the port talbot steelworks (power generation … port talbot steelworks (power generation...
TRANSCRIPT
Planning Act 2008 The Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009
The Port Talbot Steelworks (Power Generation Enhancement) Order
10.01 Planning Statement
PINS Reference EN010062
Document No. 10.01
Regulation 5(2)(q)
Author GVA
Revision Date Description
0 July 2014 Submission Version
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 2
CONTENTS 1 Introduction .............................................................................................................. 8
1.1 Overview ......................................................................................................... 8
1.2 The Applicant .................................................................................................. 9
1.3 The Background & Justification for the Proposed Development ................... 10
1.4 The Structure of this Statement .................................................................... 15
2 Site Context & The Proposed Development ........................................................ 16 2.1 Site Location ................................................................................................. 16
2.2 General Site History ...................................................................................... 17
2.3 Planning History ............................................................................................ 18
2.4 Land Ownership & Existing Land Use .......................................................... 18
3 The Proposed Development ................................................................................. 20 3.1 Preface ......................................................................................................... 20
3.2 Proposed Development: Project Summary ................................................... 20
3.3 Proposed Development: Project Detail ......................................................... 23
3.4 Proposed Development: Decommissioning of Existing Equipment............... 29
3.5 Proposed Development: Construction .......................................................... 29
4 Planning Policy Context ........................................................................................ 35 4.1 Preface ......................................................................................................... 35
4.2 National Planning Policy ............................................................................... 36
4.3 The Development Plan ................................................................................. 42
5 Planning Assessment ........................................................................................... 51 5.1 Introduction ................................................................................................... 51
5.2 NPS 1 – Overarching National Policy Statement for Energy (NPS EN-1) ..... 52
5.3 NPS 2 – Fossil Fuel Electricity Generating Infrastructure (NPS EN-2) ......... 97
5.4 NPS 4 – Gas Supply Infrastructure & Gas and Oil Pipelines (NPS EN-4) .. 104
5.5 NPS 5 – Electricity Networks Infrastructure (NPS EN-5) ............................ 108
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 3
5.6 National Planning Policy ............................................................................. 111
6 DCO Requirements .............................................................................................. 120 6.1 Overview ..................................................................................................... 120
6.2 Planning Requirements .............................................................................. 120
7 Conclusion ........................................................................................................... 122
APPENDICES Appendix A Existing Site Layout Plan (inclusive of the “Order Limits”)
(Document Reference: 2.02)
Appendix B Site Location Plan (Document Reference: 2.01)
Appendix C Sites of Landscape Importance (Document Reference: 2.07.2)
Appendix D Nature Conservation Sites, Habitats and Diversity Features
(Document Reference: 2.07.1)
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 4
GLOSSARY
AA Appropriate Assessment
AONB Area of Outstanding Natural Beauty
AQMA Air Quality Management Area
ASIDOHL Assessment of Significance of Impacts of Development on
Historic Landscape
BTA Boiler Turbo Alternator
CAA Civil Aviation Authority
CCS Carbon Capture Storage
CO2 Carbon Dioxide
CoCP Code of Construction Practice
CTMP Construction Traffic Management Plan
DAM Development Advice Map
DECC Department of Energy & Climate Change
DCO Development Consent Order
EIA Environmental Impact Assessment
EP Environmental Permit
ES Environmental Statement
EU European Union
FCA Flood Consequences Assessment
FWEP Flood Warning and Evacuation Plan
GGAT Gwent and Glamorgan Archaeological Trust
Ha / ha Hectare
HGV Heavy Goods Vehicle
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 5
HMP Habitat Management Plan
HRA Habitats Regulations Assessment
IfA Institute for Archaeologists
IPC Infrastructure Planning Commission
Km Kilometre
LDP Local Development Plan
LNR Local Nature Reserve
LPA Local Planning Authority
MMP Materials Management Plan
MOD Ministry Of Defence
MWe Mega Watts Electrical – measure of energy, one million watts
MWth Mega Watts Thermal – measure of heat energy
NATS National Air Traffic Services
NGR National Grid Reference
NO2 Nitrogen Dioxide
NPS National Policy Statement
NPS EN-1 Overarching National Policy Statement for Energy
NPS EN-2 National Policy Statement for Fossil Fuel Electricity
Generating Infrastructure
NPS EN-4 National Policy Statement for Gas Supply Infrastructure and
Gas and Oil Pipelines
NPS EN-5 National Policy Statement for Electricity Networks
Infrastructure
NPTCBC Neath Port Talbot County Borough Council
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 6
NPTUDP Neath Port Talbot Unitary Development Plan
NRW Natural Resources Wales (formally EAW and CCW)
NSIP Nationally Significant Infrastructure Project
NSR Noise Sensitive Receptor
Order Limits The site boundary defined by the Development Consent
Order and denoted by a red line in figures.
PDR Peripheral Distributor Road
PEIR Preliminary Environmental Information Report
PINS Planning Inspectorate
PJ Petajoule - measure of energy
PPG Pollution Prevention Guidelines
PPW Planning Policy Wales
PM10 Extremely small particulates or particulate matter (in the
order of ~10 micrometres or less)
PPP Pollution Prevention Plan
PROW Public Rights of Way
Ramsar Wetlands of international importance, designated under the
Ramsar Convention
SAC Special Area of Conservation
SINC Sites of Interest for Nature Conservation
SoS Secretary of State
SPA Special Protection Area
SPG Supplementary Planning Guidance
SSP Site Safety Plan
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 7
SSSI Site of Special Scientific Interest
SWMP Site Waste Management Plan
TA Turbo Alternators (Differentiation - this is followed by a
number)
TA Traffic Assessment
TAN Technical Advice Note
Tata Steel The overarching company (Includes the Applicant)
Tata Steel UK Limited The Applicant
TP Travel Plan
TSUL Tata Steel UK Limited. The Applicant
UDP Unitary Development Plan
ULCOS Ultra-Low CO2 Steelmaking
WG Welsh Government
ZTV Zone of Theoretical Visibility
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 8
1 Introduction
1.1 Overview
1.1.1 This Planning Statement has been prepared by GVA, on behalf of Tata Steel
UK Limited (the Applicant), in support of an application for a Development
Consent Order (DCO) pursuant to the Planning Act 2008 (PA 2008) (‘the
Application’), for a scheme that proposes the enhancement of existing power
generation facilities (hereafter known as the ‘proposed development’) at Tata’s
Port Talbot Steelworks in South Wales.
1.1.2 As the proposed development comprises an electricity generating station with a
capacity of more than 50MW, it constitutes a Nationally Significant Infrastructure
Project (NSIP) under section 15 of the PA 2008. Accordingly, it requires
development consent under section 31 of the PA 2008. Development consent
may only be granted by order (a DCO) following an application to the Secretary
of State for Energy and Climate Change pursuant to section 37 of the PA 2008.
1.1.3 The location of the proposed development site and the limits of the DCO are
shown on the Existing Site Location Plan included in Appendix A (Document
Reference: 2.02).
1.1.4 This Application for development consent is for the installation of up to two new
boilers (nominally 164 Mega Watt thermal (MWth) each) and associated new
steam turbine sets with a gross capacity of up to 150 Mega Watt electrical
(MWe), which would be connected to the existing process gases (i.e. blast
furnace gas, etc) distribution network in order to receive these gases through
new pipe work, all to be located within the Order Limits. The proposed
development also includes the 66kV electrical connection to the grid (a cable
route of around 2.8km in length) and extensions to the existing on-site utility
connections (water, nitrogen, natural gas and compressed air).
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 9
1.1.5 The proposed development would result in the total on-site power generation
capacity at the Port Talbot site increasing up to a maximum of 245 MWe.
1.1.6 In accordance with the PA 2008, this Application is submitted to the Planning
Inspectorate (PINS) (the Examining Authority) for consideration and, ultimately,
for its recommendation to the Secretary of State, who will determine the
Application.
1.2 The Applicant
1.2.1 Tata Steel UK Limited (hereafter referred to as “TSUL”) is the Applicant for the
DCO and has control of the vast majority of the land identified for the proposed
development (see the plan in Appendix A of this statement (Document
Reference: 2.02 for the Order Limits). The Order Limits also include two small
sections of Network Rail owned land which comprise a disused internal railway
within the steelworks site. The railway line would be crossed by the proposed
electricity connection and an extension to the gas pipe network, authorisation
for which is included within the DCO.
1.2.2 For the purposes of this Application, reference may be made to Tata Steel in a
wider sense which includes a number of steelmaking companies all owned by
the same parent company operating in various jurisdictions, of which Tata Steel
UK Limited is the company operating in the UK. However, it should be clear
from the outset that TSUL is the Applicant for the Application.
1.2.3 The Applicant is committed to environmental care and protection, to a
sustainable society, and the safety of its neighbours and everyone on its sites.
The Applicant recognises its environmental responsibilities, and is committed to
minimising the environmental impact of its operations and products by adopting
sustainable practices and by continuously improving environmental
performance. The Applicant has implemented environmental management
systems that have been certified as meeting the requirements of international
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 10
standard ISO14001 at all of its main manufacturing sites, including its Port
Talbot site.
1.2.4 Tata Steel is a leading member of ULCOS (Ultra-Low CO2 Steelmaking) – a
pioneering partnership of 48 companies and organisations from 15 European
countries that recently completed the first phase of a cooperative research
initiative to achieve a step change in CO2 emissions from steelmaking. The
ambitious aim of the ULCOS project, which began in 2004 and is supported by
the European Commission, is to reduce CO2 emissions per tonne of steel
produced by at least 50% by 2050.
1.3 The Background & Justification for the Proposed Development
1.3.1 The current total on-site power generation capacity of the Port Talbot site is
115.7 MWe. This capacity provides electrical power and process steam to the
production processes on-site. However the majority of this existing power
generation equipment dates back to the 1950’s and is becoming increasingly
unreliable and inefficient due to its age.
1.3.2 The Port Talbot steelworks represents a major contributor to the local and
regional economies. It directly employs approximately 3,500 people in a variety
of disciplines and supports a huge amount of subsidiary businesses in the local
area, but also at a national and international level. The Welsh Government
recognises Tata Steel as an “anchor employer” within south Wales, employing
up to 17,000 people both directly and indirectly through the localised supply
chain. It must also be noted that the operations of the Port Talbot site support
the other Tata Steel sites at Llanwern, Shotton, Corby and Trostre.
1.3.3 The steel market is a global one and, at Port Talbot, TSUL is making continual
investment to increase its competitiveness in that marketplace. The applicant is
committed to the Port Talbot site and in recent times has made significant
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 11
investment in the steelworks to increase its competitiveness in the global steel
market. Recent investment in the Port Talbot site includes:
the commissioning of a £60m energy efficiency scheme in 2010 to capture
and reuse of gas from the Basic Oxygen Steelmaking (BOS) plant;
a £50m investment scheme to recover and re-use process-generated waste
heat, which was fully commissioned in early 2013, and
the £185m rebuild of Blast Furnace 4 (also in 2013).
1.3.4 However, market competition is intense, and on 1st July 2014, TSUL
announced restructuring proposals to improve the competitiveness of its South
Wales steelmaking business. The proposed changes would enable the UK
Strip Products business to compete in Europe’s lower market demand era by
reducing costs equivalent to the loss of about 400 jobs in Port Talbot. Extracts
from a news report published on the BBC website are included below to
illustrate the rationale for the restructuring:
The company [TSUL] said in statement the job losses would reduce
costs and enable it to compete in an era of lower market demand.
Mr Koehler [TSUL Chief Executive] said: "Steel demand and prices are
likely to be under pressure for some years. Our business rates in the
UK are much higher than other EU countries and our UK energy costs
will remain uncompetitive until new mitigation measures come into
effect.
"These proposed changes then are vital if we are to build a competitive
future for our strip products business in the UK."
The company spends £60m on electricity in Wales alone, and pays
about 40% more for the electricity than competitors in continental
Europe.
http://www.bbc.co.uk/news/uk-wales-28104757
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 12
1.3.5 This demonstrates the commercial pressure TSUL is currently experiencing in
the UK and highlights the acute economic need for the proposed development.
1.3.6 The proposed development represents a further investment in the Port Talbot of
around £200m which will increase economic efficiency through reduction in
electricity import costs and will help to protect the long-term future of
steelmaking in South Wales. Clearly, the proposed development will also
contribute to the economic stability of the steelworks and therefore the County
Borough of Neath Port Talbot and the wider regional economy. This
contribution will come during the construction and operational phases of the
proposed development.
1.3.7 The following sections outline the current and future operations of the Port
Talbot site in the context of the proposed development.
Current Operations
1.3.8 The iron and steel making process generates by-product gases which, if not
utilised or recycled by the site, are burnt through the flare stacks. The current
minimum operational flare is approximately 1 Petajoule (PJ).
1.3.9 Energy represents a large proportion of steel manufacturing costs. In order to
remain competitive within the market place, the Applicant has embarked on a
series of improvement measures, of which energy efficiency is one. A
significant opportunity is presented by the enhancement of the existing on-site
power generation which could result in a considerable reduction in imported
electricity against current site demand.
1.3.10 Although the total on-site power generation capacity is 115.7 MWe, the relative
age and efficiency of the existing equipment, combined with the variable cycle
of process gas production, results in an average power generation of 75 MWe.
Combined with the grid import of 50MWe, this meets current site demand of 125
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 13
MWe. The minimum amount of flared process gases is approximately 1 PJ per
annum.
Future Operations without Proposed Development
1.3.11 The Applicant has an ambition to increase production to 4.7 million tonnes of
iron per annum at the Port Talbot site. Once production increases to this level,
and in the absence of the proposed development and/or any other energy
efficiency improvements, the amount of process gas being flared would
increase to approximately 7 PJ per annum. With on-going tactical
improvements and capital projects, the flare could be reduced by 2.2 PJ to 4.8
PJ per annum and therefore deliver a reduction in reliance on imported fuel
(natural gas).
1.3.12 The existing power generation facilities contain equipment dating back to the
1950s and do not have sufficient capacity to convert the available process
gases associated with the current and increased iron production.
1.3.13 In terms of demand for electricity, at 4.7 million tonnes of iron per annum the
site would require approximately 140 MWe, but the total average site capacity,
without the proposed development, would remain the same (at 75 MWe),
resulting in electrical imports increasing to 65 MWe from 50 MWe.
Future Operations with Proposed Development
1.3.14 In order to improve efficiency and increase generation, the Applicant proposes
to enhance the total on-site power generation by installing up to two new boilers
(nominally 164 MWth each) and associated steam turbine sets with a gross
capacity of 150 MWe. The proposed development would be housed in a new
building and would be connected to the existing blast furnace gas distribution
network in order to receive fuel gases through new pipe work.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 14
1.3.15 The enhancement of the existing on-site power generation through the
development of new facilities will allow the existing inefficient facilities to be
decommissioned as part of the proposed development. It is proposed that the
decommissioned facilities would be retained in situ on site but would not be
operational. Further detail on the equipment to be decommissioned is provided
in section 3.4 of this statement.
1.3.16 The total on-site power generation capacity, inclusive of the proposed
development, would be increased up to a maximum of 245 MWe. This would
result in an average power generation of approximately 130 MWe (due to the
variable cycle of process gas production on-site). This would result in a
reduction of grid import to 10 MWe (a decrease of 55Mwe). The estimated
amount of process gases being flared would significantly reduce by 4.3 PJ to
approximately 0.5 PJ per annum.
1.3.17 The proposed development would have a number of net benefits including:
Air quality improvements through the reduction in flared process gases;
Saving of up to approximately 400,000 tonnes per annum of CO2
compared to grid generators (based on generation from coal fired stations);
Reduced on-site electricity imports (to 10Mwe on average);
Increased operational efficiency and reliability of on-site power and steam
production; and
Increased economic efficiency through cost reduction to protect the long-
term future of steelmaking in South Wales.
1.3.18 In conclusion, the increase in total on-site power generation capacity as a result
of the proposed development would reduce the requirement for electricity
imports and hence significantly reduce the site’s cost base and improve its
environmental performance through reduction in flaring of process gases.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 15
1.4 The Structure of this Statement
1.4.1 This statement sets out the justification for the proposed development in
planning terms. Following this introductory section, the statement includes:
a description of the site, its location and context (Section 2);
an explanation of the proposed development, which is considered to a key
element of the future viability and sustainability of the steelworks site as a
whole (Section 3);
a review of the key points presented by the planning policy context to the
site, including an overview of the relevant National Policy Statements
(NPS), the Unitary Development Plan (UDP) for Neath Port Talbot and the
emerging Local Development Plan (LDP) (Section 4);
an assessment of planning policy compliance with the national and local
planning policy in relation to the principle of installing internal power
generation enhancement at the application site (Section 5);
an examination of the role played by the DCO requirements for the
proposed development (Section 6); and
key conclusions on the merits of the proposal to develop this vacant area of
land, within the confines of the existing steelworks, to improve the efficiency
of the site operations (Section 7).
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 16
2 Site Context & The Proposed Development
2.1 Site Location
2.1.1 The Port Talbot steelworks is located wholly within the County Borough of
Neath Port Talbot and extends to a total of 1005.5 hectares, which comprises
all of the major components of the steelworks, together with the ancillary
structures/buildings. The proposed development site sits within the steelworks
site and the Order Limits of the proposed development extends to a total of
22.9ha.
2.1.2 The site is located approximately 1.5km to the southeast of Port Talbot. The
Peripheral Distributor Road, known as “Harbour Way” (which opened in October
2013), lies just to the east of the site running parallel to the M4. The Port Talbot
Docks Industrial Area lies to the northwest as does Port Talbot Parkway station
and Port Talbot town centre.
2.1.3 Within the wider locality, existing residential communities include Margam,
Cwmavon, Goetre, Bryn, Pwll-y-glaw, Pontrhydyfen, North Cornelly, South
Cornelly, Pyle, Kenfig, Briton Ferry, Llandarcy, Skewen, Neath and Baglan.
The location of the proposed development is illustrated on the plan included in
Appendix B (Document Reference: 2.01).
2.1.4 The proposed development would be located in the north of the Port Talbot
steelworks site adjacent to the existing power generation facilities. The
proposed development would be separated from local communities by Harbour
Way.
2.1.5 An Air Quality Management Area (AQMA) is located directly to the northeast
and east of the proposed development. There are two Landscape of
Outstanding Historic Interest designations located to northeast (partially within
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 17
the blue line boundary) and to the south. These are shown on the plan included
in Appendix C (Document Reference: 2.07.2).
2.1.6 Within 10km of the proposed development site, there are a number of
ecological designations. These comprise eleven Sites of Special Scientific
Interest (SSSI), three Special Areas of Conservation (SACs), one Ramsar and
two National Nature Reserves (NNR) – all designated for their habitats and
plant assemblages. These are shown on the plan included in Appendix D
(Document Reference: 2.07.1).
