the integrated distribution management system (idms) · pdf filethe integrated distribution...
TRANSCRIPT
e-terradistribution – August 20091 1
The Integrated Distribution ManagementSystem (IDMS)
e-terradistribution – August 20092 2
What are Utilities looking for in a DMS/OMS
The key applications are the User Interface and theTrouble Call / Outage Management System.
Many utilities develop their own OMS because it is “corebusiness”. It is a major change to move to a “product”.
Priority order is OMS, SCADA, DMS
Reliability
Performance under worst-case conditions
Ability to support the changing regulatory environment
e-terradistribution – August 20093 3
Network AnalysisPower Flow (RT & Study)Limit MonitorFault Location
Network OptimizerFISRFeeder ReconfigurationVoltVar Management
Network OutageUnPlanned/Planned Lifecycle
Trouble Calls/AMICustomer Updates
Crew Monitor/AssignPerformance Indices
Switching OperationsCreate, Simulate,
Execute, Switch Ordersand Safety Docs
Network ViewDynamic Operations Map
Geographic/SchematicPersistence of Dressings
SCADA
“IDMS” Functional Components
e-terradistribution – August 20094 4
IDMS - Typical Business Drivers
Provide SCADA automation to distribution networks Improve operational efficiency through user interface consolidation
(DMS/SCADA/OMS) Improve reliability and safety through better visualization of
distribution network status and use of switching plan tools Improve reliability indices and customer satisfaction through faster
and more predictable outage restoration Reduce peak demand and longer term energy consumption with
coordinated Load and Volt/Var management (green initiatives) An operational platform from which to manage distributed generation Reduce energy losses and network operational costs with
coordinated Load and Volt/Var management Reconfigure control center operations dynamically Reduce penalty payments through faster outage restoration
e-terradistribution – August 20095 5
A suite of applications for distributionutility operational needs - providing acomprehensive real-time networkmanagement solution
A Control Room presentation ofinformation to better comprehend andimprove the state of the distributionsystem – geographic, schematic, tabular,real-time and analytics
Seamless integration of systems(SCADA/DMS/OMS = IDMS) into theControl Room user interface based uponthe e-terrabrowser product
Builds upon, and complements, GIS/AssetManagement, SCADA, AMI, and fieldautomation investments
Provides virtual and dynamic controlcenter configurability
Performance in high activity stormsituations as well as blue sky days
e-terradistribution
e-terradistribution – August 20096 6
e-terradistribution – August 20097 7
The Historic Control Center Environment
7
e-terradistribution – August 20098 8
Outage is confirmedfor all devicesdownstream of
Recloser
e-terradistribution – August 20099 9
The Key Elements
Outage Management
Distribution Management
Switching Operations
Network Optimization
SCADA Integration
Study Tools
Training / Simulation Tools
Model Management
e-terradistribution – August 200910 10
SwitchingOperations
CrewMonitor &Assign
OutageMgmt
Call Center(Call Handling Front End)
IVR
Planned WorkManagement•Maintenance Planning•New Construction•Return to Normal•Seasonal Reconfigure
CIS(Customer Data andElectrical Address)
Asset Data (GIS etc.)
NetworkOperations•Connectivity visualization•SCADA•Network Analysis/Opt•Geographic & Schematic•Outage Extent & Cause•unPlanned & PlannedOutage Lifecycle•Performance Indices•Historical Archive
CIM Adaptor
CIM Adaptor
CIM
Ada
ptor
CIM
Ada
ptorCustomer
Notification
ResourceManagement•Mobile Data System•Crew Callout•Crew Optimization
e-terrabrowser
AMR/AMI(Customer Energization
and Consumption)
e-terradistributionIntegratedDistributionManagementSystem
e-terradistribution – August 200911 11
IDMSApps Server
Typical IDMS Configuration
User IntServer SCADA
User IntServer SCADA
Client PCs running e-terrabrowserMain
Viewport
SCADAPrimary
IDMS/OMSApplicationPrimary
PERMIT ALARM
ALARM
SCADAStandby
IDMSApplicationStandby
IDMSApps Server
e-terradistribution – August 200912 12
e-terradistribution - Key Features and Value Proposition Integrated Distribution Network Management
