term- and auto-dlm webinar

29
1 December 4, 2020 Term- and Auto-DLM Webinar

Upload: others

Post on 01-Oct-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Term- and Auto-DLM Webinar

1

December 4 2020

Term- and Auto-DLM Webinar

Agenda

bullCompetitive Procurement Framework

bullTerm- and Auto-DLM Programs

bullApplication Process and Schedule

bullEvaluation and Contracts

bullCustomer Eligibility and Metering Requirements

bullCustomer Enrollment

bullPerformance Evaluation and Payments

bullContract Transfers

2

Competitive Procurement FrameworkLong Term Contracts for DR Resources

bullContracts are awarded through a Request for Proposal (RFP) process

bullParticipants can seek 3-5 year contracts

bullCapability Period for both programs is May 1 through September 30

bullBidders provide a single per kW Incentive Rate for each bid which determines

annual per kW compensation

bullOnce clearing bids are determined Participants are given the chance to accept

or reject a contract including all clearing bids

bullPerformance standards are more demanding than for CSRP and DLRP

bullFor this year only the Procurement will be for both 2021 and 2022

3

4

bull Purpose Day ahead peak shaving (Similar to CSRP)

bull System wide activation

Can activate at 88 of forecasted system peak

Will activate at 92 percent of forecasted system peak

4-hour Call Windows

bull 21-hour notifications

bull Dual Participation with DLRP allowed

bull One-hour test events

Term ndash DLMKey Features

5

Term ndash DLMLoad Forecast Threshold Frequency

Year

92 Percent of

Forecasted Summer

System Peak (kW)

88 Percent of

Forecasted Summer

System Peak (kW)

Weekdays above 92

percent of

Forecasted Summer

System Peak

Weekdays above 88

percent of

Forecasted Summer

System Peak

2016 12600 12100 2 6

2017 12400 11900 0 3

2018 12300 11800 6 12

2019 12300 11800 1 4

2020 12100 11600 0 3

6

bull Purpose Peak shaving and Reliability

bull Participates in Term-DLM in addition to Auto-DLM

Events

bull System wide andor one or several networks

10 min notifications

bull Cannot participate in CSRP or DLRP

bull 7 days a week program

bull Four-hour events one-hour test events

Auto ndash DLMKey Features

7

Auto ndash DLMPast DLRP Event Calling Frequency

YearDays with DLRP

Events

Maximum Events any

Network was Called forTest Events

2016 10 6 1

2017 3 3 2

2018 4 2 1

2019 8 5 1

2020 18 13 1

In 2020 three networks faced a multiday contingency causing a large

number of events to be called in a short period

8

Application Process and ScheduleKey Dates

MilestonesDates for

2021 Vintage Year

Dates for

2022 Vintage Year

1 Release RFP Monday November 30 2020

2 Webinar Friday December 4 2020

3Applicants submit clarification

questionsFriday December 11 2020

4 Responds to clarification questions Friday December 18 2020

5Deadline for Aggregator enablement in

Oracle amp Applicants to express interestMonday January 4 2021

6 RFP response deadline Friday January 15 2021

7 RFP awardnotification Friday February 12 2021

8 Contract execution date Friday February 26 2021

9 Early Exit Fee exercise amp payment due NA Monday November 1 2021

10 Enrollment deadline Thursday April 1 2021 Friday April 1 2022

11 Capability Period start Saturday May 1 2021 Sunday May 1 2022

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 2: Term- and Auto-DLM Webinar

