the london court of international arbitration · team alias - gaja the london court of...
TRANSCRIPT
Team Alias - GAJA
THE LONDON COURT OF INTERNATIONAL ARBITRATION
UNDER THE LCIA RULES
LCIA ARBITRATION NO. 00/2014
VASIUKI LLC … CLAIMANT
V.
REPUBLIC OF BARANCASIA … RESPONDENT
MEMORIAL ON BEHALF OF THE RESPONDENT
Table of Contents
-MEMORIAL FOR THE RESPONDENT- ii
TABLE OF CONTENTS
LIST OF AUTHORITIES…………………………………………………………………...v
LIST OF ABBREVIATIONS…………………………………………………………….....xi
STATEMENT OF FACTS…………………………………………………………………..1
SUMMARY OF ARGUMENTS…………………………………………………………….3
ARGUMENTS ADVANCED………………………………………………………………..4
JURISDICTION
I. ACCESSION OF THE CONTRACTING PARTIES TO THE EU TERMINATES THE BC BIT...4
A. The BIT stands terminated under Article 59(1)(a) of the VCLT…………………4
i) The two Treaties cover the same ‘investments’……………...................................5
ii) The two Treaties serve identical purposes…………………………………………5
iii) The two Treaties have the same ‘standards of protection’………………………...6
iv) Both the Treaties provide for the same system of remedies……………………….6
B. The BC BIT stands terminated under Article 59(1)(b) of the VCLT……………..7
i) Material provisions of the two Treaties are in conflict…………………………….7
ii) The dispute resolution mechanisms of the two Treaties are incompatible………...8
C. The BC BIT has been superseded by the TFEU in accordance with Article
59(2)…………………………………………………………………………………...9
i) The BC BIT has been terminated by the actions of the Respondent………………9
ii) The European Commission considers Intra-EU BITs to be incompatible with the
TFEU………………………………………………………………………………9
D. The procedure to be followed under Article 65 has been complied with………..10
i) Procedure as required by Article 65 was followed……………………………….10
ii) Procedure as required by customary international law was complied with……...10
II. THE CLAIMANT HAS WAIVED ITS RIGHT TO RAISE AN OBJECTION TO THE
TERMINATION OF THE BC BIT………………………………………………………..11
A. The Claimant did not object to the termination of the BC BIT…….……………11
B. The Claimant has not approached domestic judicial forums of the
Respondent…………………………………………………………………………..12
III. IN THE ALTERNATIVE, THE ECJ HAS THE EXCLUSIVE JURISDICTION TO DECIDE UPON
THE CLAIMS SUBMITTED BY THE CLAIMANT………………………………………….12
A. Requirement of incompatibility of individual provisions………….......................12
Table of Contents
-MEMORIAL FOR THE RESPONDENT- iii
B. Similarity of dispute resolution mechanisms of both Treaties…………………...12
ADMISSIBILITY
IV. THE CLAIMANT’S CLAIMS ARE NOT ADMISSIBLE UNDER THE BC BIT……………..13
A. The Claimant’s photovoltaic plants / projects are not covered under the ambit of
the BC BIT…………………………………………………………………………..13
B. The Claimant’s photovoltaic projects are not protected investments under the
BC BIT………………………………………………………………………………14
MERITS
V. THE RESPONDENT DID NOT BREACH ITS OBLIGATIONS UNDER THE BC BIT,
INCLUDING THE FAIR AND EQUITABLE TREATMENT STANDARD...…………………...15
A. The Respondent’s legislative actions did not frustrate the Claimant’s legitimate
expectations...………………………………………………………………………..15
i) The Claimant’s expectations were not legitimate...……………………………….16
ii) The said expectation did not induce the Claimant’s investment...…………..........18
iii) No specific warranties were made and later repudiated……………………..........18
B. The Respondent’s actions did not violate its transparency obligation…………..19
C. The Respondent’s legislative actions were not arbitrary………………………...20
D. There was no breach due to the refusal of grant of license to Project Alfa……..20
VI. ALTERNATIVELY, THE RESPONDENT’S ACTIONS ARE EXEMPTED ON THE BASIS OF
THE EXCEPTION UNDER ARTICLE 11 OF THE BC BIT………………………………...21
A. Article 11 of the BC BIT is a self-judging provision and is applicable to the
current dispute…………………………………………………………………........21
i) Article 11 of the BC BIT is substantially different from Article 25 of the ILC
Articles…………………………………………………………………………….21
ii) Article 11 has a simple purpose requirement for it to be applicable……………...22
iii) A severe economic crisis constitutes a security interest of the State………...........22
B. Alternatively, Article XX of the GATT is applicable to the present case……….23
i) Reference to the GATT is appropriate……….......................................................23
ii) Interpretation of the term “necessary”………........................................................23
REMEDIES
VII. ALTERNATIVELY, THE RESPONDENT CAN NEITHER BE ORDERED TO RESCIND
THE 2013 AMENDMENT NOR TO PAY THE PRE-2013 AMENDMENT TARIFF…………..25
A. An order of specific performance will be in violation of Respondent’s
sovereignty…………………………………………………………………………..25
Table of Contents
-MEMORIAL FOR THE RESPONDENT- iv
B. Alternatively, an order of specific performance will cast a disproportionate
burden on the Respondent………………………………………………………….25
VIII. THE CLAIMANT’S BASIS FOR CLAIMING AND QUANTIFYING THE
COMPENSATION IS NOT APPROPRIATE………………………………………………...26
A. The Claimant is not entitled to compensation for its loss of profits……………..26
i) There is no established record of profitability………………………………..26
ii) Future profits cannot be calculated without past performance record……….27
B. The Claimant’s basis for claiming and quantifying the compensation is
inappropriate………………………………………………………………………..27
i) The Claimant is not entitled to compensation for Project Alfa………………28
ii) The WACC is the incorrect rate for discounting the Claimant’s cash flows...28
iii) The Claimant cannot claim compensation for ‘wasted investment in land’…29
iv) The Claimant is not entitled to compensation for future investment in
expansion of its projects……………………………………………………...30
PRAYER FOR RELIEF……………………………………………………………………31
List of Authorities
-MEMORIAL FOR THE RESPONDENT- v
LIST OF AUTHORITIES
ABBREVIATION FULL CITATION
BOOKS
Dorsett/Godden
Shaunnagh Dorsett and Lee Godden,
A Guide to Overseas Precedents of Relevance to Native Title
(1998)
Douglas
Zachary Douglas,
The International Law of Investment Claims (2012)
Marboe
Irmgard Marboe
Calculation of Compensation and Damages in International
Investment Law (2009)
Metcalf/Papageorgiou
Katrin Nyman Metcalf and Ioannis Papageorgiou,
Regional Integration and Courts of Justice (2005)
JOURNALS
Schreuer
Christoph Schreuer,
Fair and Equitable Treatment in Arbitral Practice
6 J. World Investment & Trade 357 (2005)
Tellez
Felipe Mutis Téllez,
Conditions and Criteria For The Protection of Legitimate
Expectations Under International Investment Law,
27 ICSID Rev. 432 (2012)
MISCELLANEOUS
EU Commission Paper
Commission Staff Working Document Capital Movements and
Investments in the EU Commission,
Service’s Paper on Market Monitoring, Brussels,
3.2.2012 SWD(2012)
STATUTES AND TREATIES
ILC Articles
International Law Commission, Articles on State Responsibility for
Internationally Wrongful Acts (including official Commentary),
Yearbook of the International Law Commission
2001, Vol. II (Part 2)
List of Authorities
-MEMORIAL FOR THE RESPONDENT- vi
TFEU Treaty on the Functioning of the European Union,
2012/C 326/01.
VCLT Vienna Convention on the Law of Treaties,
May 23, 1969, 1155 U.N.T.S. 331
ARBITRAL DECISIONS
Achmea v. Slovak Achmea B.V. v. The Slovak Republic,
UNCITRAL, PCA Case No. 2008-13, (Dec. 7, 2012)
ADC v. Hungary
ADC Affiliate Limited and ADC & ADMC Management Limited v.