2.1.7 There are no archaeological designations, listed buildings, scheduled ancient
monuments or registered parks and gardens located within the site boundary
but some are located within close proximity of the proposed development and
within the 15km study area assessed within the cultural heritage chapter of the
ES.
2.2 General Site History
2.2.1 Steelmaking at the Port Talbot site began with the Margam Iron and Steel
Works (completed between 1923 and 1926) and then the Abbey Works, which
opened in 1951 and was fully operational by 1953. These sites formed part of
the Steel Company of Wales. At the time of peak employment in the 1960s, the
Abbey Works was Europe's largest steelworks and the largest single employer
in Wales, with a labour force of 18,000.
2.2.2 In 1967, the Steel Company of Wales was merged with the UK’s other main
steel producing companies to form the British Steel Corporation. The British
Steel Corporation was later privatised to form British Steel Plc before becoming
an entirely private company in 1999; British Steel Limited. British Steel later
merged with Dutch steelmaker Koninkijke Hoogovens to form Corus UK Limited
in the year 2000. In 2007, Corus UK Limited was acquired by Tata Steel.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 18
2.2.3 The Port Talbot site is an integrated steelmaking site using imported raw
materials. The site makes hot-rolled, cold-rolled and metallic coated strip steels
and provides solutions in product design, processing technologies and
management of the supply chain. The steel products are transported direct to
customers, to other Tata downstream processors and to distribution centres (in
the UK and Europe) for use in the flat products steel markets.
2.2.4 The Port Talbot Steelworks competes in a global market and significant
investment has been, and continues to be, made to increase its
competitiveness in that marketplace. As summarised earlier, significant
investment has already been made at the Port Talbot site, for example the
rebuild of Blast Furnace 4, construction of a BOS Off gas waste heat recovery
plant, and the recovery and re-use of process-generated waste heat.
2.2.5 Therefore, this proposed development will increase economic efficiency through
cost reduction and will help to protect the long-term future of steelmaking in
South Wales.
2.3 Planning History
2.3.1 The planning history of the site is extensive and relates to the on-going
operation and development of the steelworks. However, the previous planning
applications are not considered to be of direct relevance to the proposed
development and as such a summary has not been included within this
statement.
2.4 Land Ownership & Existing Land Use
2.4.1 The vast majority of the proposed development site (denoted by the Order
Limits shown on the plan in Appendix A) falls within the ownership of TSUL.
However, the electrical connection and gas pipework cross a disused railway
line which runs through the steelworks site, and is in the ownership of Network
Rail (the proposed development would not affect the operations of the rail line
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 19
should it become operational again in the future). The applicant is in dialogue
with Network Rail to agree the necessary rights required to cross these two
sections of land. However, for the reasons set out in the Statement of Reasons
(Document Reference 4.01), acquisition of the necessary rights have also been
included in the Book Reference (Document Reference 4.03) and the draft DCO
submitted with the Application.
2.4.2 The location of the main generation facilities within the Order Limits was
historically the location of an on-site coke works, which was demolished in the
1960s. The site is currently open scrubland with a car park/concrete
hardstanding in the north-western portion of the site. A new internal site road
was constructed within the proposed development site in 2013. Overall, the site
has a low-lying industrial land character.
2.4.3 Harbour Way runs directly to the north of the main generating station site with
the existing Port Talbot works to the east, an internal railway line (owned by
Network Rail) to the south and the existing power station to the west.
2.4.4 The land use within the corridor for the electrical connection is predominantly
within the internal highway verge and where new cable length is needed, these
would be in areas characterised by scrubland. New ducts and pipe work would
be routed under or over the existing internal railway track as site conditions
allow. For most of the route, the cables would either be run underground (either
in new and existing ducting and excavations) or be supported off existing
structures. There would potentially be a cable bridge constructed, due to
restricted space to run cables underground, at the southern end of the cable
route between the two onsite existing substations. If required, this cable bridge
would be consistent with the other cable bridges on site and be constructed of a
metal lattice structure approximately 5m in height (to provide suitable clearance)
and approximately 800m in length.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 20
3 The Proposed Development
3.1 Preface
3.1.1 This section of this statement provides a summary of the description of the
proposed development. A full description is set out in the Environmental
Statement (ES) and Schedule 1 (authorised development) of the DCO that
accompanies the Application.
3.2 Proposed Development: Project Summary
3.2.1 Within the DCO limits, the proposed development comprises the following
major components and ancillary buildings:
up to two steam boilers and their associated stacks (maximum 80m in
height), annexe bay and boiler house;
a turbine hall housing turbine sets and associated condensers;
cooling tower units;
an electrical switchgear station building;
a condensate storage tank and additional condensate polishing units;
water treatment plant and chemical dosing system skids;
administration, workshop, pump house, gas booster house, control
buildings and ancillary infrastructure;
the extension of existing pipe work connections (for water, nitrogen,
process gases, natural gas and compressed air) from the existing on site
utilities pipe work infrastructure to the generating station. All the extended
pipe work will be contained within the Order Limits. The indicative location
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 21
of these connections are shown in Figure 3.10 of the ES (Document
Reference: 6.02.2);
a 66kV electrical connection up to 2.8km in length to connect the
generating station to the existing on-site substations on the southeast of
the site. For most of the route, the cables will either be run underground
(either in new and existing ducting and excavations) or be supported off
existing structures. There will potentially be a cable bridge constructed,
due to restricted space to run cables underground, at the southern end of
the electrical connection between the two on-site existing substations. If
required, this cable bridge will be consistent with the other cable bridges
on the wider steelworks site and be constructed of a metal lattice structure
approximately 5m in height (to provide suitable clearance) and
approximately 800m in length;
modifications to the two existing on-site substations to accept the electrical
connection including the installation of new 66kV bays at each substation;
security infrastructure, including perimeter fencing and site lighting
infrastructure;
connections to the existing internal road layout for the provision of site
vehicular access(es), roads, pedestrian network, parking and cycle
storage;
temporary construction compounds; and
connection to site drainage systems.
3.2.2 Smaller standalone buildings and structures are also included within the
proposed development. These include tanks, pump house for cooling water
pumps for the cooling towers, booster house for process gases supply to the
boilers, switch gear housing, electrical control room for cooling towers and for
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 22
the power station. There is also a motor control centre building housing
electrical drives, computer system and an operator’s control centre.
3.2.3 The following table provides the physical dimensions of the above
components:
Table 3.1: Summary of Project Description Components
Item Indicative & Maximum Dimensions
Stack(s) 80m high
Cooling Towers Up to 22m high x 160m long x 16m wide
Turbine Hall Up to 25m high x 55m long x 65m wide
Boiler House Up to 35m high (at apex) x 60m long x 65m wide
Electrical Connection 66kV cables, approximately 2.8km in length to be run underground, off existing above ground infrastructure, on a cable bridge or a combination
Switchgear Station Building
Up to 35m long x 55m Wide
3.2.4 On average, all the electricity produced by the on-site power generation
facilities would be utilised on-site. However, due to the cyclical nature of
electricity demand on-site (in line with current operations), excess electricity
may be exported to the Grid for short periods.
3.2.5 The proposed location of the main components of the proposed development
(i.e. the new turbine sets and two new boilers) is centred at National Grid
Reference (NGR) SS 77198 88433 with the electrical connection extending
2.8km south east to two onsite substations at with NGRs centred on SS 78263
86743 and SS 78505 86021 at the electrical connection termination point.
3.2.6 There is the potential for a two phase construction approach. Option 1 would
involve the full and complete construction of the proposed development.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 23
Option 2 would involve half the proposed development (one stack, one boiler
and associated turbine sets) being installed (Phase 1) with all foundation and
engineering being undertaken in that Phase. Phase 2 of Option 2 would
involve the second and complete installation of the second stack, boiler and
associated turbine sets. Phase 2 could occur up to 10 years after Phase 1.
Further details can be found in Chapter 3 Project Description of the ES.
3.2.7 The following sections of this statement provide more detail in relation to the
utilities connections within the proposed development.
3.3 Proposed Development: Project Detail
External Appearance
3.3.1 The external appearance of the proposed development would be subject to
requirements included within the DCO. It is anticipated and the exterior finish
of the proposed development would be consistent with other buildings within
the steelworks which are finished in grey with blue accents.
Landscaping
3.3.2 The community consultation identified a desire for the boundary of the site with
Harbour Way to be sensitively landscaped to soften the visual impact of the
proposed development. It is anticipated that the landscaping strategy would
include tree planting along the frontage with Harbour Way, and this would be
subject to approval by NPTCBC as a requirement of the DCO.
Access and Traffic Movement
3.3.3 All construction traffic would access the proposed development directly from
the existing junction from Harbour Way. No additional access would be
required to be constructed.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 24
3.3.4 Staff travel would be regulated by a Code of Construction Practice (CoCP)
which would be agreed with NPTCBC prior to the commissioning and
operational phase of the scheme.
Fuel
3.3.5 The proposed development would be predominantly fuelled by gases, which
are generated by the steel making processes, with imported Natural Gas being
used as a standby fuel to maintain minimum load on the boiler if and when
process gases are not available.
3.3.6 The proposed development would not entirely remove the requirement to flare
process gases but will significantly reduce it to create a positive impact.
Gas and Utilities
3.3.7 The gas, steam and utilities network pipes are integral to the proposed
development.
3.3.8 The pipe work would be an extension of the pipe work that is already in place
for the existing power generation facilities and the existing on site gas
distribution, steam and utilities network. Therefore, no significant additional
pipe work is required. The extension of individual existing utilities and fuel
pipe work would be up to 450m in length and contained within the Order
Limits.
3.3.9 Any such pipe work would form an integral part of the proposed development
and would be contained within the Order Limits.
Electrical Connection Cable Route
3.3.10 A 66kV electrical connection would be located adjacent to the proposed
development and within the Order Limits. This new 66kV cable would connect
the new switchgear building to the two existing on-site substation
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 25
approximately 2.8km to the southeast. The cables would either be run
underground (either in new and existing ducting and excavations) or be
supported off existing structures.
3.3.11 Where a new section of ducting is required, a trench would be excavated and
the new cables installed. This denotes a 12m corridor which is required to
take account of local ground conditions and existing infrastructure.
3.3.12 Such works would be carried out by hand/machine to install plastic ducts
which are then backfilled with sand and cable tiles placed on top.
Cooling Method
3.3.13 The proposed cooling system would be an open circuit (i.e. water used in the
turbine condensers is cooled in cooling towers and recycled back into the
system), whereas the current cooling system operates as a once through feed
and return system (i.e. the cooling water is abstracted from the Port Talbot
Dock, goes through the turbine condensers and is then returned directly to the
Port Talbot Dock). The new proposed system would therefore no longer
require the current volume of abstraction from, and discharge to, the Port
Talbot Dock.
3.3.14 The volumes of water required for operation of the proposed development
would be significantly less than the present system of continually abstracting
and discharging water for the turbine condenser cooling operations. There
would, however, be an additional abstraction requirement from the River Afan
on top of the current average abstraction rate. Stresses placed on the River
Afan would be managed by utilising a proposed abstraction hierarchy,
whereby the River Afan would be the primary abstraction source, followed by
two secondary sources; the Nant Ffrwdwyllt and the Port Talbot Dock.
3.3.15 An alert system would be agreed with Natural Resources Wales (NRW) for the
implementation of the proposed abstraction hierarchy. This would involve
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 26
NRW informing the Applicant of times when low flow / no flow is expected and
when NRW have concerns about this impacting upon salmon migration. This
would be enforced so that the Applicant can switch abstraction to the
secondary back up sources. All abstractions would be made through existing
infrastructure and no new abstraction points are proposed.
3.3.16 Due to the close proximity of the proposed development to Harbour Way, the
cooling towers will be designed to mitigate any potential visibility issues
associated with the release of a water vapour plume. This would be confirmed
as part of the detailed design process.
3.3.17 An additional condensate tank and additional condensate polishing unit are
included as part of the proposed development within the Order Limits. No net
additional de-mineralisation capacity is required given decommissioning of the
four boilers within the Port Talbot Site. However, some refurbishment of the
existing de-mineralisation plant may be required.
3.3.18 Further details on abstractions and discharges, including volumes associated
with the cooling method are outlined in ES Chapter 14 (Surface Water
Environment).
Drainage System
3.3.19 Surface waters from the plant roofs, impermeable hardstanding (including car
park and roads), and external areas of gravel and landscaping would be
collected within surface water drains and discharged via the W2 discharge
point to the Arnalt Culvert. During storm events surface water would
discharge via W3 to Swansea Bay. Some surface waters would also flow via
lateral ditches and attenuation ponds into nearby watercourses / bodies.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 27
Emissions to Air
3.3.20 Up to two new stacks would be installed as part of the proposed development.
These would be no higher than 80m.
3.3.21 Combustion gas released to air will be discharged from the stack(s).
Emissions to Land
3.3.22 There would be no emissions to land from the plant.
Noise Emissions
3.3.23 Noise impacts would be adequately mitigated through building design and
controlled by the Environmental Permit.
Waste and Fugitive Emissions
3.3.24 Waste generation during operation would be minimal, resulting mainly from
maintenance activities. Low volume waste streams are likely to comprise:
oily rags and residues from oily water separators and minor oil spills;
spent turbine inlet filter elements;
washing effluent;
packaging and other general maintenance waste; and
office waste.
3.3.25 Waste would either be recycled using the onsite recycling facilities or where
this is not possible be disposed of in the on-site landfill.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 28
Proximity to Community & Health and Safety
3.3.26 The location of the proposed development in relation to nearby dwellings is a
key design factor not only from an amenity aspect but also health and safety.
The ES assesses residential amenity from nearby dwellings and also
incorporates details on health and safety considerations such as release of
gases and emergency situations.
Hours of Operation and Shift Pattern
3.3.27 The proposed development would have continuous operation throughout its
lifecycle except for planned maintenance. It is assumed that it would be
operational for approximately 8716.2 hours a year or approximately 99.5%
available.
3.3.28 Two shift patterns operate on site consisting of 12 hour shifts which are
rotated on a daily basis. This would continue in connection with the operation
of the proposed development.
Lighting
3.3.29 It is proposed that ancillary and security lighting would be provided on the
main buildings and in the small car park area of the proposed development.
The Civil Aviation Authority (CAA) has provided guidance that aviation lighting
may be required for the stack(s) if the stacks are over 80m in height.
Temporary Construction Buildings & Infrastructure
3.3.30 Temporary construction compounds would be required. These would be
located within the Order Limits and will comprise a number of modular
buildings. Buildings will be used for site offices and will provide staff welfare
facilities. There will also be a storage area for small plant and equipment,
materials and waste layout areas and a construction staff car park area.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 29
3.4 Proposed Development: Decommissioning of Existing Equipment
3.4.1 Three turbo alternators (TAB1, TA2 and TA3 (nominally 7 to 8 MWe each)),
four steam boilers (Service Boilers 4 and 5, Boiler 5 (Margam A) and Mitchell
Boiler (Margam B)) and three stacks will be decommissioned. The
decommissioning of this equipment (which is located at various positions
throughout the steelworks site) will take place once the proposed development
is fully commissioned and in reliable and continuous operation in order to
maintain a continuous power supply.
3.4.2 The three turbo alternators and four steam boilers to be decommissioned are
contained within existing buildings and there is no intention to demolish the
buildings. Three existing stacks will also be decommissioned and left in situ.
The buildings and stacks have been constructed as integral parts of other
operational buildings within the steelworks site, and as such, demolition of
these components in isolation would be unachievable. Once these facilities
have been decommissioned, however, future re-use is too costly to be
feasible. Should any demolition works be required, this will be subject to
receiving the prior planning consent from NPTCBC.
3.5 Proposed Development: Construction
3.5.1 Two construction scenarios are proposed for the development. These are
known as Option 1 and Option 2, and both have been assessed as part of the
EIA undertaken in connection with the proposed development. The proposed
construction and operational phasing for each option is outlined below.
Option 1
3.5.2 Option 1 represents the full single installation of the proposed development
and involves installation and construction of the boilers and their associated
stacks, the turbine sets and the full installation of the electrical connection to
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 30
the existing on-site substations in one single Phase of construction. All
smaller standalone buildings and structures would also be included within the
full single-phase installation of the proposed development.
3.5.3 This construction phase would be 36 months with a commissioning phase
lasting for a 6 month period within this timeframe. Delivery routes for
construction traffic will be via Junction 38 of the M4 and then via Harbour Way
directly to the proposed development through the existing Harbour Way
junction.
3.5.4 The proposed decommissioning of the existing 4 boilers and 3 turbo
alternators would be undertaken once the new equipment is in continuous
reliable operation.
Table 3.2: Summary of Project Description Components for Single Phased Build (Option 1)
Item Indicative & Maximum Dimensions
Stack(s) Up to two stacks, both at 80m high
Cooling Tower Units Up to 22m high x 160m long x 16m wide
Turbine Hall Up to 25m high x 55m long x 65m wide
Boiler House Up to 35m high (at apex) x 60m long x 65m wide
Electrical Connection 66kV cables, approximately 2.8km in length to be run underground, off existing above ground infrastructure, on a cable bridge or a combination of both
Switchgear Station Building
Up to 35m long x 55m Wide
Option 2
3.5.5 This is an alternative scenario where the proposed development components
(boiler and turbine sets) are installed in two phases - (i.e. one boiler and one
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 31
stack at a time with corresponding turbine sets). The first installation (Phase
1) would be after development consent is granted and the second installation
(Phase 2) at a later stage (which could be up to 10 years after the
commencement of development on Phase 1).
Phase 1
3.5.6 Construction timescales would be 36 months for first installation (as per Option
1). The full building footprint of the switchgear station would be built but only
sufficient building envelopes to house one boiler, and the corresponding stack
and turbine sets would be constructed in the first phase of the installation. The
ground would also be fully prepared for the second boiler and remainder of the
turbine house (for example utility connections and ground works including
creation of the building slab footprint) but with no above ground structures
being installed. The electrical connection would still be fully installed as per
Option 1.
3.5.7 Around 50% of the total cooling tower unit(s) infrastructure would be
constructed in Phase 1.
3.5.8 Construction workforce would be the same for Phase 1 of Option 2 as it would
be for Option 1 (500 over the whole construction period and 300 at peak). The
same delivery routes would be used as per Option 1 (Junction 38 of the M4
and onto Harbour Way).
3.5.9 During the interim period between Phase 1 and Phase 2, the existing power
generation equipment would remain operational and would only be
decommissioned once Phase 2 is complete and is in reliable continuous
operation. Therefore the existing emissions to air, and water abstractions and
discharges from the existing generating facilities would still occur during this
interim period.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 32
3.5.10 The flared gas, however, would be significantly reduced as per Option 1 as the
first boiler (installed during Phase 1) would take the process gas which
otherwise would be flared – therefore there would be immediate improvements
as per Option 1.
