"The importance of effective assessmentwhen indentifying optimal
trenchless rehabilitation solutions.“
By
Mr. Jan Borje PerssonDirector
JBP Consultancy Services Asia Sdn. Bhd.
Ho Chi Minh City
11-12th March
The importance of effective assessment when indentifying optimal trenchless
rehabilitation solutions:
1. JBP Group overview
2. Pipeline Assessment
3. Training and Education
4. Rehabilitation technologies
Presentation Overview
Ho Chi Minh City
11-12th March
JBP Group overview
Reline
Asia
Ho Chi Minh City
11-12th March
JBP Group overview
• Established: 2004
• Business partner to BKP Berolina Polyester GmbH (Germany)
since 2004, international Sales & Marketing
•. Experience: more than 25 years experience with Trenchless Technologies, in International markets
• Focus:
� Product sales and support
�Training and education
�Technical consulting & Project management
� Business Development
JBP Composites S.L.
Reline
Asia
Ho Chi Minh City
11-12th March
JBP Group overview
Reline
Asia
• Established: 2011
• Focus:
� Certified industry training and support (PACP)– WRc approved
� Professional assessment and project management for pipeline rehabilitation
� Product sales and support of UV-Cured CIPP rehabilitation solutions and inspect and assessment equipment.
JBP Consultancy Services Asia Sdn. Bhd. (No: 879241-P)
www.jbp-consultancy.com
2
Ho Chi Minh City
11-12th March
JBP Group overview
Reline
Asia
• Established: 2008
• Focus:
� Pipeline rehabilitation solutions for utilities, municipalities and contractors
� Expert assessment, advice and solutions to meet local needs
� Distribution partner in in the region for the Berolina-Liner System, UV Cured pipeline rehabilitationsystem, produced in Germany by; BKP Berolina Polyester GmbH & Co. KG
BKP Berolina-Liner System (M) Sdn Bhd (No: 834485-K)
Ho Chi Minh City
11-12th March
i. Pipeline assessment
ii. PACP Training
Pipeline Assessment & Training
Ho Chi Minh City
11-12th March
Pipeline Assessment
i. Inspection
ii. Investigation
iii.Condition Assessment
iv.Trenchless technologies Assessment
v. Selection of Rehabilitation Methods
Ho Chi Minh City
11-12th March
REHABILITATION
DECISIONS
CONDITION
ASSESSMENT
INSPECTION/
INVESTIGATIONDIAGNOSTIC TOOLS
Condition Assessment
Pipeline Assessment:
Ho Chi Minh City
11-12th March
Assessment – Why?
• Manages risk through identifying likelihood of failure
• Bridges the gap between:
o Raw data from desk study and field inspection and
o Information that forms the platform for decisions and action
• Transforms data into actionable information
The Condition Assessment Process:
Pipeline Assessment:
Ho Chi Minh City
11-12th March
0 1 2 3 4 5
0
1
2
3
4
5
Consequence of Failure
Lik
elih
oo
d o
f F
ailu
re
DO NOTHING
MONITOR
INVESTIGATE& ASSESS
ACT NOW!
Condition
assessment identifies thisand enables
decisionsto be made
Risk
Assessment
Pipeline Assessment:
www.jbp-consultancy.com
3
Ho Chi Minh City
11-12th March
Assessment – How?• Understand the existing system from records and desk study
• Determine what information and where investigation is needed to fill gaps in the data
• Decide on method of investigation/inspection necessary
• Investigate/Inspect
• Assess the system condition and performance from the total data available after investigation/inspection
• Make rehabilitation decisions to support efficient and effective Asset Management
Pipeline Assessment:
Ho Chi Minh City
11-12th March
Major component of any proactive maintenance or rehabilitation programme. Must
aggressively minimize the likelihood of emergency failures, sewage spills, infiltration, inflows, ex-filtration, etc.
• CCTV
• Sonar
• Ground Penetrating Radar
• Laser – laser scanning can provide a profile of the inner pipe surface
including measurement of crown corrosion due to H2S
Pipeline Assessment Techniques
14
Pipeline Assessment:
Ho Chi Minh City
11-12th March
CCTV
15
Sonar
Pipeline Assessment:
Ho Chi Minh City
11-12th March
Ground Penetrating Radar
16
Pipeline Assessment:
Ho Chi Minh City
11-12th March
Laser Scanning
17
Pipeline Assessment:
Ho Chi Minh City
11-12th March
Man in manhole inspection
18
Pipeline Assessment:
www.jbp-consultancy.com
4
Ho Chi Minh City
11-12th March
Clear knowledge of sewer condition and level of risk which is used to:
•Predict service life at acceptable level of risk
•Determine need and priority for rehabilitation
•Determine feasible and cost-effective options and solutions
•Develop strategies to support active and effective Asset Management
Deliverables from Condition Assessment
Pipeline Assessment:
Ho Chi Minh City
11-12th March
Pipe assessment combined with modern pipeline rehabilitation solutions,
Key factors:
Extensive, and detailed regional knowledge of the networks, conditions and
requirements.
