technical method statement standard technical...© reduct 2018: standard technical method statement....

22
Technical Method Statement Edition 2019

Upload: others

Post on 17-Mar-2020

12 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

Technical Method Statement

Edition 2019

Page 2: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 2

Table of Contents

Introduction ..................................................................................... 3

About Reduct ..................................................................................................... 3

Product Positioning ............................................................................................. 3

Brief introduction to Inertial Measurement Systems ................................................ 4

The DuctRunner Technology ................................................................................ 5

Calibration Procedure.......................................................................................... 8

System Accuracy ................................................................................................ 9

System Output ................................................................................................. 10

Pipeline Mapping System Description: DR-4 ....................................... 11

OMU System Components and Specifications ........................................................ 11

Centralizing Wheel Sets ..................................................................................... 12

Invert wheel sets .............................................................................................. 12

Laptop and Software ......................................................................................... 13

High Speed Electrical Winches ............................................................................ 14

General Method Statement .............................................................. 15

Scope of the Works ........................................................................................... 15

General Site Preparations ................................................................................... 15

Access Point Safety Arrangements ....................................................................... 16

Plant................................................................................................................ 17

Space requirements........................................................................................... 18

Description of the operational procedures ............................................................. 19

Skill Requirements and Documentation ................................................................ 21

Personal Protective Equipment (PPE) ................................................................... 21

Annex 1: Europower Generator – technical specifications ..................... 22

Page 3: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 3

Introduction

About Reduct

Reduct is a global market leader in the development of Gyroscopic Pipeline

Mapping Systems. Before starting Reduct, the founders were active in the deployment of telecommunication networks in both Europe and the United

States. They realized early on that locating existing non-metallic underground pipes and ducts was often an impossible task due to both the

small pipe diameter and limited access opportunities. Therefore, in 2001 they started Reduct to develop a technology to solve this locating issue.

They key to the solution was a system that would travel autonomously

inside an underground pipeline and record the path travelled.

Product Positioning

Location, location, location. That’s the primary concern when it comes to

underground infrastructure operations, maintenance and rehabilitation. Many operators and authorities are investing in state of the art Geographic

Information Systems (GIS) to store network related data, including XYZ.

However, the quality of existing XYZ data is often inaccurate as a result of:

▪ Ageing or lack of information.

▪ 2-dimensionality, i.e. depth is often unknown.

▪ Referencing to no longer existing aboveground landmarks.

▪ Non-digital format.

▪ A multitude of scales and coordinate systems used, making exchange

of data very inefficient.

▪ Inability to map infrastructure installed by means of Trenchless

Technologies, such as river crossings, underneath buildings, etc.

The risk is therefore high that costly GIS platforms become populated with inaccurate and low value XYZ data, yet the value of a GIS platform is directly

related to the quality of the data contained in it.

Page 4: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 4

Survey crews use several methods to locate and map the as-built

schematics of underground pipelines.

Most non-gyroscopic mapping systems require personnel to trace the path

of a pipeline, using either a beacon system or ground-penetrating radar to

map the utilities. However, none of these systems get the exact measurement of the pipe’s centreline. Moreover, beacon-based systems

can measure to a limited depth and are highly susceptible to electromagnetic interference, rendering them virtually useless in densely

piped areas or near railways and power lines.

Brief introduction to Inertial Measurement Systems

The DuctRunner Technology is the world’s first small diameter pipeline mapping technology based on inertial sensor technology. Inertial sensors

include gyroscopes, accelerometers, magnetometers, thermometers, etc. and are typically found in the airline and defence industry as well as GPS

systems. However, in these applications, the systems are used as on-line systems.

PipelinesTraditional

Surveying

Walkover

Beacon

Systems

Ground

Penetrating

Radar

Gyroscopic

Systems

Existing

Shallow

depth

only

Shallow

depth

only

Newly

Trenched

Not

economically

viable

Not

economically

viable

Trenchless

Shallow

depth

only

Shallow

depth

only

This comparison is valid for

piggable buried pipes and ducts

only.

Page 5: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 5

Gyroscopes have a natural tendency to

drift over time. In on-line systems, this drift does not get a chance to be of

significant influence on the object (plane, car, ship, etc.) because the object can re-

assess its actual position via satellite regularly and take corrective action. The

impact of the drift (resulting in deviations)

is therefore minimized.