Transparent integration of DMS, OMS and SCADA activity in one graphical userinterface - increase efficiency and safety and reduce inadvertent outages
Physical realism - based upon dynamic network operations connectivity modelwith detail of all phases - improve situational awareness and field coordination
Asset model updates go on-line transparently without failover, while persistingtemporary changes made online – maintain business continuity across updates
Online Network Analysis Tools for balanced and unbalanced systems – reactiveand proactive operational recommendations to speed outage restoration,maintain operational limits, and reduce demand/losses
Leverage GIS investment for asset model source – avoid redundant modeling
CIM based interfaces to other enterprise applications – facilitate integration
Integration of automated observations like AMI
Performance and Scalability (Storms .vs. “Blue Sky” DMS/OMS) Distribution Network Object Model supports connectivity of >5M customers and
>25M electrical objects
Hurricane level outage performance >1M customers, 200K calls/hr
Supports 1000’s of users with smart clients
e-terradistribution – August 200913 13
Network View
Network Operations User InterfaceGeographic Network Display
Topology Analysis (Loop Detection)
Energization Status
Operator Annotations
Network Tracing
Tagging
Network Operations ModelStatic Data Model (entire network in its normal state)
Dynamic Data Model (switching changes & temporarynetwork modifications)
Supports on-line updates
e-terradistribution – August 200914 14
IDMS User Interface Demonstration
e-terradistribution – August 200915 15
The Southern Company Case for IDMS
e-terradistribution – August 200916 16
The Southern Company
Serve 4.4 Million Retail CustomersGenerating Capacity : 42,000 MW120,000 Square Miles
e-terradistribution – August 200917 17
Alabama Power CompanySite of the first IDMS implementation
APCo serves over 1.4M Customers
10,163 Miles Transmission
76,137 Miles Distribution
44,500 Square Mile Service Territory
Six Geographic Divisions
e-terradistribution – August 200918 18
Present Distribution Operations
Applications integration on-the-fly by operator across multipledisparate User Interfaces and paper
• Distribution SCADA
• Switching Management
• Outage Management
• Crew Call Out System
• Work Force Management
e-terradistribution – August 200919 19
SOCo Operational Environment
Switching
DSCADAOutage Mgt
Separate and Disparate Systems
e-terradistribution – August 200920 20
DOES : Hurricane IVAN - Sept 15-21, 2004
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
Sep
15
2004
9:4
1PM
Sep
16
2004
1:4
2AM
Sep
16
2004
5:4
2AM
Sep
16
2004
9:4
4AM
Sep
16
2004
5:3
0PM
Sep
17
2004
1:3
2AM
Sep
17
2004
9:3
1AM
Sep
17
2004
5:3
1PM
Sep
18
2004
1:2
9AM
Sep
18
2004
9:0
0AM
Sep
18
2004
4:3
9PM
Sep
18
2004
9:5
9PM
Sep
19
2004
3:1
9AM
Sep
19
2004
8:3
9AM
Sep
19
2004
1:5
9PM
Sep
19
2004
7:1
8PM
Sep
20
2004
12:
38A
M
Sep
20
2004
6:1
8AM
Sep
20
2004
11:
39A
M
Sep
20
2004
4:5
8PM
Sep
20
2004
10:
17P
M
Sep
21
2004
3:3
7AM
Sep
21
2004
8:5
8AM
Sep
21
2004
2:1
8PM
Sep
21
2004
7:3
7PM
Date-Time
Customers Outas Percentage
of Company Total
840,000 peak customers out
1,831 feeders affected
e-terradistribution – August 200921 21
Why Change?
Improve distribution operation capabilities toaddress:
System loading, maximize assets utilizingconnected model
Predicting, locating, isolating, and analyzing faultswith or without operator intervention – self healingsystems
Autonomous application systems
Reliability and asset maintenance – ConditionBased
Demand Management – system losses and demandreduction programs
Distributed generation
Operator Training
Enable active customer participation through AMI
RAW DATA
Less ofthis
INFORMATION
More ofthis
e-terradistribution – August 200922 22
IDMS Benefits
IDMS assumption of .5% loss reduction will contribute to a greenerenvironment by less required generation
• Industry accepted recoverable loss estimates range from .5% to4.1% of the distribution kWh sold at a typical utility
A 33% reduction in outage duration would be the largestincremental gain of any system reliability project
• Utilizing FISR within the IDMS system will reduce SAIDI to ourcustomers
e-terradistribution – August 200923 23
IDMS Benefits (cont.)