The Republic of Hungary,
ICSID Case No. ARB/03/16, (Oct. 2, 2006)
AES v. Hungary
AES Summit Generation Limited & AES-Tisza Erömü Kft v. The
Republic of Hungary,
ICSID Case No. ARB/07/22, (Sep. 23, 2010)
Al-Bahloul Mohammad Ammar Al-Bahloul v. The Republic of Tajikistan,
SCC Case No. V (064/2008), (Jun. 8, 2010)
Amoco v. Iran
Amoco International Finance Corp. v. The Government of the
Islamic Republic of Iran, et al.,
15 Iran-U.S. C.T.R. 189, Partial Award No. 310-56-3, (Jul. 14,
1987)
CME v. Czech CME Czech Republic B.V. v. The Czech Republic,
IIC 62 (2003), (Mar. 14, 2003)
CMS v. Argentina CMS Gas Transmission Co. v. Argentine Republic,
ICSID Case No. ARB/01/8, (May 12, 2005)
CMS v. Argentina
Annulment
CMS Gas Transmission Co. v. Argentine Republic,
ICSID Case No. ARB/01/8, Annulment Proceeding, (Sept. 25,
2007)
Continental v. Argentina Continental Casualty Co. v Argentina Republic,
ICSID Case No ARB/03/9, (Sept. 5, 2008)
Duke Energy
Duke Energy Electroquil Partners & Electroquil S.A. v. Republic of
Ecuador,
ICSID Case No. ARB/04/19, (Aug. 18, 2008)
EDF v. Argentina EDF International S.A., SAUR International S.A. and León
Participaciones Argentinas S.A. v. The Argentine Republic,
List of Authorities
-MEMORIAL FOR THE RESPONDENT- vii
ICSID Case No. ARB/03/23, (Jun. 11, 2012)
EDF v. Romania EDF (Services) Limited v. Romania,
ICSID Case No. ARB/05/13, (Oct. 8, 2009)
Enron v. Argentina Enron Corp. v. Argentine Republic,
ICSID Case No. ARB/01/3, (Aug. 2, 2004)
Eureko v. Slovak Eureko BV v. The Slovak Republic,
UNCITRAL, PCA Case No. 2008-13 (Oct. 26, 2010)
Glamis Gold v. USA Glamis Gold v. United States of America,
UNCITRAL, (Jun. 8, 2009)
Hochtief v. Argentina Hochtief AG v. The Argentine Republic,
ICSID Case No. ARB/07/31, (Oct. 24, 2011)
Lemire v. Ukraine Joesph Charles Lemire v. Ukraine,
ICSID Case No. ARB/06/18, (Mar. 28, 2011)
Levy v. Peru Renée Rose Levy and Gremcitel S.A. v. Republic of Peru,
ICSID Case No. ARB/11/17, (Jan. 9, 2015)
LG&E v. Argentina LG&E Energy Corp. & Ors. v. Argentine Republic,
ICSID Case No. ARB/02/1, (Jul. 25, 2007)
MTD v. Chile MTD Equity Sdn. Bhd. v. Republic of Chile,
ICSID Case No. ARB/01/7, (May 25, 2004)
MCI v. Ecuador
M.C.I. Power Group L.C. and New Turbine, Inc. v.
Republic of Ecuador,
ICSID Case No. ARB/03/6, (Jul. 31, 2007)
Metalclad v. Mexico Metalclad Corp. v. The United Mexican States,
Case No. ARB(AF)/97/1, (Aug. 30, 2000)
Micula v. Romania Ioan Micula & Ors. v. Romania,
ICSID Case No. ARB/05/20, (Dec. 11, 2013)
Occidental Petroleum v.
Ecuador
Occidental Exploration and Production Co. v. Republic of Ecuador,
ICSID Case No. UN 3467, (Jul. 1, 2004)
OKO v. Estonia
Oko Pankki Oyj, VTB Bank (Deutschland) AG
and Sampo Bank Plc v. The Republic of Estonia,
ICSID Case No. ARB/04/6, (Nov. 19, 2007)
Parkerings v. Lithuania Parkerings-Compagniet AS v. Lithuania,
ICSID Case No. ARB/05/8, (Sept. 11, 2007)
List of Authorities
-MEMORIAL FOR THE RESPONDENT- viii
Paushok v. Mongolia
Sergei Paushok, CJSC Golden East Company
and CJSC Vostokneftegaz Company v. The Government of
Mongolia,
UNCITRAL, (Apr. 28, 2011)
PSEG v. Turkey
PSEG Global, Inc., The North American Coal Corporation,
and Konya Ingin Electrik Üretim ve Ticaret Limited
Sirketi v. Republic of Turkey,
ICSID Case No. ARB/02/5, (Jan. 19, 2007)
Romak v. Uzbekistan Romak S.A. (Switzerland) v. The Republic of Uzbekistan,
UNCITRAL, PCA Case No. AA280, (Nov. 26, 2009)
Salini v. Morocco
Salini Costruttori S.p.A. and Italstrade S.p.A. v. Kingdom
of Morocco,
ICSID Case No. ARB/00/4, (Jul. 31, 2001)
Saluka v. Czech Saluka Investments B.V. (The Netherlands) v. The Czech Republic,
Partial Award, UNCITRAL (Mar. 17, 2006)
Sempra v. Argentina
Annulment
Sempra Energy International v. The Argentine Republic,
Decision on the Argentine Republic’s Application for
Annulment of the Award,
ICSID Case No. ARB/02/16, Annulment Proceeding, (Jun. 29,
2010)
Siemens Siemens A.G. v. The Argentine Republic,
ICSID Case No. ARB/02/8, (Feb. 6, 2007)
Societe Generale v.
Dominican Republic
Société Générale In respect of DR Energy Holdings Limited
and Empresa Distribuidora de Electricidad del Este, S.A. v. The
Dominican Republic,
UNCITRAL, LCIA Case No. UN 7927, (Sept. 19, 2008)
Swembalt v. Latvia Swembalt AB, Sweden v. The Republic of Latvia,
UNCITRAL, (Oct. 23, 2000)
Tecmed v. Mexico
Tecnicas Medioambientales Tecmed S.A. v. The United Mexican
States,
Case No. ARB (AF)/00/2, (May 29, 2003)
Thunderbird International Thunderbird Gaming Corporation v. The United
Mexican States,
List of Authorities
-MEMORIAL FOR THE RESPONDENT- ix
IIC 136 (2006), (Jan. 26, 2006)
Total S.A. v. Argentina Total S.A. v. The Argentine Republic,
ICSID Case No ARB/04/1, (Dec. 21, 2010)
Vivendi
Compañía de Aguas del Aconquija S.A. and Vivendi Universal S.A.
v. The Argentine Republic,
ICSID Case No. ARB/97/3, (Aug. 20, 2007)
INTERNATIONAL COURT CASES
Commission v. Austria
Commission of the European Commission v. Republic of
Austria,
Case C-205/06, [2009] ECR I-01301, (Mar. 3, 2009)
Commission v. Ireland Commission of the European Communities v. Ireland,
Case C-459/03, [2006] ECR I-04635, (May 30, 2006)
Commission v. Italian
Republic
Commission of the European Comminities v. Italian Republic,
Case C-174/04, [2005] ECR 1-4933, (Jun. 2, 2005)
Commission v.
Netherlands
Commission of the European Communities v. Kingdom of the
Netherlands,
Case C-542/09, [2006] ECR I-9141, (Sep. 28, 2006)
Commission v. Sweden
Commission of the European Communities v. Kingdom of
Sweden,
Case C-249/06, [2009] ECR I-01335, (Mar. 3, 2009)
Erich v. MISAT Erich Gasser GmbH v. MISAT Srl,
Case C-116/02, [2003] ECR I-14721, (Dec. 9, 2003)
Francovich v. Italian
Republic
Andrea Francovich and Danila Bonifaci and others v. Italian
Republic,
Cases C-6/90 and C-9/90, [1991] ECR I-05357, (Nov. 19, 1991)
WTO PANEL & APPELLATE BODY REPORTS
AB, Brazil–Tyres
Appellate Body Report, Brazil – Measures Affecting Imports of
Retreaded Tyres,
WT/DS332/AB/R, (Dec. 17, 2007)
China–Products
Appellate Body, China – Measures Affecting Trading Rights
and Distribution Services for Certain Publications and
Audiovisual Entertainment Products,
WT/DS363/AB/R, (Jan. 19, 2010)
List of Authorities
-MEMORIAL FOR THE RESPONDENT- x
EC–Asbestos
Appellate Body Report, European Communities – Measures
Affecting Asbestos and Asbestos Containing Products,
WT/DS135/AB/R, (Mar. 12, 2001)
Panel, Brazil–Tyres
Panel Report, Brazil — Measures Affecting Imports of
Retreaded Tyres,
WT/DS332/R, (Jun. 12, 2007)
US–C.O.O.L.
Appellate Body Report, United States – Certain Country of
Origin Labelling (COOL) Requirements,
WT/DS384/AB/R & WT/DS386/AB/R, (Jun. 29, 2012)
US–Gasoline
Appellate Body Report, United States – Standards For
Reformulated And Conventional Gasoline,
WT/DS2/AB/R, (Apr. 29, 1996)
List of Abbreviations
-MEMORIAL FOR THE RESPONDENT- xi
LIST OF ABBREVIATIONS
¶/¶¶ Paragraph(s)
2013 Amendment Amendment of Article 4 of the Law on Renewable Energy
Art. Article(s)
BC BIT Barancasia-Cogitatia Bilateral Investment Treaty
BEA Barancasia Energy Authority
BIT Bilateral Investment Treaty
Claimant Vasiuki LLC
COE Cost of Equity
Contracting Parties Republic of Barancasia and Federal Republic of Cogitatia
DCF Discounted Cash Flow
ECJ European Court of Justice
ECR European Court Reports
ECT European Community Treaty
EU European Union
FDI Foreign Direct Investment
FET Fair and Equitable Treatment
GATT General Agreement on Tariffs and Trade
ICSID International Centre for Settlement of Investment Disputes
ILC International Law Commission
LRE Republic of Barancasia’s Law on Renewable Energy
MFN Most Favoured Nation
NAFTA North American Free Trade Agreement
p./pp. Page Number(s)
PCA Permanent Court of Arbitration
Respondent Republic of Barancasia
TFEU Treaty on the Functioning of the European Union
UNCITRAL United Nations Commission on International Trade Law
VCLT Vienna Convention on Law of Treaties, 1969
WACC Weighted Average Cost of Capital
WTO World Trade Organisation
Statement of Facts
-MEMORIAL FOR THE RESPONDENT- 1
STATEMENT OF FACTS
Parties Involved
1. Vasiuki LLC (“Vasiuki”) is a company incorporated in the Republic of Cogitatia
(“Cogitatia”), and is the Claimant in the present dispute. It is engaged in the development,
construction and operation of renewable energy facilities in Cogitatia and elsewhere in the
region, including the Republic of Barancasia (“Barancasia”), since 2002. Barancasia is
the Respondent in the present dispute.
