Subsea Integration Alliance is a nonincorporated strategic global alliance between Subsea 7 and OneSubsea® the subsea technologies, production, and processing systems division of Schlumberger. Other company, product, and service names are the properties of their respective owners. Copyright © 2020 Subsea 7 and Schlumberger. All rights reserved. 20-SIA-761140 subseaintegrationalliance.com Integrated solution included using subsea delivery of multiphase pump as alternative to ESP Multiphase pump technology leaving Horsoy, Norway for the Otter Field in the North Sea. Coupled with the long-distance tieback, the subsea boosting technology provided production security for the late-life asset. Tieback length 18 mi [30 km] Water depth 597 ft [182 m] Awarded Q2 2017 Startup Q4 2018 UK North Sea Otter Field Background TAQA approached Subsea Integration Alliance for a solution that would provide production security for a late-life asset—the Otter Field— resulting in an installation of the longest subsea boosting tieback in the UK North Sea. The 18-mi [30-km] tieback uses a multiphase pump as an alternative to an electrical submersible pump (ESP) for enhanced production. Boosting technology will enable TAQA to finish production on the Eider platform on schedule and keep Otter Field in production. Technologies Multiphase pump technology including overtrawlable pump skid TAQA achieves record-breaking 18-mile tieback in UK North Sea

Upload: others

Post on 18-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TAQA achieves record-breaking 18-mile tieback in UK North Sea · TAQA approached Subsea Integration Alliance for a solution that would provide production security for a late-life

Subsea Integration Alliance is a nonincorporated strategic global alliance between Subsea 7 and OneSubsea® the subsea technologies, production, and processing systems division of Schlumberger. Other company, product, and service names are the properties of their respective owners. Copyright © 2020 Subsea 7 and Schlumberger. All rights reserved. 20-SIA-761140subseaintegrationalliance.com

Integrated solution included using subsea delivery of multiphase pump as alternative to ESP

Multiphase pump technology leaving Horsoy, Norway for the Otter Field in the North Sea. Coupled with the long-distance tieback, the subsea boosting technology provided production security for the late-life asset.

Tieback length 18 mi [30 km]Water depth 597 ft [182 m]Awarded Q2 2017Startup Q4 2018

UK North SeaOtter Field

BackgroundTAQA approached Subsea Integration Alliance for a solution that would provide production security for a late-life asset—the Otter Field— resulting in an installation of the longest subsea boosting tieback in the UK North Sea. The 18-mi [30-km] tieback uses a multiphase pump as an alternative to an electrical submersible pump (ESP) for enhanced production. Boosting technology will enable TAQA to finish production on the Eider platform on schedule and keep Otter Field in production.

Technologies � Multiphase pump technology including

overtrawlable pump skid

TAQA achieves record-breaking 18-mile tieback in UK North Sea