  • 8/8/2019 SW Configuration Mgmt

    1/27

    GSFC

    SPI

    Software Configuration

    Management

    Presented by: Susan SekiraSoftware Process Improvement (SPI) Project

  • 8/8/2019 SW Configuration Mgmt

    2/27

    Software Configuration Management, March 2008 2

    GSFC

    SPI

    Agenda

    s Configuration Management (CM) Background CM Concepts

    CM Benefits

    Process Overviews Configuration Management Implementation

    Planning and Startup Tasks

    Execution Taskss CM Support Information

  • 8/8/2019 SW Configuration Mgmt

    3/27

    Software Configuration Management, March 2008 3

    GSFC

    SPI

    Purpose and Objectives

    s Purpose: Describe CM Concepts and theimplementation approach

    s Objective: After this session you should

    understand: Four key functions of CM

    How to apply CM to your project

    Which CM records to maintain

    Where to find additional information on CMprocesses and tools

  • 8/8/2019 SW Configuration Mgmt

    4/27

    Software Configuration Management, March 2008 4

    GSFC

    SPI

    Configuration Management Overview

    s The purpose of Software ConfigurationManagement (CM) is to establish and maintain theintegrity of products throughout the software lifecycle

    s Software CM involves four key functions:1. identification of work products and baselines that are

    subject to configuration control

    2. control (i.e., approval/rejection) of proposed changes toconfiguration items

    3. status accounting of configuration data and changes

    4. audits to maintain the integrity of the configurationbaselines

  • 8/8/2019 SW Configuration Mgmt

    5/27

    Software Configuration Management, March 2008 5

    GSFC

    SPI

    CM Benefits

    s

    Improves Product protection

    Product visibility

    Product control

    Team communication

    Customer Confidences Decreases

    Rework

    Confusion

    Project Risk

  • 8/8/2019 SW Configuration Mgmt

    6/27

    Software Configuration Management, March 2008 6

    GSFC

    SPI

    Key Definitions

    s Configuration Item (CI) - an aggregation of workproducts (e.g., hardware, software, firmware, or documentation) that is designated for configuration management and treated as asingle entity in the configuration managementprocess

    s Baseline a set of specifications or workproducts that has been formally reviewed andagreed on, which thereafter serves as the basis

    for further development, and which can bechanged only through change controlprocedures. Typically defined for each projectlife-cycle phase

  • 8/8/2019 SW Configuration Mgmt

    7/27

    Software Configuration Management, March 2008 7

    GSFC

    SPI

    Configuration Management Rolesand Responsibilities

    s Product Development Lead (PDL) - Responsible for CMplanning and overall control and approval of CMactivities and tools. Develops and maintains theprojects CM Plan

    s Configuration Management Officer (CMO) Implements and maintains the CM system according tothe projects CM Plan. Coordinates, supports, andperforms CM activities and reports those activities tothe PDL

    s Control Board composed of technical andadministrative representatives who recommendapproval/disapproval of changes to a CI or baseline(e.g., Configuration Control Board (CCB), InternalReview Board (IRB))

  • 8/8/2019 SW Configuration Mgmt

    8/27

    Software Configuration Management, March 2008 8

    GSFC

    SPI

    Configuration Management ProcessOverview

    Work products;change

    requests

    Controlled work products;

    approved changerequests

    Status reports;audit results

    CM Plan

    Project Management Processes

    Project Planning

    ProjectMonitoring &

    Control

    Project Startup

    Project Closeout

    ProjectFormulation

    Product Development Processes

    Requirements

    Engineering

    Product ReleaseSustaining

    Engineering &Maintenance

    Design

    Implementation

    Testing

    Systems

    Engineering

    ConfigurationManagement

    Process

    Planning Data

  • 8/8/2019 SW Configuration Mgmt

    9/27

    Software Configuration Management, March 2008 9

    GSFC

    SPI

    Configuration Management Tasks

    CM planning and startup tasks

    Establish thesoftware

    project CCBSetup CM toolsand libraries

    Define levels of control and

    responsibilities

    Identifyconfiguration

    items

    Define CMprocedures

    Prepare the CMPlan

    CM execution tasks

    Identify workproducts/baselines

    Perform

    configurationcontrol

    Perform

    configurationstatus accounting

    Perform

    configurationaudits

    NOTE: See the ISD Software Configuration Management Asset, 3.1, for complete task descriptions