Barancasia-Cogitatia Bilateral Investment Treaty (“BIT”)
2. In 1998, Barancasia and Cogitatia concluded a BIT, as part of their wide-ranging
economic reforms. They joined the European Union (“EU”) in 2004. Between 1 May 2004
and 15 November 2006, Barancasia examined their Intra-EU BITs and concluded they had
become obsolete. On 15 November 2006, it declared its intention to terminate its Intra-EU
BITs. Accordingly, on 11 December 2006, the Government of Barancasia formally
resolved to terminate all its Intra-EU BITs.
3. In 2007, Barancasia notified Cogitatia of its intention to immediately terminate the BIT;
and the Cogitatatian Foreign Ministry acknowledged the receipt of Barancasia’s
notification. In 2008, Barancasia removed the BIT from the section of its Ministry of
Finance website which lists valid and binding international agreements.
Vasiuki’s Photovoltaic Projects in Barancasia
4. In 2009, Vasiuki went ahead and purchased land plots in Barancasia and decided to launch
an experimental solar project called “Alfa”. By 2010, solar panels of the Project Alfa were
connected to the grid and became operational, but the project was initially operating at a
loss.
Barancasia’s Law on Renewable Energy (“LRE”)
5. In 2010, Barancasia adopted the LRE which fixed general “feed-in tariffs” for renewable
energy providers who receive a license from the national regulator – the Barancasia
Energy Authority (“BEA”). The LRE also guaranteed that the feed-in tariff applicable at
the time of the issuance of a license would apply for twelve years. The BEA publicly
Statement of Facts
-MEMORIAL FOR THE RESPONDENT- 2
announced the fixed feed-in tariff of 0.44 EUR/kWh. Vasiuki applied for a license for the
Project Alfa, as well as Project Beta. But in August 2010, the BEA denied Vasiuki’s
license application for Project Alfa, while simultaneously granting a license for its Project
Beta.
6. By 2011, Project Beta became operational. In the same year, a ground-breaking
technology was developed making solar panels substantially cheaper to manufacture and
dramatically reducing the costs of development. In September 2011, Vasiuki borrowed
substantial sums of money from the United Bank of Cogitatia to acquire several land plots
suitable for the development of photovoltaic power plants. And in April 2012, Vasiuki
applied for licenses for its 12 new photovoltaic power plants. By July 2012, Vasiuki had
obtained licenses from the BEA for the development of all 12 photovoltaic power plants
with an approved 0.44 EUR/kWh feed-in tariff, and it ordered solar panels and started the
construction of photovoltaic power plants based on the new technology.
Amendment to Barancasia’s LRE
7. By 2012, a solar bubble had been created in Barancasia. And in June 2012, teachers
organized national strikes in Barancasia, demanding an increase of salaries and
educational funding Therefore, in January 2013, after prior consultations with the relevant
stakeholders, the Barancasian Parliament adopted an amendment to Article 4 of LRE as
per which the feed-in tariffs could be reviewed annually. The BEA announced the new
fixed feed-in tariffs: 0.15 EUR/kWh, to be applicable retrospectively from 1 January 2013.
Request for Arbitration
8. Aggrieved by the arbitrary amendment in the LRE and subsequent reduction of the feed-
in-tariff, Vasiuki notified Barancasia’s Ministry of Foreign Affairs of its intention to
pursue legal remedies. In November 2014, Vasiuki commenced arbitral proceedings
before the London Court of International Arbitration pursuant to Article 8 of the BIT.
Summary of Arguments
-MEMORIAL FOR THE RESPONDENT- 3
SUMMARY OF ARGUMENTS
JURISDICTION: This Tribunal does not have jurisdiction to decide the claims submitted by the
Claimant because the Barancasia-Cogitatia BIT has been automatically terminated by virtue
of the Contracting Parties accession to the EU. Further, the BIT has been validly terminated
by the Respondent in accordance with the provisions of international law and the BIT itself.
In any case, the ECJ has exclusive jurisdiction to decide cases concerning the interpretation
of EU law, as well as the Claimant, through its conduct, has waived its right to now raise an
objection to the termination of the BIT.
ADMISSIBILITY: The Claimant’s claims concerning its photovoltaic projects in the
Respondent’s territory are not admissible because the photovoltaic projects do not constitute
a valid ‘investment’ under the BIT, and are not protected investments as per the provisions of
the BIT.
MERITS: The Respondent’s actions were not in violation of its obligations under the BIT,
including the FET standard, as the Claimant’s expectations were not legitimate. In any event,
the Respondent’s actions are exempted by virtue of the exception provided in the BIT,
because the severe economic crisis in the Respondent’s territory constituted a security interest
for the Respondent, and the Respondent’s actions are covered by the margin of appreciation
in Article 11 of the BIT.
REMEDIES: Regardless of its findings on the substantive merits of the claims, this Tribunal
cannot order specific performance against the Respondent because any such order of the
Tribunal would violate the sovereignty of the Respondent, and place a disproportionate
burden on it. Furthermore, the Claimant is not entitled to the full compensation claimed by it
because there are fundamental flaws in the Claimant’s expert’s quantification of the
compensation amount.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 4
ARGUMENTS ADVANCED
JURISDICTION AND ADMISSIBILITY
PART I – JURISDICTION OF THE TRIBUNAL
1. The Tribunal is not vested with the jurisdiction to decide upon the merits of the claims
brought before it by the Claimant because: the Barancasia-Cogitatia Bilateral Investment
Treaty1 (“BC BIT”) has become obsolete due to the accession of Barancasia and
Cogitatia (“Contracting Parties”) to the European Union (“EU”) (I); the Claimant has
waived its right to raise an objection to the termination of the BC BIT (II); and in the
alternative, the European Court of Justice (“ECJ”) has the exclusive jurisdiction to decide
upon the claims submitted by the Claimant (III).
I. ACCESSION OF THE CONTRACTING PARTIES TO THE EU TERMINATES THE BC BIT.
2. The BC BIT has become obsolete due to its termination as per Article 59(1)(a) of the
Vienna Convention on the Law of Treaties, 1969 (“VCLT”), as it deals with the same
subject matter as the Treaty on the Functioning of the European Union (“TFEU”) (A); as
well as the fact that it is materially incompatible with the TFEU as per Article 59(1)(b) of
the VCLT (B). The BIT has been superseded by the TFEU in accordance with Article
59(2) of the VCLT as such was the intention of the Contracting Parties (C). Further, the
procedure to be followed under Article 65 of the VCLT has been complied with, as it is a
necessity for Article 59 of the VCLT to be applicable (D).
A. The BIT stands terminated under Article 59(1)(a) of the VCLT.
3. The BC BIT stands terminated due to its becoming obsolete as a result of the accession of
the Contracting Parties to the EU. The subject matter of both the BIT and the TFEU is
similar. Article 59(1)(a) of the VCLT prohibits two treaties with the same ‘subject matter’
and between the same parties from existing simultaneously. When interpreting a treaty it
must be interpreted in the broadest manner as to determine its ambit.2 This rule has been
1 Agreement between the Republic of Barancasia and Federal Republic of Cogitatia for the Promotion and
Reciprocal Protection of Investments, Barancasia-Cogitatia, December 31, 1998. 2 Dorsett/Godden, p. 3.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 5
applied to determine the meaning of the provisions of the TFEU and other Bilateral
Investment Treaties (“BIT”) by the ECJ and numerous other tribunals.3
i) The two Treaties cover the same ‘investments’.
4. This “subject matter” can be determined by a comparison of the two treaties. With respect
to the ‘covered investments’, Article 1(1) of the BC BIT has defined the investments as
“every kind of asset invested in connection with economic activities by an investor of one
Contracting Party in the territory of the other Contracting Party” and lists a set of
examples of possible investments. Under EU law, the protection of investments is
provided under the commercial policy laid down by Article 207 of the TFEU. The TFEU
frames the ‘Common Commercial Policy’4 to be followed by all Member States. There are
other provisions providing for freedom of the internal market,5 such as the freedom of
establishment6 and the free movement of goods,
7 workers,
8 services,
9 et al. Although the
TFEU has not explicitly defined the term “investment”, a subsequent explanatory note by
the EU Council and decisions of the ECJ have determined and upheld the term
“investments” to include the exact similar types of investments as covered under the BC
BIT.
ii) The two Treaties serve identical purposes.
5. The BC BIT and the TFEU intend to serve identical purposes, especially if one is to
compare the Preambles, as well as the principle provisions, of both the BC BIT and the
TFEU. The fundamental purpose of both these treaties is to broaden and strengthen mutual
economic relationships and to promote the flow of capital and economic development of
the Contracting Parties, and at the same time, guarantee fair and equitable treatment. It
must be specifically pointed out that the Preamble of the BC BIT and Articles 2, 3 and 12
of the TFEU are similar and indicate that the two treaties have the same purpose. The BC
BIT constitutes a subset, and its role elapses upon the Contracting Parties accession to the
EU.
3 Metcalf/Papageorgiou, p. 4.
4 TFEU, Art. 207 addresses the common term investment along with the decisions of the ECJ have confirmed
the term investments under the Council Directive is a wide ambit as per Commission v. Italian Republic; Eureko
v. Slovak, ¶67. 5 TFEU, Art. 26.
6 Ibid, Art. 49.
7 Ibid, Art. 57.
8 Ibid, Art. 45.
9 Ibid, Art. 56.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 6
iii) The two Treaties have the same ‘standards of protection’.
