Temporary Road Closures for Almond PP Pipeline Project
Temporary Road Closures for Almond PP Pipeline Project
Castro Valley Municipal Advisory Council Meeting
March 17, 2014
![Page 2: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/2.jpg)
Meeting Agenda
•Project Scope
•Community Outreach
•Temporary Road Closure Plan
•Road Restoration
2
![Page 3: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/3.jpg)
Project Location – Castro Valley
Proposed Road Closures
3
![Page 4: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/4.jpg)
EBMUD Scope of Work
• Replace Almond Pumping Plant
• Replace Pipelines
• Rehab El Portal Reservoir
• Total construction cost ~$11 million
• Project benefits surrounding community
4
![Page 5: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/5.jpg)
Project Location – Castro Valley
174th Ave
President Dr
Ehle St
5
New Pipelines
![Page 6: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/6.jpg)
Narrow Residential Roads
6
![Page 7: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/7.jpg)
Narrow Residential Roads
7
![Page 8: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/8.jpg)
Narrow Residential Roads
8
![Page 9: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/9.jpg)
Construction Schedule and Work Hours
• Start construction: February 2014
• Pipeline & road closures: ~3 months, June to August 2014
• Road closures: 9 am to 6 pm, M to F
• In-Service: February 2016
9
![Page 10: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/10.jpg)
Community Outreach
• Postcards (Sept 2011)
• CEQA Documentation (Oct 2011)
• Project website (Oct 2011)
• Pre-construction postcards (Jan 2014)
• Portable Changeable Message Signs (during construction)
10
![Page 11: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/11.jpg)
County Agency Outreach
• Met & gained support of County Agencies:
– Public Works Dept
– Sheriff Dept
– Fire Dept
– Emergency Medical Services
• Emergency Communications:
– Continuous open radio channel
– 10 minute passage requirement11
![Page 12: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/12.jpg)
Road Closure Report
• Traffic counts
• Closure analysis
• Detour plans
• Traffic control plans
12
![Page 13: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/13.jpg)
Detour Plan
Road Closure Location Duration(days)
1 173rd Ave btw Ehle & Roberto 5
2 173rd Ave btw Roberto & Robey 4
3a Robey Dr / 174th Ave 12
3b Robey Dr / 174th Ave 5
3c Robey Dr / 174th Ave 7
Total 33
5 road closures, totaling 33 days, over ~ 3 months
13
![Page 14: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/14.jpg)
Traffic Control
Road Closure
Activity Work by Duration
3a Install Pipelines Contractor 6 days for 1st 400 linear feet +/-6 days for next 400 linear feet +/-
3b Transfer Services District 5 days
3c Pave full width Contractor 7 days
Closure of Robey Dr / 174th Ave
• Work hours 9:00am to 6:00pm, M to F
• Road opened at end of the day w/ plates and temporary AC
• Residents access maintained with minor delays
• No street parking
• Street improvement with full width pavement restoration
• Required internal welding for 36” Pipe and CDF backfill to accelerate installation
14
![Page 15: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/15.jpg)
Pavement Restoration
Temporary Service LateralsWMWM
15
![Page 16: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/16.jpg)
Pavement Restoration
16
![Page 17: Temporary Road Closures for Almond PP Pipeline … Road Closures for Almond PP Pipeline Project Castro Valley Municipal Advisory Council Meeting March 17, 2014](https://reader034.vdocument.in/reader034/viewer/2022042801/5abf7db57f8b9a8e3f8e540d/html5/thumbnails/17.jpg)
Questions?
Thank You!