  • 8/8/2019 SW Configuration Mgmt

    10/27

    GSFC

    SPI

    CM Planning and Startup Tasks

    Establish thesoftware

    project CCB

    Setup CM toolsand libraries

    Define levels of control and

    responsibilities

    Identifyconfiguration

    items

    Define CMprocedures

    Prepare the CMPlan

  • 8/8/2019 SW Configuration Mgmt

    11/27

    Software Configuration Management, March 2008 11

    GSFC

    SPI

    CM Planning/Startup Tasks (1 of 2)

    s Identify the CIs (e.g., deliverable products,interim products, requirements, software) anddefine the naming conventions

    s Identify the levels of control for each CI

    s List the identified items in the datamanagement list ( DML)

    s Determine when each item will be placed under configuration control (i.e., Baselined )

    s Select a role that is responsible for maintainingthe integrity of items under CM

    s Establish a CCB or IRB to manage, assess, andcontrol changes to configured items

  • 8/8/2019 SW Configuration Mgmt

    12/27

    Software Configuration Management, March 2008 12

    GSFC

    SPI

    CM Planning/Startup Tasks (2 of 2)

    s Define the mechanism used to control changes Change requests (e.g., What forms / tools will be

    used?) CCB / IRB (e.g., What meetings (if any) will be

    held? How will changes be dispositioned, logged ,and tracked ?) Audits to confirm the approved changes and

    ensure the integrity of the configuration baseliness

    Identify tools used to support CM and how theywill be used (e.g., MKS, CVS, ClearCase)s Document approaches, procedures, and tools in

    a separate CM Plan or as part of your SMP/PP

  • 8/8/2019 SW Configuration Mgmt

    13/27

    GSFC

    SPI

    CM Execution Tasks

    Performconfiguration

    control

    Performconfiguration

    status accounting

    Performconfiguration

    audits

    Identify workproducts/baselines

  • 8/8/2019 SW Configuration Mgmt

    14/27

    Software Configuration Management, March 2008 14

    GSFC

    SPI

    1 - Configuration IdentificationIdentify Work Products and Baselines

    s Document the baseline items in the BaselinesTable in the SMP/PP

    s Identify by phase (per your life cycle model) the CIsthat will be baselined or re-baselined

    Go to http://software.gsfc.nasa.gov/tools.cfm and look for CM Baselines Template

    .

  • 8/8/2019 SW Configuration Mgmt

    15/27

    Software Configuration Management, March 2008 15

    GSFC

    SPI

    Recording the Baselines

    s

    Update the Baselines Table at the conclusion of each phase to record the baseline date and thebaseline versions for each configured item

    s Save your updated Baselines Table asspecified in your DML

    .

  • 8/8/2019 SW Configuration Mgmt

    16/27

    Software Configuration Management, March 2008 16

    GSFC

    SPI

    Document CIs in Data Management List (DML)

    Go to http://software.gsfc.nasa.gov/tools.cfm and look for Data Management List

  • 8/8/2019 SW Configuration Mgmt

    17/27

    Software Configuration Management, March 2008 17

    GSFC

    SPI

    2 - Configuration Control

    sIdentify and record desired changes to abaselined item

    s Define the need / problem rather than thedesired resolution

    s Document the analysis of change Impact analysis, costs, urgency

    s Review and disposition each change requests

    Use a tool* to record and track the status of all change requests

    *Go to http://software.gsfc.nasa.gov/tools.cfm and look for Change Request Formand Change Request Log Template