6. The ‘standard of protection’ provided by both the Treaties are the same. This may be
determined by the comparison between the Treaties, with respect to the establishment of
investments – Article 2 to Article 4 of the TFEU deal with the same ambit of internal
markets and treaties undertaken by its Member States. Article 4 of the TFEU further
prohibits any restrictions on the free movement of capital and payments. With respect to
equal treatment and non-discrimination, it is important to note the similarities between the
promise in Article 2(2) of the BC BIT and the principles of non-discrimination and
equality of treatment fundamentally protected by EU law through Articles 12 and 49 of the
TFEU and under the Charter on Fundamental Rights of the European Union.10
7. The summary below is further substantiates the similarities between the two Treaties:
BC BIT TFEU
Free Transfer of Capital (Art. 4) Free Movement of Capital (Art. 4)
Fair and Equitable Treatment (Art. 3(1)) Prohibition of Discrimination (Art. 12)
Indirect Expropriation (Art. 5) Freedom of Establishment (Art. 49)
Full Security and Protection (Art. 3(2)) Freedom of Establishment (Art. 49)
iv) Both the Treaties provide for the same system of remedies.
8. Finally, both the BC BIT and the TFEU provide for the same system of remedies where
investments have been impaired as a result of State action. Under the TFEU, investors can
pursue their claims before the respective national courts with the involvement of the ECJ
through a preliminary ruling procedure; and under the BC BIT, the investors can have
their dispute heard before an arbitral tribunal. Both mechanisms aim at the same objective,
namely, the protection of investments. Under both mechanisms, investors may seek
compensation for damages from States for unlawful conduct.11
10
TFEU, Arts. 18 and 49. 11
Francovich v. Italian Republic, ¶22.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 7
B. The BC BIT stands terminated under Article 59(1)(b) of the VCLT.
9. The BC BIT and the TFEU have materially incompatible provisions which cannot be
applied at the same time. The effective exercise of exclusive competence under Article
207 of the TFEU requires regulation of investment in the internal market by the EU, which
leads to a potential conflict with the BC BIT (i). Also, Article 8 of the BC BIT is
incompatible with Article 344 and Article 267 of the TFEU which confer exclusive
competence to the ECJ to rule on matters related partially or wholly to EU law (ii).
i) Material provisions of the two Treaties are in conflict.
10. Independent of a finding that the BC BIT has been terminated by virtue of Article 59(1)(a)
of the VCLT, Article 59(1)(b) has, in any case, already been satisfied; which renders the
BC BIT void because it has become obsolete. This is because the provisions of the TFEU
are so far incompatible with those of the BC BIT that the two Treaties are not capable of
being applied at the same time. Under Article 59(1)(b), a conflict occurs when the
performance of one treaty necessarily causes a breach of the other treaty; in other words,
the obligations arising out of the BC BIT and the TFEU cannot both be fulfilled at the
same time. The provisions on the ‘free movement of payments’ and the ‘protection and
security of investments’ guaranteed under the BC BIT are incompatible with the TFEU
because Article 58 of the TFEU permits exceptions to the free movement of capital
relating to taxation and financial supervision or public policy and security. Thus, a State
may be in breach of the BC BIT while simultaneously being in compliance with the
TFEU.
11. Further, the expropriation clause in Article 5 of the BC BIT is incompatible with the
regulation of expropriation and damages under EU law, which is derived largely from the
European Commission on Human Rights. This is because EU law enables possible
restrictions on proprietary rights “necessary for the general interest” which could cause a
breach of Article 5 of the BC BIT. Article 5 of the BC BIT also breaches Article 10 of the
TFEU which deals with loyal cooperation. The ECJ, in its judgments of 2009 against
Sweden, Austria and Finland,12
held that BITs’ provisions on free transfers related to
investment in a third country (commonly referred to as a "transfer clause") are
incompatible with EU law if they do not allow the application of potential EU measures
12
Commission v. Finland, ¶3.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 8
restricting capital movements. A similar situation would arise if the Claimant claims a
‘transfer clause’ under the BIT rather than the TFEU. Therefore, the Claimant has failed to
address the Extra-EU BIT cases, even though the cases mentioned above precisely define
what the incompatibilities are between EU law and international law instruments.
ii) The dispute resolution mechanisms of the two Treaties are incompatible.
12. The arbitration clause in Article 8 of the BC BIT is also incompatible with the TFEU for
two reasons: the arbitration clause violates the exclusive competence of the ECJ to
interpret EU law (a); and the TFEU does not provide for arbitration proceedings between
investors and Member States thereby leading to a discrimination problem (b).
a. Article 8 violates the exclusive competence of the ECJ to interpret EU law.
13. Arbitral tribunals, unlike national courts, are not entitled to refer preliminary questions of
EU law to the ECJ, under Article 234 of the TFEU. Hence, if an arbitral tribunal were to
resolve questions of EU law in the absence of a referral to the ECJ, this would seriously
jeopardise the uniform application of EU law.13
14. Although it is acknowledged that this Tribunal is obligated to apply EU law, it is
prevented from doing so because it will not be able to ensure the uniform application and
interpretation of EU law, which is the role of the ECJ under Article 220 of the TFEU.
Even if this Tribunal could request a national court to assist, such a national court could
not do so because it would not ultimately decide the present case on its merits. Moreover,
the uniform application of EU law may not be sufficiently safeguarded by the possibility
of annulment or enforcement proceedings in national courts because: (i) such proceedings
are not obligatory; (ii) such remedies are limited by specific prerequisites and not every
misinterpretation of the law results in the annulment of an award or refusal of its
recognition and enforcement; and (iii) if such proceedings are commenced outside the EU,
then the national courts will neither be obliged nor entitled to request a preliminary ruling
from the ECJ.
b. Incompatibility between the two Treaties leads to discrimination.
15. Furthermore, Article 8 of the BC BIT is incompatible with the TFEU because it
fundamentally violates the principle of equality as stipulated in Article 12 of the TFEU.
13
Eureko v. Slovak, ¶114.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 9
Article 12 prohibits discrimination on the grounds of nationality. Investors from Member
States which have not concluded BITs with the Respondent would be discriminated
against as a result of Article 8. Thus, the fact that only certain EU nationals may seek
compensation for damages caused by a breach of EU law before an international arbitral
tribunal is discriminatory and in violation of Article 12 of the TFEU. Since TFEU came
into force after the BC BIT, it supersedes the latter.
C. The BC BIT has been superseded by the TFEU in accordance with Article 59(2).
i) The BC BIT has been terminated by the actions of the Respondent.
16. The Contracting Parties became members of the EU on 1 May 2004. On 15 November
2006, the Respondent announced its intention to terminate all its Intra-EU BITs,14
and
thereon the Respondent terminated all such BITs.15
On 29 June 2007, there was formal
notification16
of the termination of the BC BIT sent by the Respondent to the Republic of
Cogitatia (“Cogitatia”), which became active after one year as per Article 13(2).
Following such one-year period, any subsequent investment by the Claimant was on its
own volition, and not protected by or subject to the provisions of the BC BIT. On 28
November 2008, the BC BIT was removed from the section listing valid and binding
international agreements on the website of the Respondent’s Finance Ministry.17
This is an
indication that the parties had intended to phase out of their existing BITs post accession
to the EU. This intention to let the TFEU supersede the BC BIT satisfies the test of Article
59(2) of the VCLT.
ii) The European Commission considers Intra-EU BITs to be incompatible with the TFEU.
17. The BC BIT was concluded with the objective of regulating the investment legal
framework in a context preceding the Contracting Parties’ accession to the EU, and thus, it
is obsolete in a post-accession economic and legal context. Further, the European
Commission has asserted in a recent decision that the rule of pacta sunt servanda does not
apply to agreements between EU Member states, because of the jurisprudence establishing
that the EU law takes supremacy not only over the national legal systems but also over the
14
Statement of Uncontested Facts, ¶5. 15
Statement of Uncontested Facts, ¶9. 16
Statement of Uncontested Facts, ¶6. 17
Statement of Uncontested Facts, ¶11.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 10
BITs concluded between Member States. This rule applies to pre-accession BITs
concluded between Member States.
18. If there is a conflict between such a pre-accession BIT and the TFEU, then the latter
prevails. The principle of ‘acquis communautaire’ applies as soon as the Member State
signs the EU Accession Treaty.18
The European Commission has further held that BITs
between EU Member States are in conflict with EU law, are incompatible with the EU
single market and, therefore, should be phased out.19
D. The procedure to be followed under Article 65 has been complied with.
19. The BC BIT has been terminated in accordance with the procedure laid down under
Article 65 of the VCLT. Article 65 lays down the procedure for valid termination of treaty
as required by Article 59 of the VCLT.
i) Procedure as required by Article 65 was followed.
20. A written notification was sent by the Respondent to Cogitatia, expressing the intention to
terminate the BC BIT on 29 June 2007.20
The same was acknowledged by Cogitatia on 28
September 2008.21
Subsequent communications were made to confirm the termination of
the BC BIT. Lack of any objection to the notification of termination of the BC BIT within
a reasonable period of time amounts to tacit acquiescence to the termination of the BC BIT
by Cogitatia.
ii) Procedure as required by customary international law was complied with.
21. Though the Claimant may choose to rely on the decision of the Arbitral Tribunal in
Achmea v. Slovak,22
the facts in that case and the facts before this Tribunal can be clearly
distinguished. In the abovementioned case, the Tribunal rejected the contention that
Article 59 of the VCLT made the BIT in question obsolete because the procedure as laid
down in customary international law had not been followed. The Tribunal ruled that there
was a lack of notice of termination, and Article 59 is only applicable when the two treaties
relate to the same subject-matter and there is an incompatibility between the two. All the
above mentioned criteria have been met and satisfied by the facts in the current dispute. In
18
Eureko v. Slovak, ¶180. 19
EU Commission Paper, p. 13. 20
Statement of Uncontested Facts, ¶9. 21
Statement of Uncontested Facts, ¶10. 22
Achmea v. Slovak, ¶234.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 11
the instant case, the notification of termination was provided by the Respondent well in
advance of the final termination of the BC BIT. Moreover, such notification was
accompanied by the rationale behind the decision to terminate, which was in the form of
the legislative decision. Therefore, the BC BIT has been validly terminated by the
Respondent in accordance with the principles established by customary international law.