In off-line systems (or free run systems), frequent repositioning is not

possible. For example, if the object is underground it cannot make contact with

satellites, and as a result the full impact of the drift needs to be considered. In

essence, the standard free run accuracy is affected negatively as the time (distance)

required to travel between known points

increases.

The fundamental change in approach to overcome this shortcoming in

inertial measurement systems and to make them applicable for accurate

off-line measurements is the basis of the DuctRunner technology and subject of the patent applications US/10/536,006, PCT/BE03/00203,

JPN/2004-554084, EUR/03811699.2. and HKG/06102043.7.

The DuctRunner Technology

In its current form, the DuctRunner technology consists of 3 major

components:

1) The Orientation Measurement Unit (OMU) containing the necessary

sensors to accurately measure rotations around the X, Y and Z axis.

distance

de

via

tio

n

Standard free run accuracy

of sensors

Cumulative inaccuracy

builds up exponentially

drift

distance

de

via

tio

n

Standard free run accuracy

of sensors

Cumulative inaccuracy

builds up exponentially

driftd

evia

tio

n

On-line steering accuracy

Frequent online corrections

(eg. via satellite navigation)

devia

tio

n

On-line steering accuracy

Frequent online corrections

(eg. via satellite navigation)

Page 6: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 6

The OMU is carefully calibrated to determine the alignment of each

mechanically assembled sensor to within 0.01°.

The Reduct OMU is fully autonomous, i.e. it is battery powered and the data logged is stored internally during a measurement run. This eliminates the

need to tether a data and/or power cable behind the system. Also, autonomy means that it does not need to be traced from aboveground as it

moves from a pipe’s entry to exit point. It can thus travel to any depth and

underneath any obstacle (such as rivers, railways, highways, buildings

etc.).

2) An application specific housing and centralizing system, such as the

ABM-40/D2 for internal diameters 40 to 75mm or the ABM-90/DR-4 for internal diameters from 90mm to 1500mm+.

ABM-40 / D2 ABM-90 / DR-4

3) Proprietary X-Traction® data processing software.

X-Traction® software transfers the autonomously logged data from the OMU to a PC and then calculates the profile of the path travelled by the OMU.

The resulting profile is then linked to known coordinates at the entry and exit points, hence creating an accurate 3-dimensional line in the coordinate

system chosen.

The unique approach taken by Reduct means that it is not necessary to

know the exact position of the OMU as it travels from entry (A) to exit point (B). Rather, the software establishes where it has been after it is retrieved

from the pipe.

Page 7: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 7

As the probe travels from A to B, each of the 20+ sensors of the OMU log

passively, i.e. there is no data-processing ongoing inside the OMU. Logging

occurs at 100Hz, or 100 samples per second.

Essentially, for each sample, the X-Traction® software calculates change in the X-direction (distance), Y-direction (heading), Z-direction (pitch) and

Roll position.

From the multiple odometers on the tool the travelled distance per sample is derived and the resulting length profile is integrated with vector results,

thus giving each vector (sample) a length. When samples are placed in sequence, the path travelled is reconstructed. Then the reconstructed

trajectory is linked to the known coordinates of A and B to obtain the final

result in the chosen coordinate system.

The X-View® software generates three open platform output file formats; 1] comma separated values (.csv), 2] Excel table (.xlsx), and 3] AutoCAD

script (.scr). This enables minimum conversion time when loading results

into GIS or other platforms.

In summary, the key unique features of the DuctRunner Technology are:

▪ It operates autonomously (no data cable) and as a result can map to

any depth.

▪ Due to its high logging rate, the OMU can travel up to 2m per second.

▪ The sensors are insensitive to electromagnetic interference and can

therefore be used near power cables, train tracks, etc.

▪ The systems can be used in any type of pipe material, including steel,

PVC, HDPE and concrete.

▪ The technology is compact and modular, so it can fit in single or

compartmentalized casings.

▪ Open platform output files for seamless integration of data in most

commonly used GIS platforms.

Page 8: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 8

Calibration Procedure

Objective

Reduct pipeline mapping probes are manufactured and assembled using state of the art machinery and the best materials and components. The

primary nine inertial measurement sensors are assembled such that they are placed as accurately as possible on the X, Y or Z axis of the probe.

