphalt. All observed constructionin compliance.Bio Monitoring

Mitigation Measure in Compliance? Y

Vaults 14 -19

02/22/2011 Y The crews remained in compliance with theproject's mitigation measures while saw cutting,drilling, pouring concrete, excavating, andpavingRemarks: Compliance met

MonitoringMitigation Measure in Compliance? Y

Page 35 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 4B-1c

AlpineBlvd

02/22/2011 Y Remarks: Crews were in compliance with allmitigation measures during excavating,predrilling, and paving activities today. Noimpacts occurred outside the ROW.Bio Monitor

Mitigation Measure in Compliance? Y

AlpineAve.

02/22/2011 Y Remarks: Construction activities along thewestern portion of Alpine Avenue consisted of;Drilling at Vault 7, excavations at Vault 8, andthe completion of the installation of Vault 3.

Mitigation Measure in Compliance? Y

AlpineBlvd

02/23/2011 Y Remarks: Crews were in compliance with allmitigation measures during excavating,saw-cutting, and pre-drilling today. No impactsoccurred outside the ROW.Bio Monitor

Mitigation Measure in Compliance? Y

Vaults 14 -19

02/23/2011 Y The crews remained in compliance with theproject's mitigation measures while pavementgrinding, drilling, pouring concrete, excavating,and pavingRemarks: Compliance met

MonitoringMitigation Measure in Compliance? Y

Vault 8,10, 13

02/23/2011 Y Monitored PAR crews while trenching, sawcutting and excavating. All excavations filledproperly and topped with plates and/or asphalt.All observed construction in compliance.Bio Monitoring

Mitigation Measure in Compliance? Y

Link 402/23/2011 Y All required monitors were onsite duringconstruction activities

monitorsMitigation Measure in Compliance? Y

AlpineAve.

02/23/2011 Y Remarks: Construction activities along thewestern portion of Alpine Avenue consisted of;drilling at Vault 6 and Vault 7, excavations atVault #2 and Vault #8. In addition workcommenced on the north side bore pit for the I-8crossing. All activities were undertaken incompliance with project mitigation proceduresand stipulations and no problems were observed.

Mitigation Measure in Compliance? Y

Page 36 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 4B-1c

AlpineHeadquarters

02/24/2011 Y Two crews finished excavating holes andinstalled metal plates on top of them. A thirdcrew cut strategic lines along the asphalt. Therewere no environmental impacts.

Mitigation Measure in Compliance? N

Link 402/24/2011 Y All required monitors were onsite duringconstruction activities

monitorsMitigation Measure in Compliance? Y

BauerBridge

02/24/2011 Y Monitored Pinnick crews at Bauer bridge whileworking on crane pad on north side of bridge.All observed construction in compliance.Bio Monitoring

Mitigation Measure in Compliance? Y

Jack &Bore Hwy8Exit Pit

02/24/2011 Y Monitored PAR crews during excavation of Jack& Bore exit pit at Bauer Property. Allconstruction in complianceBio Monitoring

Mitigation Measure in Compliance? Y

BauerBridge,AlpineBlvd

02/24/2011 Y Construction activities along Alpine Boulevardcontinue with excavation of the Bore pit on thenorth side of I-8 for this crossing, Drilling atVault #7, Excavation of Ins and Outs at Vault#9, saw cutting at Vaults #6 and #7, Excavationsat Vault #2 and Vault #8. In additionexcavations of the abutments for the BauerBridge were undertaken on the north side.Archaeological Monitors, Native AmericanMonitors, SWPPP and Biological Monitorswere present where required.

Mitigation Measure in Compliance? Y

Vaults 14 -19

02/24/2011 Y The crews remained in compliance with theproject's mitigation measures while drilling,pouring concrete, and excavatingRemarks: Compliance met

MonitoringMitigation Measure in Compliance? Y

AlpineBlvd

02/24/2011 Y Remarks: Crews were in compliance with allmitigation measures during excavating,saw-cutting, drilling, and welding today. Noimpacts occurred outside the ROW.Bio Monitor

Mitigation Measure in Compliance? Y

Page 37 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 4B-1c

Vaults 14L- 19L

02/25/2011 Y The crews remained in compliance with theproject's mitigation measures while drilling,pouring concrete, saw cutting, and excavatingRemarks: Compliance met

MonitoringMitigation Measure in Compliance? Y

Link 402/25/2011 Y All required monitors were onsite duringconstruction activities

monitorsMitigation Measure in Compliance? Y

BauerBridge

02/25/2011 Y Monitored Pinnick crews at Bauer bridge whileworking on crane pad on north side of bridge.All observed construction in compliance.Bio Monitoring

Mitigation Measure in Compliance? Y

Jack &Bore Hwy8Exit Pit

02/25/2011 Y Monitored PAR crews during excavation of Jack& Bore exit pit at Bauer Property. Allconstruction in complianceBio Monitoring

Mitigation Measure in Compliance? Y

AlpineBlvd

02/25/2011 Y Remarks: Crews were in compliance with allmitigation measures during excavating,saw-cutting, drilling, and setting manhole today.No impacts occurred outside the ROW.Bio Monitor

Mitigation Measure in Compliance? Y

Link 4,section B

02/25/2011 Y One crew poured slurry into an excavated holeand sealed it with metal plates. A secondexcavated a trench and installed a pipe. A thirdshaved an area of asphalt and covered it withmetal plates. No environmental impactsoccurred.