II. THE CLAIMANT HAS WAIVED ITS RIGHT TO RAISE AN OBJECTION TO THE TERMINATION
OF THE BC BIT.
22. The Claimant has waived its right to object to the termination of the BC BIT due to two
primary reasons: the Claimant did not take any action to object to the termination of the
BC BIT for a period of seven long years (A); and the Claimant has failed to approach the
appropriate domestic judicial forums of the Respondent (B).
A. The Claimant did not object to the termination of the BC BIT.
23. It is a well-established principle of international law that the termination of a treaty or the
withdrawal of a party from a treaty may only take place in conformity with the provisions
of such treaty. In the present case, Article 13(2) of the BC BIT provides for a notification
process to terminate the Treaty. The Respondent notified Cogitatia of its resolution to
terminate the BC BIT in accordance with the provision.23
It must be noted that since 29
June 2007, no action has been taken by Cogitatia in relation to the notification of
termination, except for an acknowledgement of the receipt of said notification. Such non-
action and silence amounts to acquiescence of the termination by Cogitatia. The silence
permitted the Respondent to assume implied acceptance. The acceptance has allowed for
the pre-condition of ten years to be frustrated due to no objection to the notification of
termination of the BIT.24
23
Statement of Uncontested Facts, ¶9. 24
Hochtief v. Argentina, ¶94.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 12
B. The Claimant has not approached domestic judicial forums of the Respondent.
24. Further, the Claimant does not have the right to approach this Tribunal as it has not yet
exhausted the remedies available to it by approaching the domestic judicial forums of the
Respondent State.25
III. IN THE ALTERNATIVE, THE ECJ HAS THE EXCLUSIVE JURISDICTION TO DECIDE UPON
THE CLAIMS SUBMITTED BY THE CLAIMANT.
25. Even if Article 59 of the VCLT does not operate to terminate the BC BIT, the Tribunal
lacks jurisdiction to decide upon this case because the arbitration clause in the BC BIT is
not “compatible” with the TFEU within the meaning of Article 30 of the VCLT, which
provides:
“Successive Treaties Relating to the Same Subject Matter…
3. When all the parties to the earlier treaty are parties also to the later treaty but the
earlier treaty is not terminated or suspended in operation under article 59, the earlier
treaty applies only to the extent that its provisions are compatible with those of the
later treaty”
A. Requirement of incompatibility of individual provisions.
26. Unlike Article 59, Article 30 requires no proof of the parties’ intentions and does not
relate to the incompatibility of the treaties as a whole, but rather to the incompatibility of
individual provisions. In this arbitration, the Claimant asserts that the Respondent
violated Articles 3(1), 3(2), 4 and 5 of the BC BIT, all of which have been supplanted by
EU law. Therefore, the dispute has to be solved under and in accordance with EU law.
However, the Tribunal lacks the competence to apply and interpret EU law. It is a
principle that the jurisdiction should be decided before deciding the merits. In the facts
before an arbitral tribunal, the preliminary objection was whether the jurisdiction lies with
the ECJ.26
Thus, it is asserted that Article 30(3) of the VCLT renders Article 8 of the BC
BIT inapplicable, and the Tribunal lacks jurisdiction to decide the case.
B. Similarity of dispute resolution mechanisms of both Treaties.
27. It has been previously held by the European Commission that when all parties to an
earlier treaty are parties to the later treaty but the earlier treaty has not been terminated or
25
MCI Power v. Ecuador, ¶349. 26
Erich v. MISAT, ¶3.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 13
suspended in operation under Article 59, the earlier treaty applies only to the extent that
its provisions are compatible with those of the later treaty.27
In the case at hand, Article
54 of the TFEU addresses the concerns of a company in the same manner that the BC BIT
addresses the concerns of a ‘legal entity’.28
Hence, there is a similarity of dispute
resolution mechanisms as both Article 263 of the TFEU and Article 8 of the BIT have a
provision for redressal of grievances for unlawful conduct.29
28. Therefore, even if the Tribunal finds that the BC BIT and the TFEU are not materially
incompatible, the Tribunal will lack jurisdiction under Article 30(3) of the VCLT because
the ECJ has exclusive jurisdiction over Intra-EU disputes, as has been enshrined in
Articles 344 and 267 of TFEU.30
PART II – ADMISSIBILITY OF CLAIMS
IV. THE CLAIMANT’S CLAIMS ARE NOT ADMISSIBLE UNDER THE BC BIT.
29. The Claimant’s claims concerning the photovoltaic projects are not admissible in relation
to the dispute under the BC BIT because: the Claimant’s photovoltaic plants / projects are
not covered under the ambit of the BC BIT (A); and they are not protected
investments under the BC BIT (B).
A. The Claimant’s photovoltaic plants / projects are not covered under the ambit of
the BC BIT.
30. The Claimant’s investments in Project Alfa, Project Beta and the 12 photovoltaic projects
were made post the termination of the BC BIT, and therefore, they cannot be accorded the
status of ‘investment’ under the BC BIT. In a similar decision of Romak v. Uzbekistan,31
Uzbekistan had contended before the Tribunal that Romak did not own an ‘investment’ as
required under the BIT since Romak had delivered only one order, which too was post the
27
Commission v. Austria; Commission v. Sweden, ¶29. 28
Law on Renewable Energy (“LRE”), Art. 2(b). 29
Francovich v. Italian Republic, ¶31. 30
Commission v. Ireland, ¶123-126. 31
Romak v. Uzbekistan, ¶182.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 14
signing of another acceding treaty, thus lending that order to be on the Company’s own
volition rather than an investment according to the BIT. The Tribunal had accepted
Uzbekistan’s contention and held that the transaction did not amount to an ‘investment’.
31. Further, to constitute a valid ‘investment’ under a BIT, there must be some development
and benefit accruing to the host nation. In the instant case, there are no plants which are
already operational. Hence, the planned photovoltaic projects do not constitute
‘investments’ as there is no benefit or development in the Respondent’s territory.32
B. The Claimant’s photovoltaic projects are not protected investments under the BC
BIT.
32. As has been previously submitted, the BC BIT was terminated and any transaction post
such termination (in 2007) would have been made on the investor’s own volition and not
protected by the provisions of the BC BIT. A parallel can be drawn between the facts of
the present case and the decision of the Arbitral Tribunal in Societe Generale v.
Dominican Republic,33
wherein it was decided that the treaty was designed to protect only
nationals and the Claimant’s would fail the test to constitute a valid ‘protected
investment’ under the BC BIT, as the BIT has been terminated.
33. Furthermore, the rationale behind the principle of any post-termination investment being
treated at par with an independent investment is that post the termination of the BIT, the
transaction shall be deemed to be unprotected as it suggests the transaction was ‘too late’.
Thus, it is the Claimant’s fault for knowingly taking the risk of investing post termination
of the BC BIT.34
32
Salini v. Morocco, ¶5. 33
Societe Generale v. Dominican Republic, ¶106. 34
Levy v. Peru, ¶145.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 15
MERITS
V. THE RESPONDENT DID NOT BREACH ITS OBLIGATIONS UNDER THE BC BIT, INCLUDING
THE FAIR AND EQUITABLE TREATMENT STANDARD.
34. The Respondent has not breached its obligations under the BC BIT, including the Fair and
Equitable Treatment (“FET”) standard. The FET Standard is autonomous and consists of
various elements.35
These include the need for a State to: act in good faith, act
transparently, act without discrimination, act non-arbitrarily, act within the framework of
due process, provide investors the freedom from coercion and harassment, and protect
legitimate expectations of investors.36
The Respondent has not violated any of the
aforementioned components.
35. The standard of treatment need not be anything in addition to the international minimum
standard.37
The threshold for a breach as under international minimum standards is very
high. A breach can only result from treatment that is “shocking” or “egregious”.38
Even if
the standard of protection is to be considered autonomous, the right of protection of the
investor has to be balanced against the right of the host State to exercise its sovereign
power to regulate in public interest.39
36. The Respondent’s legislative actions did not frustrate Claimant’s legitimate expectations
(A); the Respondent’s legislative actions did not violate its transparency obligations (B);
the Respondent’s legislative actions were not arbitrary (C); and the Respondent did not
breach the FET standard with respect to Project Alfa (D).
A. The Respondent’s legislative actions did not frustrate the Claimant’s legitimate
expectations.
37. The Respondent’s actions have not frustrated Claimant’s legitimate expectations because
the three elements, namely: legitimacy of expectations40
(i); inducement of investment on
35
Schreuer, pp. 374-385. 36
Ibid. 37
MTD v. Chile, ¶110. 38
Glamis Gold v. USA, ¶627. 39
Saluka v. Czech, ¶305; EDF v. Romania, ¶219. 40
Tellez, p. 441.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 16
the basis of such expectations41
(ii); and specific warranties by the host State that were
later repudiated42
(iii); have not been satisfied in the current case.
i) The Claimant’s expectations were not legitimate.
38. The Claimant’s expectations that the laws of the Respondent will remain frozen were not
legitimate. Legitimacy has three key elements viz. reliance on the law, its reasonableness
and its beneficial effect for the investor.43
The expectations of the Claimant do not fulfil
the legitimacy requirement. More specifically, the Claimant’s expectations did not rely on
the law (a), and they were not reasonable (b).
a. Claimant’s expectations did not arise out of reliance on law.
