koralm tunnel - current status of construction works

22
Koralm tunnel - Current Status of Construction Works Gerhard Harer ÖBB-Infrastruktur AG, Graz - Austria

Upload: buidieu

Post on 04-Jan-2017

227 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Koralm tunnel -Current Status of Construction Works

Gerhard HarerÖBB-Infrastruktur AG, Graz - Austria

Page 2: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Project overview

2

Koralm tunnel -overview of investigation and construction lots

Page 3: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Tertiary sediments

Crystalline basement

Tertiary sediments

WE

32,9 km

Investigation tunnels

KAT1 KAT2 KAT3

Project overview

Koralm tunnel – geological framework

Page 4: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Contract Period Overall tunnel meters Advance

Investigation shaft/ -tunnel Paierdorf 2004-2010 5.616 m completed

Investigation tunnel Mitterpichling 2004-2007 2.516 m completed

Investigation tunnelLeibenfeld 2005-2007 2.226 m completed

KAT1 2008-2013 4.825 m completed

KAT2 2011-2019 39.928 m at present 12,1 km excavated(NATM 4,0 km, TBM 8,1 km)

Ventilation shaft Paierdorf 2012 - completed

KAT3 2013-2019 23.397 m Start of construction 4/11/2013

4

Koralmtunnel -present status of investigation and construction works

Project overview

Page 5: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

5

Lot KAT1

Koralm tunnel – present status of works

Page 6: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Project overview – site installation KAT2

6

Lot KAT2

Concrete & segment plant „North“

Concrete & segment plant „South“

Site offices

Tunnel alignment

Landfill & aggregate processing

Feeder line

Page 7: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

7

RingMedium width 1,90 mSectioning 6+0 (+ invert element)Outer diameter 9,5 mSegment thickness 35 cm

ProductionNo. of segments 103.500 pcs.No. of invert elements 17.250 pcs.Weight per ring 47,5 tWeight invert element 13,4 tAlready produced 32.000 pcs.

Project overview – segmental lining KAT2

Page 8: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

8

2 segment plants

Stock for around 2 x 300 rings4 portal cranes, 50 m span width, 30/60 t load

Project overview – segment plant & storage place KAT2

Page 9: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Project overview – mass management KAT2

9

Total excavationTotal excavation8,6 Mio. to8,6 Mio. to

ConcreteConcrete1,5 Mio. to1,5 Mio. to

DumpingDumping3,0 Mio. to3,0 Mio. to

External recyclingExternal recycling1,2 Mio. to1,2 Mio. to

(removal by rail)(removal by rail)

Open sectionsOpen sections2,9 Mio. to2,9 Mio. to

∼ 60 % of the excavated material will be reused!

Page 10: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Material managementKAT2

Total excavationTotal excavation8,6 Mio. to8,6 Mio. to

Koralm tunnel – present status of works

View from the top of sieve tower

Page 11: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Project overview – rail logistics KAT2

11

1.200.000 t mucking material350.000 t pea gravel950.000 t cement

are handled by rail

Page 12: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Project overview – TBM-DS KAT2 - scheme

12

Page 13: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Project overview – TBM-DS KAT2 – shop assembly

13

Page 14: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Project overview – TBM-DS KAT2 - installation

14

Page 15: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Project overview – KAT2 – progress with TBM

15

Max. daily advance 41 m (with one TBM!)Monthly advance in average ∼ 500 – 700 m (with each TBM!)Max. water inflow 140 l/sAt present 8,1 km excavated with the TBMsWe are exactly in time and budget

Page 16: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Key factors of success for construction

16

Enough time for a stepwise investigation and design processDesign, which considers ground quality and behaviorConstruction contract allowing modifications ofexcavation and support during construction, even more with TBM Appropriate monitoring programSite organization, allowing a flexible response to changing behaviorSafety management planCompetent staff on site & good workmanship

Page 17: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Key factors of success– matrix organization of ÖBB-project management team

17

Matrix project organization: Project responsibility and functional responsibility are networked to each other

TB

ET

AH

BB

OB

STB

Project team

Project responsibilityFu

nctio

nal r

espo

nsib

ility

K. BetriebOverall project responsibility by the project manager

Functional responsibility by the specialists

Continuous combination of project and functional responsibility

Legend:

Application of MATRIX ORGANIZATION within the ÖBB Infra

Page 18: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Key factors of success – we keep schedule and budget stable

18

Overall deviation in budget in average < 1%!

A proper project controlling is essentialClear cost structure is neededRisk management (also during construction) is essential

Page 19: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

Key factors of success: site organization

19

Owner / Client Contractor

□ Site Management□ Site Supervision

Contract

… on behalf of the client

Page 20: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

20

Owner / Client

Contractor□ Site Management□ Site SupervisionDesigner/ Experts

□ Geotechnical Engineer□ Engineering Geological Documentation□ Geotechnical Monitoring

□ Geotechnics□ Geology□ Hydrology□ Structure□ Objects□ …

Tunneling expert

Key factors of success: proper site organization

≅ 5 persons

Page 21: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

... is a successful project!

Koralm tunnel

Because of

… properly performed investigation and design (with sufficient time and budget for it)

… its appropriate site organization and staff

… a client, who is experienced in managing mega projects (targets, strategies, controlling, …)

& … it is important that one does not stop asking!* *) Albert Einstein

Page 22: Koralm tunnel - Current Status of Construction Works

ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013

... is a successful project!

Koralm tunnel

Thank you very much for listening!