Phase 2
3.5.11 Construction timescales would be an additional 24 months for the second
phase of installation. This will commence within 10 years of the
commencement of development of Phase 1.
3.5.12 In Phase 2, the above ground structures of the remaining turbine housing and
second boiler housing would be constructed immediately alongside the
existing boiler and turbine house. In order to minimise noise impact of the
operating turbine sets, the external wall installed at Phase 1 (which would in
effect become an internal wall), would not be removed until all the final
installation is complete. This wall would only consist of the external waterproof
cladding and appropriate insulation, hence, no demolition of brickwork would
be required and the dust could be controlled through existing best practice
methods as it would be contained within the new building envelope. The boiler
and the turbine housings would be built / extended to incorporate the second
boiler and turbine sets up to the dimensions outlined in Option 1.
3.5.13 The remaining cooling tower unit(s) would be constructed during the second
installation.
3.5.14 The second stack would only be installed at Phase 2 when the second boiler
unit is constructed. At the appropriate time, the second boiler would then take
on the capacity of the existing boiler units being decommissioned.
3.5.15 Construction workforce would be similar to the first installation phase (500
over the whole construction period and 300 at peak) but over a shorter
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 33
construction period of 24 months. There would be no change in operational
workforce.
3.5.16 The same delivery routes would be used as per Option 1. It is assumed that
the second turbine and boiler building would be to the north of the first
installation. The temporary laydown area would remain the same for both
installations.
3.5.17 The ES Chapter 3 Project Description incorporates a construction timetable for
each option and a summary of the components to be delivered under each
phase is provided below.
3.5.18 It is assumed the 35 years life cycle of the proposed development will start
from the completion of Phase 1.
Table 3.3: Summary of Project Description Components for Phased Build (Option 2)
Item Phase 1 Phase 2
Stack(s) One 80m stack One 80m stack
Cooling Tower Units Up to 22m high x 80m long x 16m wide
Up to 22m high x 160m long (to take structure to maximum length as in option 1 ) x 16m wide
Turbine Hall Up to 25m high x 55m long x 45 wide
Up to 25m high x 55m long x 65m wide as in option 1
Boiler House Up to 35m high (at apex) x 60m long x 45m wide
Up to 35m high (at apex) x 60m long x 65m wide as in option 1
Electrical Connection
66kV cables, approximately 2.8km in length to be run underground, off existing above ground infrastructure, on a cable bridge or a combination of above.
Switchgear Station Building
Up to 35m long x 55m wide (to be installed as part of first installation)
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 34
Proposed Development Decommissioning Phase
3.5.19 At the end of the 35 year indicative operational lifespan of the proposed
development, a number of options would exist:
The proposed development would be decommissioned;
An application would be made to extend the life of the proposed
development using existing equipment; or
An application would be made to replace the existing equipment and to
refurbish the proposed development for continuing power and steam
generation.
3.5.20 Decommissioning would involve shutting off and isolating electrical and utility
connections and switching off the mechanical and plant equipment, including
the boilers and turbines. It is likely that the main power generation equipment
and electrical connection would remain in situ but electrically decommissioned.
The stack(s) would remain in situ but would be closed off to disable their
potential for future emissions.
3.5.21 It is not anticipated that the new power generation building would be
demolished. Smaller ancillary buildings may be removed subject to receiving
necessary consent from NPTCBC (if required) but this is unlikely.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 35
4 Planning Policy Context
4.1 Preface
4.1.1 The planning policy applicable to the proposed development exists at a
number of levels and extends to a range of guiding documents.
4.1.2 To highlight the proposed development’s potential, the following sections
record the main provisions of the principal statutory planning documents and
strategies of relevance. It establishes the context within which any proposed
development would need to be brought forward.
4.1.3 This section looks at existing policy at the national level, before moving on to
consider adopted planning policy at the local level.
4.1.4 National guidance comprises the relevant National Planning Policy Statements
(NPS), Planning Policy Wales Edition 6 (PPW) (February 2014), as well as a
range of supplementary Technical Advice Notes (TANs). At the local level, the
Neath Port Talbot Unitary Development Plan (NPTUDP) (March 2008)
constitutes the statutory development plan against which the proposed
development will be assessed, alongside the emerging Local Development
Plan (LDP). Policies of relevance in terms of both the national and local
context are set out below.
4.1.5 The NPSs comprise the principal level of planning policy that is applicable to
the consideration of DCO applications. Accordingly, whilst PPW, the TANs,
the NPTUDP, and the emerging LDP form material considerations, the NPSs
are considered to be the most important policy to the decision-making process
and have been assessed in detail in the following section of this statement.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 36
4.2 National Planning Policy
National Planning Policy Statements
4.2.1 The PA 2008 requires that any DCO application is decided in accordance with
any relevant national policy statement, with certain exceptions. For this
proposed development, the relevant national policies contained within those
NPSs are outlined below:
NPS for Energy (EN – 1) (July 2011) – The overarching NPS relevant to the proposed development;
NPS for Fossil Fuel Electricity Generating Infrastructure (EN – 2);
NPS for Gas Supply Infrastructure and Gas and Oil Pipelines (EN – 4);
and
NPS for Electricity Networks Infrastructure (EN – 5).
4.2.2 The overarching NPS for Energy (EN-1), published by The Department for
Energy and Climate Change (DECC) in July 2011, provides the principal
planning policy context of relevance to the proposed development, but
consideration is also be given to the provisions of NPSs EN-2, EN-4, and EN-5
where applicable in the context of the proposed development.
4.2.3 NPS EN-1 sets out the UK Government’s policy for delivery of major new
energy infrastructure in England and Wales. The policies within EN-1 reflect
the UK Low Carbon Transition Plan (DECC, 2008) which sets out a detailed
low carbon transition plan to 2020. Underlying the Government’s climate
change strategy is a legally binding target of cutting emissions by 80% by
2050 compared to 1990 levels, set in legislation by the Climate Change Act
2008. The Government’s five steps to meet this target are:
1. Protecting the public from immediate risk;
2. Preparing for the future;
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 37
3. Limiting the severity of future climate change through a new
international agreement;
4. Building a low carbon UK including: cutting emissions, maintaining
secure energy supplies, maximising economic opportunities, and
protecting the most vulnerable; and
5. Supporting individuals, communities, and businesses to play their
part.
4.2.4 NPS EN-1 establishes a significant need for new major energy infrastructure
over the next 10-15 years delivered through a diverse mix of energy
generating technologies. Under Section 3.1 EN-1 states that:
“It is for industry to propose new energy infrastructure projects within
the strategic framework set by Government. The Government does not
consider it appropriate for planning policy to set targets for or limits on
different technologies.
The IPC should therefore assess all applications for development
consent for the types of infrastructure covered by the energy NPSs on
the basis that the Government has demonstrated that there is a need
for those types of infrastructure…”
4.2.5 In taking its decision on the DCO application, the SoS is required to have
regard to ‘any national policy statement which has effect in relation to
development of the description to which the application relates’ (Planning Act
2008, s104(2))(a)). The SoS must also, in accordance with s104(3), decide
the application in accordance with any relevant national policy statement,
unless certain limited exceptions apply. As such, the NPSs, principally EN-1
but also (where applicable) EN-2, EN-4 and EN-5, provide the primary basis
for decisions by the SoS. However, it is highly likely that in relation to NSIPs
the SoS will also regard Welsh policy as being both important and relevant to
his decision (s104(2)(d)).
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 38
4.2.6 A detailed assessment of the proposed development against the provisions of
the relevant NPSs is set out in the next chapter of this statement.
Planning Policy Wales
4.2.7 The Welsh Government (WG) issued the sixth edition of Planning Policy
Wales (PPW) in February 2014. The updated document incorporates
amendments to strengthen and clarify the presumption in favour of economic
development in-line with the release of TAN 23 (Planning for Economic
Development), and a revised Chapter 12 in relation to ‘planning to manage
waste’ and ‘renewable and low carbon energy’.
4.2.8 PPW sets out the land use planning policies of the WG and translates the
WG’s commitment to sustainable development into the planning system. It is
supplemented by a series of TANs, with procedural advice given in circulars
and policy clarification letters – together, these comprise national planning
policy for Wales. PPW and the Wales Spatial Plan are required to be taken
into account in the preparation of development plans and may be material to
decisions on individual planning applications. They are taken into account by
the Welsh Ministers and Planning Inspectors in the determination of called-in
planning applications and appeals.
4.2.9 Chapter 7 of PPW defines the WG’s objectives for the delivery of economic
development through the planning system. Para 7.1.3 states:
“The planning system should support economic and employment
growth alongside social and environmental considerations within the
context of sustainable development.”
4.2.10 The guidance seeks to ensure that economic development is encouraged and
advises Local Authorities to support the shift towards a low carbon economy.
PPW states that Local Planning Authorities should:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 39
“look favourably on proposals for new on-site low carbon energy
generation (para 7.4.1); adopt a positive and constructive approach to
applications for economic development (para 7.6.1); take account of the
likely economic benefits of the development [when determining planning
applications] based on robust evidence” (para 7.6.1).
4.2.11 Chapter 12 of PPW sets out the WG’s policy for delivering infrastructure and
services across Wales. One of the key aims of this national policy is to:
“Promote the generation and use of energy from renewable and low
carbon energy sources at all scales and promote energy efficiency,
especially as a means to secure zero or low carbon developments and
to tackle the causes of climate change.”
4.2.12 This guidance also confirms the WG’s commitment to achieving the UK target
of 15% of energy from renewables by 2020 by specifically stating:
“The Welsh Government is committed to playing its part by delivering
an energy programme which contributes to reducing carbon emissions
as part of our approach to tackling climate change whilst enhancing the
economic, social and environmental wellbeing of the people and
communities of Wales in order to achieve a better quality of life for our
own and future generations. This is outlined in the Welsh
Government’s Energy Policy Statement Energy Wales: A Low Carbon
Transition (2012).”
Technical Advice Notes
4.2.13 As set out above, PPW is supplemented by a series of Technical Advice Notes
(TANs). A range of these apply to the proposed development, and their
specific provisions are addressed through the technical reports and ES
submitted in support of this DCO Application. Relevant TANs include:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 40
Technical Advice Note 5 (Nature Conservation and Planning), published in 2009, provides advice on the procedure that LPAs should
follow to protect designated nature conservation sites and conserve the
natural environment.
Technical Advice Note 8 (Renewable Energy) was published in July
2005 and provides technical advice in relation to renewable energy. This
TAN relates to land use planning considerations of renewable energy,
however, UK and national energy policy provide its context.
Technical Advice Note 11 (Noise) was published in October 1997 and
provides advice on how the planning system can be used to minimise the
adverse impact of noise without placing unreasonable restrictions on
development or adding unduly to costs and administrative burdens of
business.
Technical Advice Note 12 (Design) was published in June 2009 and has
been amended in 2014. It provides detailed advice on how good design in
development may be facilitated by the planning system. The guidance
states that good design has the potential to assist in environmental
sustainability, economic growth and social inclusion.
Technical Advice Note 14 (Coastal Planning) was published in 1998
and recognises that on-shore development can often have an impact off-
shore. This TAN outlines the specific planning considerations that will
relate to a coastline location.
Technical Advice Note 15 (Development and Flood Risk) was
published in July 2004 and advises on development and flood risk as this
relates to sustainability principles, and provides a framework within which
risks arising from both river and coastal flooding, and from additional run-
off from development in any location, can be assessed.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 41
Technical Advice Note 18 (Transport) was published in 2007 and
recognises the key role of the planning system to facilitate sustainable
travel patterns. As in TAN 12, the guidance aims to influence the location
of new development to reduce the need to travel and subsequently
promote more sustainable forms of transport which contribute to
environmental improvement in the longer term.
Technical Advice Note 21 (Waste) was introduced in 2014 and provides
advice on how land use planning should contribute towards sustainable
waste management and resources efficiency, reflecting the new waste
management drivers at a European Union and Wales Level.
Technical Advice Note 23 (Economic Development), was published in
February 2014 and focuses on the need to encourage development in
order to generate wealth, jobs and income. This TAN recognises the
importance of all aspects of development and that planning decisions are
made in a sustainable way which balance social, environmental and
economic considerations.
The Wales Spatial Plan (2008)
4.2.14 The purpose of the Wales Spatial Plan is to ensure that what is done in the
public, private and third sectors in Wales is integrated and sustainable, and
that actions within an area support each other and jointly move towards a
shared vision for Wales and for the different parts of Wales. The Spatial Plan
area which the proposed development falls under is South East Wales ‘Capital
Region’.
4.2.15 It is a principle of the Wales Spatial Plan that development should be
sustainable. Sustainable development is about improving wellbeing and
quality of life by integrating social, economic and environmental objectives in
the context of more efficient use of natural resources. The Wales Spatial Plan
aims to deliver sustainable development through its Area Strategies in the
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 42
context of the Welsh Assembly Government’s statutory Sustainable
Development Scheme.
4.2.16 Chapter 11 if the Plan refers to ‘promoting a sustainable economy’ and
recognises that the economy in Wales has a spatial dimension. Paragraph
11.6 states that “we must take a joint approach with local authorities, travel
consortia, and others to tackling regional infrastructure problems on issues of
housing, transport, water, sewerage, energy, waste and ICT.”
Environment Strategy for Wales (2006)
4.2.17 The Environment Strategy for Wales outlines the Welsh Government’s long
term strategy for the environment of Wales, setting out the strategic direction
for the next 20 years.
4.2.18 The purpose of the Strategy is to provide a framework within which to achieve
an environment that is clean, healthy, biologically diverse and valued by the
people of Wales.
4.2.19 The Welsh Government wishes to see the Welsh environment thriving and
contributing to the economic and social well-being and health of all of the
people of Wales. The Environment Strategy is currently being reviewed by the
Welsh Government to ensure that it reflects the relevant commitments in the
Natural Resource Management Programme.
4.3 The Development Plan
Introduction
4.3.1 The site lies within the administrative area of NPTCBC. The statutory
development plan for the site, in accordance with Section 38 of the Planning
and Compulsory Purchase Act 2004, is the Neath Port Talbot Unitary
Development Plan (NPTUDP). This was formally adopted in March 2008.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 43
4.3.2 The Council is currently in the process of preparing its Local Development
Plan (LDP) which once adopted will replace the existing UDP. The LDP will
contain land use allocations and policies for future development in Neath Port
Talbot for the period up to 2026. The LDP preparation process commenced in
2007 and the Deposit LDP was published for public consultation from 28th
August 2013 to 15th October 2013. Following this period, the ‘Register of
Alternatives Sites’ was published in January 2014 for a six week consultation
period (closing 10th March 2014). It is anticipated that the LDP will be
adopted in November 2015.
Neath Port Talbot Unitary Development Plan (Adopted March 2008)
4.3.3 The NPTUDP was adopted on 26th March 2008 and comprises a range of
policies against which all planning applications are considered. These include
the plan’s development strategy and its policies on environment, economy and
employment, community and social considerations, transport, infrastructure
and energy, and waste. For clarity, this statement considers in detail only the
policies central to the development proposals subject to this DCO application.
4.3.4 The Community Plan sets out the vision for Neath Port Talbot that by 2012 its
communities will be:
healthier, more prosperous, attractive and welcoming;
able to offer an increasingly skilled and qualified workforce;
able to offer a better quality of life; and
able to offer a wider range of facilities, services and jobs within easy
travelling distance.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 44
Strategic Policies
4.3.5 The strategic policies within Part 1 of the UDP reflect the key objectives of the
Council. The plan seeks to guide development to locations that will minimise
the need to travel promoting good design and preservation of the County
Borough’s natural and historic resources. These strategic objectives inform
and underpin the UDP’s detailed policies. A list of the strategic policies
relevant to the consideration of the proposed development is included below
for ease of reference.
Environment
Policy 1 – Countryside, Seascapes & Landscapes
Policy 2 – Wildlife & Habitats
Policy 4 – Pollution
Policy 5 – Built Environment
Policy 6 – Historic Environment
Economy & Employment
Policy 8 – Employment
Policy 9 – Diversification & Strengthening of the Local Economy
Policy 10 – Expansion of Existing Enterprises
Community & Social Considerations
Policy 11 – Social Needs
Transport
Policy 13 – Sustainable Communities
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 45
Policy 14 – Highway Considerations
Policy 18 – Efficient Use of Infrastructure & Resources
Policy 19 – Opportunities to Create Renewable Energy
Waste
Policy 24 – Minimise the Creation of Waste
Policy 26 – Collection, Treatment or Disposal of Waste
4.3.6 Overall, the strategic policies of the UDP seek to support the economy,
encourage sustainable patterns of development and preserve the natural and
historic resource. The proposed development is considered to accord with
these strategic policy principles and objectives and the ES demonstrates that
all technical policy requirements can be met. The development would ensure
that a sustainable steel industry is maintained at the Port Talbot site, creating
direct and indirect positive effects to the local economy during construction
and operation.
Site Specific Policy
4.3.7 The Port Talbot Steelworks complex is not subject to any specific land use
allocation and lies outside the defined settlement boundary for Port Talbot. In
this light, the proposed development is assessed against the generic policies
of the NPTUDP (including inter alia those relating to contaminated and
previously developed land, design, air quality, noise, flood risk, nature
conservation, landscape, and archaeology).
4.3.8 In the absence of any specific land use designation, the principle of the
proposed development will be assessed against Policy EC2, which seeks to
support the redevelopment, intensification and expansion of existing industrial
premises subject to their impact on local amenities, existing industrial and
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 46
commercial activities, townscape, landscape, biodiversity or highway safety.
The proposed development will also be assessed against Policy IE2, which
seeks to ensure that proposals for new infrastructure have taken account of
potential alternative options (including the reuse of existing facilities), and
given careful consideration to location and design to minimise any detrimental
impact.
4.3.9 In relation to nearby allocations, the site subject to this DCO Application lies at
the northern end of the Port Talbot complex to the east of land identified as the
route for the Port Talbot Distributor Road (Policy T8(a)), and to the west of
land allocated for mixed use redevelopment as part of the Port Talbot
Harbourside Regeneration Area (under policies PT1, EC1/4 and H1/33).
Technical Planning Policies
4.3.10 In addition to the above named policies, we outline below the technical and
detailed UDP policies that are relevant to this DCO Application.