Agenda

bullCompetitive Procurement Framework

bullTerm- and Auto-DLM Programs

bullApplication Process and Schedule

bullEvaluation and Contracts

bullCustomer Eligibility and Metering Requirements

bullCustomer Enrollment

bullPerformance Evaluation and Payments

bullContract Transfers

2

Competitive Procurement FrameworkLong Term Contracts for DR Resources

bullContracts are awarded through a Request for Proposal (RFP) process

bullParticipants can seek 3-5 year contracts

bullCapability Period for both programs is May 1 through September 30

bullBidders provide a single per kW Incentive Rate for each bid which determines

annual per kW compensation

bullOnce clearing bids are determined Participants are given the chance to accept

or reject a contract including all clearing bids

bullPerformance standards are more demanding than for CSRP and DLRP

bullFor this year only the Procurement will be for both 2021 and 2022

3

4

bull Purpose Day ahead peak shaving (Similar to CSRP)

bull System wide activation

Can activate at 88 of forecasted system peak

Will activate at 92 percent of forecasted system peak

4-hour Call Windows

bull 21-hour notifications

bull Dual Participation with DLRP allowed

bull One-hour test events

Term ndash DLMKey Features

5

Term ndash DLMLoad Forecast Threshold Frequency

Year

92 Percent of

Forecasted Summer

System Peak (kW)

88 Percent of

Forecasted Summer

System Peak (kW)

Weekdays above 92

percent of

Forecasted Summer

System Peak

Weekdays above 88

percent of

Forecasted Summer

System Peak

2016 12600 12100 2 6

2017 12400 11900 0 3

2018 12300 11800 6 12

2019 12300 11800 1 4

2020 12100 11600 0 3

6

bull Purpose Peak shaving and Reliability

bull Participates in Term-DLM in addition to Auto-DLM

Events

bull System wide andor one or several networks

10 min notifications

bull Cannot participate in CSRP or DLRP

bull 7 days a week program

bull Four-hour events one-hour test events

Auto ndash DLMKey Features

7

Auto ndash DLMPast DLRP Event Calling Frequency

YearDays with DLRP

Events

Maximum Events any

Network was Called forTest Events

2016 10 6 1

2017 3 3 2

2018 4 2 1

2019 8 5 1

2020 18 13 1

In 2020 three networks faced a multiday contingency causing a large

number of events to be called in a short period

8

Application Process and ScheduleKey Dates

MilestonesDates for

2021 Vintage Year

Dates for

2022 Vintage Year

1 Release RFP Monday November 30 2020

2 Webinar Friday December 4 2020

3Applicants submit clarification

questionsFriday December 11 2020

4 Responds to clarification questions Friday December 18 2020

5Deadline for Aggregator enablement in

Oracle amp Applicants to express interestMonday January 4 2021

6 RFP response deadline Friday January 15 2021

7 RFP awardnotification Friday February 12 2021

8 Contract execution date Friday February 26 2021

9 Early Exit Fee exercise amp payment due NA Monday November 1 2021

10 Enrollment deadline Thursday April 1 2021 Friday April 1 2022

11 Capability Period start Saturday May 1 2021 Sunday May 1 2022

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 3: Term- and Auto-DLM Webinar

Competitive Procurement FrameworkLong Term Contracts for DR Resources

bullContracts are awarded through a Request for Proposal (RFP) process

bullParticipants can seek 3-5 year contracts

bullCapability Period for both programs is May 1 through September 30

bullBidders provide a single per kW Incentive Rate for each bid which determines

annual per kW compensation

bullOnce clearing bids are determined Participants are given the chance to accept

or reject a contract including all clearing bids

bullPerformance standards are more demanding than for CSRP and DLRP

bullFor this year only the Procurement will be for both 2021 and 2022

3

4

bull Purpose Day ahead peak shaving (Similar to CSRP)

bull System wide activation

Can activate at 88 of forecasted system peak

Will activate at 92 percent of forecasted system peak

4-hour Call Windows

bull 21-hour notifications

bull Dual Participation with DLRP allowed

bull One-hour test events

Term ndash DLMKey Features

5

Term ndash DLMLoad Forecast Threshold Frequency

Year

92 Percent of

Forecasted Summer

System Peak (kW)

88 Percent of

Forecasted Summer

System Peak (kW)