Mitigation Measure in Compliance? Y

B-7aVaults 14 -19

02/22/2011 Y Excavations were properly covered with steelplates and/or asphalt at the end of the work dayRemarks: Compliance metUnderground

Mitigation Measure in Compliance? Y

Vaults 14 -19

02/22/2011 Y Excavations were checked at least three times aday while monitoring vaults 14-19Remarks: Compliance metExcavation

Mitigation Measure in Compliance? Y

Page 38 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 4B-7a

Vaults 14 -19

02/23/2011 Y Excavations were properly covered with steelplates and/or asphalt at the end of the work dayRemarks: Compliance metUnderground

Mitigation Measure in Compliance? Y

Vaults 14 -19

02/23/2011 Y Excavations were checked at least three times aday while monitoring vaults 14-19Remarks: Compliance metExcavation

Mitigation Measure in Compliance? Y

Vaults 14 -19

02/24/2011 Y Excavations were properly covered with steelplates and/or asphalt at the end of the work dayRemarks: Compliance metUnderground

Mitigation Measure in Compliance? Y

Vaults 14 -19

02/24/2011 Y Excavations were checked at least three times aday while monitoring vaults 14-19Remarks: Compliance metExcavation

Mitigation Measure in Compliance? Y

Vaults 14L- 19L

02/25/2011 Y Excavations were properly covered with steelplates and/or asphalt at the end of the work dayRemarks: Compliance metUnderground

Mitigation Measure in Compliance? Y

Vaults 14L- 19L

02/25/2011 Y Excavations were checked at least three times aday while monitoring vaults 14L-19LRemarks: Compliance metExcavation

Mitigation Measure in Compliance? Y

B-8aVault 15Notified Link

Lead32°50'0'N,116°44'32'W

02/22/2011 Y A potential nest was observed near vault 15 andwas not observed to be in use.Remarks: Inactive large nest in a coast live oaktree along the right-of-way

NestingMitigation Measure in Compliance? Y

AlpineBlvd

Notified LinkLead

02/23/2011 Y Remarks: A 100-ft buffer was establishedaround a bushtit nest near Vault 2, excluding allbut foot traffic to prevent disturbing nestingbirds.Nest Buffer

Mitigation Measure in Compliance? Y

Page 39 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 4B-8a

Vault 15 &17

Notified LinkLead

32°49'59'N,116°44'18'W,32°50'0'N,116°44'34'W

02/23/2011 Y Two inactive nests were found near vaults 15and 17Remarks: Both nests were found on coast liveoaks just south of Alpine Blvd.

NestingMitigation Measure in Compliance? Y

165+50Suspend Work0521806,3633088NAD 83,11S

02/23/2011 Y Red-shoulderedHawk

Found active nest, work suspended and 8:15 and500' buffer in place (172+00 to 162+00

Active NestMitigation Measure in Compliance? Y

AlpineHeadquarters/Link4

Flagging installedE 521807,N 3633093

02/24/2011 Y Red-shoulderedHawk

Nest #35; the nest had previously been deemedactive, today a Red-shouldered hawk wasobserved entering the nest area and circling thetree (Eucalyptus)

Mitigation Measure in Compliance? Y

Vault 15 &17

Divert work in theimmediate areaand notified theLink Lead

32°50'0'N,116°44'33'W

02/24/2011 Y Bushtit An active bushtit nest was spotted south of vault15Remarks: A 100 ft buffer was establishedaround the nest

NestingMitigation Measure in Compliance? Y

AlpineBlvd

Notified LinkLead

02/24/2011 Y Remarks: 100-ft buffer established around activebushtit nest. Signs and flagging tape excluded allbut foot traffic.Nest Buffer

Mitigation Measure in Compliance? Y

Vault 17L,18L

Notified LinkLead

02/25/2011 Y Three medium-sized stick nests were foundsouth of Viejas Creek on two coast live oaktrees. A large stick nest was observed on aeucalyptus tree south of Vault 17LRemarks: The nests did not appear to have beenused while being observed by the biologicalmonitor.

NestingMitigation Measure in Compliance? Y

AlpineBlvd

02/25/2011 Y Remarks: 100-ft buffer established around activebushtit nest. Signs and flagging tape excluded allbut foot traffic.Nest Buffer

Mitigation Measure in Compliance? Y

Page 40 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 4BIO-APM-4

Link 402/23/2011 Y Link Leads carpooled together

carpoolMitigation Measure in Compliance? Y

Link 402/24/2011 Y Link Leads carpooled together.

carpoolMitigation Measure in Compliance? Y

Link 402/25/2011 Y Link Leads carpooled together.

carpoolMitigation Measure in Compliance? Y

C-1eAlpineBoulevard,Vault 8

02/22/2011 Y PAR excavated vault 8 and conducted potholingjust west of the intersection of East Victoria andAlpine Boulevard.Cultural

Mitigation Measure in Compliance? Y

AlpineBlvd, vault9

02/22/2011 Y Work was monitored by an archaeological andNative American monitor and all work was incompliance.Cultural

Mitigation Measure in Compliance? Y

Link 4underground

02/22/2011 Y All work was observed by an archaeological andNative American monitor

CulturalMitigation Measure in Compliance? Y

Vault 2L02/23/2011 Y The crew was compliant with allowing thearchaeologist and Native American monitor toobserve the excavation and sift through the soil.No artifacts were found during the day.