Policy GC1 New Buildings/Structures & Changes of Use
Policy GC2 Engineering Works & Operations
Policy ENV3 Impacts on the Landscape
Policy ENV4 International & National sites for Nature Conservation
Policy ENV5 Nature Conservation
Policy ENV10 Coastal Protection
Policy ENV11 Proposals in Areas of Flood Risk
Policy ENV12 Proposals Affecting Water Resources
Policy ENV15 Air Quality
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 47
Policy ENV16 Contaminated Land
Policy ENV17 Design
Policy ENV19 Proposals Affecting the Setting of a Listed Building
Policy ENV22 Archaeological Remains
Policy ENV23 Archaeological Evaluation
Policy ENV24 Archaeological Recording
Policy ENV26 External Lighting
Policy ENV28 Polluting or Hazardous Installations
Policy ENV29 Environmental Quality & Amenity
Policy EC2 Extensions to Industrial/Business Premises
Policy T1 Location, Layout & Accessibility of New Proposals
Policy T3 Public Transport Quality Corridors
Policy T11 Traffic Management
Policy IE1 Existing & Programmed Infrastructure
Policy IE2 Infrastructure Facilities (Not Including Drainage
Policy IE3 Main Sewage Treatment
Policy IE6 Renewable Energy
Policy W6 Recycling of Industrial Waste
Policy PT1 Regeneration Initiative
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 48
Supplementary Planning Guidance
4.3.11 A range of adopted Supplementary Planning Guidance (SPG) documents
provide further detailed guidance on, and facilitate the implementation of, the
adopted UDP policies. The SPGs of relevance to this DCO Application are as
follows:
Biodiversity (July 2008) – This expands on Policies ENV4 and ENV5 of
the UDP to clarify how they will be applied. It is aimed at helping to
ensure that biodiversity is appropriately considered, protected and
enhanced within any proposed development.
Landscape (July 2008) – This document expands on Policies ENV2,
ENV3 and GC1 of the UDP. It explains the application of national
guidance in a Neath Port Talbot context, provides an introduction to the
general principles and practice of landscape, heritage protection and
enhancement within the planning process, and provides a strategic good
practice guide for development.
Emerging Planning Policy: Local Development Plan
4.3.12 The Planning and Compulsory Purchase Act 2004 introduced the requirement
for all local planning authorities to produce a new form of development plan for
their areas – a Local Development Plan.
4.3.13 The NPTUDP will remain the adopted development plan until it is superseded
by the LDP, which is scheduled for adoption in 2015. Until it is formally
adopted, and its soundness has been tested at Examination, the Deposit LDP
carries limited weight for development management purposes.
Emerging Neath Port Talbot Local Development Plan (Deposit, August 2013)
4.3.14 In terms of emerging planning policy, the NPTLDP was placed on Deposit on
28th August 2013 for a period of consultation until the 15th October 2013. The
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 49
consultation has now closed and, on the 27th January 2014, the Council
commenced its consultation on the ‘Alternative Sites’ submitted as part of the
Deposit consultation. The consultation ran until 10th March 2014. Having had
regard to the representation received following the respective consultations,
along with the consideration of new information that has emerged following the
Council’s decision to place the LDP of ‘deposit’, the Council considered and
agreed its response to the representation received. Accordingly, Full Council
met on the 23rd July 2014 to consider the officer responses and
recommendations, together with the proposed focussed changes to the
deposit plan contained with the report to the Committee. At this meeting Full
Council endorsed the responses and focussed changes. The Council will now
run a six week consultation period on these changes and responses, which is
set to commence on the 2nd September and will close on the 13th October.
4.3.15 Following this, the Council will submit the NPTLDP along with a variety of
accompanying documents to the Welsh Government (WG) and Planning
Inspectorate for examination. The Council anticipate that this will take place
on the 29th September 2014.
4.3.16 The NPTLDP is intended to provide a more concise and evidence-based set of
development policies that will replace the current NPTUDP. It will set the
objectives and policies for the development and use of land in the County
Borough up to 2026. As one of its key strategic policy objectives, the LDP
seeks to address the causes and consequences of climate change including
the promotion of renewable and low carbon energy sources. The plan
recognises Tata Steel as one of the major employers with the County Borough
and seeks to safeguard and support existing employment uses. The Port
Talbot Steelworks complex lies within the Coastal Corridor Strategy Area, but
outside the defined settlement limit of Port Talbot.
4.3.17 As the NPTLDP has yet to be subject to formal Examination, it can only be
given limited weight as a material consideration. However, these emerging
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 50
policies have been considered as context to the proposed development and
the assessment of its impact as set out in the ES.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 51
5 Planning Assessment
5.1 Introduction
5.1.1 The Government issued a number of National Policy Statements (NPSs) in
accordance with the provisions of the PA 2008. These statements form the
primary policy context for the assessment of DCO applications and include the
Government’s objectives for the development of nationally significant
infrastructure, and include any policies or circumstances that Ministers consider
should be taken into account in decisions on nationally significant infrastructure
development. Accordingly, applications for a DCO must be determined in
accordance with the relevant NPSs.
5.1.2 The determination process for DCO applications is controlled by The Planning
Inspectorate (PINS) who examine the applications for nationally significant
infrastructure and then make a recommendation to the SoS as to whether
consent should be granted.
5.1.3 There are six NPSs which apply to the ‘energy sector’. Four of these
statements are applicable to this DCO Application and have been considered
during the preparation of this Application (see paragraph 4.2.1).
5.1.4 The PA 2008 does not require the Development Plan for Neath Port Talbot to
be applied as it would be if this were an application under the Town and
Country Planning Act. However, Section 104(2) of the PA 2008 allows the SoS
to have regard to any matters which it thinks are both important and relevant to
its decision. Under Section 60(2) of the PA 2008, PINS will invite relevant local
authorities (i.e. the host local authority for the proposed development plus all
neighbouring local authorities) to submit Local Impact Reports (LIRs) to inform
examination of the DCO application. Section 60(3) of the PA 2008 confirms that
a LIR is a report giving details of the likely impact of the proposed development
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 52
on the relevant local authority’s area, to which consideration must be given by
PINS.
5.1.5 In view of this, this section of the Planning Statement will also consider the
other relevant planning policy documents (at a national and local level) which
are considered to be likely to inform the LIRs that will be submitted to PINS by
the host and neighbouring local authorities.
5.2 NPS 1 – Overarching National Policy Statement for Energy (NPS EN-1)
5.2.1 This NPS is the overarching statement which is applicable to all types of new
energy infrastructure and sets out how the impacts of energy infrastructure
development in general are to be assessed.
5.2.2 Part 4 of NPS EN-1 sets out the general policies against which applications
relating to energy infrastructure are to be decided, whilst Part 5 of NPS EN-1
references generic impacts associated with such proposals. This section of this
statement seeks to assess the proposed development having regard to the
relevant headings set out under Parts 4 & 5 of NPS EN-1.
Assessment Principles
Environmental Statement (NPS EN-1, 4.2)
5.2.3 The Council Directive of the 27th June 1985 on the assessment of the effects of
certain public and private projects on the environment (amended by Directives
97/11/EC, 2003/35/EC, 2009/31/EC and a codified Directive 2011/92/EU) states
that all proposals which are subject to the European Environmental Impact
Assessment Directive must be accompanied by an ES describing the aspects of
the environment likely to be positively and negatively affected by the proposed
development at all stages. Measures for avoiding or mitigating significant
adverse effects must also be included.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 53
5.2.4 The Directive is implemented principally by the Town and Country Planning
(Environmental Impact Assessment) Regulations 2011. However, since the
original implementation of the Directive a wide range of project-specific
Regulations have been developed.
5.2.5 The Infrastructure Planning (Environmental Impact Assessment) Regulations
2009 (as amended) (the EIA Regulations) apply in the case of applications
under the PA 2008. Accordingly, this DCO Application is accompanied by an
ES (Document Reference 6.01), which reports the conclusions of an
Environmental Impact Assessment (EIA) which assessed the likely significant
environmental, social and economic effects that may arise during the various
stages of the proposed development.
5.2.6 A Scoping Report was submitted to the SoS on the 25th September 2013 as
part of a request for an opinion on the scope of the assessment in the ES.
PINS responded on the 5th November 2013 enclosing their Scoping Opinion
having undertaken a consultation exercise with prescribed consultation bodies
and other interested parties, taken account of the received responses, and
taken account of the specific characteristics of the project.
5.2.7 The main steps followed in the EIA were as follows:
Baseline surveys have been undertaken in order to identify and describe
the environmental character of the area potentially affected by the
proposed development. This information was provided to the scheme
designers at the earliest opportunity;
Relevant natural and manmade processes that may change the character
of the site were identified;
Consideration was then given to the possible interactions between the
proposed development and both existing and future site conditions. These
interactions or impacts have been assessed using set criteria based on
accepted guidance and good practice;
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 54
The likely significant environmental effects, both direct and indirect, have
been established as a result of the proposed development;
Recommendations have been made to avoid, minimise or mitigate adverse
effects and enhance positive effects. The proposed development was then
reassessed talking account of the proposed mitigation and the residual
significance of likely environmental impacts assessed; and
Following statutory consultation, the results of the EIA in combination with
the responses to the Preliminary Environmental Impact Report (PEIR) are
set out in the ES.
Habitats & Species Regulations – Impact upon European Site (NPS EN-1, 4.3)
5.2.8 Paragraph 4.3.1 of NPS EN-1 discusses the need for PINS to consider whether
the proposed development may have a significant effect on a European site, or
on any site to which the same protection is applied as a matter of policy, either
alone or in combination with other plans or projects. Accordingly, prior to
granting a DCO, PINS must review the proposed development in the context of
the Conservation Habitats and Species Regulations 2010 (SI 2010/490).
5.2.9 A desk study (Chapter 6 (Ecology) of the ES) was undertaken to identify
designated sites within close proximity to the proposed development site. This
confirmed that there are no statutory internationally or nationally designated
nature conservation sites within a 1km radius of the proposed development site.
However, there are eleven Sites of Special Scientific Interest (SSSI), three
Special Areas of Conservation (SACs), one Ramsar and two National Nature
Reserves (NNR) within 10km of the proposed development site, designated for
their habitats, bird and plant assemblages. The ES provides further details on
these designations.
5.2.10 It should be noted that there are no designated sites within 10km of the
proposed development that have reference to or been designated for great
crested newts or other amphibian populations. In addition, there are no
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 55
designated sites within 10km of the proposed development that have reference
to or been designated for bats.
5.2.11 An Article 6 Test of Likely Significance (The Conservation (Natural Habitats)
Regulations 2010 (as amended)) is required for all the Natura 2000 sites within
a 30km buffer zone around the proposed development to ascertain if the
proposed development may have a Likely Significant Effect on the interest
features of the sites alone or in-combination with other plans/projects.
Accordingly, a Habitats Regulation Assessment (HRA) (Document Reference:
5.03) also contained within Volume 3, Appendix 6.6 of the ES) has been
undertaken paying due regard to the PINS guidance document: Advice Note
Ten: Habitats Regulations Assessment relevant to nationally significant
infrastructure projects (2013).
5.2.12 The HRA, in accordance with the Conservation (Natural Habitats, etc.)
Regulations 2010 (as amended), considers whether the proposed development
is likely to have a significant effect on a Natura 2000 Site. As part of this
assessment, consideration has been given to the effect of the proposed
development in isolation and in-combination with other plans or projects. The
HRA concluded that the proposed development would not result in any likely
significant effects on any Natura 2000 sites either alone or in-combination with
other proposals. In particular, the HRA concludes that the proposed
development would not have any likely significant effects on Natura 2000 Sites
as the acidifying and eutrophying emissions of the proposed development each
contribute to <1% of the relevant Critical Loads for the individual Qualifying
Features on each Natura 2000 Site.
5.2.13 NRW supports the conclusions of the HRA in relation to the proposed
development in isolation and agrees that there are no likely significant effects
which would require an Appropriate Assessment. NRW and the Applicant are
still in discussions as to HRA's conclusions on the in-combination effects of the
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 56
proposed development and therefore whether an Appropriate Assessment is
required.
Alternatives (NPS EN-1, 4.4)
5.2.14 Paragraph 4.4.1 of NPS EN-1 states that there is no general requirement to
consider alternatives to the proposed development or to establish whether the
proposed project represents the best option. However, it does indicate that the
main reasons for the choice of the project and information about the main
alternatives that have been considered should be included in the ES.
5.2.15 In order to improve the efficiency of the steelworks site and secure its long-term
viability, the Applicant has implemented a variety of projects to increase
productivity and cost effectiveness. Given the scale of the site, energy
efficiency is a key area for improvement and forms the basis of this DCO
Application.
5.2.16 In accordance with this assessment principle, a summary of the main
alternatives to the proposed development, which are covered in further detail in
Chapter 2 (Environmental Impact Assessment) of the ES, has been provided
below:
Do Nothing Scenario: The existing on-site equipment would eventually
reach a position of uneconomical repair with a resulting drop in electrical
generation capacity and an increase in process gas flare. This would
increase electricity imports from the grid, resulting in a significant cost
penalty to the business. The existing facility may also become obsolete
due to controls imposed by the Industrial Emission Directive (IED), which
requires adherence to emission limits for a range of pollutants. Emission
Limits are maximum concentrations of residual pollutants that can be
released at source usually from a stack from the proposed development.
Historic plant and equipment will struggle to meet such regulation.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 57
Alternative Scenario: Import electricity from the grid to support steel
making activities at the site, which would be an expensive and
uneconomical exercise. This would increase the cost of steel making
and would adversely impact on its market competitiveness, not to
mention increase the site’s carbon footprint.
Alternative Locations for the Proposed Development: The Kepner
Tregoe decision analysis tool has been used to select the most optimal
location for the proposed development. Further detail regarding this
selection method is contained within the ES. Through the use of this
analysis tool, three possible locations for the proposed development
were identified as listed below (1 – 3). Having assessed these sites
location (1) was identified as the most suitable site.
1) Old Margam Coke Oven Site;
2) North Side of Harbour Way Dock Site; and
3) Old A Strand Sinter Plant Site
Alternative Technology: Alternative technologies have been considered
to ascertain what type of technology would best generate power from the
available process gases at the site.
1) Boiler Turbo Alternator (BTA) Units; and
2) Combined Cycle Gas Turbine (CCGT)
5.2.17 The ES considers each of these technologies in further depth. Following a full
assessment, it has been concluded that the BTA unit is the preferred
technology for the proposed development given that it would be more adaptable
and less expensive.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 58
Criteria for “good design” for Energy Infrastructure (NPS EN-1, 4.5)
5.2.18 Section 4.5 of NPS EN-1 refers to the need to apply good design to energy
projects, which should produce sustainable infrastructure sensitive to place.
However, Paragraph 4.5.1 does acknowledge that:
“…the nature of much energy infrastructure development will often limit
the extent to which it can contribute to the enhancement of the quality of
the area.”
5.2.19 Paragraph 4.5.2 goes on to discuss how good design is also a means by which
many policy objectives in the NPS can be met. Good design can often be used
to mitigate adverse impacts such as noise etc.
5.2.20 The design of the proposed buildings and various components of this proposed
development have been considered throughout the scheme’s evolution. This
DCO Application is accompanied by a Design and Access Statement
(Document Reference: 10.03), which sets out the design principles for the
development and provides information on the design parameters of the
proposed development as far as practicable to allow for the Application to be
fully considered by the SoS.
5.2.21 It is not possible to fix the exact size/design of the buildings/structures
associated with the proposed development. As such, the technical
assessments that support this Application have assessed ‘maximum
parameters’ within which the work would take place. This strategy accords with
the principles of the ‘Rochdale Envelope’, as identified in NPS EN-1, which
allows an element of flexibility to be built into development proposals to address
areas of uncertainty which will be clarified as proposals progress.
5.2.22 The design parameters for this proposed development have been outlined in
further depth in Section 3 of this statement. Whilst the build parameters have
been set, the detailed design of the proposed development would be subject to
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 59
separate approval by NPTCBC prior to the commencement of development
through the requirements in the DCO.
5.2.23 The Applicant considers that the current broad design parameters of the
proposed development are acceptable, particularly when taking into
consideration the location of the application site, which sits against the context
of the existing steelworks site that is wholly industrial in character. To this end,
the proposed development complies with the design requirements of NPS EN-1.
5.2.24 Paragraph 4.5.3 of NPS EN-1 states that the SoS will need to be satisfied that:
“energy infrastructure developments are sustainable and, having regard
to regulatory and other constraints, are as attractive, durable and
adaptable (including taking account of natural hazards such as flooding)
as they can be”.
5.2.25 The Development Advice Map (DAM) referred to in TAN 15 show large areas of
the proposed development site to be located within Flood Zones B and C. The
key sources of flooding shown in these maps are the River Afan, the Ffrwdwyllt,
plus the Severn Estuary (i.e. the sea), which appear to flow over land during
extreme flood events towards the site.
5.2.26 However, since the models used to produce this mapping were completed (in
2009), new embankments and a diversion of the Ffrwdwyllt, through culverts for
Harbour Way, have been constructed. Modelling of these works as part of the
FCA prepared in support of this DCO indicate that they divert fluvial flooding
away from the Port Talbot steelworks site. In extreme events, such as the 1 in
1000 chance fluvial + MHWS tidal, whilst the main power generation site does
not flood, some of the 66kV cable route is shown to flood and some parts of the
Harbour Way to the north are shown to flood to depths of up to 1m. This will be
accounted for in a FWEP for the proposed development (to be incorporated into
either within the CoCP or as part of wider emergency planning procedures in
operation).
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 60
5.2.27 In terms of sustainability, the proposed development would be sited within the
confines of the existing steelworks site and would enable a significant reduction
in the amount of imported energy from the national grid. Moreover, the
proposed development would vastly improve the energy efficiency of the
steelworks as a whole, allowing for continued production and increased
competiveness.
5.2.28 Paragraph 4.5.4 of NPS EN-1 seeks that applicants:
“demonstrate in their application documents how the design process was
conducted and how the proposed design evolved. Where a number of
different designs were considered, applicants should set out the reasons
why the favoured choice has been selected”.
5.2.29 The design evolution is explained in further depth in the Design and Access
Statement (Document Reference: 10.03), and the alternatives to the proposed
development are set out briefly above at paragraph 5.2.15 onwards and further
explored in Chapter 2 (Environmental Impact Assessment) of the ES. These
documents discuss the nature of the proposed development, the scheme
design and extent of the built-form required as part of the proposals.
5.2.30 Given the nature of the proposed development, the design has largely evolved
in response to the objectives of the proposals. The proposed development
seeks to increase the power generation of the site through the installation of an
internal power generation enhancement system. The plant and equipment
associated with which have been chosen to achieve this specific objective and
fairly rigidly dictate the form, design and arrangement of proposed buildings on
the site. Whilst the scale and form of these buildings has been kept to a
minimum, for both visual impact and cost reasons, they would be viewed in the
context of the overall steelworks site, which is a wholly industrial landscape.
Consideration of Combined Heat & Power (CHP) (NPS EN-1, 4.6)
5.2.31 Section 4.6.6 of NPS EN-1 states that:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 61
“Under guidelines issued by DECC (then DTI) in 2006, any application to
develop thermal generating station under Section 36 of the Electricity Act
1989 must either include CHP or contain evidence that the possibilities
for CHP have been fully explored to inform the [Secretary of State]’s
consideration of the application.”
