the austrian koralm tunnel - investigation, design and ... · Öbb-infrastruktur/na (Öffentlich)...

31
ÖBB-Infrastruktur/NA The Austrian Koralm tunnel - Investigation, Design and Construction Process for a large Base Tunnel Project Gerhard Harer ÖBB – Austrian Federal Railways [email protected]

Upload: phungkhue

Post on 29-Jul-2019

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

The Austrian Koralm tunnel -Investigation, Design andConstruction Process for a largeBase Tunnel Project

Gerhard HarerÖBB – Austrian Federal [email protected]

Page 2: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Project overview

11.05.2012 2

Koralm railway as a part of theBaltic – Adriatic Corridor

Double-track line, electrified 127 km overall length

(at present 228 km overall length)

Max. travel speed 250 km/h Travel time Graz – Klagenfurt 55‘

(at present 2 – 3 h)

Koralmtunnel length 32,9 km At present rd. 63% in operation or under

construction Final operation 2023 Target costs 5.400 mill. EUR

Koralm railway

Page 3: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel alignment

19.10.2012 3

GroßerSpeikkogel

Deutschlandsberg

St. Paul i.L.

St. Georgen

Wolfsberg

St. Andrä i.L.

Page 4: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel - key data

19.10.2012 4

Length of Koralm tunnel: 32,9 km Tunnel system: twin-tube – single-track

tunnel Tunnel i: 7,90 m Max. overburden 1.200 m Start of planning: 1996 Start of geological investigation works: 1998 Construction of investigation tunnels: 2003 -

2010 Start of construction of the Koralm tunnel:

2010

Page 5: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – investigation process

19.10.2012 5

Project phases

Requirements

Strategy

Page 6: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – investigation process

19.10.2012 6

Investigation

Project phase

Desk studies Aerial &satellite data

interpret.

Mapping Drilling Geophysicalsurvey

Feasibility study 1:25.000/1:10.000

Route preselection

1:10.000

Route selection &environmentalimpactassessment

1:5000

Detailed & tenderdesign

1:5.000/1:1.000

Σ 21.000 lfm

Page 7: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – investigation strategy

19.10.2012 7

0,0

2000,0

4000,0

6000,0

8000,0

10000,0

12000,0

< 100m 100-300m 300-500m 500-1200m

62 Stk. 62 Stk. 4 Stk. 5 Stk.

Bohrmeter (gesamt [m])

7

Stepwise investigation campaigns – „from coarse to fine“ Investigations composed of:

– Satellite- and aerial data interpretation– Approx. 300 km² of engineering geological mapping– 133 core drillings, overall length 21.000 rm– Approx. 4.000 springs, wells, creeks under observation– Geophysical surveys from surface and in boreholes– Investigation tunnel system with10 km length in total

Special attention was paid to:– Structured processes– 3-dimensional compilation of the

geological model– Advancement of methods– Diversity of methods– High quality of work– GIS-based data management

Page 8: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)8

Koralmtunnel – integration of investigation data

19.10.2012

Page 9: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – geological conditions

19.10.2012 9

Crystallinebasement

Tertiarysediments

W

32,9 km

Investigation tunnels

Tertiarysediments

E

Page 10: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 19.10.2012 10

KAT1

KAT3

KAT2

Koralm tunnel – geological conditions

Page 11: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Baulos Zeitraum Vortriebsmetergesamt Fortschritt

InvestigationtunnelPaierdorf 2004-2010 5.616 m finished

InvestigationtunnelMitterpichling 2004-2007 2.516 m finished

InvestigationtunnelLeibenfeld 2005-2007 2.226 m finished

KAT1 12/2008-4/2013 4.825 m excavation works finished

KAT2 1/2011-3/2019 39.928 m at present 4.375 m excavated

Ventilation shaftPaierdorf 1/2012-12/2012 under progress

KAT3 11/2013-6/2020 23.397 m tender process

Koralm tunnel – present status of works

19.10.2012 11

Page 12: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 12

Suitable site organization is essential for flexible response, particularly in case ofchanging behavior !