39. The expectations of the Claimant did not arise out of its reliance on law. In the absence of
a stabilisation clause, a nation’s laws are reasonably expected to evolve over time.44
The
licenses to operate the photovoltaic projects were granted in pursuance of the Law on
Renewable Energy (“LRE”).45
Under the LRE, the feed-in tariff was not allowed to
change for a period 12 years from the date of grant of the license.46
40. Article 4 of the LRE is not a stabilisation clause. A stabilisation clause can only be
contained in State contracts with foreign investors which provide that the host State’s legal
framework would be frozen as on a certain date.47
In such a specific situation, any
regulatory changes would be illegal.48
However, in the current scenario, the licenses
themselves did not have any such provision. Therefore, no such warranty was specifically
made to the Claimant by the Respondent.
b. The Claimant’s expectations were not reasonable.
41. The Claimant’s expectations were unreasonable. The Arbitral Tribunal in Duke Energy
held that the assessment of reasonableness should take into account “not only the facts
surrounding the investment, but also the political, socioeconomic, cultural and historical
41
Continental v. Argentina, ¶261. 42
Ibid. 43
Tellez, p. 441. 44
Parkerings v. Lithuania, ¶332. 45
LRE, Art. 5. 46
LRE, Art. 4. 47
Total S.A. v. Argentina, ¶101. 48
Ibid.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 17
conditions prevailing in the host State”.49
Only when investors fulfill their due diligence
duties concerning potential circumstance changes can their expectations be considered
legitimate and reasonable.50
42. In the present dispute, both the political and the socioeconomic conditions which were
prevailing prior to the Claimant’s investment were ignored by it. The failure of the
Claimant to conduct adequate due diligence attenuates the legitimacy of Claimant’s
expectations. In Parkerings v. Lithuania, the Arbitral Tribunal ruled that since Lithuania
was in the middle of a transition from being a part of the Soviet Union to becoming a
member of the EU, legislative changes in its legal regime should have been considered to
be likely.51
The investor in the case should have been aware of the risk of change in the
legal framework in Lithuania, and therefore, the investor’s expectation that the laws
would remain unchanged could not be considered to be legitimate.52
In the instant case,
even though the Respondent was a new EU member, the Claimant went ahead with its
investment. Therefore, it was likely that the feed-in tariff would change along with other
laws, and the Claimant should have been aware of such risk.
43. Further, even the economic circumstances at the time of the Claimant’s investment prove
that stability of the legal environment was not a legitimate expectation. Particularly, in
relation to the Claimant’s twelve subsequent photovoltaic projects, the discovery of the
ground-breaking technology in 2011 prior to said investment made it clear that the feed-in
tariff could have changed.53
Hence, it can be inferred that stability of legal environment
was not the reason behind the Claimant’s investment.
44. Furthermore, under no circumstances can it be held to be reasonable to expect the laws to
not change even during a crisis. In Continental v. Argentina, the Arbitral Tribunal held
that:
“Stability of the legal framework is undoubtedly conducive to attracting foreign
investments, especially direct investments where business plans can extend over a
number of years; and even more so in respect of those where initial investments are
substantial and are recouped only over a long period of time. On the other hand, it
would be unconscionable for a country to promise not to change its legislation as time
and needs change, or even more to tie its hands by such a kind of stipulation in case a
crisis of any type or origin arose. Such an implication as to stability in the BIT’s
49
Duke Energy, ¶340. 50
Parkerings v. Lithuania, ¶333. 51
Ibid, ¶335. 52
Ibid. 53
Statement of Uncontested Facts, ¶25.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 18
Preamble would be contrary to an effective interpretation of the Treaty; reliance on
such an implication by a foreign investor would be misplaced and, indeed,
unreasonable.”54
45. In the present case, an economic crisis did arise in the Respondent’s territory.55
It was in
aftermath of the aforementioned crisis that the Respondent’s laws were changed.
Therefore, the Claimant’s expectations that the position of laws would remain frozen,
even in such circumstances, were unreasonable. Consequently, the Claimant’s
expectations were not legitimate.
ii) The said expectation did not induce the Claimant’s investment.
46. In any case, the aforementioned expectation of the Claimant did not induce the
investment. The factual matrix is bereft of any evidence that would point to such
inducement. On the contrary, the facts clearly show that while Project Alfa was instituted
as an experimental solar project,56
Project Beta was commissioned to build on the efforts
from Project Alfa57
and the last twelve projects were to build on the efforts of Projects
Beta and Alfa.58
Hence, it is clear that there was no active reliance placed by the Claimant
on the stability of the legal environment. Consequently, such an expectation did not
induce the Claimant to invest in the Respondent.
iii) No specific warranties were made and later repudiated.
47. No specific warranties were made by the Respondent to the Claimant that were later
repudiated. To constitute a legitimate expectation, warranties should be unequivocally
directed towards the Claimant. Moreover, the Respondent should unequivocally make the
specific warranty the Claimant seeks to enforce. However, in the current dispute, both
these requirement have not been satisfied.
48. In OKO v. Estonia, the Arbitral Tribunal stated that the warranty in question should be
unequivocally directed towards the Claimant.59
Municipal legislations cannot, in and of
themselves, amount to specific warranties until and unless they are expressly aimed at a
54
Continental v. Argentina, ¶258. 55
Statement of Uncontested Facts, ¶29, ¶30, ¶32. 56
Statement of Uncontested Facts, ¶12. 57
Statement of Uncontested Facts, ¶23. 58
Statement of Uncontested Facts, ¶27. 59
OKO v. Estonia, ¶247.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 19
foreign investor.60
Article 4 of the LRE is part of a municipal legislation. Therefore, no
specific warranties were directed at the Claimant by the Respondent.61
49. Additionally, the Arbitral Tribunal in PSEG Global v. Turkey held that even though a host
nation’s foreign investment policy might be framed to induce foreign investments in
general, it cannot amount to a specific warranty until and unless a specific warranty of
profitability is made to a particular investor.62
In the present dispute, no such warranties
were made to the Claimant.63
Therefore, not only do the alleged warranties lack specificity
as to the warrantee, but also as to the nature or the contents of the warranty itself.
Consequently, the requirement of subsequent repudiation of specific warranties is not
fulfilled as well.
B. The Respondent’s legislative actions did not violate its transparency obligation.
50. With respect to the Amendment of Article 4 of the Law on Renewable Energy, 2013
(“2013 Amendment”), even though only private consultations were held with selected
stakeholders, the Respondent has not violated its transparency obligations.
51. In Paushok v. Mongolia, the Arbitral Tribunal ruled that even if the legislative or
regulatory changes in question were made without any consultations or debates, such
changes would not be in violation of the transparency obligations of the Respondent State
until and unless the procedure followed was in violation of the municipal laws of the
Respondent State.64
Consequently, the standard for the transparency obligation is that the
regulatory change in question should not be in violation of the Respondent’s own
municipal laws.
52. In the present dispute, the Respondent did abide by its own municipal laws. Barancasian
law grants sufficient discretion to the national parliament board in consulting the public in
course of legislative changes.65
They are not bound by any rules regarding their choice of
stakeholders.66
Therefore, even if there is an obligation to consult stakeholders, there is no
obligation to consult or invite any specific stakeholders since the margin of discretion in
this regard is considerably high. The Respondent did consult the stakeholders it considered
60
Continental v. Argentina, ¶261. 61
Statement of Uncontested Facts, ¶20; LRE, Art. 4. 62
PSEG Global v. Turkey, ¶243. 63
Statement of Uncontested Facts, ¶20; LRE, Art. 4. 64
Paushok v. Mongolia, ¶304. 65
Procedural Order No. 3, ¶5. 66
Ibid.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 20
relevant.67
Hence, there has been no breach of the transparency obligation by the
Respondent.
C. The Respondent’s legislative actions were not arbitrary.
53. The 2013 Amendment was not arbitrary because if a measure is based on a considered
opinion, such a consideration is enough for the measure to not qualify as arbitrary.68
In
LG&E v. Argentina, the Tribunal held that even if a measure is inequitable or unfair, it
would not be arbitrary as long as it is in furtherance of a reason.69
In other words, an
action is considered arbitrary when it inflicts damage upon an investor without serving any
legitimate purpose.70
In AES v. Hungary, the Tribunal ruled that a policy in pursuance of
public interest is a legitimate policy.71
54. The appropriateness of the reasoning behind a policy is irrelevant so long as the policy
itself is based on a reason.72
In the present dispute, it had become economically
unsustainable for the Respondent to continue with the old feed-in tariff.73
The educational
system would have been adversely affected, too.74
Hence, the Respondent reduced the
feed-in tariff for a legitimate reason as opposed to being arbitrary.
D. There was no breach due to the refusal of grant of license to Project Alfa.
55. There was no breach of the FET standard, or otherwise, due to the refusal of the grant of
license to Project Alfa. The refusal was in light of criteria specifically laid down under
Article 5 of the LRE, which clearly shows that only projects that have a scope of
development of their capacity or are new projects are entitled to a license.75
Since Project
Alfa was a project that predated the LRE, it was not entitled to a license.76
There was no
lack of transparency in this regard.