5.2.32 Due consideration has been given to the general support in NPS EN-1 for CHP.
5.2.33 The steam produced in the boiler(s) of the proposed development would be
used for electricity generation and would also be recycled (via new pipework
connections into existing infrastructure) for office heating, space heating within
the wider steelworks site and for various other on-site process requirements,
contributing to the overall sustainability of the proposed development and the
critical plant operations of the steelworks site. The existing on-site demand for
heat is sufficient such that it would make any export of waste heat from the
plant to other external users uneconomical. Accordingly, the export of the heat
to users outside the steelworks site is not proposed by the Applicant.
Carbon Capture Storage (CCS) & Carbon Capture Readiness (CCR) (NPS EN-
1, 4.7)
5.2.34 Section 4.7 of NPS EN-1 explains the considerations to be given to CCS and
CCR and explains that all applications for new combustion plant which are of a
generating capacity at or over 300MW and of a type covered by the EU’s Large
Combustion Plant Directive (LCPD) should demonstrate that the plant is
“Carbon Capture Ready”.
5.2.35 The maximum total combined output of the generating facilities at the
steelworks site following the construction of the proposed development with be
245MW and would therefore not meet or exceed the threshold of 300MW. The
proposed development is therefore not required to demonstrate carbon capture
readiness.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 62
Climate Change Adaption (NPS EN-1, 4.8)
5.2.36 Section 4.8 of NPS EN-1 relates to climate change adaption and covers the
Government’s energy and climate change strategy, advising that the effects of
climate change should be taken into account when developing and consenting
infrastructure. Paragraph 4.8.5 states that:
“New energy infrastructure will typically be a long-term investment and
will need to remain operational over many decades, in the face of a
changing climate. Consequently, applicants must consider the impacts
of climate change when planning the location, design, build, operation
and, where appropriate, decommissioning of new energy infrastructure.”
5.2.37 In terms of flood risk, the application site falls mainly within Flood Risk Zone B
(areas known to have flooded in the past), however, the north-western corner of
the site falls within Zone C1 (areas served by significant infrastructure, including
flood defences), as defined by the Development Advice Map (DAM) referred to
under TAN 15 (Development & Flood Risk) (2004). In view of this, a Flood
Consequences Assessment (FCA) has been undertaken in accordance with the
requirements of TAN 15 and is submitted in support of this Application
(contained within Appendix 13.1 of the ES). This document considers the
effects of climate change over the lifetime of the proposed development.
5.2.38 The FCA has identified the key sources of flooding as being the River Afan, the
Ffrwdwyllt, and the Severn Estuary. Since NRW undertook their previous
modelling to produce the DAM, new embankments and a diversion of the
Ffrwdwyllt have been constructed. These have significantly lessened the
impacts associated with flooding. Following discussions, NRW has requested
modelling for the minor watercourses which flow into the reservoir, as they may
affect fluvial flooding to the site. This work has since been carried out (see
Chapter 13 (Flood Risk) of the ES) and indicates that these minor watercourses
divert fluvial flooding away from the Port Talbot steelworks site. In extreme
events such as the 1 in 1000 chance fluvial + mean high water spring tidal,
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 63
whilst the main power generation site would not flood, some of the 66 kV cable
route is shown to flood and some parts of the Harbour Way to the north are
shown to flood to depths of up to 1.0 m. This would need to be accounted for in
a flood warning evacuation plan for the proposed development (either within the
CoCP or as part of wider emergency planning procedures in operation).
5.2.39 Ordinary watercourses near to the site are not considered to be a constraint to
the proposed development.
5.2.40 There is anticipated to be a number of pressurised proposed process water
pipes which present a potential flood risk at all stages of the development due
to failures of the system. This would be mitigated through the design of the
system
5.2.41 The site is partially located in an area potentially at risk of flooding from the
Eglyws Nunydd and Cwmwernderi Reservoirs; however modelling and
engineering assessment (see Chapter 13 (Flood Risk) of the ES) has shown
that neither presents a significant constraint to the proposed development.
5.2.42 Groundwater flooding is not anticipated to be a significant constraint to the
construction, operational or decommissioning stages as there are no significant
below ground works during construction or operation of the proposed
development.
5.2.43 Following submission of the hydraulic model (contained within the FCA,
Appendix 13.1.5 of the ES) and associated FCA to NRW for review, a
consultation response was issued by NRW on the 23rd May 2014 (Document
Reference: 6.02, Volume 2, Chapter 13) stating that they have confidence in the
findings and conclusions of the FCA. As such, NRW accept that flood risk to
the site can be managed and that the proposed development complies with the
requirements of Welsh Government guidance TAN 15: Development and Flood
Risk (July 2004).
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 64
5.2.44 In terms of surface water resources, the proposed development has the
potential to impact upon water quality, which is interrelated with effects on
groundwater and flood risk.
5.2.45 The proposed development would involve an initial abstraction of water from the
River Afan during the construction phase of the cooling towers. Abstraction
would also be needed to make up for evaporative loses. The River Afan would
be the primary source of abstraction, with secondary sources during no flow/low
flow conditions being the Nant Ffrwdwyllt, followed by the Port Talbot Dock.
5.2.46 The effects of the abstraction-discharge regime have been assessed under
chapter 14 of the ES on the basis that the River Afan would be the primary
source of abstraction and that an abstraction hierarchy would be employed.
This approach has been agreed in principle with NRW. A statement of common
ground will be sought for this prior to examination process.
5.2.47 The Applicant will secure the necessary abstraction license agreements and will
adhere to monitoring requirements of NRW. Essentially, this proposed
development presents an opportunity to improve flow conditions and strain
placed on salmon migration over and above the existing situation.
5.2.48 Surface water is proposed to discharge into Swansea Bay. Such discharges
are not considered to be significant and would be managed through the
imposition of suitable conditions and via an amended discharge permit.
5.2.49 Miscellaneous discharges from rainwater run-off and discharges from ancillary
equipment may also occur. Such discharges can be addressed through
adherence to a CoCP and by managing and pre-treating site drainage, as
necessary, before discharging via consented discharge points, which are
controlled through the conditions of an environmental permit. Additionally,
surface water run-off effects on the drainage channel (Middle Mother Ditch)
outside the site boundary, and other downstream water bodies / courses would
be mitigated via the attenuation ponds constructed as part of the Harbour Way
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 65
development. Therefore, the effect on controlled waters from intermittent
miscellaneous discharges is not significant and presents a residual negligible
effect.
5.2.50 The abstraction necessary during the commissioning of the cooling towers to
full operation would not have a significant effect on the River Afan flows as this
is a one off and small abstraction volume presenting a residual negligible effect
only.
5.2.51 The abstraction during operation of the proposed development would also have
a residual negligible effect on the River Afan flows. Abstraction effects on the
River Afan flows would be mitigated through abstraction licence agreements,
agreed monitoring requirements and operation of the agreed abstraction
hierarchy with NRW. The operation of this abstraction hierarchy between NRW
and the Applicant would actively manage additional stress placed on the River
Afan during low flow periods, enabling an effective and more sustainable
operating system for the Applicant by ensuring flows are available for the
additional abstraction when required without adversely affecting the flows in the
River Afan.
5.2.52 Discharges to Swansea Bay during all phases of the proposed development
would have a residual negligible effect and therefore insignificant effect on the
water body. Discharges would be managed through conditions imposed by an
amended permit or new permit.
5.2.53 Chapter 14 (Surface Water Environment) of the ES includes details of baseline
data, together with a full assessment of surface water matters and
methodology.
Grid Connection (NPS EN-1, 4.9)
5.2.54 Section 4.9 of NPS EN-1 relates to the connection of the proposed development
to the national grid. Specifically, paragraph 4.9.1 states that:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 66
“In the market system, it is for the applicant to ensure that there will be
necessary infrastructure and capacity within an existing or planning
transmission or distribution network to accommodate the electricity
generated.”
5.2.55 The proposed development represents an extension to the existing operational
steelworks. As such, there is already a grid connection in place. The proposed
development would however involve the need to install new and additional
infrastructure to integrate the proposed buildings/structures into the existing
facility. Whilst the electricity generated by the proposed development would be
intermittently exported to the national grid, the majority of the power generated
would be used on-site to reduce the site’s external energy draw. In order to
facilitate the connection of the proposed development to the national grid
upgrading works would be required, involving the installation of a 66kV
switchgear building adjacent to the generating station and modifications to the
existing on-site sub-stations. These modification works would be undertaken
following direct consultation with Western Power Distribution and are included in
the works authorised by the DCO at Schedule 1 of the draft DCO.
Pollution Control & Other Environmental Regulatory Regimes (NPS EN-1, 4.10)
5.2.56 The assessment principle outlined at Section 4.10 of NPS EN-1 relates to
issues involving discharges or emissions from the proposed facility that may
affect air quality, water quality, land quality and the marine environment, or
which may include noise and vibration. Whilst NPS EN-1 acknowledges that
the planning and pollution control systems are separate entities, it does point
out that they can work together to achieve the best result. Paragraph 4.10.3
states that:
“In considering an application for development consent, the [Secretary of
State] should focus on whether the development itself is an acceptable
use of the land, and on the impacts of that use, rather than the control of
processes, emissions or discharges themselves. The [Secretary of
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 67
State] should work on the assumption that the relevant pollution control
regime and other environmental regulatory regimes….will be properly
applied….It should act to complement but not seek to duplicate them.”
5.2.57 The ES that has been submitted in support of this DCO Application identifies
and considers all of the environmental issues associated with this proposed
development. Discussion has been undertaken with relevant pollution control
authorities to ensure that potential releases can be regulated appropriately.
Accordingly, a number of permits, licences and consents would be required for
the proposed development. The requirement for additional consents and
licences is referenced and considered within Chapter 5 (Air Quality), Chapter 8
(Noise and Vibration), and Chapter 14 (Surface Water Environment) of the ES
and a list of expected required consents and licences is set out within the
[Additional Consents and Licence Document]. These relevant matters are
controlled under separate legislation that should not be duplicated through the
planning process. Instead, it is advised that the necessary consents etc would
be gained following the approval of this DCO and prior to the commencement of
works.
5.2.58 As required by the Environmental Permitting (England and Wales) Regulations
2010 as amended, the Applicant will submit an application for an Environmental
Permit, required to operate the proposed development, to Natural Resources
Wales. The Applicant has met with Natural Resources Wales who have
indicated that, at this stage, they see no impediment to the grant of the
Environmental Permit but reserve their right to decide the application for the
Environmental Permit after it has been submitted.
Safety (NPS EN-1, 4.11)
5.2.59 Occupational health and safety legislation is regulated by the Health and safety
Executive (HSE) and would be applicable to the construction, operation and
decommissioning of the proposed development. Paragraph 4.11.1 of NPS EN-
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 68
1 states that consultation should be undertaken with the HSE on matters
relating to safety.
5.2.60 Early engagement and consultation has been undertaken with the HSE as part
of this DCO Application. The Applicant already engages with the HSE in
respect of the existing on-site operations. Liaison with the HSE will continue to
inform the detailed design of the proposed development. A Health and Safety
Statement has been prepared as part of the Application (Document Reference:
8.07).
Hazardous Substances (NPS EN-1, 4.12)
5.2.61 Paragraph 4.12.1 of NPS EN-1 advises that in the event that the proposed
development would hold stocks of or is intending to use hazardous substances,
consultation should be undertaken with the HSE at the pre-application stage to
determine whether hazardous substances consent is required.
5.2.62 The proposed development would not involve the use of hazardous substances
and therefore no such consent would be required.
Health (NPS EN-1, 4.13)
5.2.63 Section 4.13 of NPS EN-1 refers to the potential impact on the health and well-
being of the population as a result of energy production processes. Paragraph
4.13.2 states that:
“…where the proposed project has an effect on human beings, the ES
should assess these effects for each element of the project, identifying
any adverse health impacts, and identifying measures to avoid, reduce or
compensate for these impacts as appropriate.”
5.2.64 As advised by NPS EN-1, the ES fully considers the potential impacts of the
proposed development on public health in relation to contamination (Chapter 9),
air quality (Chapter 5), noise, vibration (Chapter 8), and water quality (Chapter
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 69
14). Certain aspects (i.e. air pollution) are covered by separate legislation.
Nevertheless, all matters have been afforded due consideration as part of this
submission and an assessment of the individual topics has been made below,
with further information available within the ES.
Statutory Nuisance (NPS EN-1, 4.14)
5.2.65 Section 4.14 of NPS EN-1 relates to statutory nuisances as outlined under
section 79(1) of the Environmental Protection Act 1990. Paragraph 4.14.2 of
NPS EN-1 states that:
“It is very important that, at the application stage of an energy NSIP,
possible sources of nuisance under section 79(1) of the 1990 Act and
how they may be mitigated or limited are considered by the [Secretary of
State]…”
5.2.66 Document 5.02 (Statement in respect of Statutory Nuisance) contains further
information on such matters and considers how the proposed development
would engage s79(1) of the Environmental Protection Act 1990.
5.2.67 The Statement concludes that whilst the proposed development has the
potential to engage some of the matters set out in s 79(1), appropriate
mitigation measures have been incorporated (including embedded mitigation in
the design of the project - and additional measures to be implemented during
construction and operation) to ensure that these impacts do not give rise to a
statutory nuisance within the meaning of s. 79(1). These measures include the
CoCP and other measures as set out in ES Chapter 17 Schedule of Mitigation).
Security Considerations (NPS EN-1, 4.15)
5.2.68 Paragraph 4.15.2 of NPS EN-1 states that, where possible, proportionate
protective security measures are designed into new infrastructure projects at an
early stage as there may be national security considerations.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 70
5.2.69 The existing steelworks site is already subject to rigorous security measures
which would be applicable to the development proposed under this Application.
The following security measures are already in place at the steelworks site and
would continue to operate in relation to this proposed development:
A network of close circuit television cameras;
24 hour on-site security presence;
Security fencing to contain areas and prevent access; and
Restricted access controlled via security passes.
Generic Impacts
5.2.70 Part 5 of NPS EN-1 covers those impacts that are termed as ‘generic’ given that
they arise from the development of any type of energy infrastructure project. A
breakdown of the generic impacts listed within Part 5 is provided below with
commentary in relation to the proposed development.
Air Quality & Emissions (NPS EN-1, 5.2)
5.2.71 Paragraph 5.2.6 of NPS EN-1 states that:
“Where the project is likely to have adverse effects on air quality the
applicant should undertake an assessment of the impacts of the
proposed project as part of the Environmental Statement (ES).”
5.2.72 In accordance with this requirement, the ES submitted in support of this
proposed development duly considers the potential for impacts associated with
air quality (Chapter 5) and contains a full air quality assessment.
5.2.73 In summary, the results of the air quality assessment at sensitive receptors
along the construction route indicate that the proposed development is
expected to have a negligible effect on annual mean NO2 and PM10
concentrations at the worst affected sites.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 71
5.2.74 In terms of emissions from the proposed development, these have been
assessed through detailed atmospheric dispersion modelling using best practice
approaches (included in Chapter 5 (Air Quality) of the ES).
5.2.75 Construction-phase dust effects have been assessed to be low to medium risk if
unmitigated, but are expected to be negligible following the implementation of
appropriate mitigation measures (set out in ES Chapter 5 Air Quality and ES
Chapter 15 Construction Environmental and Waste Management, together with
the Dust Management Plan and the Code of Construction Practice (CoCP)
(Document Reference: 8.06).
5.2.76 Construction related traffic effects on air quality are predicted to be negligible at
receptors adjacent to the main access routes used by traffic associated with the
proposed development.
5.2.77 Overall, the maximum long-term impacts with the worst-case conditions are
negligible. Despite this marginal impact, it is noted that paragraph 5.2.10 of
NPS EN-1 provides allowance for the breach of air quality limits by stating that:
“Where a project is likely to lead to a breach of such limits the developer
should work with the relevant authorities to secure appropriate mitigation
measures to allow the proposal to proceed.”
Biodiversity & Geological Conservation (NPS EN-1, 5.3)
5.2.78 Section 5.3 of NPS EN-1 places emphasis on the need to provide
environmental information that is proportionate to the infrastructure proposed
and has taken advantage of the opportunities to conserve and enhance
biodiversity and geological conservation interests.
5.2.79 As part of the decision making process the SoS will take account of the context
of the challenge of climate change, which in itself will result in significant
adverse impacts to biodiversity. Whilst the proposed development may result in
harm to features of acknowledged ecological importance, this must be weighed
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 72
against the benefits of nationally significant low carbon energy infrastructure
development which, as paragraph 5.3.6 of NPS EN-1 recognises, may include
wider benefits for biodiversity and geological conservation interests.
5.2.80 Section 5.3 of NPS EN-1 identifies the following as designations as being key
for consideration by the SoS:
International Sites (Ramsar, Special Area of Conservation (SAC), Special
Protection Areas (SPA) (including proposed sites);
Sites of Special Scientific Interest (SSSI);
Regional and Local Sites (e.g. Local Nature Reserves (LNR));
Ancient Woodland and Veteran Trees;
Biodiversity within Developments; and
Protection of Habitats and Other Species (i.e. species and habitats of
principle importance nationally, or species and habitats of regional
importance.
5.2.81 The Applicant has included as part of the Application a detailed ES which
provides the environmental information required by the NPS. The following
detailed survey work has been undertaken to inform the ES:
A Desk Study (Chapter 6 (Ecology) of the ES);
Extended Phase 1 Habitat Survey (Volume 3, Appendix 6.1 of the ES);
Bat Survey (Chapter 6 (Ecology) Table 6.1 of the ES);
Reptile Survey (Volume 3, Appendix 6.2 of the ES);
Great Crested Newt Habitat Suitability Assessment (Volume 3, Appendix
6.3 of the ES);
Breeding Bird Suitability Assessment (Volume 3, Appendix 6.4 of the ES);
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 73
Kidney Vetch Survey (Volume 3, Appendix 6.5 of the ES);
Walkover of the cable route to identify and map habitats and identify
presence or potential for habitats to host protected and priority species
(Volume 3, Appendix 6.1 of the ES); and
Invertebrate Habitat Suitability Assessment of the cable route and
proposed development (Volume 3, Appendix 6.5 of the ES).
5.2.82 The land within the Order Limits comprises scattered scrub, semi-improved
grassland, amenity grassland, pipe work, hard standing, gravelled areas,
buildings and a ditch.
5.2.83 Whilst it would be necessary to remove vegetation on the site, the appropriate
surveys have been carried out to assess the potential for biodiversity and the
associated impacts thereon and mitigation proposed.
5.2.84 In accordance with the findings of the Phase I Survey, Phase II surveys have
been undertaken to identify species present on the site and potential effects on
species and populations.