However, all mechanical assembly is invariably imperfect, i.e. the angles

between the nine key inertial sensors are not exactly 90°. The objective, therefore, of the Reduct calibration procedure is to measure the angular

errors and compensate them mathematically.

Method

Reduct has developed the DR-CR-

002, a proprietary calibration robot. Over a period of about two hours, the

robot moves a probe through over 440 static positions and dynamic

moves in an inclination range between -60° to +60° (red arrows)

while rotating the unit 360° around its X-Axis (yellow arrow) and 360°

around its Y-Axis (blue arrows).

Upon completion of the calibration

procedure the data gathered by the probe during the calibration

procedure is uploaded to the calibration software for further

analysis.

Mathematical adjustment

A perfectly assembled system calibration data yields perfect sine curves.

The data gathered from a probe is processed and an initial match to the perfect sine curve is made in the form of a scaling to the curve (BLUE

columns in the table on the reverse side). Then, a series of proprietary algorithms will mathematically adjust the assembly angle of each primary

sensor until it finds the best fit to the perfect sine curve. The remaining

scaling values for the primary inertial sensors must be below 0.4% for the probe to pass the SCT test. The resulting calibrated settings are then

uploaded into the X-Traction software that matches the probe’s serial

number.

Page 9: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 9

Track validation

As a final check, the probe’s

performance is tested on a fixed track. The probe is passed through the track in

both directions and moving forward as well as backward a total of eight times.

The repeatability of the eight

measurements must be high: the absolute spread (as a percentage of pipe

length) on the XY-plane may not exceed 0.25% and in the Z-plane may not

exceed 0.10%.

Once a probe meets Reduct’s stringent post-calibration specifications, an OMU

Calibration Certificate is issued for a

period of one year.

System Accuracy

All systems delivered from June 01, 2018 onwards are equipped with

technology generation 4.5.

DR systems equipped with 4.5 generation technology leave the factory with a guaranteed Calibrated Accuracy of 10cm XY and 6cm Z over 500m pipe

length (or 0.02% XY and 0.01% Z as a % of pipe length).

ABM systems equipped with 4.5 generation technology leave the factory with a guaranteed Calibrated Accuracy of 10cm XY and 6cm Z over 300m

pipe length (or 0.03% XY and 0.01% Z as a % of pipe length).

Page 10: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 10

System Output

X-View software has the following Save and output File Format options.

Output content File Format

XYZ coordinate list at user defined spacing interval

Longitude / Latitude list

csv, xlsx

Project log information, XYZ coordinate list, Azimuth and

Pitch in degrees, 3D and 2D bend radius data (X-View Pro

only)

csv, xlsx,

xml

XYZ data for AutoCAD scr

LZ data for AutoCAD (depth profile) scr

XY and LZ graphs bmp

Google Earth kml

Page 11: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 11

Pipeline Mapping System Description: DR-4

The DR-4 Pipeline Mapping System is the most versatile standard system

on offer and will therefore be used as an example for the system description.

The probe comprises of (1) an Orientation Measurement Unit (OMU) and

(2) one or more wheel sets.

OMU System Components and Specifications

Code Component

OMU-84442 Orientation Measurement Unit

BP-4 3 Batteries + 2 Chargers

CU8444X-R 2 Control Units

LPC8444X-R Semi-Ruggedized Laptop PC

FC84441 Custom Flight Case

Technical Specifications

Length OMU 492mm Water resistance IP68

Diameter in middle 42mm Power supply 3.7V

Weight 1.6 kg Operating temp -10 to 60 °C

2

1

Page 12: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 12

Centralizing Wheel Sets

Measurement accuracy is directly related to the degree that the OMU is

aligned with the direction of the pipe it is measuring. The standard centralising wheel sets are specially designed to ensure an optimal

alignment in the pipe. The standard sets cover a pipe ID range from 90mm up to 1000mm.

Code Component

WUS-0320 DR4 Centraliser Sets for Pipe ID 90-500mm

WUS-2040 DR4 Centraliser Sets for Pipe ID 500-1000mm

If larger diameters are required, bespoke frames can be supplied.