Mitigation Measure in Compliance? Y

Vault 18,AlpineBlvd

02/23/2011 Y Work was monitored by an archaeological andNative American monitor and all work was incompliance.Cultural

Mitigation Measure in Compliance? Y

AlpineBlvd, vault9

02/23/2011 Y Work was monitored by an archaeological andNative American monitor and all work was incompliance.Cultural

Mitigation Measure in Compliance? Y

Page 41 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 4C-1e

Link 4underground

02/23/2011 Y All work was observed by an archaeological andNative American monitor

CulturalMitigation Measure in Compliance? Y

Vault 18,AlpineBlvd

02/24/2011 Y Work was monitored by an archaeological andNative American monitor and all work was incompliance.Cultural

Mitigation Measure in Compliance? Y

Vault 2,AlpineBlvd

02/24/2011 Y Work was monitored by an archaeological andNative American monitor and all work was incompliance.Cultural

Mitigation Measure in Compliance? Y

BauerProperty

02/24/2011 Y The crew was compliant with allowing thearchaeologist and Native American monitor toobserve the excavation and sift through the soil.No artifacts were found during the day.

Mitigation Measure in Compliance? Y

BauerProperty

02/25/2011 Y The crew was compliant with allowing thearchaeologist and Native American monitor toobserve the excavation and sift through the soil.No artifacts were found during the day.

Mitigation Measure in Compliance? Y

Link 4underground

02/25/2011 Y All work was observed by an archaeological andNative American monitor

CulturalMitigation Measure in Compliance? Y

LINK: 5B-1c

HartungCY

02/23/2011 Y Par excavated a hole on the driveway leading tothe Hartung CY, followed by HankinsConstruction installing rebar in the hole. Therewere no environmental impacts.

Mitigation Measure in Compliance? Y

Page 42 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 5B-1c

Helix Yard(El CajonGolfCourse)

02/23/2011 Y Remarks: The Alternate Helix Yard Entrancewas monitored for birds, nests, and sensitivespecies of animals and plants. The area wasassessed and pictures were taken by the BioMonitor before and after the plants/trees weretrimmed by PAR personnel. The plants/treeswere were trimmed to allow better access forequipment to the Helix Yard. The plants/treesspecies that were trimmed are Tamarisk,Eucalyptus, California Pepper, Sugar Bush,Chinese Elm and Tree of Heaven. No Sensitivespecies were encountered.

Tree TrimmingMitigation Measure in Compliance? Y

HartungYard

02/24/2011 Y Remarks: Hankins crews pouring concrete andpaving Hartung yard entrance. Equipment usedwash station before re-entering public roads.All mitigation measures met.

Mitigation Measure in Compliance? Y

HelixYard/ LakeJennings/ElMonte Rd

02/24/2011 Y All work was in compliance.Remarks: The Helix yard and its surroundingperimeter were monitored for wildlife, birds andnests. Sensitive species were not encountered atthis site. Colwell equipment graded twoentrances to the Helix yard by removing thetopsoil, compacting the underlying soil andspreading a class 2 base and rocks in theentrance area. The soil density was tested.Grading was done to prepare the entry way forthe traffic of heavy machinery. Pictures weretaken before and after completion of thegrading. The Area West crew members securedthe Helix yard fence and Crux set-up and storeddrilling equipment.

GradingMitigation Measure in Compliance? Y

CP10802/24/2011 Y All work was in compliance with all APMs andMitigation Measures. There were no impactsoutside of footprint nor environmental issuesrequiring attention.

Mitigation Measure in Compliance? Y

Page 43 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 5B-1c

Helix /HartungYard

02/25/2011 Y Remarks: Monitored all activity at Helix andHartung Yards. All mitigation measures met.Mitigation Measure in Compliance? Y

CP 51-202/25/2011 Y Remarks: Crew was in compliance.

Compliance MetMitigation Measure in Compliance? Y

CP 45-102/25/2011 Y Remarks: Crew remained in compliancethroughout the day.

Bio MonitorMitigation Measure in Compliance? Y

69kVReconductor,near TowerCP2

02/25/2011 Y All work in compliance during BMPinstallation.

BiomonitorMitigation Measure in Compliance? Y

Helix /HartungYard

02/26/2011 Y Remarks: Par crews fill dirt and place steelplates along entrance to Hartung Yard, allequipment removed from site.

Mitigation Measure in Compliance? Y

B-7aHartungYard

02/24/2011 Y Remarks: A Hawks nest (#8) along the entranceto Hartung Yard was confirmed as active, linklead notified. Lead reports that SDGE willtemporarily allow road improvement to continuebecause the road is an emergency access fornearby Hartung residence.