Integrated Single User Environment• An integrated view of the power system increases
operation efficiency Power flow analysis
• Real time information leads to improved asset utilization Fault location
• Saves time and expense of crews searching for faultswhen they occur / less customer outage time
Power quality• Identify harmonic problems
Maximized return on SCADA and GIS investment withautomatic interface and transparent database changemanagement to on-line distribution network model
e-terradistribution – August 200924 24
Future Distribution Operations
• To achieve a seamless integration of operating applications – combining OMS,SCADA, Distribution Analysis applications, and integration with AMI into asingle user interface to improve operator Situational Awareness (efficiency,accuracy, safety gains)
• Utilizes GIS as the major source of electrical asset data and applies real-timedynamics for a connected and “intelligent” model
• GIS topology and attribution facilitates the use of advanced network analysisapplications to enhance operational decisions
• Improve distribution system electrical efficiency and expand demandmanagement programs
• Distribution Operator Training Simulator with Storm mode
Integrated Distribution Management System (IDMS) Project
SCOPE of IDMS PROJECT
e-terradistribution – August 200925 25
IDMS Facilitates Smart Grid Operations
Advanced IDMS Applications enabled by the integration of static asset data,real-time observations, historical data, and manual dressings
• Unbalanced power flow analysis for real-time Operations and study modeswitching planning
• AFISR (Automatic Fault Isolation and Service Restoration)• De-centralized• Centralized
• Pro-Active as well as reactive mode Feeder Reconfiguration• Fault detection and location• Volt/Var Control for demand management and minimizing distribution losses• Integrated system coordination and protection analysis• Distribution Contingency analysis• Switching Management• Advanced Crew Management• Dynamic Deration of Power Equipment (Harmonic loading)
e-terradistribution – August 200926 26
e-terradistribution – August 200927 27
IDMS Facilitates Smart Grid Operations
DOE and EPRI Support
IDMS project being co-funded by US Department of Energy’sGridWise Program and the Electric Power Research Institute(EPRI)
Demonstration project completed in June 2008
Complete Implementation at Alabama Power Company in2010
e-terradistribution – August 200928 28
IDMS Advanced Functions
e-terradistribution – August 200929 29
Switching Operations
Creation, Validation and Execution of Switching Orders.
A detailed set of instructions used to plan and coordinateswitching actions that are performed on the network.
Creation and Management of Safety Documents.
The formal documents that transfer jurisdiction of a definedsection of the network between operations staff andmaintenance staff.
e-terradistribution – August 200930 30
Advanced DMS Function Values Cross functional geographic displays provide a physical map
alternative for visualization of the distribution network More intuitive assimilation of outage information (customer call patterns
and outage island extents) More intuitive viewing of crew locations and subsequent crew
dispatching as well as navigation Improvement of system reliability and reduced outage times through
automatically generated restoration switching plans with the optionof closed loop execution through SCADA.
Real-time and planning power flow calculation for preciseintervention. Power flow calculation takes into account physicalequipment, cables, switches, transformer and metered data on thecircuit. Can detect if a circuit is overloaded or if there is an excessivepower consumption compared to the expected load.
Optimization calculations take into account short term load trendsobserved in real-time and cold load pickup models to provide moreuseful switching recommendations.
Advanced tools for optimal switching result in estimated 33%reduction in restoration times for complicated outages as well asfewer mistakes in heavily loaded situations (ALABAMA POWER aSouthern Company).
VoltVar Management can achieve 1.5 – 4% demand reduction inenergy conservation mode
e-terradistribution – August 200931 31
Network Analysis and OptimizationFunctional Groups
Distribution Power Flow and derivatives Real-time state estimation and study modes
Detailed Dynamic Models – phase domain
Limit monitoring and exception/Alarm reporting
Distribution System Optimizer Switching Reconfiguration – fault isolation and restoration
as well as optimization of circuits
Load & Volt/Var Management – loss minimization anddemand management
Closed-loop and advisory modes
e-terradistribution – August 200932 32
Distribution Management System (DMS)Network Analysis Functions
Power Flow Analysis
Load Allocation – real-time modelling of loads
Limit Monitor - overloads
Power Quality – Voltage Violations
Short Circuit Analysis for Protection Validation
Loss Analysis
Load Model&Forecast
Fault Location – uses Smart Relays and Fault Indicators
e-terradistribution – August 200933 33
Network Optimizer - Automatic FeederReconfiguration
A means of developing optimal switching plans for thedistribution network to achieve the desired outcome
Can be used to reduce demand through intelligent loadshed – a component of Demand Management
Can be used to address reliability issues on network byrelocating as many customers as possible frominherently unreliable line sections
Primarily works by shifting open points on feeders
Run in real-time in response to overload events and as astudy mode operation
Can be used to generate return-to-normal plans afternetwork has been large disturbances
e-terradistribution – August 200934 34
Network Optimizer - Fault Isolation andService Restoration (FISR)
Analyze faults based upon input from real-time SCADA (FaultDetectors and Fault Currents) and crew reports.