Weekdays above 92

percent of

Forecasted Summer

System Peak

Weekdays above 88

percent of

Forecasted Summer

System Peak

2016 12600 12100 2 6

2017 12400 11900 0 3

2018 12300 11800 6 12

2019 12300 11800 1 4

2020 12100 11600 0 3

6

bull Purpose Peak shaving and Reliability

bull Participates in Term-DLM in addition to Auto-DLM

Events

bull System wide andor one or several networks

10 min notifications

bull Cannot participate in CSRP or DLRP

bull 7 days a week program

bull Four-hour events one-hour test events

Auto ndash DLMKey Features

7

Auto ndash DLMPast DLRP Event Calling Frequency

YearDays with DLRP

Events

Maximum Events any

Network was Called forTest Events

2016 10 6 1

2017 3 3 2

2018 4 2 1

2019 8 5 1

2020 18 13 1

In 2020 three networks faced a multiday contingency causing a large

number of events to be called in a short period

8

Application Process and ScheduleKey Dates

MilestonesDates for

2021 Vintage Year

Dates for

2022 Vintage Year

1 Release RFP Monday November 30 2020

2 Webinar Friday December 4 2020

3Applicants submit clarification

questionsFriday December 11 2020

4 Responds to clarification questions Friday December 18 2020

5Deadline for Aggregator enablement in

Oracle amp Applicants to express interestMonday January 4 2021

6 RFP response deadline Friday January 15 2021

7 RFP awardnotification Friday February 12 2021

8 Contract execution date Friday February 26 2021

9 Early Exit Fee exercise amp payment due NA Monday November 1 2021

10 Enrollment deadline Thursday April 1 2021 Friday April 1 2022

11 Capability Period start Saturday May 1 2021 Sunday May 1 2022

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 4: Term- and Auto-DLM Webinar

4

bull Purpose Day ahead peak shaving (Similar to CSRP)

bull System wide activation

Can activate at 88 of forecasted system peak

Will activate at 92 percent of forecasted system peak

4-hour Call Windows

bull 21-hour notifications

bull Dual Participation with DLRP allowed

bull One-hour test events

Term ndash DLMKey Features

5

Term ndash DLMLoad Forecast Threshold Frequency

Year

92 Percent of

Forecasted Summer

System Peak (kW)

88 Percent of

Forecasted Summer

System Peak (kW)

Weekdays above 92

percent of

Forecasted Summer

System Peak

Weekdays above 88

percent of

Forecasted Summer

System Peak

2016 12600 12100 2 6

2017 12400 11900 0 3

2018 12300 11800 6 12

2019 12300 11800 1 4

2020 12100 11600 0 3

6

bull Purpose Peak shaving and Reliability

bull Participates in Term-DLM in addition to Auto-DLM

Events

bull System wide andor one or several networks

10 min notifications

bull Cannot participate in CSRP or DLRP

bull 7 days a week program

bull Four-hour events one-hour test events

Auto ndash DLMKey Features

7

Auto ndash DLMPast DLRP Event Calling Frequency

YearDays with DLRP

Events

Maximum Events any

Network was Called forTest Events

2016 10 6 1

2017 3 3 2

2018 4 2 1

2019 8 5 1

2020 18 13 1

In 2020 three networks faced a multiday contingency causing a large

number of events to be called in a short period

8

Application Process and ScheduleKey Dates

MilestonesDates for

2021 Vintage Year

Dates for

2022 Vintage Year

1 Release RFP Monday November 30 2020

2 Webinar Friday December 4 2020

3Applicants submit clarification

questionsFriday December 11 2020

4 Responds to clarification questions Friday December 18 2020

5Deadline for Aggregator enablement in

Oracle amp Applicants to express interestMonday January 4 2021

6 RFP response deadline Friday January 15 2021

7 RFP awardnotification Friday February 12 2021

8 Contract execution date Friday February 26 2021

9 Early Exit Fee exercise amp payment due NA Monday November 1 2021

10 Enrollment deadline Thursday April 1 2021 Friday April 1 2022

11 Capability Period start Saturday May 1 2021 Sunday May 1 2022

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 5: Term- and Auto-DLM Webinar