Koralm tunnel – site organization

Owner /Client Contractor

□ Site Management□ Site Supervision

Contract

… on behalf of the client

19.10.2012

Page 13: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 13

Koralm tunnel – site organization

Owner / Client

Contractor□ Site Management□ Site SupervisionDesigner/ Experts

□ Geotechnical Engineer□ Engineering Geological Documentation□ Geotechnical Monitoring

□ Geotechnics□ Geology□ Hydrology□ Structure□ Objects□ …

Tunneling expert

19.10.2012

Page 14: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 14

Koralm tunnel – site organization – regular behavior

Tunneling expert

□ Geotechnical Engineer□ Engineering Geological Documentation□ Geotechnical Monitoring

Owner / Client

Contractor□ Site Management□ Site SupervisionDesigner/ Experts

□ Geotechnics□ Geology□ Hydrology□ Structure□ Objects□ …

Daily evaluation ofgeological & geotechnicalconditions of excavationDaily geotech. report

Information exchange

Decision makingprocess(consensually no dispute!)

Design check

19.10.2012

Page 15: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 11.05.2012 15

Koralm tunnel – investigation tunnels

G. Harer

12.2003 beginning of construction• 2003-2004 Investigation shaft Paierdorf• 2004-2007 Investigation tunnel Mitterpichling• 2005-2010 Investigation tunnel Paierdorf• 2005-2007 Investigation tunnel Leibenfeld

Koralm tunnel – present status of works

Page 16: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 16

Lot KAT1

Koralm tunnel – present status of works

19.10.2012

Page 17: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 19.10.2012 18

Ventilation shaft Paierdorf

G. Harer

Koralm tunnel – present status of works

Page 18: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Controlcenter

Lot KAT2 – site installation

Koralm tunnel – present status of works

19.10.2012

Page 19: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 20

6 months after beginning

Koralm tunnel – present status of works

Lot KAT2 – site installation

19.10.2012

Page 20: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 21

15 months after beginning

Lot KAT2 – site installation

Koralm tunnel – present status of works

19.10.2012

Page 21: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 22

Material managementKAT2

Total excavation8,6 Mio. to

Concrete1,5 Mio. to

Dumping3,0 Mio. to

Removal1,2 Mio. to

(by railway)

Open sections2,9 Mio. to

Koralm tunnel – present status of works

19.10.2012

Page 22: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 24

Segment production KAT2

Ring Width 1,90 m Segmentation 6+0 (+ invert element) Outer diameter 9,5 m Thickness 35 cm

Production Number of segments 103.500 pcs. Number of invert elements 17.250 pcs. Unit weight per ring 47,5 t Unit weight invert element 13,4 t

Koralm tunnel – present status of works

19.10.2012

Page 23: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Cross headingfor logisticsduringconstruction

25

Some impressions KAT2

Koralm tunnel – present status of works

19.10.2012

Page 24: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 26

Some impressions KAT2

Koralm tunnel – present status of works

19.10.2012

Page 25: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 27

Tunnel boring machine

Koralm tunnel – present status of works

19.10.2012

Page 26: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 28

Tunnel boring machine

Koralm tunnel – present status of works

19.10.2012

Page 27: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 29

Tunnel boring machine - installation

Koralm tunnel – present status of works

19.10.2012

Page 28: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

The portion of investigation with respect of the budget of time andcosts for large tunnel projects must not be neglected. Therefore from the very early stages of planning a strategy of a

stepwise investigation has to be executed.

All investigations have to beperformed under high quality standards.

The knowledge obtained by this stepwise investigation procedurehas to be summarised in an expert system, e.g. by means of GIS.

Conclusion – design and investigation

19.10.2012

Page 29: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

The benefits of the performed stepwise investigation strategy anddesign process are clearly evident and enabled us at the Koralmtunnel to reduce risks and save significantly time and money.

Conclusion - design and investigation

19.10.2012

Page 30: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich)

Essential aspects for site organization are: Clear responsibilities of all project members Competent staff on site at all times (contractor and owner)

Efficient decision makingallowing for a flexible response

Conclusion – site organization

19.10.2012

Page 31: The Austrian Koralm tunnel - Investigation, Design and ... · ÖBB-Infrastruktur/NA (Öffentlich) The Austrian Koralm tunnel - Investigation, Design and Construction Process for a

ÖBB-Infrastruktur/NA (Öffentlich) 01.12..201122.11.2011

Muchas gracias por suatención!