  • 8/8/2019 SW Configuration Mgmt

    18/27

    Software Configuration Management, March 2008 18

    GSFC

    SPI

    Change Request Form and Log

    Describing

    the desiredchange

    Thoroughlyanalyzing the

    change

    Decision andformal

    approval

    ProjectName:

    TrackingNumber Item Type Systems/Subsystems Short Description of Change Urgency Requestor

    DateSubmitted

    Analysis AssignedTo: Result

    Change Request Log

    Keeping track of all the desired changes

  • 8/8/2019 SW Configuration Mgmt

    19/27

    Software Configuration Management, March 2008 19

    GSFC

    SPI

    3 Configuration Status Accounting

    s Maintain records of the CIs throughout theprojects life cycle

    s Record and monitor all changes to CIss Document the contents of versions, builds,

    and baseliness Generate periodic status reports your CM

    tool may provide the reporting for you!

  • 8/8/2019 SW Configuration Mgmt

    20/27

    Software Configuration Management, March 2008 20

    GSFC

    SPI

    4 Configuration Audits

    s Conduct audits to maintain the integrity of theconfiguration baselines

    s Three types of CM Audits are required: Baseline Audit

    Functional Configuration Audit (FCA)

    Physical Configuration Audit (PCA)

    s Audits correspond to major milestones andmust be planned and on your schedule

  • 8/8/2019 SW Configuration Mgmt

    21/27

    Software Configuration Management, March 2008 21

    GSFC

    SPI

    Baseline Audit

    s Conducted at the end of each life cycle phaseor at each major delivery

    s Conducted by the teams CMO or designatedteam personnel; reviewed by the teams

    Software Quality Engineer (SQE)s Baseline Audit -- verifies the content of the

    baseline Correct versions of CIs were used to build the

    baseline

    Correct version of documentation are includedin the baseline

  • 8/8/2019 SW Configuration Mgmt

    22/27

    Software Configuration Management, March 2008 22

    GSFC

    SPI

    FCA and PCA

    s

    Functional Configuration Audit ( FCA ) -- Verifiesfunctionality of baseline after final testing Ensures that CIs achieve the performance and functional

    requirements Ensures that operational and support documents are

    complete and satisfactorys Physical Configuration Audit ( PCA ) -- Verifies content of

    baseline for major builds or deliveries Ensures that baseline items of a delivery match the

    documentation that defines it (e.g., Version DescriptionDocument (VDD), design documents)

    s Both conducted by the teams CMO or designatedteam personnel; verified by the teams SQE

  • 8/8/2019 SW Configuration Mgmt

    23/27

    Software Configuration Management, March 2008 23

    GSFC

    SPI

    CM AssetsProcedures, Guidelines, and Tools

    Go to http://software.gsfc.nasa.gov/process.cfm and look under Organizational Support

  • 8/8/2019 SW Configuration Mgmt

    24/27

  • 8/8/2019 SW Configuration Mgmt

    25/27

    Software Configuration Management, March 2008 25

    GSFC

    SPI

    Summary

    s Software Configuration Management establishesand maintains the integrity of products throughout thesoftware life cycle

    s CM planning and implementation support

    include: Configuration Identification

    Configuration Control

    Configuration Status Accounting Configuration Audits

    s CM records must be organized and maintained

  • 8/8/2019 SW Configuration Mgmt

    26/27

    Software Configuration Management, March 2008 26

    GSFC

    SPI

    Questions?

  • 8/8/2019 SW Configuration Mgmt

    27/27

    Software Configuration Management, March 2008 27

    GSFC

    SPI

    Acronyms

    CCB Configuration Control BoardCI Configuration ItemCM Configuration ManagementCMO Configuration Management Officer CR Change Request

    DML Data Management ListFCA Functional Configuration AuditIRB Internal Review BoardISD Information Systems DivisionPCA Physical Configuration AuditPDL Product Development LeadSMP/PP Software Management Plan/Product PlanSPI Software Process ImprovementSQE Software Quality Engineer VDD Version Description Document