the design and monitoring of geotextile tube use in ccr...

21
CONFIDENTIAL The Design and Monitoring of Geotextile Tube Use in CCR Impoundment Closure Christopher M. Gee, Dominion Energy Scott Sheridan, Geosyntec Consultants

Upload: others

Post on 18-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

CONFIDENTIAL

The Design and Monitoring of Geotextile Tube Use in CCR Impoundment Closure

Christopher M. Gee, Dominion Energy

Scott Sheridan, Geosyntec Consultants

Page 2: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

22

Chesterfield Power Station

Lower Ash Pond

Page 3: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

3

Layout of the Lower Ash Pond (LAP)

Area 1

Operational Pool

Ash Management Operations

Page 4: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

4

Dominion wanted to start the Intermediate Water Management Plan (IWMP) for the Lower Ash Pond (LAP) while continuing the operate the pond– Initially, Dominion desired to implement the IWMP by December 2018– Chesterfield Power Station needed to continue sluicing CCRs to the Lower Ash

Pond through December 2017 while the station was being converted from wet to dry ash handling

• Design Consideration - One of the VPDES limit for the operating pond was TSS• The IWMP needed to control sediment runoff from the filling of Area 1

Initial Approach – Use of Sheet Piles Walls– Sheet piles required a platform for access, 50 ft– Concern with embedment depths including possible impacts to underlying natural

soils. How could the IWMP target date be met? Geotubes Design Considerations for Using the Geotubes

– Safety during installation– Environmental compliance must be maintained during installation– Stability during and after installation

4

Why the Use of Geotubes was Selected?

Page 5: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

5

Layout of the Lower Ash Pond (LAP)

Area 1

Operational Pool

Ash Management Operations

Page 6: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

6

Field Investigations

SPT (2015)

CPT (2015)

FFP (2016)

Page 7: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

7

Geotechnical Investigation

Coal Combustion

Residuals

Alluvium

Stronger Cretaceous Sediments

Full flow penetrometer ball tip pressure (psf)

CPT cone tip pressure (tsf)

020,000

0100

CPT sleeve friction (tsf)

04

Field SPT N-values (bpf)

040

Page 8: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

8

Sheet Pile Wall Concept

30

Page 9: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

9

Geotextile Tube Wall Concept Construct a geotextile tube wall between Area 1 and pool side Fill geotextile tubes with ash dredged from the operational pool Geotextile tubes will act as a gravity structure to improve stability while

fill is placed on land side Geotextile tubes provide BMP for maintaining compliance with

discharge permit during filling and grading in Area 1.

Page 10: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

10

Polymer Laboratory Testing Bench-scale testing with multiple polymers and multiple dosages Goal: identify polymer that will most improve the dewatering process

Page 11: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

11

Slope Stability Analysis

Page 12: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

12

Stability of Construction of Geotextile Tube Wall Pad

Page 13: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

13

Stability of Construction of Geotextile Tube Wall

CriticalCross

SectionConstruction Condition

CumulativeGeotextile Tube

Filling Height(ft)

CalculatedFS

(min. 1.3)

Target FS

MetTarget

FS?

C First geotextile tube layer, first filling 2 1.30 1.3 Yes

C First geotextile tube layer, second filling 5.5 1.32 1.3 Yes

C Second geotextile tube layer, first filling 8.5 1.30 1.3 Yes

C Second geotextile tube layer, second filling 11 1.31 1.3 Yes

BPlacement of final cover with 5 ft

of stockpile11 1.36 1.3 Yes

BPlacement of final cover with 5 ft of

stockpile – long-term conditions11 1.74 1.5 Yes

Page 14: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

14

Construction of Geotextile Tube Wall

Lesson Learned• Provide additional positive slope, anticipating settlement and construction impacts, for

liner to reduce ponding at tubes while filling.

Page 15: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

15

Construction of Geotextile Tube Wall

Lesson Learned• Provide additional grading behind the geotubes for stormwater control under

varying conditions, keeping in mind the tubes act as a dam.

Page 16: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

16

Construction of Geotextile Tube Wall

Lessons Learned• Polymer dosing can be highly variable during the dredging operations, so a

thorough monitoring plan that provides the ability to adjust dosing is necessary.

Page 17: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

17

Pore Pressure Monitoring

Lessons Learned• Provide adequate space for

piezometer readouts so they are not too close to the geotubes for future monitoring

• Strong communication of monitoring program and expectations.

Design Engineer Input

Design Engineer Input

Page 18: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

1818

Aerial View of Post Construction Condition of Geotextile Tube Wall Construction

Geotextile Tube 2

Geotextile Tube 1

Page 19: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

1919

Post Construction Gradation of Ash in Tubes

Page 20: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

2020

Post Construction %Moisture of Ash in Tubes

Page 21: The Design and Monitoring of Geotextile Tube Use in CCR ...worldofcoalash.org/wp-content/uploads/2018/04/2-acaa-presentation-20… · Geotextile tubes will act as a gravity structure

21

A thorough monitoring plan is needed to track the dosing rate. Stormwater controls should be considered under varying conditions. On this project, pore pressures dissipated quicker than expected. The geotubes provided effective separation between construction and

operations. The structural fill was placed successfully within Area 1 without any

compliance or stability issues. The condition of the ash in the geotubes may or may not vary, depending on

the variable of dosing, runoff control, filling sequence, and time. Geotubes were more cost-effective than sheet pile wall installation.

21

Lessons Learned / Effectiveness