5

Term ndash DLMLoad Forecast Threshold Frequency

Year

92 Percent of

Forecasted Summer

System Peak (kW)

88 Percent of

Forecasted Summer

System Peak (kW)

Weekdays above 92

percent of

Forecasted Summer

System Peak

Weekdays above 88

percent of

Forecasted Summer

System Peak

2016 12600 12100 2 6

2017 12400 11900 0 3

2018 12300 11800 6 12

2019 12300 11800 1 4

2020 12100 11600 0 3

6

bull Purpose Peak shaving and Reliability

bull Participates in Term-DLM in addition to Auto-DLM

Events

bull System wide andor one or several networks

10 min notifications

bull Cannot participate in CSRP or DLRP

bull 7 days a week program

bull Four-hour events one-hour test events

Auto ndash DLMKey Features

7

Auto ndash DLMPast DLRP Event Calling Frequency

YearDays with DLRP

Events

Maximum Events any

Network was Called forTest Events

2016 10 6 1

2017 3 3 2

2018 4 2 1

2019 8 5 1

2020 18 13 1

In 2020 three networks faced a multiday contingency causing a large

number of events to be called in a short period

8

Application Process and ScheduleKey Dates

MilestonesDates for

2021 Vintage Year

Dates for

2022 Vintage Year

1 Release RFP Monday November 30 2020

2 Webinar Friday December 4 2020

3Applicants submit clarification

questionsFriday December 11 2020

4 Responds to clarification questions Friday December 18 2020

5Deadline for Aggregator enablement in

Oracle amp Applicants to express interestMonday January 4 2021

6 RFP response deadline Friday January 15 2021

7 RFP awardnotification Friday February 12 2021

8 Contract execution date Friday February 26 2021

9 Early Exit Fee exercise amp payment due NA Monday November 1 2021

10 Enrollment deadline Thursday April 1 2021 Friday April 1 2022

11 Capability Period start Saturday May 1 2021 Sunday May 1 2022

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 6: Term- and Auto-DLM Webinar

6

bull Purpose Peak shaving and Reliability

bull Participates in Term-DLM in addition to Auto-DLM

Events

bull System wide andor one or several networks

10 min notifications

bull Cannot participate in CSRP or DLRP

bull 7 days a week program

bull Four-hour events one-hour test events

Auto ndash DLMKey Features

7

Auto ndash DLMPast DLRP Event Calling Frequency

YearDays with DLRP

Events

Maximum Events any

Network was Called forTest Events

2016 10 6 1

2017 3 3 2

2018 4 2 1

2019 8 5 1

2020 18 13 1

In 2020 three networks faced a multiday contingency causing a large

number of events to be called in a short period

8

Application Process and ScheduleKey Dates

MilestonesDates for

2021 Vintage Year

Dates for

2022 Vintage Year

1 Release RFP Monday November 30 2020

2 Webinar Friday December 4 2020

3Applicants submit clarification

questionsFriday December 11 2020

4 Responds to clarification questions Friday December 18 2020

5Deadline for Aggregator enablement in

Oracle amp Applicants to express interestMonday January 4 2021

6 RFP response deadline Friday January 15 2021

7 RFP awardnotification Friday February 12 2021

8 Contract execution date Friday February 26 2021

9 Early Exit Fee exercise amp payment due NA Monday November 1 2021

10 Enrollment deadline Thursday April 1 2021 Friday April 1 2022

11 Capability Period start Saturday May 1 2021 Sunday May 1 2022

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 7: Term- and Auto-DLM Webinar