5.2.85 The main findings of the survey of the main power generation facilities area
included the presence of small blue butterfly and gulls; habitat suitable to
support small passerines; and several stands of Japanese knotweed. No
reptiles were found during the Phase II surveys and habitats were not assessed
as suitable for amphibians or bats. No evidence of badgers was observed.
5.2.86 In reference to the electrical connection, this would mainly be located within the
verge of the existing internal road which consists of a combination of
hardstanding and scrubby areas. The route is also routed once across the
internal railway line in existing ducting or be supported off existing structures.
Nevertheless, a walkover survey of the cable route has been undertaken is
reported in Chapter 6 (Ecology) of the ES.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 74
5.2.87 The key ecological impacts have been split into two categories and are
described in further detail in the ES Chapter 6 (Ecology):
i. Minor effects are likely to occur during construction where there is:
Temporary damage of semi-improved grassland;
Permanent disturbance to buildings;
Loss of habitat for breeding birds;
Killing or injuring of reptiles; and
Loss of habitat for reptiles.
ii. Moderate effects are likely to occur during construction where there is:
Permanent loss of semi-improved grassland;
Permanent loss of semi-improved scrub;
Permanent drying of the ditch;
Temporary loss of habitat along the cable route;
Temporary degradation of habitat for invertebrates; and
Potential spread of invasive species.
iii. Major effects are likely to occur during construction where there is:
Permanent loss of invertebrate habitat.
5.2.88 The ES Ecology Chapter (Chapter 6) also considers impacts of the proposed
development on designated sites. All effects on designated sites would be
minor to negligible.
5.2.89 The proposed development will have a residual minor adverse effect on semi-
improved grassland through the partial and temporary loss of the habitat during
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 75
construction. The creation of an ‘invertebrate sanctuary’ will manage an
existing area of semi-improved grassland to be of equal or greater value than
that removed and will provide compensation for the partial loss of the semi-
improved grassland. The semi-improved grassland removed temporarily will be
reinstated after the completion of the cable installation works. The effect on
semi-improved grassland is deemed to be not significant.
5.2.90 There would be a residual minor adverse effect on invertebrates through the
removal of the wet ditch and partial removal of the semi-improved grassland
and scrub. Management of a retained area of semi-improved grassland to
create an ‘invertebrate sanctuary’ will mitigate the loss of habitats. In addition,
there will be a proportion of the habitat retained on-site and there is grassland
habitat of equal or greater value in the immediate surroundings. The effect on
invertebrates is deemed to be not significant.
5.2.91 There would be no effect on any other habitats or species during operation.
5.2.92 The proposed development will have a residual minor adverse effect on wet
ditch through the infilling of the habitat during construction. There is similar
habitat of equal or greater in the surrounding landscape. No mitigation or
compensation is proposed for the partial loss of the habitat. The effect on the
wet ditch is deemed to be not significant.
5.2.93 The proposed development will have a residual minor adverse effect on reptiles
through the partial loss of the semi-improved grassland. No mitigation or
compensation is proposed for the partial loss of the habitat with potential to
support reptiles. The effect on reptiles is deemed to be not significant.
5.2.94 During decommissioning there would be no effect to designated sites as there is
no demolition proposed because the existing steam boilers and turbo
alternators are contained within an existing building which would be
decommissioned and left insitu. There is no intention to demolish this building.
Similarly, the three existing stacks would also be decommissioned and left in
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 76
situ. Should any demolition works be required, this would be subject to
receiving the prior approval of NPTCBC.
5.2.95 Details of this translocation and also management of habitats and invasive
species are outlined in ES Appendix 6.8 Mitigation.
Civil & Military Aviation & Defence Interests (NPS EN-1, 5.4)
5.2.96 Paragraph 5.4.1 of NPS EN-1 states that:
“Civil and military aerodromes, aviation technical sites, and other types of
defence interests (both onshore and offshore) can be affected by new
energy development.”
5.2.97 The proposed development incorporates the erection of up to two new chimney
stacks each reaching a height of up to 80m. Accordingly, this element of the
proposed development has the potential to effect civil or military aviation and/or
other defence assets. As advised by paragraph 5.4.11 of NPS EN-1,
consultation has been undertaken with the Ministry of Defence (MoD), the Civil
Aviation Authority (CAA), and the National Air Traffic Services (NATS).
5.2.98 Consultation with the CAA has identified the requirement of omni-directional red
lighting on the top of cranes during construction and also on the top of the
stacks during operation. This is consistent with other lighting on the wider Port
Talbot Steelworks site. The proposed development would not be venting any
gases and due to the implementation of the proposed development, the
presence of the flare would be greatly reduced. Therefore there is no impact to
aerodromes or nearby aviation facilities.
Coastal Change (NPS EN-1, 5.5)
5.2.99 Section 5.5 of NPS EN-1 refers to the protection of coastal communities which
are susceptible to change and can be affected by the direct and indirect impact
associated with energy infrastructure projects. Paragraph 5.5.2 defines coastal
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 77
change as “physical change to the shoreline (i.e. erosion, coastal landslip,
permanent inundation and coastal accretion).” Paragraph 5.5.4 goes on to
state that indirect changes to the coastline and seabed can also arise, which
have the potential to lead to localised or more widespread coastal erosion.
5.2.100 The steelworks site occupies a coastal location, and whilst the application site is
set back from the coastline, within the confines of the steelworks, the proposed
development has the potential to impact upon the coast by reason of discharge
and abstraction from nearby water resources.
5.2.101 The ES incorporates an assessment of the effects of the proposed development
on the coast (Document Reference: 6.02, Volume 2, Chapter 13), which
considers physical changes to the integrity of coast and the associated
implications for matters of ecology, shoreline management, coastal recreation
etc. The HRA has shown that effects are negligible and, cumulatively with
Swansea tidal lagoon, effects of discharges are negligible.
5.2.102 Principally, the SoS will need to be satisfied that the proposed development
would be resilient to coastal erosion and deposition, also taking account of
climate change and the risks from flooding.
5.2.103 A FCA has been carried out separately and forms part of this DCO Application.
This demonstrates that the risk and consequences of coastal flooding can be
acceptably managed. NRW has reviewed the FCA and hydraulic modelling and
accepts that the risk and consequences of flooding cab be suitably managed in
line with TAN 15.
Dust, Odour, Artificial Light, Smoke, Steam & Insect Infestation (NPS EN-1, 5.6)
5.2.104 Impact upon existing occupiers’ amenity is outlined as a key consideration
under Section 5.6 of NPS EN-1, which indicates that an assessment should be
made of the proposals potential for insect infestation and emissions of odour,
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 78
dust, steam or smoke and artificial light. Paragraph 5.6.1 of NPS EN-1 states
that:
“During construction, operation and decommissioning of energy
infrastructure there is potential for the release of a range of
emissions….All have the potential to have a detrimental impact on
amenity or cause a common law nuisance or statutory nuisance under
Part III, Environmental Protection Act 1990.”
5.2.105 The Statement in Respect of Statutory Nuisance included as part of the
Application (Document Reference: 5.06) sets out the extent to which the
proposed development would engage section 79(1) of the Environmental
Protection Act 1990.
5.2.106 Increasing the steel production at the site using the current processes to 4.7
million tonnes per annum, if electricity generation was to remain constant, would
result in around 4.8 PJ per annum of process gases that would need to be
flared. This would obviously have detrimental implications for the surrounding
populace. The proposed development, to replace four existing boilers with two
new larger boilers, would reduce the flaring rate to 0.5 PJ per annum. Whilst
this is a considerable reduction, in accordance with the requirements of
paragraphs 5.6.7 – 5.6.10 of NPS EN-1, the ES takes account of air quality
(Chapter 5) and the associated implications for surrounding sensitive receptors,
having particular regard for the emissions generated by the proposed
development, which would principally be through the operational emissions to
the atmosphere from the gases exhausted by the boiler stack.
5.2.107 Following a thorough assessment of the emissions in the ES, it is concluded
that the predicted concentrations of pollutants from the operational phase of the
proposed development would meet all relevant air quality standards and
objectives. No further mitigation is required beyond that incorporated into the
design of the scheme. Moreover, the proposed development would need to
obtain an Environmental Permit (either a new bespoke Permit or a variation on
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 79
the wider Port Talbot Steelworks Permit) under the Environmental Permitting
Regulations (EPR), which would be monitored and would need to be strictly
adhered to.
5.2.108 Other possible sources of emissions include dust and emissions from transport
associated with the construction of the proposed development. In this respect,
the ES concludes that the number of traffic movements (which are assumed to
use the M4 for accessing the site) generated by the construction of the
proposed development and its future operation will be negligible when
considered against the volume of traffic on the M4 and the distance of the
nearest properties to the site. In addition the implementation of a Dust
Management Plan as part of the CoCP which incorporates the Applicants
existing “traffic light” dust management system, would also manage any effects
of dust, as well as other potential construction effects.
5.2.109 Consultation has been undertaken with NPTCBC in respect of the modelling
and to scope out the consideration of operational traffic effects.
5.2.110 Overall, it is considered that the requirements of Section 5.6 of NPS EN-1 are
satisfied.
Flood Risk (NPS EN-1, 5.7)
5.2.111 Section 5.7 of NPS EN-1 provides advice in relation to the aims of planning
policy on development and flood risk. Paragraph 5.7.4 states that:
“Applications for energy projects of 1 hectare or greater in Flood Zone 1
in England or Zone A in Wales and all proposals for energy projects
located in Flood Zones 2 and 3 in England or Zones B and C in Wales
should be accompanied by a flood risk assessment (FRA).”
5.2.112 The application site is located partially within Flood Risk Zones B and C. As
such, a FCA (contained in Volume 3, Appendix 13.1 of the ES) has been
undertaken and is submitted in support of this DCO Application. The FCA has
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 80
been informed by a hydraulic modelling review following early engagement with
NRW. This takes account of the newly constructed Harbour Way (distributor
road) which acts as a barrier from flooding. It has also modelled the minor
watercourses that flow into the Eglwys Nunydd Reservoir.
5.2.113 The FCA assesses the risks and consequences associated with flooding for the
development site, together with the impacts that the development could have on
flood risk conditions as well as taking account of climate change.
5.2.114 Given its location, the site is considered to be at risk from flooding in both the 1
in 200 year (0.5%) and 1 in 1000 year (0.1%) tidal event. However, the risk and
consequences of flooding can be managed acceptably in accordance with TAN
15. Accordingly, NRW has confirmed that the proposed development is
acceptable from a flood risk perspective.
5.2.115 The proposed development would be undertaken in accordance with the
findings of the FCA, and the exact finished floor levels of the proposed buildings
would be subject to the approval of NPTCBC through the detailed design
requirements as set out within Schedule 2 (Requirements) to the DCO.
5.2.116 The FCA has been undertaken in consultation with NRW, with the hydraulic
model created for the proposed development submitted for validation, and NRW
have concluded that the risks and consequences of flooding can be acceptably
managed as the modelling has been validated. As such, the proposed
development complies with the requirements of Section 5.7 of EN-1.
Historic Environment (NPS EN-1, 5.8)
5.2.117 The historic environment consists of assets that are considered to be valued for
their historic, archaeological, architectural or artistic interest. Such assets can
include buildings, monuments, sites, places or landscapes. Paragraph 5.8.1
states that:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 81
“the construction, operation and decommissioning of energy
infrastructure has the potential to result in adverse impacts on the historic
environment.”
5.2.118 Paragraph 5.8.8 goes on to state that:
“As part of the ES the applicant should provide a description of the
significance of the heritage assets affected by the proposed development
and the contribution of their setting to that significance. The level of
detail should be proportionate to the importance of the heritage assets
and no more than is sufficient to understand the potential impact of the
proposal on the significance of the heritage asset.”
5.2.119 A Cultural Heritage Assessment (contained within section 11.3 of Chapter 11
(Cultural Heritage & Archaeology) of the ES) has been carried out for the
application site, which follows the guidelines from the Institute for
Archaeologists (IfA) for historic environment desk-based assessments (2012).
5.2.120 Within the 1km study area there are 99 previously recorded heritage assets,
including five Scheduled Ancient Monuments, one Grade II* Listed Building,
three Grade II Listed Buildings, and one Grade II Registered Park and Garden.
5.2.121 Consultation has been undertaken with Glamorgan Gwent Archaeological Trust
(GGAT), Cadw and NRW. The main heritage assets were deemed to be the
Margam Copper Works and the Margam Iron and Steel Works. The
construction of the proposed development may have a direct physical impact
upon these sites, however, the ES (Chapter 11 – Cultural Heritage) has
determined the level of significance to be minor adverse.
5.2.122 In relation to the impact of the proposed development on the setting of nearby
heritage assets, the Grade II* Listed Church of St. Theodore has the potential to
be affected by reason of the proposed boiler chimney stack(s). A cultural
heritage assessment (contained within Chapter 11 of the ES) has been
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 82
undertaken and considers the impact of the proposed stack(s) on the setting of
the listed church to be negligible.
5.2.123 NRW recommended that an Assessment of the Significance of Impacts of
Development on Historic Landscape (ASIDOHL) should be undertaken.
However, following further discussion with Glamorgan Gwent Archaeological
Trust (GGAT) and Cadw such an assessment was not considered to be
necessary on the basis of the industrial use of the site, which has been in
operation since the 1800s.
5.2.124 GGAT has reviewed and approved the draft ES Chapter and supporting
appendices, and advised that a written scheme of archaeological investigation
will need to be carried out for the proposed development site. This is contained
as a requirement in the draft DCO.
Landscape & Visual (NPS EN-1, 5.9)
5.2.125 Section 5.9 of NPS EN-1 relates to landscape and visual effects of energy
projects and indicates that common features of energy infrastructure are cooling
towers and, exhaust stacks and their plumes, which have the most obvious
impact on landscape and visual amenity.
5.2.126 Paragraph 5.9.5 states that:
“The applicant should carry out a landscape and visual assessment and
report it in the ES. A number of guides have been produced to assist in
addressing landscape issues.”
5.2.127 Paragraph 5.9.8 goes on to state that:
“Landscape effects depend on the existing character of the local
landscape, its current quality, how highly it is valued and its capacity to
accommodate change….Virtually all nationally significant energy
infrastructure projects will have effects on the landscape.”
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 83
5.2.128 A LVIA has been carried out for the site in accordance with the relevant
guidance, including the Guidelines for Landscape and Visual Impact
Assessments (3rd Edition). Further detail on this is included in Chapter 7
(Landscape & Visual) of the ES.
5.2.129 The LVIA covers an area of 15km radius from the building extent within the
Order Limits, with the exception of the electrical connection and potential cable
bridge as agreed with statutory consultees in the Scoping Report. The Zone of
Theoretical Visibility (ZTV) used in the LVIA is based on the presence of the
stack(s) and overall building mass of the proposed development as these are
the largest and most visible structures and, therefore, may result in the most
significant impact upon the landscape.
5.2.130 The LVIA has reviewed the effects of the proposed development during the
construction, operation and decommissioning stages. It focuses on the physical
changes to the fabric of the land, such as the addition or removal of industrial
buildings, plant, machinery and lighting.
5.2.131 Within the 15km study area the sensitive landscape designations and main
receptors include:
Margam Mountain, Merthyr Mawr, Kenfig and Margam Burrows (Historic
Landscape Areas (HLA));
Glamorgan Coast (Heritage Coast);
Gower (Area of Outstanding National Beauty (AONB));
Talbot Memorial Park and Margam Country Park (Registered Parks &
Gardens);
Corus Abbey Works (NPTCL004) (LANDMAP Aspect Areas);
Mumbles Head to Porthcawl Point (Swansea Bay) (Seascape Unit No.46);
and
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 84
The residential properties located between Port Talbot Town Centre,
Taibach, Pen-y-Cae and Margam, the M4 motorway, the A48 and Harbour
Way.
5.2.132 Landscape character is defined by the Guidelines for Landscape and Visual
Impact Assessment (3rd Edition) as “distinct, recognisable and consistent
pattern of elements in the landscape that makes one landscape different from
another, rather than better or worse.” The LVIA outlines that the application site
is located within the Port Talbot steelworks site which is heavily industrialised in
nature. The proposed development comprises a new building adjacent to the
existing power station that would house new power generation facilities together
with new gas, steam and utilities network connections.
5.2.133 There are currently 16 existing buildings and structures within the red line
boundary of the proposed development. The existing chimney stack connecting
to the existing power station has an overall height of 135 metres.
5.2.134 The LVIA has been undertaken on a daytime (in relation to lighting impact)
basis from publically accessible locations from a range of receptors including
residences, public rights of way (PROW), public open spaces, settlements and
transport routes. This approach was agreed with NPTCBC at the scoping
stage, when it was confirmed by NRW that the proposed development would be
unlikely to result in any significant night-time visual effects through additional
lighting given the existing heavily illuminated character of the steelworks site.
5.2.135 The proposed development would be visible from a number of the identified
landscape designations, however, the buildings/structures would be viewed in
the context of the existing steelworks site. Whilst the sensitivity of some of the
landscape designations would normally be considered to be very high, the
susceptibility to change would actually be low due to the existing steelworks that
encases the site.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 85
5.2.136 Through dialogue with the City & County Swansea, it was agreed that three
additional viewpoints would be included within the LVIA. These are:
i. Grape & Olive Bar & Restaurant, Meridian Quay
ii. Verdi's Cafe, Knab Rock, Mumbles
iii. Swansea Bay Promenade
5.2.137 These three viewpoints have been assessed and are reported on within the ES
(Chapter 7 – Landscape & Visual).
5.2.138 In conclusion, the LVIA has determined the landscape impacts on the above-
mentioned identified receptors to be minor and not significant. In relation to the
visual effects, these would be minor and negligible and not significant, aside
from those from Harbour Way which would be moderate and significant.
However, the scale of the proposed development within the confines of the
existing steelworks site should be afforded considerable weight when
considering landscape and visual impact.
5.2.139 Despite the industrialised nature of the site there are opportunities to reduce the
visual presence of the proposed development. Such mitigation would take the
form of tree planting and earth bank development, particularly along the
Harbour Way frontage. Landscaping will form part of the [Landscaping Plan]
which has to be submitted to and approved by NPTCBC in accordance with
requirements in the draft DCO. In addition, the colour of the buildings/structures
will be approved by NPTCBC as part of the detailed design approval process, in
accordance with the requirements of the draft DCO, to limit the effect of close
and more distant views. It is considered appropriate to use a mid to light grey
for the building masses, with Tata blue for the trim details. In terms of lighting
requirements, this is minimal and there are techniques included within the ES
Chapter 3 which can be used to limit detrimental impacts. The DCO Application
covers the need for lighting, and specific details of lighting can be controlled by
way of requirement in the DCO.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 86
5.2.140 Further information in relation to the LVIA assessment methodology and
findings can be found in Chapter 7 of the ES. Given the scale of the proposed
development set against that of the existing steelworks site and taking into
account the sensitivity of the receptors it is considered that the proposed
development is compliant with Section 5.9 of NPS EN-1.