Invert wheel sets

In addition to the centralizing wheel sets Reduct offers a Standard Invert Wheel Set for pipes with internal diameters starting from 150mm. Invert

wheel sets run along the bottom of the pipe and can bypass more

irregularities than the standard centralized wheel sets.

Page 13: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 13

Product Code

Component

IWS-0612

Pipe ID range: 6-12” Invert Wheel set + Ø72mm/3“ Wheels + Ø125mm/5“ Wheels

IWS-1440

Pipe ID range: 14-40” Invert Wheel set + Ø125mm/5“ Wheels Ø150mm/6“ Wheels Ø200mm/8“ Wheels

IWS-0640

IWS-0612 + IWS-1440 + Case

Laptop and Software

The standard OMU system laptop is a Semi-Ruggedized Panasonic Toughbook (or equivalent). The following pre-installed software is part of

the OMU:

▪ X-Traction® - Post processing software, is used to convert the logged

raw data into 3D profiles.

▪ X-View® - 3D imaging and comparison software, providing the

average of a multitude runs of a pipe segment. The Pro version also contains the bend radius analysis functionality. Bend Radius data is

typically used:

o To verify installation specifications of new built pipes.

o As input to pipe stress calculation models for pressurized

pipelines (Gas, Water, Crude, Chemicals).

Page 14: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 14

High Speed Electrical Winches

The performance of the DuctRunner Pipeline

Mapping Systems is best if pulled at a relatively constant speed of about 1 to 2 meters per

second. Therefore, Reduct has developed a custom rapid electrical winch system, the

DRW-560S.

A survey team requires two winches, one on at each man hole. This significantly improves

efficiency and allows for multiple runs to be

executed in a very short time frame.

Per winch Reduct recommends a EuroPower EP3300 generator (see Annex

1 for technical details).

Page 15: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 15

General Method Statement

This General Method Statement outlines the operational procedures of Reduct’s Pipeline Mapping Systems when the system is propelled by means

of a pulling wire only. Should propulsion by means of pulling not be an option, please contact Reduct so that a suitable alternative propulsion

method can be agreed.

Despite the fact that certain safety recommendations are made, local Health

and Safety regulations (i.e. at the location of the job site) prevail over the

recommendations in this document.

Scope of the Works

The objective is to map an underground pipeline segment from a known entry point to a known exit point and obtain accurate three-dimensional

coordinates at regular intervals. The standard propulsion method described

herein is by means of pulling the DR-4 probe through the pipe segment.

General Site Preparations

To ensure optimal productivity, certain site preparations are assumed to be

carried out in advance. Amongst these are:

▪ Arranging all necessary permits from the municipality.

▪ Ensuring site safety measures are in accordance with local Health and

Safety regulations.

▪ The pipeline entry and exit points are freely accessible by foot and

that there is sufficient hard soil to place the winch on.

▪ The pipeline is empty and clean. Ideally its integrity (roundness) is tested in advance

using a standard calliper pig.

▪ A pulling cord is installed (4-6mm

Polypropylene preferred) prior to arrival.

▪ The contractor have available the XYZ coordinates of the TOPSIDE of the pipe that

will be mapped at entry and exit point (See

picture).

Page 16: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 16

Access Point Safety Arrangements

Type of access Safety requirements

Street manhole

▪ General safety requirements.

Open dug pit

▪ General safety requirements.

▪ Groundwater drainage pump.

▪ Ladder.

▪ Shoring up of pit walls.

Shaft access

▪ General safety requirements.

▪ Ladder.

▪ Toxic gas metering.

▪ Operator must have successfully completed a locally approved

Confined Space Training course.

Underground chamber

▪ General safety requirements.

▪ Ladder.

▪ Toxic gas metering.

▪ Operator must have successfully

completed a locally approved Confined Space Training course.

Page 17: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 17

Plant

Pipeline Mapping Tool

Example: DR-4

2 x Electrical Winches (one with sufficient rope

for the segment length)

For lengths shorter than 150m manual handling is

recommended.

2 x Petrol Powered Generators

Semi-Ruggedized Laptop PC

Page 18: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 18

Space requirements

Typically, about 3-4m of firm

underground directly behind the entry and exit points is required to set up the

pulling winches (and generator if

applicable). The Reduct van can be parked off-site if space is limited.