7

Auto ndash DLMPast DLRP Event Calling Frequency

YearDays with DLRP

Events

Maximum Events any

Network was Called forTest Events

2016 10 6 1

2017 3 3 2

2018 4 2 1

2019 8 5 1

2020 18 13 1

In 2020 three networks faced a multiday contingency causing a large

number of events to be called in a short period

8

Application Process and ScheduleKey Dates

MilestonesDates for

2021 Vintage Year

Dates for

2022 Vintage Year

1 Release RFP Monday November 30 2020

2 Webinar Friday December 4 2020

3Applicants submit clarification

questionsFriday December 11 2020

4 Responds to clarification questions Friday December 18 2020

5Deadline for Aggregator enablement in

Oracle amp Applicants to express interestMonday January 4 2021

6 RFP response deadline Friday January 15 2021

7 RFP awardnotification Friday February 12 2021

8 Contract execution date Friday February 26 2021

9 Early Exit Fee exercise amp payment due NA Monday November 1 2021

10 Enrollment deadline Thursday April 1 2021 Friday April 1 2022

11 Capability Period start Saturday May 1 2021 Sunday May 1 2022

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 8: Term- and Auto-DLM Webinar

8

Application Process and ScheduleKey Dates

MilestonesDates for

2021 Vintage Year

Dates for

2022 Vintage Year

1 Release RFP Monday November 30 2020

2 Webinar Friday December 4 2020

3Applicants submit clarification

questionsFriday December 11 2020

4 Responds to clarification questions Friday December 18 2020

5Deadline for Aggregator enablement in

Oracle amp Applicants to express interestMonday January 4 2021

6 RFP response deadline Friday January 15 2021

7 RFP awardnotification Friday February 12 2021

8 Contract execution date Friday February 26 2021

9 Early Exit Fee exercise amp payment due NA Monday November 1 2021

10 Enrollment deadline Thursday April 1 2021 Friday April 1 2022

11 Capability Period start Saturday May 1 2021 Sunday May 1 2022

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 9: Term- and Auto-DLM Webinar

bull Applications will contain one or more Aggregations which are bids to provide a quantity of Load Relief in a

Network successful Applicants will have to accept all Aggregations they are cleared for

bull Aggregations must specify

1) Amount of Load Relief the Aggregation will supply in kW -gt If accepted this becomes the Cleared Quantity

2) The per kW Incentive Rate an Aggregation is seeking Participants who perform perfectly on all events will earn an

annual per kW Reservation Payment equivalent to this Incentive Rate which is paid at the end of the season

3) The Network Load Relief will be supplied in

4) Whether this is a Term- or Auto-DLM Aggregation

5) Desired contract length from 3-5 years

bull Each row represents a separate Aggregation

bull As many as three Sub-aggregations can be submitted for each Network so long as each provides 50 kW of

Load Relief Each of these will be evaluated separately for clearing purposes

bull Separate submissions for the Term- and Auto-DLM Programs and for Vintage Years 2021 and 2022

9

Application Process and ScheduleProcess

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 10: Term- and Auto-DLM Webinar

10

Application ProcessExample

Program Monthly per kW

Incentive Rate

(Fixed)

Annual per kW

Incentive Rate

Annual Reservation

Payment with 100

Performance

CSRP $18 $18 x 5 months = $90

CSRP + DLRP $18 + $18 = $36 $36 x 5 months = $180

Term-DLM $90 $90

Auto-DLM $180 $180

Note These values are for explanatory purposes only and do not imply clearance prices

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 11: Term- and Auto-DLM Webinar

Application Process and ScheduleProcess

11

115Applicants must submit completed RFP Proposal(s) via Con Edisonrsquos Oracle Supplier Portal by 1152021

14Applicants must be enabled within Oracle AND have expressed interest in bidding to Lauren Armely by 142021 to participate in RFP

1218Con Edison will consolidate all questions and post responses to the DLM RFP Website by 12182020 After which no additional questions will be accepted