Effective and accurate assessment procedures and reporting
Appropriate selection and application of trenchless technologies which will meet
specific local needs and conditions
Professional training and support, to develop relevant local expertise and skills
Pipeline Assessment & Conclusions:
Ho Chi Minh City
11-12th March
Training & Education
PACP Training
Professional training and support, to develop relevant local
expertise and skills
Ho Chi Minh City
11-12th March
Training
Training & Local Expertise
Ho Chi Minh City
11-12th March
Training
Ho Chi Minh City
11-12th March
Training
www.jbp-consultancy.com
5
Ho Chi Minh City
11-12th March
Strong Enforcement from the Regional Authorities
Certify Technical Personnel - valid certification
� GIS & Sewer-Data Processing
� Pipeline Condition Assessment
� Flow Monitoring & Analysis
� Assessment tools
� Rehabilitation Technologies
� Design and Selection
� Sewer Maintenance
Training
Ho Chi Minh City
11-12th March
Training and Approvals
Generated by CamScanner from intsig.com
Ho Chi Minh City
11-12th March
Rehabilitation Technologies
CIPP-General Overview
UV-Cured CIPP in General
The Berolina-Liner System
Ho Chi Minh City
11-12th March
Sewer rehabilitation – History CIPP
Since its inception in 1971 , Cure In Place Pipes (CIPP) has taken enormous
strides in market development as well materials and technology improvements.
Till to date, more than 100,000 km installed globally since its introduction
UV cured liners now account for an estimated up to 50% of liners installed in
Europe, with similar trends taking place in other markets around the globe
Pipeline rehabilitation – General overview
Ho Chi Minh City
11-12th March
Pipeline rehabilitation – General overview
Sewer rehabilitation needs - Europe
Ho Chi Minh City
11-12th March
Pipeline rehabilitation General overview
CIPP v. Total rehabilitation
– Europe (2010)
www.jbp-consultancy.com
6
Ho Chi Minh City
11-12th March
COMPARISONof
CIPP Trenchless Technology Methods using
UV-LIGHT CURED CIPP and HOT-WATER/STEAM CURED CIPPSystems
forSewer Pipe Installations
Trenchless Technologies – Comparison of Cured in Place Pipe (CIPP) systems
Ho Chi Minh City
11-12th March
Trenchless Technologies – Comparison of Cured in Place Pipe (CIPP) systems
Resources: Water / Raw materials / Waste / Energy…
Control unit for UV-Light Curing
(NO boiler requirement)
Liner winched in place
(NO need scaffolding)
Transportation of the liner
(NO need refrigeration / ice)
UV Light Cured CIPP System (UVC)
Ho Chi Minh City
11-12th March
Trenchless Technologies – Comparison of Cured in Place Pipe (CIPP) systems
Resources: Water / Raw materials / Waste / Energy…
Boiler required for
Hot Water/Steam Cured.
Scaffolding for
inversion of liner.
Refrigeration (Ice) required during
storage and transportation of the liner.
Hot Water / Steam Cured CIPP System (HWSC)
Ho Chi Minh City
11-12th March
A COMPARISON OF CIPP SYSTEMS
Traditional Felt/Resin – Hot Water/Steam CuredReinforced Glass Fibre - UV Cured
Ho Chi Minh City
11-12th March
Cure Characteristic UV Light Curing Hot-Water and Steam Curing
Resin Type ISO NPG Polyester
or Vinyl Ester (VE)
Unsaturated Polyester
& VE-resins
Catalyst UV Initiator Peroxide (Hazard Chemical)
Liner Storage Condition Light Proof at Room Temp. Cool or Iced - avoid Direct Sun
Liner Storage Temperature 5 - 35 ºC 5 - 10 ºC
Storage Life ~ 6 months 1-3 days, for some steam cured versions some weeks
Installation Equipment Mobile or Truck Mounted Boiler Truck + Scaffold Tower
Cure Process Control Monitor time, temperature, pressure, LT speed
and no. of lights Monitor Input/output/and interface pipe temperature
Installation Time 4 - 6 hours 6 - 24 hours
Inspection CCTV during curing process Cannot inspect till cooled, drained and liner ends
removed
Waste Disposal Cured Off cuts + inner foil Off cuts + styrene contaminated cured water
Uniformity of Cure Generally good Increased risk of variability
Shrinkage after Cure Minor Can be significant
Short Term Bending Stress
MPa 150 50
Short Term Flexural
Modulus MPa 9,000 - 12,000 2,200 - 2,800
Long Term Flexural
Modulus MPa 5,500 - 7,000 620 - 1,400
Reference: Paper titled “UV Cured Structural Lining, Overcoming the Challenges”, presented by Borje Persson (BKP-Berolina Polyester GmbH & Co. KG, Germany)
at TRENCHLESS MIDDLE EAST 2010 (Abu Dhabi, UAE) on 15 March, 2010.