Mitigation Measure in Compliance? Y

B-8aHartungCY

Flagging installedE 515341 N3638981

02/23/2011 Y Red-tailedHawk

Nest #7 was observed for 30 minutes, twoRed-tailed hawks were observed visiting thenest, one of them remained perched on the nest.Staking with flagging had previously beeninstalled to delineate the 500' buffer from thenest.

Mitigation Measure in Compliance? Y

Page 44 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: 5BIO-APM-1

CP2Notified LinkLead

11 S0495569,3634648

02/25/2011 Y Cooper's Hawk Hawk observed flying, no associated nestobserved

BiomonitorMitigation Measure in Compliance? Y

CP2Notified LinkLead

11 S0495560,3634641

02/25/2011 Y WesternSpadefoot

Tadpoles were observed occupying water on theroad. Crews were directed around the occupiedpuddles.

BiomonitorMitigation Measure in Compliance? Y

BIO-APM-3Helix Yard02/25/2011 Y Remarks: Water truck used for dust control.

Dust ControlMitigation Measure in Compliance? Y

LINK: ALLB-1c

EP 87-1,CP 108

02/22/2011 Y AmericanKestrel

Remarks: A pair of redtail hawks and a pair ofAmerican kestrels were observed from CP 108.No active nests were observed.

Bio MonitorMitigation Measure in Compliance? Y

EP220,BartlettYard/PotreroTruck Trail

02/24/2011 Y Bio monitor was present throughoutconstruction activities and all work was incompliance.Remarks: All work in compliance.

Bio monitoringMitigation Measure in Compliance? Y

PAR Yard,AlpineYard

02/24/2011 Y No impacts outside footprint.Remarks: All mitigation measures were met.

GeneralMitigation Measure in Compliance? Y

B-2aPAR Yard,AlpineYard

02/24/2011 Y Remarks: An office trailer was delivered andinstalled at the Alpine Underground Reels Yard.A ProTools crew delivered and installed theoffice trailer while a NEW electrical crewinstalled an electrical line to the trailer.

LimitsMitigation Measure in Compliance? Y

Page 45 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: ALLB-3a

EP22002/24/2011 Y The two trucks and backhoe that entered EP220returned to the Rough Acres Ranch Yard to bewashed at the weed station after work wascompleted at EP220 and before moving to theBartlett Yard.Remarks: All work was in compliance.

Vehicle washMitigation Measure in Compliance? Y

LINK: NAB-1c

IVsubstation

02/21/2011 Y Remarks: Crews continued drilling foundationpiers and continued excavations. No issuesnoted.Bio monitoring

Mitigation Measure in Compliance? Y

IVsubstation

02/22/2011 Y Remarks: Crews continued drilling foundationpiers and continued excavations. No issuesnoted.Bio monitoring

Mitigation Measure in Compliance? Y

69 kVreconductoring

02/22/2011 Y All work was in compliance with all APMs andMitigation Measures. There were no impactsoutside of footprint nor environmental issuesrequiring attention.Remarks: BMP work was done for the 69kVline. A rumble strip was installed at theVigilante Yard, and four signs notifyinghikers/bikers of Sunrise construction were putup at various locations in Mission Trails park.

Mitigation Measure in Compliance? Y

San LuisReySubstation

102/22/2011 Y Bio-monitor on-site compliance met.Remarks: ROEL continued excavating a trench.

Compliance metMitigation Measure in Compliance? Y

San LuisRey

02/22/2011 Y Remarks: Site was in compliance duringSDG&E 69kV configuration

Mitigation metMitigation Measure in Compliance? Y

Page 46 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-1c

Encina02/22/2011 Y Remarks: Site was in compliance

Mitigation metMitigation Measure in Compliance? Y

IV Sub02/22/2011 Y Remarks: Site was in compliance duringtrenching and construction activities

Bio monitorMitigation Measure in Compliance? Y

EncinaSubstation

02/22/2011 Y In compliance - Biological monitoring tookplace during placement of doorways, digging ofpads, masonry, and demolition of concrete pad.Remarks: Biological monitor was on-site duringdemolition, pad digging, door hanging, andmasonry.

MonitoringMitigation Measure in Compliance? Y

69kVReconductor

02/22/2011 Y All mitigation measures are metRemarks: Area is in compliance. United Powerreinsulated 69kV wires adjacent to AlliantUniversity - 2 poles completed ( 771473 &774815).

MMs metMitigation Measure in Compliance? Y

San LuisRey

02/23/2011 Y Remarks: Site was in compliance duringSDG&E 69kV confirguration

Mitigation metMitigation Measure in Compliance? Y

Encina02/23/2011 Y Remarks: Site was in compliance

Mitigation metMitigation Measure in Compliance? Y

IV Sub02/23/2011 Y Remarks: Site was in compliance duringtrenching and construction activities

Bio monitorMitigation Measure in Compliance? Y

IVsubstation

02/23/2011 Y Remarks: Crews continued drilling foundationpiers and continued excavations. No issuesnoted.Bio monitoring

Mitigation Measure in Compliance? Y

Page 47 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-1c

San LuisReySubstation

102/23/2011 Y Bio-monitor on-site compliance met.Remarks: ROEL continued work in trench inpreparation for reconnection.Compliance met

Mitigation Measure in Compliance? Y

EncinaSubstation

02/23/2011 Y In compliance - Biological monitoring tookplace during masonry, detail carpentry,back-filling and digging of bore holes.Remarks: Biological monitor was on-site duringboring, carpentry details, back-filling andmasonry.