124Con Edison Hosts Webinar on 1242020 Con Edison will collect questions from the Webinar Applicants should submit any additional questions to Supply Chain representative Lauren Armely armelylconedcom

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 12: Term- and Auto-DLM Webinar

Application Process and ScheduleProcess

bull Aggregator enablement in Oracle Deadline 14ndash Please use Internet Explorer to log into the Oracle

iSupplier Homepagebull iSupplier Websitebull iSupplier User Guide

ndash Log-inbull Username (Your email address in all capital letters) bull Case-sensitive password (included in workflow mailer)

bull If there are issues with the password please click on lsquologin assistancersquo to reset it A new workflow mailer will be sent to your email address

bull Applicants must also formally express interest by 14 ndash Applicants must email Con Edisonrsquos Supply Chain

representative Lauren Armely directly via email armelylconedcom

12

httpssupplierprdconedcom

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 13: Term- and Auto-DLM Webinar

Application Process and ScheduleProcess

13

226

Con Edison will send back to Applicant accepted Aggregations for each given Vintage Year Should Applicant accept or reject the award they will do so in a manner established by Con Edison Applicant must provide executed contract by2262021

212Con Edison will evaluate bid submissions and clear competitively priced Aggregations Con Edison will summarize which Aggregations clear and which have not cleared and notify bidders of RFP Award by 2122021

115Applicant will submit RFP Proposal(s) by 1152021 for each applicable Vintage Year (20212022) detailing proposed Networks Load Relief Duration amp Pricing

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 14: Term- and Auto-DLM Webinar

Application Process and ScheduleSubmission Form

14

bull Two separate Excel files ldquoDLM Applicant Proposal

Summary Templaterdquo for each Vintage Year

ndash Three tabs within including a cover sheet Term-DLM

proposal sheet and Auto-DLM proposal sheet

ndash Please read the instructions in red Each Network may

only include up to 3 sub-aggregations

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 15: Term- and Auto-DLM Webinar

Application Process and ScheduleUseful Tips

bull Begin the Aggregator Enrollment Process immediately if you are not already a Con Edison

approved Aggregator by contacting demandresponseconedcom

bull Register as a DER Provider with the PSC here if you plan to enroll residential customers

bull Obligations associated with each Aggregation must be met separately with separate groups of

customers

bull Participants will have to accept or reject all cleared Aggregations for a Vintage Year so please

ensure that Incentive Rates are calculated accordingly

bull Incentive Rates are based on a single per kW payment based on performance during the

Capability Period

bull Ensure that all customers you are counting on will be able to enroll by April 1 and can satisfy

both permitting and metering requirements

bull Be mindful that aggregations that perform poorly can be subject to performance penalties or

early termination

15

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 16: Term- and Auto-DLM Webinar

Evaluation and ContractsEvaluation and Clearing

bullAll Aggregations will be evaluated individually

bullCon Edison will use a Benefit-Cost Analysis framework to clear bids

bullTerm-DLM provides Load Relief value comparable to CSRP alone because

Load Relief capabilities are similar

bullAuto-DLM will be evaluated based on the Load Relief capabilities provided by

both CSRP and DLRP

bullProposals for Auto-DLM will receive additional consideration compared to those

for Term-DLM

bullAggregations in Tier 2 Networks as listed on page 11 of this document

16

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 17: Term- and Auto-DLM Webinar

Evaluation and ContractsContract Offers and Acceptance Options

bull Con Edison will send signed contracts to successful bid winner

bull These contracts will list for a given Vintage Year all Aggregations that have cleared

bull Each line will contain

ndashCleared Quantity Load Relief in kW

ndash Incentive Rate

ndashNetwork

ndashProgram

ndash Length of obligation from 3-5 years

bull Participants have the option of accepting or rejecting the terms in full

bull Applicants cannot accept or reject individual Aggregations

bull Separate contracts will be offered for each Vintage Year

17

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 18: Term- and Auto-DLM Webinar

Customer Eligibility and Metering RequirementsEligibility Requirements for Customers

