TEX RAIL UPDATE AND T MASTER PLAN

PA U L J B A L L A R D P R E S I D E N T & C H I E F E X E C U T I V E O F F I C E R

F O RT W O RT H T R A N S P O RTAT I O N A U T H O R I T Y ( T H E T )

The Future of Transit and Commuter Rail in Tarrant

County

6th Annual Northeast Tarrant Transportation Summit

February 13, 2015

Page 2: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

P2 2/13/15

Page 3: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

TEX Rail MapEnhanced Bus

Corridor Development

ConceptEast Lancaster

Pilot Project

P3 2/13/15

Page 4: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

DFW Rail Access

P4 2/13/15

Page 5: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

Terminal B

Terminal A

Terminal Connector

The T Station DART Station

EmployeeDrop-off Area

Terminals A-B Station Concept

1 P5 2/13/15

Page 6: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

Photo of DCTA’s A-trainP6 2/13/15

Page 7: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

Photo of DCTA’s A-trainP7 2/13/15

Page 8: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

Photo of DCTA’s A-trainP8 2/13/15

Page 9: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

TEX Rail Project Funding Through 2019 when Short Term Construction Debt is

Retired

Primarily Sales Taxes from the City of Fort Worth

62/12/15

$446M FTA New Starts

Grant

$41M Other Federal $132M The T

$110M Grapevine

$20M Tarrant County

$86M Texas State Mobility

Fund $32M Dallas-Fort Worth Inter-

national Airport

$25M Regional Toll Revenue

Total $892M

P9 2/13/15

Page 10: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

Connection in progress

Included in the President’s FY15 Budget

FY15 New Starts rating Medium-High

FY16 New Starts Annual Update submitted and under evaluation by the FTA

Record of Decision received September 2014

Included in President’s FY16 Budget - $100,000,000

P10 2/13/15

Page 11: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

Issued RFP for CMGC Contractor – Dec 2014

Award Vehicle Contract – Early 2015

Full Funding Grant Agreement Award – Q1 2016

Revenue Service – 2018

Schedule

P11 2/13/15

Page 12: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

T Master Plan

Community

Involvement

• Five Year Service Plan• Funded by the North Central Texas Council of Governments

P12 2/13/15

Page 13: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

End ResultComprehensive Plan

with maps and visuals laying out what we

and the Community feel should be our network of public

transportation in the future

P13 2/13/15

Page 14: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

The T Ridership for All ModesFY 2003-2014

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 201450,000

2,050,000

4,050,000

6,050,000

8,050,000

10,050,000

12,050,000

8,488,133

8,047,988

8,468,8358,519,850

9,606,59210,101,791

10,192,437

10,031,427

10,190,810

10,835,927

10,662,463

11,020,228

P14 2/13/15

Page 15: TEX RAIL UPDATE AND T MASTER PLAN PAUL J BALLARD PRESIDENT & CHIEF EXECUTIVE OFFICER FORT WORTH TRANSPORTATION AUTHORITY (THE T) 6 th Annual Northeast

Questions?