MonitoringMitigation Measure in Compliance? Y

69kV STR40, 43

02/23/2011 Y All work in complianceRemarks: A PAR crew worked at 69kVStructures 43-40 for line reinsulation work,located off of Pomerado and Scripps RanchBlvd. A bucket truck and a crane were used forthe work. All work was in compliance.

BiomonitorMitigation Measure in Compliance? Y

69kVReconductor(Appx 1mile E. ofCalle deVida inMTRP)

02/23/2011 Y Remarks: All construction work(reinsulating)was in compliance with the MMCRP.

Bio MonitoringMitigation Measure in Compliance? Y

69kVReconductor(TL 6916)

02/23/2011 Y Remarks: Crew was in compliance during BMPinstallation.

Compliance MetMitigation Measure in Compliance? Y

RoughAcresRanch(RAR)

02/23/2011 Y Remarks: Rough Acres Ranch (RAR),Contactors: SDGE & Daley Corporation. DaleyCorporation- Installed 1 helicopterprecautionary sign near helicopter landing padsite at Rough Acres Ranch (RAR).

ComplianceMitigation Measure in Compliance? Y

Page 48 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-1c

IVSubstation

02/23/2011 Y Remarks: Imperial Valley Substation (IVSubstation), Contractors: SDGE & DaleyCorporation. Daley Corporation- Installed 6speed limit signs on access road off HWT98 in a4.3 mile span.

ComplianceMitigation Measure in Compliance? Y

69kVReconductor(Tie Line639)

02/24/2011 Y The lineman strung rollers on three separatepoles on Tie Line 639, and the BMP crewinstalled wattles at several of the surroundingtowers. The work areas were checked forwildlife prior to entering. No active nests wereobserved in the vicinity of the work areas oraccess roads, and no sensitive species (QCB,Gnatcatcher, etc.) were observed.Remarks: Crews in compliance.

Compliance MetMitigation Measure in Compliance? Y

San LuisRey

02/24/2011 Y Remarks: Site was in compliance duringSDG&E 69kV confirguration

Mitigation metMitigation Measure in Compliance? Y

Encina02/24/2011 Y Remarks: Site was in compliance

Mitigation metMitigation Measure in Compliance? Y

San LuisRey

02/24/2011 Y Remarks: Site was in compliance duringSDG&E 69kV confirguration

Mitigation metMitigation Measure in Compliance? Y

Encina02/24/2011 Y Remarks: Site was in compliance

Mitigation metMitigation Measure in Compliance? Y

IVSubstation

02/24/2011 Y Remarks: All monitors onsite at Encina, IV, andSLR during construction activities

Mitigation MetMitigation Measure in Compliance? Y

Page 49 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-1c

IV Sub02/24/2011 Y Remarks: Site was in compliance duringtrenching and construction activities

Bio monitorMitigation Measure in Compliance? Y

EncinaSubstation

02/24/2011 Y In compliance - Biological monitoring tookplace during masonry, demolition, back-fillingand digging of bore holes.Remarks: Biological monitor was on-site duringboring, demolition, back-filling and masonry.

MonitoringMitigation Measure in Compliance? Y

IV Sub02/24/2011 Y Remarks: Site was in compliance duringtrenching and construction activities

Bio monitorMitigation Measure in Compliance? Y

69kV STR26

02/24/2011 Y All work in complianceRemarks: A PAR crew worked on 69kVStructures 26-27 for line reinsulation work @32.90100, 117.06667. Plywood boards werestaged to minimize ground disturbance by thetrucks gaining access to STR 26 from the pavedroad.

BiomonitorMitigation Measure in Compliance? Y

IVsubstation

02/24/2011 Y Remarks: Roel crews continued pouringconcrete in foundations and pads. No issuesnoted.Bio monitoring

Mitigation Measure in Compliance? Y

San LuisReySubstation

102/24/2011 Y Bio-monitor on-site compliance met.Remarks: ROEL continued work in trench inpreparation for reconnection.Compliance met

Mitigation Measure in Compliance? Y

IVSubstation

02/24/2011 Y Remarks: Imperial Valley Substation (IVSubstation), Contractors: SDGE & DaleyCorporation. Daley Corporation- Installed 6speed limit signs on access road off HWT98 in a4.3 mile span.

ComplianceMitigation Measure in Compliance? Y

69kVReconductor(Z171633-Z171640)

02/25/2011 Y All straw wattle installation was done incompliance with the Project's mitigationmeasures and the bio-APMs were met.compliance

Mitigation Measure in Compliance? Y

Page 50 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-1c

69kVReconductor,Structure#37(VigilanteYard)

02/25/2011 Y Remarks: All work performed was incompliance. Par and UPC worked on"Dead-ending" top of electrical pole (structure#37) circuits.Compliance

Mitigation Measure in Compliance? Y

San LuisReySubstation

102/25/2011 Y Bio-monitor on-site compliance met.Remarks: ROEL continued work in trench inpreparation for reconnection.Compliance met

Mitigation Measure in Compliance? Y

69kVReconductor

32.83856,-117.06087

02/25/2011 Y Remarks: All mitigation measures were met.PAR replaced parts on electrical poles and setout straw wattles to prevent the wash-out ofdebris. No sensitive species were encountered.Poles/Wattles

Mitigation Measure in Compliance? Y

EncinaSubstation

02/25/2011 Y In compliance - Biological monitoring tookplace during masonry, digging of bore holes,and pouring of concrete.Remarks: Biological monitor was on-site duringboring, concrete pouring, and masonry.