The winches are operated by an electrical motor and emit no harmful

fumes. They are designed to dissemble easily so that they can easily be

lowered into an underground chamber

by hand.

The winches can be placed on an HDD

rig in case of mapping pilot bore strings.

Page 19: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 19

Description of the operational procedures

A standard measurement broadly contains three steps:

Step 1: Raw data collection

1. At entry and end points a winch and generator are prepared.

2. The (pre-installed) pulling cord is connected to the DuctRunner probe.

Another cord is attached to the back of the probe.

3. The probe is switched into logging mode.

4. The probe is manually inserted into the entry point of the pipe in the FORWARD

direction.

5. Underneath the entry point coordinate a 30-

60 second period of calibration is observed.

6. The probe is pulled through the pipeline (±

1m/sec) until the nose of the probe is

arrives underneath the end-point coordinate.

7. A 30-60 second period of calibration is observed.

8. The probe is pulled back to the entry point of the pipe (± 1m/sec).

9. Back at the entry point a 30-60 second period of calibration is observed.

10. The probe is pulled out of the pipe turned around and reinserted into the pipe in the BACKWARD direction.

11. Steps 5 to 9 are repeated.

12. The probe is retrieved from the pipe and logging is stopped. The

recorded data is uploaded to a PC and checked for validity.

Page 20: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 20

Step 2: Data Processing

Raw data logged by the DR-4 probe is

combined with known entry and exit point

coordinates to produce the following output:

• Coordinate table at a customer defined

frequency (e.g. 1 sample per meter)

• 3D pipeline profile

• 2D depth profile

• Inclination analysis

• Bend radius chart (optional)

• The DRC-1 and DRC-2 Pipeline

Inspection Systems will also provide an

XYZ synchronized in-pipe video image.

Results from multiple measurements in opposite directions can be

compared and averaged in X-View®.

Step 3: Upload into GIS platform

Resulting pipeline data is saved in open platform formats (.xlsx, .csv and

.scr) for seamless integration in common GIS platforms such as:

• AutoCAD

• MicroStation

• Excel

• ESRI

• …

Seamless integration into other GIS platforms can be programmed upon

demand.

The entire process typically takes about 1 hour per pipe segment of 500m.

Page 21: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 21

Skill Requirements and Documentation

A survey team consist of a minimum of two persons (Operators 1 and 2),

one at each side of the pipeline segment.

At the entry point (usually also the location where the laptop resides) Operator 1 should have sufficient knowledge and experience to safely

perform the system preparation and handling, data downloading and

processing procedures of the Pipeline Mapping System used. At the exit point Operator 2 should have sufficient skills to operate the electric winch

and power generator.

Operators are trained by Reduct during a two-day training session. This training includes all operational features of the system and detailed data

assessment. Most of the second day will be focused on troubleshooting and recognising operational errors and unsuccessful measurements. Successful

trainees will obtain the title Certified DR-XXXX Operator.

The basic two-day course only familiarizes the Operators with the system and operational tools. However, extensive field trials are required to become

experienced Operators. Reduct will include in its offer a fee for two weeks of field supervision by an experienced Reduct engineer.

Required knowledge of the following manuals and instructions:

▪ DR-XXXX User Manual

▪ Wheel Unit User Manual

▪ Winch Manual

▪ Power generator Manual

▪ Health and Safety Instruction card

In case of Shaft Access or underground Chamber access, Reduct

recommends a certified first-aid worker is present at each access point.

Personal Protective Equipment (PPE)

Reduct recommends that all operational personnel wear safety clothing with a minimum of:

▪ An approved helmet

▪ A reflective vest/coat

▪ Steel tipped safety shoes

▪ Gloves

▪ Safety glasses

Page 22: Technical Method Statement Standard Technical...© Reduct 2018: Standard Technical Method Statement. 2 Table of Contents Introduction 3 About Reduct 3 Product Positioning ..... 3

© Reduct 2018: Standard Technical Method Statement. 22

Annex 1: Europower Generator – technical specifications

Type quoted: EP3300

A = 2 Sockets 230V - 16A

F = Frame

O = Oil guard

R = Recoil Starter

Th = Circuit breaker