Land Use Including Open Space, Green Infrastructure & Green Belt (NPS EN-1,
5.10)
5.2.141 NPS EN-1 notes at 5.10 that:
“An energy infrastructure project will have direct effects on the existing
use of the proposed site and may have indirect effects on the use, or
planned use, of land in the vicinity for other types of development.”
5.2.142 The proposed development is located on land within the existing operational
boundary of the Port Talbot Steelworks. The power generation plant can be
accommodated within the Order Limits on previously developed land. It is
considered that the proposed development has been sited, laid out, and
designed with the appropriate regard to the land use provisions of the NPS.
Noise & Vibration (NPS EN-1, 5.11)
5.2.143 Noise and vibration is a generic impact referred to under Section 5.11 of NPS
EN-1. This section promotes effective noise management in order to maintain
good health and good quality of life. It also places emphasis on the potential for
noise to adversely affect wildlife and biodiversity. Paragraph 5.11.4 of NPS EN-
1 states that:
“Where noise impacts are likely to arise from the proposed development,
the applicant should include the following in the noise assessment:
a description of the noise generating aspects of the
development proposal leading to noise impacts, including the
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 87
identification of any distinctive tonal, impulsive or low
frequency characteristics of the noise;
identification of noise sensitive premises and noise sensitive
areas that may be affected;
the characteristics of the existing noise environment;
a prediction of how the noise environment will change with
the proposed development;
in the shorter term such as during the construction period;
in the longer term during the operating life of the
infrastructure;
at particular times of the day, evening and night as
appropriate;
an assessment of the effect of predicted changes in the
noise environment on any noise sensitive premises and
noise sensitive areas; and
measures to be employed in mitigating noise.”
5.2.144 Chapter 8 (Noise & Vibration) of the ES incorporates a full noise and vibration
assessment. This concludes that operational noise from the installation of plant
during each Option/Phase of the proposed development will be below existing
background levels at nearby Noise Sensitive Receptors (NSRs) such that there
will be no adverse impacts.
5.2.145 During daytime periods, the Rating Level of plant (within inclusion of a +5dB
penalty for tonal/impulsive elements) is predicted to be 21 to 22 dB below the
measured background noise levels at each NSR survey location. During night-
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 88
time periods the Rating Level of plant is predicted to be 39 to 42 dB below
background levels.
5.2.146 The survey results show that there will be a reduction in sound levels when the
existing power plant is removed. It is considered that the dominant noise
source in the area will continue to be road traffic along the M4 motorway and so
the future background noise levels will be broadly similar to the measured
background noise levels from the AECOM survey.
5.2.147 Predicted noise levels from plant are considered to be sufficiently below existing
background levels such that they would be indiscernible and not significantly
contribute to the noise environment at the identified NSRs.
5.2.148 Due to the distance between the proposed development site and NSRs,
operational vibration impacts are considered to be negligible.
5.2.149 In terms of decommissioning noise, it is anticipated that there will be no noise
impacts from these works as there will be no demolition or removal of plant and
equipment. The boilers and associated turbine sets will be decommissioned
and left insitu.
5.2.150 This DCO Application is considered to satisfy the requirements of Section 5.11
of NPS EN-1. Further information and a detailed analysis of noise and vibration
are contained within ES Chapter 8 (Noise & Vibration).
Socio-economic (NPS EN-1, 5.12)
5.2.151 The proposed development would result in socio-economic impacts during the
construction, operation and decommissioning stages at a local and regional
level, which is recognised under Section 5.12 of NPS EN-1 as a generic impact
for all energy infrastructure projects. Paragraph 5.12.2 states that:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 89
“Where the project is likely to have socio-economic impacts at local or
regional levels, the applicant should undertake and include in their
application an assessment of these impacts as part of the ES…”
5.2.152 Paragraph 5.12.3 goes on to provide a list of relevant socio-economic impacts
(not exclusive) which may be included in such an assessment. These include
matters of job creation and training opportunities, provision of community and
infrastructure improvements, effects on tourism, and changing population
dynamics from increased employment in the area.
5.2.153 In accordance with the requirements of Section 5.12, a socio-economic impact
assessment (Document Reference 6.02, Volume 2, Chapter 12) has been
included in the ES (Chapter 12 – Scio-Economics) which considers the
proposed development in view of the local community and associated
economies in the vicinity of the proposed development, tourist/visitor attractions,
as well as recreational land uses.
5.2.154 The steelworks site already represents a major contributor to the local and
regional economies. It employs approximately 3,500 people in a variety of
disciplines. Dependent upon the contracts being serviced the secondary supply
chain can vary although the Welsh Government has recognised the Applicant
for being the largest “anchor employer” in South Wales with up to 17,000 people
either directly or indirectly employed in the local supply chain. It must also be
noted that the operations of the Port Talbot site support the other Tata Steel
sites at Llanwern, Shotton, Corby and Trostre.
5.2.155 The key potential effects based on the impact assessment are outlined below
and have been split into the three project stages:
i. Construction:
Regional employment opportunities;
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 90
Indirect economic effects as a result of expenditure in the local area
through increased activity in the area;
Temporary effects on local community associated with increased
disturbance from construction activities;
Temporary local adverse effects on users of local PROWs
associated within increased disturbance; and
Effects on tourism (use of accommodation & impact upon views);
ii. Operation:
Effects on tourism (use of accommodation & impact upon views);
Regional employment opportunities.
iii. Decommissioning:
The plant and equipment contained within the old power station
would be decommissioned but not demolished. Therefore, there is
limited scope for employment opportunities or impacts to tourism.
5.2.156 It is acknowledged that there would be both positive and negative impacts at a
socio-economic level. However, the positive impacts would considerably out-
weigh the negative impacts, which largely relate to visual implications that
would only marginally impinge upon the tourism economy. These would be
greatly overshadowed by the fact the proposed development would be located
in an industrialised area surrounded by similar works which are already a
feature of Port Talbot’s character. Moreover, the proposed development is
vastly important to ensuring the competitiveness of the Port Talbot steelworks in
the steel industry. As such, the proposed development will enable the site to
improve efficiency, the viability of the site and, therefore, its longevity.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 91
5.2.157 In view of the findings of the socio-economic impact assessment, Section 5.12
of NPS EN-1 has been suitably satisfied.
Traffic & Transport (NPS EN-1, 5.13)
5.2.158 The consideration and mitigation of transport is an essential part of the
Government’s wider policy objectives for sustainable development. Impacts
associated with the transport of materials, goods and personnel to and from the
development at all phases of the proposed development can be economic,
social and environmental. Paragraph 5.13.3 states that:
“If a project is likely to have significant transport implications, the
applicant’s ES (see Section 4.2) should include a transport assessment,
using the NATA/WebTAG methodology stipulated in Department for
Transport guidance, or any successor to such methodology. Applicants
should consult the Highways Agency and Highways Authorities as
appropriate on the assessment and mitigation.”
5.2.159 Consultation has been undertaken with NPTCBC Highway Department in
relation to the study area and scope of the information required to support this
Application. ES Chapter 10 (Traffic and Transportation) provides an in-depth
analysis of the highway safety matters associated with this proposed
development. In view of the detail provided in Chapter 10 (Traffic and
Transport) of the ES, NPTCBC Highways Department has confirmed that there
is no requirement for a Transport Assessment (TA) to be submitted as part of
this DCO Application.
5.2.160 The study area includes 12 highways links, which incorporate the majority of
“Harbour Way”, and routes between the site and the M4 Junctions 38, 40 and
41. Additionally, a baseline of accessibility by all modes, including footpaths,
cycleways and PROWs has been established.
5.2.161 It is anticipated that the construction period would last approximately 36 months
in the case of Option 1, and 36 months (Phase 1) with an additional 24 months
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 92
(Phase 2) in the case of Option 2. The peak period for deliveries would be
months 8 to 11, when 14 Heavy Goods Vehicle (HGV) trips per day would be
made to and from the site for concrete deliveries. One additional HGV trip and
ten van trips would be made each day during this time. There would be no
need to remove waste material as Tata Steel readily recycle materials on-site.
5.2.162 HGV trips would be restricted to the route between the site and the M4 Junction
38 using Harbour Way. This would minimise the impact of construction traffic
on local residences and communities.
5.2.163 Construction phase delivery traffic would account for an increase of merely 5%
of the number of HGV movements for the 08:00-09:00 hour, 17:00-18:00 hour,
and 06:00-24:00 hour periods. The exception is Link 5, which would experience
a 5.4% increase in HGV movements. Chapter 10 of the ES concludes that the
overall impact would therefore be negligible.
5.2.164 Abnormal loads would be required as part of the construction phase. There are
expected to be 15-20 such deliveries during the construction phase; equating to
one trip every two months. The impact of this on the highway network would
therefore be negligible.
5.2.165 The construction period will increase the number of staff present on the site by
300. The site is currently run in a split-shift system consisting of 2000 staff per
split (total of 4000 across any one day). This will therefore amount to a 15%
increase between 07:00-19:00. Chapter 10 (Traffic & Transport) of the ES
considers this increase to be negligible given that the increase in traffic flows is
far less than the 30% which is considered to be acceptable.
5.2.166 A Construction Traffic Management Plan (CTMP) will be prepared in
consultation with NPTCBC and will identify traffic routes to serve the proposed
development. As above-mentioned, NPTCBC has confirmed that a TP will not
be required to support this DCO application given that Chapter 10 (Traffic and
Transport) of the ES covers this aspect in sufficient detail.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 93
5.2.167 In addition to an acceptable construction phase, other phases of the proposed
development are considered to comply with the requirements of Section 5.13 of
NPS EN-1 given that there would not be a significant increase in traffic
generation. This can be attributed to the following:
At the operational stage, there would be no net change in staff as those
working on the existing facility would continue to be employed at the
proposed facility, with no requirement to increase or reduce staff numbers;
The new facility would continue to operate two operational shifts; 07:00-
19:00 hours and 19:00-07:00 hours;
The existing facility would be decommissioned during the operational
phase, but there would be no demolition and all buildings and components
would be left in situ;
There would be no additional maintenance requirements as the proposed
facility would be newer and more efficient than the existing facility; and
The proposed development would be predominantly fuelled by gasses
generated by the steelmaking process, with imported Natural Gas used as
a standby fuel. These gases would be transported by pipeline.
Waste Management (NPS EN-1, 5.14)
5.2.168 Paragraph 5.14.6 of NPS EN-1 makes it a requirement to demonstrate the
arrangements for the management of any waste produced by the proposed
development. A Site Waste Management Plan should be prepared to include
information on the proposed waste recovery and disposal system for all waste
generated by the development, together with an assessment of the impact of
the waste arising from development on the capacity of waste management
facilities in the area for at least five years of operation.
5.2.169 Paragraph 5.14.7 relates to the key considerations of the PINS in relation to
waste management and states that:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 94
“The [Secretary of State] should consider the extent to which the
applicant has proposed an effective system for managing hazardous and
non-hazardous waste arising from the construction, operation and
decommissioning of the proposed development.”
5.2.170 The DCO will include a requirement for the approval of a CoCP by the relevant
planning authority prior to the commencement of construction. This will be
prepared in accordance with the outline CoCP set out in Appendix 15.1 of ES
Vol. 3 and will cover the following environmental management topics:
Pollution Prevention Plan (PPP);
Water Management Plan (WTMP);
Site Waste Management Plan (SWMP);
Dust Management Plan (DMP);
Noise Management Plan (NMP);
Construction Traffic Management Plan (CTMP);
Travel Plan (TP);
Emergency Response and Flood Management Plan (ERFMP);
Materials Management Plan (MMP);
Habitat Management Plan (HMP); and
Site Safety Plan (SSP).
5.2.171 The SWMP would follow the waste hierarchy to reduce the amount of waste
generated, and ensure as much waste as possible is recycled/reused. The
proposed development would generate waste, however, this would be disposed
of following best practice guidance.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 95
5.2.172 During construction, the building contractors would be responsible for the
removal and disposal of all packaging and waste. It should be noted that all
contractors would be made aware of the SWMP.
5.2.173 Material excavated from the site would be stored on-site and recycled at the on-
site recycling facility where possible.
5.2.174 In the event that contaminated material is found, this would be treated on-site.
No waste material would be removed from the site, and where it is not possible
to dispose of the waste on-site a licensed off-site waste disposal facility would
be used.
5.2.175 There would be minimal waste proposed during the operation of the proposed
development. Maintenance activities will be the main cause of waste
generation. Such waste will be recycled (where possible) or disposed of in the
existing landfill within the steelworks complex.
5.2.176 There would be minimal waste generation as a result of the proposed
development during construction, operation or decommissioning. It is therefore
considered that the proposal complies with Section 5.14 of NPS EN-1.
5.2.177 Further information in relation to waste disposal can be found in Chapter 15
(Environmental & Waste Management) of the ES.
Water Quality & Resources (NPS EN-1, 5.15)
5.2.178 Section 5.15 of NPS EN-1 relates to the potential adverse effects that energy
infrastructure projects can have on the water environment, including
groundwater, inland surface water, transitional waters and coastal waters.
Paragraph 5.15.2 states that:
“Where the project is likely to have effects on the water environment, the
applicant should undertake an assessment of the existing status of, and
impacts of the proposed project on, water quality, water resources and
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 96
physical characteristics of the water environment as part of the ES or
equivalent.”
5.2.179 In accordance with the requirements of Section 5.15 of EN-1, the ES
incorporates a section on surface water and water quality (Chapter 14 – Surface
Water Environment), which should be read in conjunction with ‘Ground
Conditions’ (Chapter 9).
5.2.180 Whilst there are no watercourses or groundwater source protection zones on
the proposed development site, the soil is classified as having a high leaching
potential. As such, temporary measures would be implemented to manage the
run-off draining from the construction site. Drainage infrastructure would be
created to remove excess sediment from run-off. The specific detail of which is
set out in the ES and has been agreed in consultation with NRW.
5.2.181 The abstraction of water would be minimised as far as possible for on-site
construction activities. During the construction phase, concrete would either be
delivered to site ready mixed to reduce the need to use water during the
construction phase or prepared on-site at batching plants. Due to the level of
the water table, it is unlikely that a permit to abstract water from foundation
trenches would be required.
5.2.182 During the operational and decommissioning phase, water abstraction and
discharge would be needed. As referenced in the ‘Climate Change’ section of
this statement these activities would be covered by the allowances within the
existing permit.
5.2.183 Having considered the operations proposed as part of this DCO Application at
the three identified stages it is considered that the impacts upon the local water
environment are minimal and can be suitably controlled and mitigated for.
Section 5.15 of NPS EN-1 is therefore complied with.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 97
5.3 NPS 2 – Fossil Fuel Electricity Generating Infrastructure (NPS EN-2)
5.3.1 NPS EN-2 is part of a suite of energy infrastructure NPSs, which should be read
in conjunction with the overarching NPS (EN-1). This NPS does not seek to
repeat material already outlined in EN-1. Instead, it provides a focus on Fossil
Fuel Electricity Generating Infrastructure and reiterates that fossil fuel
generating stations will play a vital role in providing reliable electricity supplies
and a secure and diverse energy mix as the UK makes the transition to a low
carbon economy (referenced in paragraph 1.1.1).
5.3.2 The assessment of such projects should begin on the basis that need has
already been demonstrated (referenced in paragraph 2.1.2).
5.3.3 The following sub-headings are taken directly from NPS EN-2 and are cited as
the factors that are specific to influencing the Applicant’s site selection for fossil
fuel NSIPs, known as ‘Assessment and Technology-specific Information’. A
number of these matters have already been considered in respect of NPS EN-1
(in the preceding section of this statement). As such, a brief summary of the
requirements of NPS EN-2, together with a short assessment of how those
requirements have been met or directions to preceding sections which cover
these matters, are provided in this section.
5.3.4 It should be noted that this NPS is only relevant insofar as the proposed
development would occasionally be fuelled by natural gas, which is the standby
fuel for the facility in instances of shortage when gases generated by the
steelmaking processes are not available.
Land Use (NPS EN-2, 2.2.2 – 2.2.4)
5.3.5 This criterion acknowledges that fossil fuel generating stations will generally
have large land footprints and will therefore only be possible where the
applicant is able to acquire a suitably-sized site. Paragraph 2.2.2 states that:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 98
“The site will also need to be big enough to confirm to Government policy
on CCR and CCS, set out in Section 4.7 of EN-1….”
5.3.6 The proposed development would not incorporate Carbon Capture Readiness
or Carbon Capture Storage given that these processes are not relevant given
the generating capacity of the proposed development. The facility would
however improve efficiency of the existing steelworks site and increase product
generation. A saving of up to 400,000 tonnes of CO2 per annum would be
made compared to fossil fuel power stations, through the vast reduction (up to
55 MWe) in on-site electricity importation.
5.3.7 As described above, the proposed development would be sited within the
existing steelworks site which provides sufficient room to incorporate the
proposed development. As set out in the Statement of Reasons (Document
Reference: 4.01) which accompanies this Application, the proposed
development would not necessitate the compulsory acquisition of any freehold
land and only seeks to acquire rights over two sections of the disused railway
line in order to facilitate the electrical connection, significantly minimising the
extent of compulsory acquisition required when compared to the large area of
land needed to bring forward a significant power generation development.
Transport Infrastructure (NPS EN-2, 2.2.5 – 2.2.6)
5.3.8 Paragraph 2.2.5 of NPS EN-2 emphasises that new fossil fuel generating
stations will need to be accessible for the delivery and removal of construction
materials, fuel, waste and equipment, and for employees. Multi-modal transport
methods are promoted by government policy.
5.3.9 The proposed development would be situated within the existing steelworks
site, which is accessible by means of road, rail or sea. All three of these modes
of transport are utilised for the existing site operations and would continue to be
used for the construction and operation of the proposed development.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 99
5.3.10 Chapter 10 (Traffic and Transport) of the ES provides an in-depth assessment
on the effects of the projects and the opportunities to improve transport
sustainability.
Water Resources (NPS EN-2, 2.2.7 – 2.2.9)
5.3.11 Paragraph 2.2.9 of NPS EN-2 states that:
“High water demands will mean that developers’ preferred sites are likely
to be coastal, beside estuaries or alongside large rivers. If sufficient
quantities of water from natural sources are not available at a site then
some use of mains supplies may be necessary, although it should be
noted that a water company has no duty to supply water. If a sufficient
supply of water is not available, an alternative means of cooling such as
air-cooled condensers would be required.”