1) Customer Accounts enrolled in Term-DLM may not enroll in CSRP

2) Customer Accounts enrolled in Auto-DLM may not enroll in CSRP or DLRP

3) Customers participating in Term- or Auto-DLM must forgo DRV and LSRV payments for as long as the

Aggregator or Direct Participantrsquos contractual obligation

4) Net Energy Metering Customers may not enroll in Term- or Auto-DLM

5) Customers enrolling for the 2021 Capability Period must have Account numbers or be in the Con Edison

Interconnection Queue

6) Customers already under contract for Non-Wires Solutions projects cannot participate in Term- or Auto-

DLM

7) Term- or Auto-DLM may bid additional Load Relief capacity into future Non-Wires Solutions projects

8) Diesel generators are forbidden to participate in Term- or Auto-DLM

9) All other customers relying on generation to provide Load Relief must meet permit and emissions

requirements

18

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 19: Term- and Auto-DLM Webinar

Customer Eligibility and Metering RequirementsMetering Requirements

bull Customer must have an interval meter or an AMI meter

ndash All customers will have AMI by 2023

ndash See the Con Edison Smart Meter website for more details

bull Customers gt500 kW Demand

ndash Con Edison may provide an interval meter at no cost

bull Customers lt500 kW Demand

ndash The customer is responsible for interval meter costs

bull Meter installations for Customers participating in Term- or Auto-DLM must be completed by April 1

bull For non-AMI Interval Meters Customers are responsible for ensuring adequate communications to ensure

that Event performance data will be available

19

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 20: Term- and Auto-DLM Webinar

Customer EnrollmentProcess

bull Enrollments in DR Portal open March 1

bull Only APPROVED Participants can access Portal

bull The Enrollment deadline is April 1

bull All Customer enrollments include

ndash Account Number

ndash Program Choice (Term- or Auto-DLM)

ndash Baseline Verification Methodology

ndash Load Relief via Curtailment (kW if any)

ndash Sub-aggregation number if any

ndash Vintage Year

ndash For Customers using Generation

bull Load Relief via Generation (kW)

bull Generator information including Nameplate Capacity (kW) Asset Type Capacity (kWh) Model year Manufacturer and any

associated compliance documentation

20

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 21: Term- and Auto-DLM Webinar

Customer Enrollment Strategy Considerations

bullCustomers must be enrolled to perform for a single cleared Aggregation

bullPerformance will reflect Load Relief provided by groups of Customers during Events

relative to the Load Relief obligation of that Aggregation

bullEnsure Customers can meet all enrollment and permitting requirements in time for

April 1 enrollment deadline in Vintage Year for an Aggregation or else those customers

may not be able to provide Load Relief during the first Capability Period

bullVerify that customers are not cross-registered for other DR Programs that would

invalidate their Term- or Auto-DLM registration and that they have not registered with

other program Participants

21

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 22: Term- and Auto-DLM Webinar

Performance Evaluation and PaymentsEvent Performance Assessment and Payments

bull Early Exit Fees can be paid to reduce the Portfolio Quantity for an Aggregation over the

remainder of a contract

bull Event performance is calculated at an Aggregation level

bull Average Seasonal Performance Factors across all events determine annual Reservation

Payments along with Incentive Rates and Portfolio Quantity of Load Relief associated with an

Aggregation

bull Aggregations are eligible to earn both Reservation Payments and Performance Payments

bull Performance Payments are based on kWh of Load Relief provided by Aggregation across events

bull Poor performance across events can result in both financial penalties at the end of a season and

early termination of Aggregations as part of a contract

22

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 23: Term- and Auto-DLM Webinar

Performance Evaluation and PaymentsEarly Exit Fees

bull When Participants accept a contract each Aggregation has a Cleared Quantity of Load Relief in kW

bull On November 1 prior to each Capability Period Participants can pay an Early Exit Fee to reduce their

