The Connectathon Process, Test Plan and

Responsibilities of Participants

The Connectathon Process, Test Plan and

Responsibilities of Participants

Steve MooreMallinckrodt Institute of Radiology

Technical Project Manager: ITI, Rad, PCC

Page 2: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop2

Treatment Planning DisclaimerTreatment Planning Disclaimer

• This talk does not really cover Treatment Planning domain/demonstration

• See separate breakout

Page 3: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop3

Technical ManagersTechnical Managers

Domain Manager

Cardiology Teri Sippel Schmidt

IT Infrastructure Steve Moore

Patient Care Coordination Steve Moore

Radiology Larry Tarbox

Radiation Oncology Bruce Curran

Page 4: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop4

Demonstration ManagerDemonstration Manager

Demonstration Manager

ACC 2006 Teri Sippel Schmidt

HIMSS 2006 John Donnelly

ASTRO 2006 Jennifer Padberg

Page 5: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop5

How Do I Recognize a Project How Do I Recognize a Project Manager?Manager?

Page 6: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop6

Educational WorkshopParticipant Workshop

Connectathon

MESA Tests

DemonstrationProduct

Page 7: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop7

How Do I Participate as a Vendor?How Do I Participate as a Vendor?

• Read/understand Technical Framework(s)

• Register for ACC Demonstration (paper)

• Register for HIMSS Demonstration (paper)

• Register for Connectathon (electronic)

• Pass pre-Connectathon tests

• Pass Connectathon tests

• Attend demonstration(s)

Page 8: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop8

Participant WorkshopParticipant Workshop

• Oct 6-7: Rosemont, IL• Only for Demonstration Participants

– HIMSS/ACC, not ASTRO

• 25% Connectathon/Demo logistics• 75% Work through demonstration scenarios

with partners

• If Connectathon only, do not attend

Page 9: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop9

Participant Workshop RequirementsParticipant Workshop Requirements

• One technical representative for each system in each demonstration– If bringing the same system to ACC and HIMSS, you

need two (2) representatives

• Technical rep needs to understand:– Technical details of Integration Profile

– Details of your application. For example, you should know what kind of documents your system can produce (discharge summary, referral note).

Page 10: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop10

What if Connectathon Only?What if Connectathon Only?

• Do not attend the Participant Workshop

• We will host a Webex conference call to go over Connectathon responsibilities

Page 11: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop11

Pre-Connectathon TestsPre-Connectathon Tests

• Software funded by sponsors

• Software simulates peers in IHE profiles

• Sends IHE transactions to your system; receives transactions from your system

• Evaluates content of your messages

• Required for you to participate

Page 12: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop12

Point of Emphasis for 2005-2006: Point of Emphasis for 2005-2006: MiddlewareMiddleware

• IHE profiles define actors that usually perform a clinical function

• IHE Integration Profiles are designed to describe end products

• Middle-ware is often necessary to adapt existing applications to IHE profiles

• Middle-ware only software will not be tested this year

• Partner with an application vendor

Page 13: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop13

Point of Emphasis for 2005-2006: Point of Emphasis for 2005-2006: Product/Prototype/FlotsamProduct/Prototype/Flotsam

• IHE has always been about products and not possibilities

• Connectathon and demonstrations are intended for products and prototypes that eventually become products

• Systems that are clearly “less than prototype” will not be successfully tested. For example, you’re your user interface to import a CD is 5 separate command line programs, you will not qualify

• Is this something you would show as “beta” to a customer?

Page 14: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop14

What Is or Is Not Acceptable?What Is or Is Not Acceptable?

• JACOBELLIS v. OHIO, 378 U.S. 184 (1964)• Justice Potter• “I shall not today attempt further to define the

kinds of material I understand to be embraced within that shorthand description; and perhaps I could never succeed in intelligibly doing so. But I know it when I see it, and the motion picture involved in this case is not that. “

Page 15: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop15

Connectathon HighlightsConnectathon Highlights

• 5 days of intense work to test with many peers

• Some time will be reserved to prepare for demonstration

• Project Managers will write test definitions; participants will follow the program

• You must be present and available during all scheduled hours

Page 16: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop16

Connectathon Management Web Connectathon Management Web ToolTool

• Developed by IHE-Europe

• Handles many management tasks for pre-Connectathon tests and Connectathon tests

• Use this to register for Connectathon

• Demonstration to follow by Eric Poiseau

Page 17: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop17

Project Manager HandoutsProject Manager Handouts

• IHE U.S. Connectathon and Demonstration Participation Handbook– What you have to do to get through this cycle.

• Connectathon and Demonstration Rulebook– All of the nit-picky rules that we can think of.

Similar to the rulebook you get at your local elementary school.

Page 18: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop18

IHE Knute Rockne SpeechIHE Knute Rockne Speech

• If you don’t allocate sufficient resources today, you will be the worst performer at the Connectathon– You risk failure

• The return on investment for pre-Connectathon and Connectathon testing is that you do not discover these problems in the field

• The Connectathon is a friendlier environment than a customer site, but don’t show up unprepared

Page 19: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop19

Page 20: The Connectathon Process, Test Plan and Responsibilities of Participants Steve Moore Mallinckrodt Institute of Radiology Technical Project Manager: ITI,

June 28-29, 2005 Interoperability Strategy Workshop20

More information….More information….

• IHE Web sites: www.ihe.net• Technical Frameworks, Supplements

– Fill in relevant supplements and frameworks

• Non-Technical Brochures :• Calls for Participation

• IHE Fact Sheet and FAQ

• IHE Integration Profiles: Guidelines for Buyers

• IHE Connect-a-thon Results

• Vendor Products Integration Statements