Generate recommended switching for isolation of a nominatedfault and restoration of unaffected customers
Isolate the fault based upon current state of distribution network
Propose multiple restoration plans based upon network status,topology, equipment limits and desired objectives
Alabama Power expects FISR could speed up restoration activityby up to 25% when entire feeders have to be analyzed
Configure switches to serve the load with: minimal switching operations
maximization of margins and/or reliability
minimization of losses and/or voltage drop
Study mode simulates contingencies and summarizes non-restorable switchable line sections.
e-terradistribution – August 200935 35
Network Optimizer - Load & Volt/Var Management
Automation of voltage and Var control can achievethe following objectives and cost justifications: Reduce losses by minimizing the transport of reactive power Maximize existing distribution capacity and defer capital outlay Reduce distribution transformer excitation losses Actively manage voltage dependent loads to:
Shave peak system loads Implement energy conservation – a component of Demand
Management Improve economics during light load periods
Enhance transmission grid reliability: Minimize reactive power impacts from the distribution network Provide reactive power support when needed for voltage stability Reduce demand during peak load conditions
Better maintain distribution circuit voltage profiles to meetcustomer quality limits
e-terradistribution – August 200936 36
Smart Grid Energy Conservation Mode ofDemand Management with VVC (Substation KW by hour)
VVO - Minimize Demand
30000.00
35000.00
40000.00
45000.00
50000.00
55000.00
60000.00
65000.00
70000.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (Hours)
Tota
l Dem
and
(kW
)
OrignalVVOLocal
e-terradistribution – August 200937 37
Advanced Function Demonstrations
Power Flow
Fault Location
Fault Isolation and Service Restoration (FISR)
Volt/Var Control
e-terradistribution – August 200938 38
Distribution Network Managementof the Future
Further demand for distribution networksituational awareness and improved performanceindices
Visualization of automation!
More severe penalties for reliability transgressions
More physical network reconfiguration capability
Dynamic model always showing current state ofnetwork
Progression towards AMI becoming the primarytool for observation and a key component ofsupervisory control of the distribution networkincluding the consumer premises -> real-timestate observation and demand response enabler
e-terradistribution – August 200939 39
Distribution Network Managementof the Future
Complementary interaction with, and supervisorycontrol of, field deployed automation (automatedfeeder/substation reconfiguration schemes likeIntelliTeam)
closed loop reconfiguration – this is a key part of the“self-healing” bit in SmartGrid
implies providing broader, and dynamic, networkconnectivity knowledge to fast field deployedautomation schemes
Further requirements for automated lossminimization, reliability, and demand managementmeans increased control at the distribution level
e-terradistribution – August 200940 40
Distribution Network Managementof the Future
Utility interface to Distributed Generation (monitorand control)
Precise fault location determination to speeddispatch/repair
Predictive and pro-active reconfiguration plans
Analytical predictions of network tampering/powertheft
e-terradistribution – August 200941 41
Outage Management System
Unplanned / Planned Outage Management – tracking andcoordination of outages, recording of statistics.
Trouble Call Management (Customer Calls, AutomatedMeter observations, SCADA information), Prediction ofinterruption device.