Cleared Quantity by a Deficient Quantity to establish a new Portfolio Quantity for the Aggregation for the

remainder of the contract term

bull Early Exit Fee = Incentive Rate ($kW) X Deficient Quantity (kW) X Remaining Length of Contract (Years)

X 10

bull All Early Exit Fees must be paid by November 1 prior to the Capability Period it takes effect for

bull Paying an Early Exit Fee does not quash obligation to pay already accumulated financial penalties

bull Participants who earn an Average Season Performance Factor of less than 0 can be

ndash Assessed financial penalties

ndash Forced to terminate Aggregations before contract expiration and pay associated Early Exit Fees on those Aggregation

23

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 24: Term- and Auto-DLM Webinar

Performance Evaluation and PaymentsPerformance Calculations

bull Load Relief provided during events is measured at an Aggregation level summing Load Relief provided by

all customers associated with that Aggregation

bull Participants can select a Baseline Verification Methodology for each Customer

bull Event Performance Factor = Sum of Load Relief provided by Customers in an Aggregation Portfolio

Quantity -gt Capped at maximum value of 100 and minimum value of 000

bull Adjusted Performance Factor for Term-DLM = Event Performance Factor if le 080

ndash = Event Performance Factor ndash (080 ndash Event Performance Factor) if gt 080

bull Adjusted Performance Factor for Auto-DLM = Event Performance Factor if le 090

ndash = Event Performance Factor ndash (090 ndash Event Performance Factor) if gt 090

bull Average Season Performance Factor = Average of all Adjusted Performance Factors for Events held

during a Capability Period

24

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 25: Term- and Auto-DLM Webinar

Performance Evaluation and PaymentsPerformance Calculation Example (Term-DLM)

25

Event Event

Performance

Factor

Adjusted

Performance

Factor

Average Season

Performance Factor

Event 1 100 100

Event 2 070 060

Event 3 020 -040

For season 120 3 Events = 040

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 26: Term- and Auto-DLM Webinar

Performance Evaluation and PaymentsPerformance Calculations

26

-100

-50

0

50

100

150

100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0

Ad

just

ed P

erfo

rman

ce F

acto

r

Event Performance Factor

Performance Factor Calculation method for the two programs

Term-DLM Adjusted Performance Factor

Auto-DLM Adjusted Performacne Factor

Term DLM calculations for negative values

Auto-DLM calculations for negative values

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 27: Term- and Auto-DLM Webinar

Performance Evaluation and PaymentsPayment Timing and Calculation

bull Both Reservation and Performance Payments will be issued once per year after the conclusion

of the Capability Period

bull Payments calculated at the Aggregation level

bull Reservation Payment = Portfolio Quantity (kW) X Incentive Rate ($kW) X Average Season

Performance Factor

bull If Average Season Performance Factor is less than 0 Aggregations will OWE penalties

ndash These can be deducted from revenue earned by other Aggregations or invoiced separately

bull Performance Payments = Aggregation Load Relief in kWh across all events X $1 per kWh

ndash Performance Payments will not be paid based on the performance of customers simultaneously participating

in a DLRP Event

ndash Performance Payments will not be paid based on the performance of customers enrolled in Rider R

27

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 28: Term- and Auto-DLM Webinar

28

CAN TAKE EFFECT ONLY BETWEEN CAPABILITY PERIODS

TRANSFERS MUST TAKE PLACE BETWEEN APPROVED PARTICIPANTS

PROGRAM AGREEMENTS MUST BE AMENDED OR CREATED TO ACCOUNT FOR THESE TRANSFERS

AGGREGATIONS CAN BE PARTIALLY OR COMPLETELY TRANSFERRED

04

03

02

01

Contract TransfersAggregation Transfers

QampA

DemandResponseconedcom

wwwconedcomdr

Page 29: Term- and Auto-DLM Webinar

QampA

DemandResponseconedcom

wwwconedcomdr