Summary Comparison of UV and Heat Cure Characteristics
Ho Chi Minh City
11-12th March
Installation Process
Winched-in-place (WIP):
Pipeline rehabilitation - UV Cured CIPP
www.jbp-consultancy.com
7
Ho Chi Minh City
11-12th March
Camera inspection before curing
Light trolley
Pipeline rehabilitation - UV Cured CIPP
Ho Chi Minh City
11-12th March
UV cured CIPP - practical solutions and advantages
UV-CIPP liner systems & key differences,
- With its extended shelf life up to 6 months, and quality controlled production from its
production plant, high liner quality can be deployed anywhere in the region without
requiring any elements of local production
- Shrinkage during the curing process, minimum annular gap
- Small wall thickness of the cured liners met the objective of enhancing flow capacity
- Cost effective and environmental friendly, low carbon foot print
Pipeline rehabilitation - UV Cured CIPP
Ho Chi Minh City
11-12th March
BKP Berolina Polyester GmbH & Co. KG
Company and PartnersProducts of BKP
Ho Chi Minh City
11-12th March
History:
•BKP’s former production hall was a former airplane hangar. The property was used as an airfield for 50 years
since 1905 and was the departing point for Zeppelins and the “Deutsche Lufthansa” before World War II.
•Founded in 1961 in the former East Germany under the name “Plastverarbeitungswerk Staaken“ the company produced a wide range of GRP and thermoplastic products using various production techniques.
Ownership (since 01.01.1999):
25% Ralf Odenwald 75% Greiffenberger AG
Production data:
Totally produced (since 1997) > 2.050.000 m Berolina-
Liner
Ho Chi Minh City
11-12th March
Surface protectionfor steel pipes
Berolina-Liner SystemDN 150 – 1.200
The Products of BKP
Material for spot repairBRS
Ho Chi Minh City
11-12th March
Products of BKP Berolina Polyester GmbH & Co. KG
The Berolina-Liner System
CIPP (cured in place pipes) has established itself as a compelling and now leading method for trenchless
pipeline rehabilitation. The procedure for liner production from fiberglass reinforced plastics (FRP) developed and patented by BKP is unique worldwide. Our high-quality composites combine high chemical resistance with high strength and extreme longevity. By independent
experts the Berolina-Liner System is certified excellent quality.
www.jbp-consultancy.com
8
Ho Chi Minh City
11-12th March
France
NetherlandsAustriaNorwaySwitzerland
1999
1998
SwedenIrelandPolandDenmark
2000
JapanLiechtensteinLithuania
Australia
BelgiumHungary
2001
2002
SloveniaSouth Africa
2003
Germany
1997
2006
Canada
2008
EstoniaSingaporeLuxemburg
2010
SpainGulf RegionTaiwan
2004
EnglandItalyLatvia
France
NetherlandsAustriaNorwaySwitzerland
1999
Installation partner of the Berolina-Liner System
Malaysia
2005 2007
Mexico
Saudi ArabiaUSA
2009
Finnland
RussiaUkraine
2012
Ho Chi Minh City
11-12th March
Benefits:
pre-impregnation under closely controlled factory
conditions
high structural strength
thin wall - reduces loss of capacity
reduced time for operatives working in confined
spaces
reduced manpower requirements during installation
no requirement for curing water
less energy consumption
no waste product/s from the curing cycle to be
disposed off, i.e. water, etc.
air conditioned transport is NOT needed
Pipeline rehabilitation - UV Cured CIPP
Ho Chi Minh City
11-12th March
Benefits:
quick process - important when working within limited installation time
easy handling- the liners are pre-packed, sealed and
crated after manufacture ready for use
no handling of chemicals at site
simple one step curing regime
very good expansion behaviour
lateral can be easily found and reopened immediately
after curing
liner can be stored up to six month without loss of quality
quality control before dispatch
abrasion surface with high resin content - is not considered for static calculation
Pipeline rehabilitation - UV Cured CIPP
Ho Chi Minh City
11-12th March
Thank You for Your Attention …
JBP Consultancy Services Asia Sdn. Bhd.
Kuala Lumpur, Malaysia
Tel: + 60 (0) 122 082 717
Fax: + 60 (0) 3 2260 1906
Email: [email protected]
Web-Site: www.jbp-consultancy.com
www.jbp-consultancy.com