MonitoringMitigation Measure in Compliance? Y

IVSubstation

02/26/2011 Y Remarks: Biological, Cultural, Paleo, and Tribalmonitors were onsite during excavation

Mitigation metMitigation Measure in Compliance? Y

San LuisRey

02/26/2011 Y Remarks: Site was in compliance duringSDG&E 69kV confirguration

Mitigation metMitigation Measure in Compliance? Y

San LuisReySubstation

102/26/2011 Y Bio-monitor on-site compliance met.Remarks: ROEL continued work in trench inpreparation for reconnection.Compliance met

Mitigation Measure in Compliance? Y

IVsubstation

02/26/2011 Y Remarks: Roel crews continued pouringconcrete in foundations and pads. No issuesnoted.Bio monitoring

Mitigation Measure in Compliance? Y

Page 51 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-2a

69 kVA02/22/2011 Y Remarks: All work occured from approvedaccess roads.Mitigation Measure in Compliance? Y

B-7aIVsubstation

02/21/2011 Y Remarks: Vehicle undersides were checkedbefore moving. No animals found.

under vehicleMitigation Measure in Compliance? Y

IVsubstation

02/21/2011 Y Remarks: Crews installed dirt or 2x4 ramps inall open excavations. Crews installed plywoodcovers on drill holes and used straw wattle tocover additional openings. No issues noted.trench ramp

Mitigation Measure in Compliance? Y

IVsubstation

02/21/2011 Y Remarks: Inspected exposed trenches threetimes a day. No animals found.

trench inspect.Mitigation Measure in Compliance? Y

IVsubstation

02/22/2011 Y Remarks: Vehicle undersides were checkedbefore moving. No animals found.

under vehicleMitigation Measure in Compliance? Y

IVsubstation

02/22/2011 Y Remarks: Crews installed dirt or 2x4 ramps inall open excavations. Crews installed plywoodcovers on drill holes and used straw wattle tocover additional openings. No issues noted.trench ramp

Mitigation Measure in Compliance? Y

IVsubstation

02/22/2011 Y Remarks: Inspected exposed trenches threetimes a day. No animals found.

trench inspect.Mitigation Measure in Compliance? Y

SLR sub02/22/2011 Y Remarks: Excavations securely covered whennot in use to prevent wildlife entrapment and orinjury.Biology

Mitigation Measure in Compliance? Y

IVsubstation

02/23/2011 Y Remarks: Vehicle undersides were checkedbefore moving. No animals found.

under vehicleMitigation Measure in Compliance? Y

Page 52 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-7a

IVsubstation

02/23/2011 Y Remarks: Crews installed dirt or 2x4 ramps inall open excavations. Crews installed plywoodcovers on drill holes and used straw wattle tocover additional openings. No issues noted.trench ramp

Mitigation Measure in Compliance? Y

IVsubstation

02/23/2011 Y Remarks: Inspected exposed trenches threetimes a day. No animals found.

trench inspect.Mitigation Measure in Compliance? Y

SLR sub02/23/2011 Y Remarks: Excavations have ramp with steps toassist in wildlife safe escape should they entertrenched area.Biology

Mitigation Measure in Compliance? Y

IVsubstation

02/24/2011 Y Remarks: Vehicle undersides were checked forpresence of wildlife before being moved.

Under vehicleMitigation Measure in Compliance? Y

IVsubstation

02/24/2011 Y Remarks: Inspected exposed trenches threetimes a day. No animals found.

Trench inspect.Mitigation Measure in Compliance? Y

SLR sub02/24/2011 Y Remarks: Excavations were covered to preventwildlife entrapment

BiologyMitigation Measure in Compliance? Y

SLR sub02/25/2011 Y Remarks: Excavations were covered to preventwildlife entrapment

BiologyMitigation Measure in Compliance? Y

SLR sub02/26/2011 Y Remarks: Excavations were covered to preventwildlife entrapment

BiologyMitigation Measure in Compliance? Y

IVsubstation

02/26/2011 Y Remarks: Vehicle undersides were checked forpresence of wildlife before being moved.

Under vehicleMitigation Measure in Compliance? Y

Page 53 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-7a

IVsubstation

02/26/2011 Y Remarks: Inspected exposed trenches threetimes a day. No animals found.