Crew Monitor /Assign
e-terradistribution – August 200942 42
Faults on Distribution Network
e-terradistribution – August 200943 43
OMS “Geobular” Incident Summary
e-terradistribution – August 200944 44
CalledCustomer
Lateral-predicted out
Transformer-predicted out
Fuse-predictedinterruption
device
OutageIndicator
(CrewAssigned)
Crew Location
e-terradistribution – August 200945 45
e-terradistribution – August 200946 46
Distribution Operations Training Simulator
Overview
Demonstration of Storm Scenarios and OutageManagement Functionality
e-terradistribution – August 200947 47
Overview
Provide a controlled environment for training operatorsprior to the real-world events
Train new employees in existing procedures Develop and test new operational procedures Identical User Interface and Applications as on-line
environment Create and store event scenarios from individual faults to
entire storm systems
e-terradistribution – August 200948 48
Network ViewControl Room Operations User Interface
Network Operations ModelNetwork Switching Operations
Network AnalysisPower Flow
Load Allocation
Network OptimizerFault Isolation and
Service Restoration
DistributionSCADA
DistributionSimulator
Network Operations Model,Event simulation,
Call/AMI simulation,Crew simulation
Asset Model•Static model CIM exports•Sub-trans & distribution•150,000 buses
•400,000 customers
DOTS Functional Architecture
e-terradistribution – August 200949 49
Pre-Fault View of Overhead Circuits
e-terradistribution – August 200950 50
Multiple Fault Scenario Created in the Simulator Instance
e-terradistribution – August 200951 51
OMS “Geobular” Thematic Map and Tabular Incident Summary
e-terradistribution – August 200952 52
Post-Fault Visualization with Calls and AMI Exceptions
e-terradistribution – August 200953 53
Crews Dispatched and Faults Located
e-terradistribution – August 200954 54
Repairs Made and Circuits Re-energized
e-terradistribution – August 200955 55
Visualization of AMI Power Restoration Messages
e-terradistribution – August 200956 56
Demonstration of Storm Scenarios and Outage ManagementFunctionality
e-terradistribution – August 200957 57
Functional Integration of Systems
IDMS (SCADA, DMS, OMS)
EMS
AMI
Work Force Management
Locally Controlled Field Automation
e-terradistribution – August 200958 58
SwitchingOperations
CrewMonitor &Assign
OutageMgmt
Call Center(Call Handling Front End)
IVR
Planned WorkManagement•Maintenance Planning•New Construction•Return to Normal•Seasonal Reconfigure
CIS(Customer Data andElectrical Address)
Asset Data (GIS etc.)
NetworkOperations•Connectivity visualization•SCADA•Network Analysis/Opt•Geographic & Schematic•Outage Extent & Cause•unPlanned & PlannedOutage Lifecycle•Performance Indices•Historical Archive
CIM Adaptor
CIM Adaptor
CIM
Ada
ptor
CIM
Ada
ptorCustomer
Notification
ResourceManagement•Mobile Data System•Crew Callout•Crew Optimization
e-terrabrowser
AMR/AMI(Customer Energization
and Consumption)
e-terradistributionIntegratedDistributionManagementSystem
e-terradistribution – August 200959 59
e-terradistribution – integration with the EMS
Integrates seamlessly with, and leverages, the AREVA NMSproducts (e-terrascada, e-terraplatform)
Uses e-terrabrowser (WebFG) viewer to provide consistencybetween applications in the e-terra product range
EMS State Estimator results are incorporated into the real-timedistribution network analysis function, in particular to providephase angle separation analysis for switching plans.
Fully integrated system (IDMS + EMS) Increased operational awareness across the boundaries of the
transmission and distribution electrical networks improvesswitching safety as well as efficiency and effectiveness of activities(manual switching status changes and tagging are entered just onceand used globally across the system)
Consolidation means reduction in network management systemmaintenance work (modeling, hardware, OS patching, user &permissions administration…)
Consolidation means reduction in manual error-prone datasynchronization activities by online users
e-terradistribution – August 200960 60
IDMS Interfaces to AMI -Added Value Smart Grid Functionality
Outage Management with AMI
Network Analysis with AMI
Demand Management with AMI
Meter Management with IDMS
e-terradistribution – August 200961 61
Smart Grid Benefits of AMI Integrationfor Outage Management
Unsolicited Automated Energization Messages from SmartMeters (reduce SAIDI and CAIDI) Power Off messages – Last Gasp
Power On messages
Know the extent of an outage before customers call
Verification and Tracking of Restoration Activity (reduceSAIDI and CAIDI) Selective interrogation of Smart Meters to know extent of
outages
Selective interrogation of Smart Meters to verify completeness ofrestoration activity
Avoid crew deployment for false internal premise issues(reduce OpEx)
Opportunity to detect customer connection model errors
e-terradistribution – August 200962 62
Smart Meter Responses to Feeder-wide Ping
e-terradistribution – August 200963 63
AMI Visualization in OMS to Improve Restoration andPerformance Indices
e-terradistribution – August 200964 64
Smart Grid Benefits of AMI Integrationfor Distribution Network Analysis
Improved detail and timeliness of customer load profiles Automated and regular adaptation of stored load profiles based upon