67
Statement of Uncontested Facts, ¶34. 68
LG&E v. Argentina, ¶160. 69
Ibid, ¶162. 70
EDF v. Romania, ¶303. 71
AES v. Hungary, ¶10.3.9. 72
Enron v. Argentina, ¶281. 73
Statement of Uncontested Facts, ¶30. 74
Statement of Uncontested Facts, ¶30. 75
LRE, Art. 5. 76
Statement of Uncontested Facts, ¶12.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 21
56. The transparency standard as established in Tecmed v. Mexico is that an investor is entitled
to know about any laws and regulations that might govern its investment.77
With respect to
transparency, the reason for refusal was already expressly stated in Article 5 of the LRE.78
57. The refusal was not arbitrary either. The only requirement for an action to not be arbitrary
is that the action should not be taken without adequate reasoning.79
It is irrelevant as to
whether the reason was appropriate or not.80
Since the reason was clearly stated by the
Respondent, the said action was not arbitrary.81
VI. ALTERNATIVELY, THE RESPONDENT’S ACTIONS ARE EXEMPTED ON THE BASIS OF THE
EXCEPTION UNDER ARTICLE 11 OF THE BC BIT.
58. The impugned measures are exempted on the basis of the exception enshrined in Article
11 of the BC BIT. This is because: Article 11 of the BC BIT is a self-judging provision
and the Respondent was within its permitted margin of appreciation (A); and in the
alternative, Article 11 of the BC BIT is closer to Article XX of the General Agreement on
Tariffs and Trade (“GATT”) and hence the latter is applicable in the present scenario (B).
A. Article 11 of the BC BIT is a self-judging provision and is applicable to the
current dispute.
i) Article 11 of the BC BIT is substantially different from Article 25 of the ILC Articles.
59. Article 11 of the BC BIT and Article 25 of International Law Commission’s Articles on
State Responsibility (“ILC Articles”) were substantially different.82
In the CMS v.
Argentina Annulment Award, the Arbitral Tribunal held that:
“Article XI and Article 25 are substantively different. The first covers measures
necessary for the maintenance of public order or the protection of each Party’s own
essential security interests, without qualifying such measures. The second
subordinates the state of necessity to four conditions. It requires for instance that the
action taken “does not seriously impair an essential interest of the State or States
towards which the obligation exists, or of the international community as a whole”, a
condition which is foreign to Article XI.”83
77
Tecmed v. Mexico, ¶154. 78
Statement of Uncontested Facts, ¶22. 79
LG&E v. Argentina, ¶162. 80
Enron v. Argentina, ¶281. 81
Statement of Uncontested Facts, ¶22. 82
CMS v. Argentina Annulment Award, ¶130. 83
Ibid.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 22
60. Moreover, unlike Article XI of the Argentina-USA BIT, Article 11 of the BC BIT does not
use the word “necessary”. Therefore, there is clearly no threshold requirement under the
latter. In Sempra v. Argentina Annulment, the Arbitral Tribunal held that application of
Article 25 of ILC Articles to Article XI of a BIT was an annullable error of law.84
ii) Article 11 has a simple purpose requirement for it to be applicable.
61. There is nothing but a simple purpose requirement under Article 11 of the BC BIT. The
2013 Amendment was in pursuance of protection of economic interests of the Respondent.
In LG&E v. Argentina, the Tribunal rejected the notion that the defence of “essential
security interests” is applicable only in situations of war or military action.85
“Essential
security interests” can include measures taken in pursuance of the objective of avoidance
of an economic crisis.86
62. In the instant case, the purpose requirement of Article 11 of the BC BIT has been fulfilled.
For understanding the terms of a provision, it must be interpreted in light of the ordinary
meaning read in good faith.87
Article 11 of the BC BIT includes the “essential security
interests” ground as it is the title of said Article. Therefore, measures undertaken by a
State in order to avoid an economic crisis are covered under Article 11 of the BIT.
iii) A severe economic crisis constitutes a security interest of the State.
63. In Continental v. Argentina, the Tribunal held that a severe economic crisis with public
order implications falls within security interests of the State, especially for developing
countries.88
Moreover, the margin of appreciation in such scenarios is quite high.89
64. In the current scenario, the Respondent is a developing country.90
Further, it had become
both economically and logistically impossible for the Respondent to continue with the old
feed-in-tariff.91
Also, there was a situation where a public order problem had become quite
84
Sempra v. Argentina Annulment, ¶208. 85
LG&E v. Argentina, ¶238. 86
Ibid. 87
VCLT, Art. 31(1). 88
Continental v. Argentina, ¶181. 89
Ibid. 90
Statement of Uncontested Facts, ¶2. 91
Statement of Uncontested Facts, ¶29, ¶30; Procedural Order No. 2, ¶13.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 23
apparent.92
Consequently, the actions of the Respondent were covered under the margin of
appreciation bestowed upon the Respondent by virtue of Article 11 of the BC BIT.
B. Alternatively, Article XX of the GATT is applicable to the present case.
i) Reference to the GATT is more appropriate.
65. Article XX of the GATT is applicable to the present dispute since it is closer to Article 11
of the BC BIT, and the requirements under the former have been satisfied in the present
dispute. With regard to the applicability of the GATT, reliance must be placed on the
Continental v. Argentina decision, wherein the Tribunal held that it is more appropriate to
use the “necessary” standard under Article XX of the GATT as opposed to Article 25 the
ILC Articles.93
66. The aforementioned proposition is premised on the fact that it is more appropriate to refer
to the GATT and World Trade Organisation (“WTO”) case law which has extensively
dealt with concept and requirements of necessity in the context of economic measures,
rather than the corresponding standard under customary international law.94
ii) Interpretation of the term “necessary”.
67. In the Continental v. Argentina decision, the Arbitral Tribunal referred to the
interpretation of the term “necessary” by the WTO Panel in the EC Tyres case.95
A relative
consideration of various factors should be undertaken to ascertain the necessity of a
measure.96
The three factors which must be considered: the relative value of interests
furthered through the challenged measures (a); contribution of the measure to the
realisation of ends pursued by it (b); and the restrictive impact of measure on imports and
exports (c); favour the Respondent.97
a. Value of the interests protected / furthered.
68. The value protected by the impugned measure in the present case is vital. To interpret the
importance of a value, reliance must be placed on the Preamble of the GATT.98
The
92
Statement of Uncontested Facts, ¶32. 93
Continental v. Argentina, ¶192. 94
Ibid. 95
Ibid, ¶194. 96
Panel, Brazil–Tyres, ¶7.104. 97
Ibid. 98
US–Gasoline, 30-31; VCLT, Art. 31(2).
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 24
Preamble of the GATT highlights the paramount importance of the objectives of “raising
[the] standards of living, ensuring full employment”. These objectives were the ultimate
values pursued by the impugned measures by means of avoidance of an economic crisis.
Hence, the values protected by the Respondent’s actions were vital.
b. Contribution of the measures to the interest pursued.
69. The contribution of the measure to the interest pursued is material. The WTO Appellate
Body (“AB”) in Brazil- Retreated Tyres stated that “the fundamental principle is the right
that WTO Members have to determine the level of protection that they consider
appropriate in a given context”.99
The evaluation can be either quantitative or
qualitative.100
The threshold to be considered is either that of a genuine means-ends
relationship101
or one of a material contribution102
. The greater the contribution a measure
makes to the objectives sought to be achieved; the more likely is it to be considered
‘necessary’.103
In the current scenario, the 2013 Amendment and the corresponding change
in the feed-in tariff were sufficient to make a material contribution to the crisis that would
have arisen due to its original numerical value.
c. No restrictive impact on imports and exports.
70. The restrictive impact of the measure on international commerce was minimal. The effect
of the measure on imports and exports was also minimal since there was a mere
application of a lower rate of feed-in tariff and not a denial of market access. Since all the
three factors are in favour of the Respondent in the present case, the measures were
necessary.
99
AB, Brazil–Tyres, ¶210. 100
AB, Brazil–Tyres, ¶146; EC–Asbestos, ¶167. 101
AB, Brazil–Tyres, ¶145. US – C.O.O.L., ¶462, ¶473. 102
Brazil–Tyres, ¶146. 103
China–Products, ¶251.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 25
REMEDIES
VII. ALTERNATIVELY, THE RESPONDENT CAN NEITHER BE ORDERED TO RESCIND THE
2013 AMENDMENT NOR TO PAY THE PRE-2013 AMENDMENT TARIFF.
71. The Respondent cannot be ordered to either rescind the 2013 Amendment or pay the pre-
2013 Amendment tariff because: the Tribunal cannot order specific performance since
such an order will be in violation of Respondent’s sovereignty (A); and alternatively, it
will cast a disproportionate burden on the Respondent (B).
A. An order of specific performance will be in violation of Respondent’s
sovereignty.
72. Specific performance, if ordered, will violate Respondent’s sovereignty. State sovereignty,
recognised in Article 2(1) of the United Nations Charter, is one of the paramount
principles of international law. In LG&E v. Argentina, the Arbitral Tribunal held that:
“The judicial restitution required in this case would imply modification of the current
legal situation by annulling or enacting legislative and administrative measures that
make over the effect of the legislation in breach. The Tribunal cannot compel
Argentina to do so without a sentiment of undue interference with its sovereignty.
Consequently, the Tribunal arrives at the same conclusion: the need to order and
quantify compensation.”104
73. Even other tribunals in the past have been reluctant in ordering specific performance.105
An order of rescission in the instant case will violate the sovereignty of Respondent.
Hence, specific performance should not be ordered, and pecuniary damages are the only
viable option.106
B. Alternatively, an order of specific performance will cast a disproportionate
burden on the Respondent.
74. Specific performance can be ordered only so long as the performance is neither materially
impossible,107
nor does it cast a disproportionate burden on the Respondent.108
An order of
specific performance would cast a disproportionate burden on the Respondent. In CMS v.
