Sea Water Intake Structure Concrete QTY : 2977 m3 Form Work QTY : 4215 m2 30000*14000*14200 Overall dimension : L*W*H

Upload: shahed-ali

Post on 06-Apr-2017

71 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete QTY : 2977 m3Form Work QTY : 4215 m2

30000*14000*14200

Overall dimension : L*W*H

Page 2: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Working Sequence & Methodology

Page 3: SWPS - Working Sequence & Methodology

Sea Water Intake StructureWorking Sequence

Page 4: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Working Sequence Detailing

Page 5: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 22m³

Sequence Detail - Blinding

Pour location

Pour

Page 6: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 672 m³

Sequence Detail - Raft

Pour location

Pour

Formwork Quantity – 141 m²

Page 7: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 359m³

Sequence Detail – Lift1 pour1 External Wall

Pour

Pour location

Pour SequenceFormwork Quantity – 538 m²

Page 8: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 346m³

Sequence Detail– Lift1 pour2 External Wall

Pour

Pour location

Pour SequenceFormwork Quantity – 580m²

Page 9: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 326m³

Sequence Detail – Lift2 pour1 External Wall

Pour

Pour location

Pour SequenceFormwork Quantity – 488 m²

Page 10: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 341m³

Sequence Detail – Lift2 pour2 External Wall

Pour

Pour location

Pour SequenceFormwork Quantity – 678m²

Page 11: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 284m³

Sequence Detail – Lift1 pour5 Internal Walls

Pour

Pour location

Pour SequenceFormwork Quantity – 494 m²

Page 12: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 273m³

Sequence Detail – Lift2 pour5 Internal Walls

Pour

Pour location

Pour SequenceFormwork Quantity – 486 m²

Page 13: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 245 m³

Sequence Detail– Lift1 pour6 Internal Walls

Pour

Pour location

Pour SequenceFormwork Quantity – 566 m²

Page 14: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 96m³

Sequence Detail – Lift2 pour6 Internal Walls

Pour

Pour location

Pour SequenceFormwork Quantity – 200 m²

Page 15: SWPS - Working Sequence & Methodology

Sea Water Intake Structure

Concrete Quantity – 16m³

Sequence Detail – External Tank

Pour

Pour location

Pour SequenceFormwork Quantity – 63m²