Trench inspect.Mitigation Measure in Compliance? Y

B-8aSan LuisRey 230kVArea

Suspend Work33 12 44 N,117 20 5 W

02/22/2011 Y Great HornedOwl

One owl on nestRemarks: Great Horned Owl nest monitoredduring Roel construction activities

Owl NestMitigation Measure in Compliance? Y

SLR sub02/22/2011 Y Great HornedOwl

Remarks: Active great horned owl nest wasmonitored for impacts from activities within thesubstation. No disturbance by owl wasobserved.Biology

Mitigation Measure in Compliance? Y

San LuisRey 230kVArea

Notified LinkLead

33 12 44 N,117 20 5 W

02/23/2011 Y Great HornedOwl

One owl on nestRemarks: Great Horned Owl nest monitored

Owl NestMitigation Measure in Compliance? Y

SLR sub02/23/2011 Y Great HornedOwl

Remarks: Active great horned owl nest wasmonitored for impacts from activities within thesubstation. No disturbance by owl was observed.Owlets may have begun hatching.Biology

Mitigation Measure in Compliance? Y

San LuisRey 230kVArea

Suspend Work33 12 44 N,117 20 5 W

02/24/2011 Y Great HornedOwl

One owl on nestRemarks: Great Horned Owl nest monitored

Owl NestMitigation Measure in Compliance? Y

San LuisRey 230kVArea

Suspend Work33 12 44 N,117 20 5 W

02/24/2011 Y Great HornedOwl

One owl on nestRemarks: Great Horned Owl nest monitored

Owl NestMitigation Measure in Compliance? Y

Page 54 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAB-8a

substationNotified LinkLead

02/24/2011 Y Great HornedOwl

Remarks: Asphalt breaking and paving occuringon edge of reduced buffer for great horned owlnest. When noise reached levels that mightdisturb brooding owl, crew was advised bybiologist to reduce noise and acoustician wascalled in to measure construction/ambient noise.Airborne particulates were blowing towardsnest. Crew was advised to reduce dust andcomplied.

BiologyMitigation Measure in Compliance? Y

SLR sub02/24/2011 Y Great HornedOwl

Remarks: Active great horned owl nest wasmonitored for impacts from activities within thesubstation.

BiologyMitigation Measure in Compliance? Y

substationNotified LinkLead

02/25/2011 Y Great HornedOwl

Remarks: Construction within buffer wasdelayed until owlets have fledged and left area.

BiologyMitigation Measure in Compliance? Y

SLR sub02/25/2011 Y Great HornedOwl

Remarks: Active great horned owl nest wasmonitored for impacts from activities within thesubstation.

BiologyMitigation Measure in Compliance? Y

San LuisRey 230kVArea

Notified LinkLead

33 12 44 N,117 20 5 W

02/26/2011 Y Great HornedOwl

One owl on nestRemarks: Great Horned Owl nest monitored

Owl NestMitigation Measure in Compliance? Y

substationNotified LinkLead

02/26/2011 Y Great HornedOwl

Remarks: Construction within buffer wasdelayed until owlets have fledged and left area.

BiologyMitigation Measure in Compliance? Y

SLR sub02/26/2011 Y Great HornedOwl

Remarks: Active great horned owl nest wasmonitored for impacts from activities within thesubstation.

BiologyMitigation Measure in Compliance? Y

Page 55 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NABIO-APM-26

EncinaSubstation

02/22/2011 Y In compliance - one side of each excavated areais sloped to allow escape of wildlife.Remarks: Excavations are slanted on one side toallow wildlife to escape during the night.

Sloped sidesMitigation Measure in Compliance? Y

EncinaSubstation

02/23/2011 Y In compliance - one side of each excavated areais sloped to allow escape of wildlife.Remarks: Excavations are slanted on one side toallow wildlife to escape during the night.

Sloped sidesMitigation Measure in Compliance? Y

EncinaSubstation

02/24/2011 Y In compliance - one side of each excavated areais sloped to allow escape of wildlife.Remarks: Excavations are slanted on one side toallow wildlife to escape during the night.

Sloped sidesMitigation Measure in Compliance? Y

EncinaSubstation

02/25/2011 Y In compliance - one side of each excavated areais sloped to allow escape of wildlife.Remarks: Excavations are slanted on one side toallow wildlife to escape during the night.

Sloped sidesMitigation Measure in Compliance? Y

BIO-APM-3EncinaSubstation

02/22/2011 Y All individuals were in compliance - driverskept to the established speed limit of 10 mph.Remarks: Vehicles observed and complied with10-mph speed limit.

Speed limitMitigation Measure in Compliance? Y

EncinaSubstation

02/23/2011 Y All individuals were in compliance - driverskept to the established speed limit of 10 mph.Remarks: Vehicles observed and complied with10-mph speed limit.

Speed limitMitigation Measure in Compliance? Y

EncinaSubstation

02/24/2011 Y All individuals were in compliance - driverskept to the established speed limit of 10 mph.Remarks: Vehicles observed and complied with10-mph speed limit.

Speed limitMitigation Measure in Compliance? Y

EncinaSubstation

02/25/2011 Y All individuals were in compliance - driverskept to the established speed limit of 10 mph.Remarks: Vehicles observed and complied with10-mph speed limit.