104
LG&E v. Argentina, ¶87. 105
Douglas, p. 100. 106
Occidental Petroleum v. Ecuador, ¶80; CMS v. Argentina, ¶408. 107
ILC Articles, Art. 35. 108
CMS v. Argentina, ¶400.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 26
Argentina, the Arbitral Tribunal held that it would be utterly unrealistic to order the
Respondent to rescind measures undertaken to remedy a crisis.109
In the current dispute, if
specific performance were to be ordered by way of rescission of the 2013 Amendment, it
would effectively lead to the actualisation of the speculated economic crisis.
75. If specific performance were to be ordered by means of payment of pre-2013 Amendment
feed-in tariff, the Respondent will be bound to pay the same tariff to all the investors from
EU Member States.110
Hence, such an order will lead to the actualisation of the speculated
economic crisis, as well.
76. In either case, any such order will be a breach of the Respondent State’s sovereignty. In
Occidental Petroleum v. Ecuador, the Tribunal stated that such a breach of a State’s
sovereignty is disproportionate compared to the pure monetary loss suffered by any
investor.111
VIII. THE CLAIMANT’S BASIS FOR CLAIMING AND QUANTIFYING THE COMPENSATION IS
NOT APPROPRIATE.
77. The Claimant is not entitled to compensation for the loss of profits allegedly suffered by it
(A); and the Claimant’s basis for claiming and quantifying the compensation is not
appropriate as it is fundamentally flawed (B).
A. The Claimant is not entitled to compensation for its loss of profits.
i) There is no established record of profitability.
78. The Claimant’s photovoltaic projects do not have an established performance record that
indicates profitability of the Claimant’s investment. The Claimant was unable to control
the construction costs of Project Alfa resulting in an overrun of more than 50% of the
estimated project cost.112
Further, Project Alfa was only operating at a capacity of 12.1%
as opposed to the Claimant’s projection of 21%.113
The Claimant’s expert’s prediction of a
109
CMS v. Argentina, ¶406. 110
TFEU, Art. 18. 111
Occidental Petroleum v. Ecuador, ¶84. 112
Statement of Uncontested Facts, ¶7. 113
Ibid.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 27
steady increase of 2.2% in the capacity of Project Alfa is mere speculation which is not
based on any concrete evidence.
79. Moreover, the twelve planned photovoltaic projects are still in the stage of construction
and are not yet operational. Therefore, they have obviously no record of performance and
profitability, and any claim of future profits based on them is mere speculation at this
stage.114
ii) Future profits cannot be calculated without past performance record.
80. When there is no established record of past profitability, as is required for granting of
compensation as per Article 36 of the ILC Articles,115
any claim for damages for future
profits would be speculative and indeterminable.116
It has been established by multiple
arbitral tribunals that no compensation for speculative or uncertain damage can be
awarded.117
B. The Claimant’s basis for claiming and quantifying the compensation is
inappropriate.
81. The Claimant’s basis for claiming and quantifying the compensation is inappropriate
because there are four fundamental flaws in the Claimant’s expert’s quantification of the
compensation: the Claimant is not entitled to damages for Project Alfa (i); the rate of
discounting cash flows must be at the Claimant’s Cost of Equity (“COE”) and not the
Weighted Average Cost of Capital (“WACC”) (ii); the calculation of the compensation
due for the Claimant’s “wasted investment” in land is erroneous (iii); and finally, the
Claimant is not entitled to compensation for its planned investment for the expansion of its
photovoltaic projects (iv).
114
Metalclad v. Mexico, ¶119-121. 115
ILC Articles, Art. 36, ¶26-27. 116
LG&E v. Argentina, ¶90; Metalclad v. Mexico, ¶120. 117
Amoco v. Iran, ¶238; LG&E v. Argentina, ¶90.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 28
i) The Claimant is not entitled to compensation for Project Alfa.
a. The Claimant could not have ‘legitimate expectations’ of profit under the LRE.
82. It is an established principle in international law that ‘legitimate expectation’ can only
exist at the time of investment.118
Further, such ‘legitimate expectation’ can only lead to
compensation if there was a link between the expectation and investment made.119
83. Project Alfa became operational on 1 January 2010, and it was only in May 2010 that the
Respondent adopted the LRE, which was to be applicable to new projects. Hence, Project
Alfa was not undertaken in response to the LRE, and therefore, the Claimant cannot claim
to have had any legitimate expectation of benefitting from the feed-in tariff specified in
the LRE, with respect to Project Alfa.
b. Denial of license to Project Alfa was not arbitrary.
84. The BEA’s denial of a license to the Claimant for Project Alfa was not arbitrary. The LRE
was brought into force to provide incentives for the subsequent photovoltaic development
projects, and not as a subsidy for pre-existing projects.120
Therefore, granting a license for
Project Alfa did not serve the LRE’s purpose of enhancing renewable energy source by
promoting more investments.
ii) The WACC is the incorrect rate for discounting the Claimant’s cash flows.
a. The rate of discount should be on the basis of the method used to compute cash
flows.
85. The Claimant has claimed compensation based on the present value of future revenues.
Such future revenue may be solely contributed to the cash flows to equity, since usually
cash flows from operations are initially used to pay the creditors, and are subsequently
used for paying shareholders. Therefore, alleged loss of future revenues should be viewed
as cash flows to equity.121
Further, having computed the cash flows to equity, the Claimant
118
AES v. Hungary, ¶138; Duke Energy, ¶138; Tecmed v. Mexico, ¶138. 119
Thunderbird, ¶138. 120
LRE, Art. 1. 121
Walter Bau, ¶14.35.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 29
should discount the cash flow at the COE to obtain the present value, and not a rate that
includes both debt and equity such as the WACC.122
b. The Discounted Cash Flow (“DCF”) method is inappropriate when the project is
not a “going concern”.
86. It has been held that future profits cannot be used to determine the fair market value of an
investment which lacks profitability and has no ‘going concern’;123
and that the DCF
approach becomes inappropriate when relying on speculative assumptions and
projections.124
The book-value method is the most appropriate for recent investments.125
Therefore, considering the fact that Project Alfa lacks profitability, Project Beta can be
considered to be a recent investment, and the 12 new photovoltaic projects are yet to
become operational or ‘going concerns’; the DCF method of computation of compensation
is inappropriate, and instead, the book-value method must be employed by the Tribunal.
iii) The Claimant cannot claim compensation for ‘wasted investment in land’.
87. The duty of the investor to mitigate its losses is a well-established principle of
international investment arbitration.126
Such a duty exists even when it has not been
expressly stipulated in the BIT.127
The injured party is expected to take reasonable steps to
mitigate its losses.128
88. In the present case, the Claimant presupposes that the land purchased by it will be
worthless. However, the price of the land is now 10% higher than when it was bought129
and is suitable to be used for other purposes as well. Therefore, the Claimant has the
opportunity to sell the land and make a profit, too.
122
CMS v. Argentina, ¶431. 123
Vivendi, ¶8.3.4. 124
Ibid., ¶8.3.3. 125
Siemens v. Argentina, ¶355. 126
EDF v. Argentina, ¶1302; Marboe, ¶3.240. 127
EDF v. Argentina, ¶1303. 128
CME v. Czech, ¶355. 129
Procedural Order No. 2, ¶29.
Arguments Advanced
-MEMORIAL FOR THE RESPONDENT- 30
iv) The Claimant is not entitled to compensation for future investment in expansion of its
projects.
a. There is no proof of the Claimant’s intention to expand.
89. Evidence in support of future plans of the Claimant is essential for it to be able to claim
compensation for loss of future profits.130
However, no such evidence has been provided
by the Claimant. The only evidence brought forward is the mere speculation of a local
manager who has stated that expansion of the projects “was a long term goal that the
company had always aspired to achieve, step by step”.
b. Compensation cannot be granted for merely speculative claims.
90. When the claim for compensation is based on mere speculation, the damages have been
held to be too remote to be awarded by the arbitral tribunal.131
The Respondent cannot be
ordered compensate for projects to which Claimant has made no commitments.132
As has
been established previously, projects that are inoperative at the time of the dispute cannot
be used to claim compensation for lost profits (lucrum cessans).133
Therefore, considering
the fact that the Claimant has put forward no evidence to prove its commitment to
expanding the photovoltaic projects in the future, it is not entitled to claim compensation
for the lost profits from such expansion.
130
Micula v. Romania, ¶1117. 131
Lemire v. Ukraine, ¶245-246; Al-Bahloul, ¶95-96. 132
ADC v. Hungary, ¶515. 133
Metaclad v. Mexico, ¶121; LG&E v. Argentina, ¶90.
Prayer for Relief
-MEMORIAL FOR THE RESPONDENT- 31
PRAYER FOR RELIEF
On the basis of the aforementioned reasons, the Respondent respectfully requests the
Tribunal to find that:
1. The Tribunal does not have jurisdiction over the present dispute, and the Claimant’s
claims are inadmissible under the Barancasia-Cogitatia BIT;
2. The Respondent did not breach its obligations under the Barancasia-Cogitatia BIT,
including, the Fair and Equitable Treatment standard;
3. In the alternative, the Respondent’s actions were exempted by virtue of the exception
provided for in Article 11 of the BIT;
4. In the alternative, the Tribunal does not have the power to order specific performance
against the Respondent;
5. In the alternative, the Claimant’s basis for claiming and quantifying compensation is
inappropriate, and is based on false and incorrect legal and factual assumptions; and
6. The Respondent is entitled to reimbursement of all costs related to these proceedings.
Respectfully submitted on 26 September 2015.
TEAM GAJA
ON BEHALF OF THE RESPONDENT
REPUBLIC OF BARANCASIA