AMI interval readings rather than single monthly billing data values Real-time and short-term planning operations
Recent premise load information will enhance the accuracy ofdistributing SCADA monitored circuit flow measurements in the real-time distribution power flow
As the ability to retrieve data from AMI eventually approaches real-time, it will provide the opportunity to include load measurementsdirectly into the real-time distribution load flow. The loadmeasurements may represent the consolidation of multiplecustomers
As the ability to retrieve data from AMI eventually approaches real-time, it will provide the opportunity to validate and improve modelingof load-voltage response and cold load pickup characteristics
Longer term planning Continuously adapted load models based upon AMI readings will
provide an enhanced basis for planning longer term switchingactivities
e-terradistribution – August 200965 65
Demand Management Levels of Control
Individual customer control through AMI Entire customer load disconnect/reconnect
Selective load management within the customer premise
Smart Meter interaction with home area networks
Manipulate feeder voltage profile to impact voltage sensitive loads throughSCADA Feeder and substation capacitors
Transformer and regulator taps
Conventional load shedding of entire feeders or primary substations throughSCADA
e-terradistribution – August 200966 66
Integrated Meter Management System
Network View presents geographic and tabular visualization of AMIstatus
Data model populated from GIS and other enterprise systems via IECCIM based interfaces Meter/customer model exists independent from any electrical distribution
equipment model, but is linked through “connection points” to maximizemetering asset use
Situational awareness of AMI exceptions and alarms AMI maintenance crew assignments, locations, and annotations
e-terradistribution – August 200967 67
e-terradistribution – August 200968 68
Work Force Management
View current Crew locations in the network operations view viaAVL
Assign Crews to incidents and coordinate with WFM system Receive updated ETRs and other status information from WFM
and make available to customers Receive and annotate follow-up work requests from WFM
e-terradistribution – August 200969 69
Functional Integration with Locally Controlled Field Automation
An IDMS will provide Visualization of automation!
Complementary interaction with, and supervisory control of, field deployedautomation (automated feeder/substation reconfiguration schemes likeIntelliTeam)
closed loop reconfiguration – this is a key part of the “self-healing” aspect ofSmartGrid
implies providing broader, and dynamic, network connectivity knowledge to fastfield deployed automation schemes
e-terradistribution – August 200970 70
Distribution Model Management
e-terradistribution – August 200971 71
Customers 4.52MGeneration Capacity 19.05GWMaximum Demand 22.4GWTransmission lines 64,000 miles
Distribution Zone Substations 550Distribution Feeders 3,850Circuit Segments 1,500,000Distribution Transformers 1,000,000Distribution Loads 4,000,000Managed Feeder Capacitors >6,000
User Interface Positions 500Current Analogs/Points >150K of 400K
SCALABILITY - Florida Power & LightCompany
The DMS system is deployed and operational throughout FPL.Control centers have been consolidated. Operator training isongoing for network optimization functions (FISR & VVC).
e-terradistribution – August 200972 72
Large Network Model Challenges
The Distribution Network Model ProblemsExtremely large models compared to the typical
transmission system – 25 million objects in theFPL case.
Visualization of the Network Data Model – it is notreasonable to build/maintain displays specificallyfor DMS – leverage the GIS
The model changes everyday – updates must besupported which do not impact users, no restartsor failovers
There are several data sources from which theonline network model database is created
e-terradistribution – August 200973 73
GIS and Network View
e-terradistribution – August 200974 74
CIM Data(Distribution Network
Model in XML fileFormat. One file per
Station)
Network OperationsModel
(Data structure optimized forfunctionality and performance)
Asset ManagementDatabase (GIS)
(Model exported asCIM Data Files)
CONVERTER(Converts data
Files to NetworkOperations Model)
CONVERTER(Converts data
Files to NetworkOperations Model)
Substation Editor(Model exportedas CIM Data Files)
CIM Data(SubstationInternals ModelIn XML Format, OneFile per Station)
UserInterfaceClient
UserInterfaceClient
Global dataDMS_Defaultsdata
BinaryStation MODFileStation_internals.xml
Station.xml
Station.mod
Station.mod
Model ManagementEnvironment for e-terradistribution 2.5x
(and until e-terrasource supports station.mod files)
Station.mod
Review with StudyEnvironment
Real-TimeDMS
Server
Classic SCADA System Data(e-terrascada data models created with e-terramodeler, “FG Modeling displays”,Graphical Modeler, customer developed tools, or e-terrasource)
e-terradistribution – August 200975 75
CIM Data in XML format
e-terradistribution – August 200976 76
Model Management Process
DMCGIS
StationEquipmt
Files
Validation ?
Failed
»Object change»Connectivity Change»Multi-station unit ofwork
»Simple Attributechanges:
RNMSModel
OperationalReview usingStudy mode of
NMS
Corrections
Change Triggered Extracts (90sec)
30sec
FieldCrews
DOC