Speed limitMitigation Measure in Compliance? Y

Page 56 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NABIO-APM-4

69kVReconductor(accessroadsZ171633-Z171640)

02/25/2011 Y Vehicles stayed on approved access roadsbetween structures Z171633 and Z171640

trucks on roadsMitigation Measure in Compliance? Y

C-1eIVSubstation

02/21/2011 Y All work observed by archaeological and NativeAmerican Monitors and was in compliance.Remarks: No cultural resources were foundduring trenching

CulturalMitigation Measure in Compliance? Y

IVSubstation

02/22/2011 Y Remarks: Cultural and Tribal monitors werepresent during all excavation

Cultural, TribeMitigation Measure in Compliance? Y

IVSubstation

02/22/2011 Y All work observed by archaeological and NativeAmerican Monitors and was in compliance.Remarks: No cultural resources were foundduring trenching

CulturalMitigation Measure in Compliance? Y

IVSubstation

02/23/2011 Y Remarks: Cultural and Tribal monitors werepresent during all excavation

Cultural, TribeMitigation Measure in Compliance? Y

IVSubstation

02/23/2011 Y All work observed by archaeological and NativeAmerican Monitors and was in compliance.Remarks: No cultural resources were foundduring trenching

CulturalMitigation Measure in Compliance? Y

IVsubstationaccess road

02/23/2011 Y Remarks: All digging for signs was monitoredby a cultural monitor and in compliance.

culturalMitigation Measure in Compliance? Y

IVSubstation

02/24/2011 Y Remarks: Cultural and Tribal monitors werepresent during all excavation

Cultural, TribeMitigation Measure in Compliance? Y

Page 57 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAC-1e

IVSubstation

02/24/2011 Y Remarks: Cultural and Tribal monitors werepresent during all excavation

Cultural, TribeMitigation Measure in Compliance? Y

IVSubstation

02/25/2011 Y All work observed by archaeological and NativeAmerican Monitors and was in compliance.Remarks: No cultural resources were foundduring trenching

CulturalMitigation Measure in Compliance? Y

IVSubstation

02/26/2011 Y All work observed by Archaeological andNative American Monitors and was incompliance.Remarks: No cultural resources were foundduring trenching

CulturalMitigation Measure in Compliance? Y

PAL-1cIV SubEntrancegate

Notified LinkLead

02/21/2011 Y Remarks: Fossils discovered during drillingactivities.

Paleo MonitorMitigation Measure in Compliance? Y

IVSubstation

02/22/2011 Y Remarks: No fossils found during excavation

Paleo monitorMitigation Measure in Compliance? Y

IV SubEntrancegate

Notified LinkLead

BoreholeBSP3

02/22/2011 Y Remarks: Fossils discovered; Link Lead andSupervisor were notified.

Paleo MonitorMitigation Measure in Compliance? Y

Encinassubstation

02/22/2011 Y Paleontological Remarks: No fossils found during excavation.

Paleo monitorMitigation Measure in Compliance? Y

IVSubstation

02/23/2011 Y Remarks: Shells found during excavation

Paleo monitorMitigation Measure in Compliance? Y

Page 58 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAPAL-1c

Encina02/23/2011 Y Remarks: No fossils found during excavationand drilling

Paleo MonitorMitigation Measure in Compliance? Y

EncinaSubstation

02/23/2011 Y Paleontological Remarks: No fossils were discovered duringexcavation.

Paleo monitorMitigation Measure in Compliance? Y

230Kvcontrolhouse, IVSubstation.

02/23/2011 Y Remarks: No fossils discovered duringexcavation.

Paleo MonitorMitigation Measure in Compliance? Y

EncinaSubstation

02/24/2011 Y Remarks: No fossils found during excavations.

Paleo monitorMitigation Measure in Compliance? Y

IVSubstation

02/24/2011 Y Remarks: Shells found during excavation

Paleo monitorMitigation Measure in Compliance? Y

IVSubstation

02/24/2011 Y Remarks: Shells found during excavation

Paleo monitorMitigation Measure in Compliance? Y

Encina02/24/2011 Y Remarks: No fossils found during excavationand drilling

Paleo MonitorMitigation Measure in Compliance? Y

Encina02/24/2011 Y Remarks: No fossils found during excavationand drilling

Paleo MonitorMitigation Measure in Compliance? Y

IVSubstation

362056302/25/2011 Y Remarks: No fossils collected today during Roelexcavations.

Paleo MonitorMitigation Measure in Compliance? Y

Page 59 of 60 Weekly Monitoring Report f_dr_02c

Sunrise Powerlink Transmission ProjectWeekly Monitoring Report No. 01469 From: Through:02/20/2011 02/26/2011

ENVIRONMENTAL COMPLIANCEMitigation Measure HGFEDCA B

TowerCommentsActionIssueCauseLoc UTMDate (Y/N) SpeciesLat-Long

LINK: NAPAL-1c

Encinasubstation

02/25/2011 Y Remarks: Paleontology monitoring wasconducted for all of todays drilling activities

Paleo monitorMitigation Measure in Compliance? Y

IVSubstation.

362056302/26/2011 Y Remarks: No fossils found during excavation.

Paleo MonitorMitigation Measure in Compliance? Y

San LuisReySubstation

02/26/2011 Y Paleontological Remarks: No fossils were found today.

Paleo MonitorMitigation Measure in Compliance? Y

Page 60 of 60 Weekly Monitoring Report f_dr_02c