5.3.12 The proposed development would use a water cooling system as part of its
operations. This would take the form of an ‘open system’, which is where water
used in the turbine condensers is cooled in cooling towers and recycled back
into the system. The current system that is in use on the site is far less efficient
and operates as a ‘feed and return system’, in which water is abstracted from
Port Talbot Dock, used in the heat exchanger and returned to the Dock.
5.3.13 The volumes of water required for the new system are far less than those
currently required. This represents betterment over and above the existing
situation and, therefore, it is considered that the proposed development
complies with Section 2.2 of NPS EN-2.
5.3.14 Further information regarding abstraction and discharge, together with the
necessary mitigation has been assessed in the ES at Chapter 14 (Surface
Water Environment).
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 100
Grid Connection (NPS EN-2, 2.2.10 – 2.2.11)
5.3.15 Paragraph 2.2.10 of NPS EN-2 relates to the technical feasibility of exporting
electricity from the proposed site, which is dependent upon the capacity of the
grid network to accept the likely electricity output, together with the voltage and
distance of the connection. Information must be provided in relation to the grid
connection and its associated environmental issues.
5.3.16 Consideration has already been afforded to the grid connection under
paragraph 5.2.53 of this statement. Further information on this topic can be
found in Chapter 3 (Project Description) of the ES.
Climate Change Adaption (NPS EN-2, 2.3.13 – 2.3.14)
5.3.17 Paragraph 2.3.13 relates to energy and climate change and makes reference to
Part 2 of NPS EN-1 which, at Section 4.8, sets out generic considerations that
the applicant and PINS should take into account. Paragraph 2.3.13 states that:
“As fossil fuel generating stations are likely to be proposed for coastal or
estuarine sites and climate change is likely, for example, to increase risks
from flooding or rising sea levels, applicants should in particular set out
how the proposal would be resilient to:
coastal changes and increased risk from storm surge;
effects of higher temperatures, including higher temperatures
of cooling water; and
increased risk of drought leading to a lack of available cooling
water.”
5.3.18 Matters relating to climate change are considered above at paragraph 5.2.35 –
52 and set out in more detail in ES Chapter 13 (Flood Risk). The proposed
development would result in numerous benefits that would combat climate
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 101
change, as well as resulting in cost reductions for the steelworks site that would
secure the long-term future of the entire operation.
Consideration of “Good Design” for Energy Infrastructure (NPS EN-2, 2.3.15 –
2.3.16)
5.3.19 Paragraph 2.3.16 of NPS EN-2 places emphasis on the need for energy
infrastructure projects to demonstrate good design, particularly in respect of
landscape and visual amenity.
5.3.20 This DCO Application is accompanied by a Design & Access Statement
(Document Reference: 10.03) which sets out the design principles for the
development and provides information on the design parameters of the
proposed development as far as practicable to allow for the Application to be
fully considered by the SoS.
5.3.21 Further information on this topic is considered under paragraph 5.2.18 of this
statement and in the ES (Chapter 7 – Landscape & Visual).
Air Quality & Emissions (NPS EN-2, 2.5)
5.3.22 Section 2.5 of NPS EN-2 relates to air quality and emissions and makes
reference to NPS EN-1, which covers generic air emissions impacts.
Paragraph 2.5.5 of NPS EN-2 states that:
“The applicant should carry out an assessment as required in EN-1,
consulting the EA and other statutory authorities at the initial stages of
developing their proposals, as set out in EN-1 Section 4.2….”
5.3.23 The Applicant has consulted extensively with NRW in preparing the Application
and Chapter 5 (Air Quality) of the ES provides detail of the methodology and
outcome of the assessment regarding the air quality and emissions impacts
related to the proposed development and sets out the mitigation measures that
would be put in place to combat significant negative effects.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 102
5.3.24 In summary, the results of the air quality indicate that the proposed
development is expected to have a negligible effect on annual mean NO2 and
PM10 concentrations at the worst affected properties.
5.3.25 Emissions from the proposed development have been assessed through
detailed atmospheric dispersion modelling using best practice approaches. The
assessment has been undertaken based on a number of worst-case
assumptions.
5.3.26 Construction-phase dust effects have been assessed to be low to medium risk if
unmitigated, but are expected to be negligible following the implementation of
appropriate mitigation measures.
5.3.27 Construction related traffic effects on air quality are predicted to be negligible at
receptors adjacent to the main access routes used by traffic associated with the
proposed development.
5.3.28 Two additional boilers (Option 1 or Option 2 Phase 2) are predicted to lead to
an improvement or a negligible increase in concentrations, depending upon the
receptor location. One additional boiler (Option 2 Phase 1) would lead to a
minor adverse impact at some receptors although this is considered to be not
significant.
Landscape & Visual (NPS EN-2, 2.6)
5.3.29 Generic landscape and visual impacts are covered in detail in NPS EN-1. In
addition the generic impacts outlined in NPS EN-2 are the specific
considerations which apply to fossil fuel generating stations. Paragraph 2.6.2
states that:
“The main structures for a fossil fuel generating station, including the
turbine and boiler halls, exhaust gas stacks, storage facilities, cooling
towers, and water processing plant, are large. They will have an impact
on the surrounding landscape and visual amenity.”
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 103
5.3.30 In accordance with the requirements of Section 4.2 of NPS EN-1 and Section
2.6 of NPS EN-2 a LVIA has been undertaken and submitted in support of this
DCO Application. A summary of this is provided at Section 3 of this statement.
Further detail and the full LVIA can be found in Chapter 7 (Landscape & Visual)
of the ES.
Noise & Vibration (NPS EN-2, 2.7)
5.3.31 Section 5.11 of NPS EN-1 covers the generic information of the assessment of
noise and vibration impacts for energy infrastructure projects. NPS EN-2 sets
out the specific considerations which apply to fossil fuel generating stations
which included: (1) the milling of coal; (2) delivery and movement of fuel and
material at coal stations; (3) the operation of gas and steam turbines; and (4)
external noise sources such as air cooled condensers.
5.3.32 Noise and vibration matters related to the proposed development have been
considered in Paragraph 5.2.54 above. A noise assessment has been
undertaken and is included in Chapter 8 (Noise & Vibration) of the ES.
Water Quality & Resources (NPS EN-2, 2.8)
5.3.33 Section 2.10 of NPS EN-2 reiterates the generic water quality and resource
impacts, which are also set out in Section 5.15 of NPS EN-1. Paragraph 2.10.2
of NPS EN-2 states that:
“Where the project is likely to have effects on water quality or resources
the applicant should undertake an assessment as required in EN-1
Section 5.15. The assessment should particularly demonstrate that
appropriate measures will be put in place to avoid or minimise adverse
impacts of abstraction and discharge of cooling water.”
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 104
5.3.34 Paragraph 5.2.35 of this statement provides an overview of the water quality
and resources impacts which area covered in further depth in Chapter 14
(Surface Water Environment) of the ES.
5.4 NPS 4 – Gas Supply Infrastructure & Gas and Oil Pipelines (NPS EN-4)
5.4.1 This NPS covers large underground gas storage and liquid natural gas facilities;
large gas reception facilities; gas transporter pipelines conveying gas to at least
50,000 potential customers; and oil and gas cross country pipelines, over 16
kilometres in length.
5.4.2 The NPS sets out technology related criteria, some of which are general and
some are relevant to specific infrastructure. General criteria include Climate
Change Adaptation, Good Design Principles, Noise and Vibration. Specific
criteria include Underground Natural Gas Storage, Liquid Natural Gas Import
Facilities, Gas Reception Facilities, and Networks Link Import Facilities,
Refineries, Storage and Distribution Facilities.
5.4.3 The proposed development incorporates an extension of the pipe work that
already exists for the existing power generation facilities and the existing gas
distribution, steam and utilities network. This alone would not constitute a NSIP
and does not meet the criteria defined in NPS EN-4. As such, NPS EN-4 is not
considered to be a material consideration applicable to the proposed
development. Nevertheless, the main headings from NPS EN-4 that are
applicable to gas supply infrastructure have been included as part of this
planning assessment.
Climate Change Adaption (NPS EN-4, Part 2 - 2.2)
5.4.4 Section 2.2 of NPS EN-4 relates to the specific considerations associated with
energy infrastructure projects and climate change. Paragraph 2.2.2 states that:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 105
“As climate change is likely to increase risks to some of this
infrastructure, from flooding or rising sea levels for example, applicants
should in particular set out how the proposal would be resilient to:
increased risk of flooding;
effects of rising sea levels and increased risk of storm surge;
higher temperatures;
increased risk of earth movement or subsidence from
increased risk of flooding and drought; and
any other increased risks identified in the applicant’s
assessment.”
5.4.5 Paragraph 5.2.34 of this statement incorporates an overview of the assessment
of climate change in relation to the proposed development. Further information
regarding this matter is included in ES Chapter 13.
Consideration of Good Design (NPS EN-4, Part 2 - 2.3)
5.4.6 Paragraph 2.3.2 refers to good design, which should be considered where
mitigating the impacts relevant to gas supply infrastructure.
5.4.7 The Design and Access Statement (Document Reference: 10.03) provides an
in-depth assessment of design related matters and the principles of design that
are incorporated into the proposal. A summary of the effects and mitigation has
been provided in paragraph 5.2.18 of this statement. Further information can
be found in ES Chapter 7 (Landscape & Visual).
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 106
Hazardous Substances (NPS EN-4, Part 2 - 2.3)
5.4.8 Section 2.4 of NPS EN-4 states that, in the case of gas supply infrastructure,
the HSE will advise PINS on the risks, taking into account the quantities of gas
to be stored, the installation type and specification, and the local population.
5.4.9 The proposed development would not result in the need to store gas on-site and
would not utilise hazardous substances.
Gas & Oil Pipelines: Safety (NPS EN-4, Part 2 - 2.19)
5.4.10 The proposed development would incorporate an extension to the existing gas
pipeline infrastructure already on the site. Paragraph 2.19.4 of NPS EN-4
relates to gas pipeline safety and requires that pipelines are designed,
constructed and operated so that risks are as low as is reasonably practicable.
5.4.11 Full details of the proposed pipeline extension work can be found in ES Chapter
3 (Project Description). The Applicant will liaise with the HSE in relation to the
construction of the additional pipeline network, albeit to existing connections
within the Order Limits. A Health and Safety Statement has been prepared as
part of the Application.
Gas & Oil Pipelines Impacts: Noise & Vibration (NPS EN-4, Part 2 - 2.20)
5.4.12 In addition to the generic considerations to be given to the impacts of noise and
vibration are the specific considerations which apply to gas pipelines during the
pre-construction and construction phases.
5.4.13 This statement considers the impacts of noise and vibration at paragraph
5.2.140. Further information on these matters is provided in the ES Chapter 8
(Noise & Vibration).
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 107
Gas & Oil Pipelines Impacts: Biodiversity, Landscape & Visual (NPS EN-4, Part
2 - 2.21)
5.4.14 Section 2.21 of NPS EN-4 relates to biodiversity, landscape and visual impacts
of gas pipelines. Paragraph 2.21.2 states that:
“Long term impacts upon the landscape for pipelines are likely to be
limited, as once operational the main infrastructure is usually buried.
They are likely to include:
limitations on the ability to replant landscape features such as
hedgerows or deep-rooted trees over or adjacent to the
pipeline; and
structures and indication points necessary to identify the
pipeline route and provide it with service access.”
5.4.15 Paragraph 5.2.77 of this statement outline the impacts of the proposed
development on biodiversity and from a visual perspective. Consideration of
the pipeline extension work has been included. Further detail regarding these
potential impacts is included in the ES Chapter 6 (Ecology).
Gas & Oil Pipelines Impacts: Water Quality & Resources (NPS EN-4, Part 2 -
2.22)
5.4.16 The generic policy on the protection of the water environment during
construction, operation and decommissioning of energy projects are set out in
Section 5.15 of NPS EN-1. Paragraph 2.22.3 of NPS EN-4 outlines the specific
considerations in respect of gas pipelines and states that:
“Where the project is likely to have effects on water resources or water
quality, for example impacts on groundwater recharge or on existing
surface water or groundwater abstraction points, or on associated
ecological receptors, the applicant should provide an assessment of the
impacts in line with Section 5.15 of EN-1 as part of the ES.”
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 108
5.4.17 An overview of the generic impacts of the proposed development on water
quality and resources, together with those impacts associated with the gas
pipeline extension has been included in this statement at paragraph 5.2.162.
Further information is incorporated in ES Chapter 14 (Surface Water
Environment).
Gas & Oil Pipelines Impacts: Soil & Geology (NPS EN-4, Part 2 - 2.23)
5.4.18 Section 2.23 of NPS EN-4 relates to the impacts on soil and geology from laying
gas pipelines. This policy document highlights the importance for Applicants to
understand the soil types and nature of underlying strata, which may present
risks to pipeline projects. It also states that impacts could include sterilisation of
mineral resources or loss of soil quality. Accordingly, an assessment of the
ground conditions associated with the pipeline route should be made
(referenced in paragraph 2.23.2 of NPS EN-4).
5.4.19 An assessment of the ground conditions at the application site has been
undertaken and has been presented in the ES. A summary of the findings and
impacts on water quality and resources is included at paragraph 5.2.162 of this
statement.
5.5 NPS 5 – Electricity Networks Infrastructure (NPS EN-5)
5.5.1 This NPS relates to above ground electricity lines whose nominal voltage is
expected to be 132kV or above. Paragraph 1.8.2 of NPS EN-5 states that:
“Any other kind of electricity infrastructure (including lower voltage
overhead lines, underground or sub-sea cables at any voltage, and
associated infrastructure as referred to above) will only be subject to the
Planning Act 2008 – and so be covered by this NPS – if it is in England,
and it constitutes associated development for which consent is sought
along with an NSIP such as a generating station or relevant overhead
line.”
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 109
5.5.2 The proposed development incorporates the provision of a 66kV electrical
connection only, which would be run underground for a distance of 2.8km
connecting the generating station to the existing on-site substation. Sections of
the cable may also be suspended overhead on cable bridges (approximately
5m high), constructed of a lattice style structure, approximately 800m in length
towards the southern end of the electrical connection route between the two
existing substations;
5.5.3 In view of the fact that the proposed development incorporates electricity
network infrastructure that has a voltage of less than 132kV, NPS EN-5 is not
considered to be applicable to the consideration of the proposed development
and, for that reason, does not form a material consideration. Nevertheless, the
most relevant heading of NPS EN-5 have been addressed below.
Climate Change Adaption (NPS EN-5, 2.4)
5.5.4 Section 4.8 of NPS EN-1 sets out the generic considerations that PINS should
take account of in relation to the impact of electricity infrastructure on climate
change. Paragraph 2.4.1 of NPS EN-5 outlines it what circumstances the
proposed development is expected to be resilient to issues associated with
climate change.
5.5.5 An overview of the proposed development’s impacts on, and mitigation for,
climate change have been set out in paragraph 5.2.34 of this statement.
Further information on such matters is included in ES Chapter 3 (Project
Description).
Consideration of Good Design (NPS EN-5, 2.5)
5.5.6 Section 4.5 of NPS EN-1 sets out the principles for good design that should be
applied to all energy infrastructure. Such matters have been broadly
considered under paragraph 5.2.18 of this statement, within the ES (Chapter 7),
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 110
and have been considered in further detail in the Design and Access Statement
which supports this DCO Application.
Biodiversity & Geological Conservation (NPS EN-5, 2.6)
5.5.7 Generic biodiversity effects are covered in Section 5.3 of NPS EN-1. However,
electrical infrastructure presents its own specific impacts for biodiversity and
geology which must be considered by applicants (referenced in paragraph
2.7.2).
5.5.8 Paragraph 5.2.65 onwards of this statement summaries those potential impacts
that the proposed development could have in relation to such matters. The ES
contained further information at Chapter 6 (Ecology).
Landscape & Visual (NPS EN-5, 2.8)
5.5.9 Paragraph 2.8.4 of NPS EN-5 states that:
“While proposed underground lines do not require development consent
under the Planning Act 2008, wherever the nature or proposed route of
an overhead line proposal makes it likely that its visual impact will be
particularly significant, the applicant should have given appropriate
consideration to the potential costs and benefits of other feasible means
of connection or reinforcement, including underground and sub-sea
cables where appropriate.”
5.5.10 The proposed development does not incorporate overhead power lines, aside
from the potential for a cable bridge associated with a small section of the
electrical cable connection route. As such, it is considered that NPS EN-5 is not
applicable to the assessment of this Application.
5.5.11 Paragraph 5.2.18 of this statement provides an overview of the visual and
landscape impacts of the proposed development, together with a summary of
the intended mitigation measures. An LVIA has been undertaken for the
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 111
proposed development and accompanies the submission of this DCO
Application.
5.5.12 Further information on this matter is also comprised in Chapter 7 (Landscape &
Visual) of the ES. These documents all take account of the generic landscape
and visual impacts, but also consider any specific points in relation to the
proposed electricity infrastructure, the impact from which would be negligible.
Noise & Vibration (NPS EN-5, 2.9)
5.5.13 Section 5.11 of NPS EN-1 covers the generic noise effects associated with
noise and vibration from energy infrastructure projects. Section 2.9.8 of NPS
EN-5 states that:
“While standard methods of assessment and interpretation using the
principles of the relevant British Standards18 are satisfactory for dry
weather conditions, they are not appropriate for assessing noise during
rain, which is when overhead line noise mostly occurs, and when the
background noise itself will vary according to the intensity of the rain.”
5.5.14 Paragraph 5.2.54 of this statement summarises the effects of the proposed
development and proposed mitigation in relation to noise and vibration. A Noise
Assessment has been undertaken and accompanies this DCO Application.
Further information on this matter is also included in Chapter 8 (Noise &
Vibration) of the ES.
5.6 National Planning Policy
Planning Policy Wales
5.6.1 As outlined in Section 4 of this statement, PPW sets out the land use planning
policies of the WG and sets out WGs commitment to creating sustainable
developments and communities.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 112
5.6.2 This policy document provides an overview of the planning system and includes
a section on the context for planning in Wales. It does not include specific
policies of relevance to NSIPs which, as-abovementioned, are governed by the
requirements of the PA 2008 and the assessment principles contained within
the relevant NPS. As such, whilst PPW is applicable to the proposed
development and forms a material consideration for this DCO Application, it can
only be afforded limited weight.
5.6.3 An analysis of the applicable sections of PPW in relation to the proposed
development has been provided below.
Chapter 4 – Planning for Sustainability
5.6.4 Section 4.5 (Planning for climate change) of PPW highlights that tackling
climate change is a fundamental part of delivering sustainable development,
which is emphasised by the WGs target to achieve carbon reduction-equivalent
emissions reductions of 3% per year from 2011. Paragraph 4.5.2 of PPW also
states that:
“We are committed to achieving at least a 40% reduction in all
greenhouse gas emissions in Wales by 2020 against a 1990 baseline.
This will assist in making a significant contribution to the UK Carbon
Budgets.”
5.6.5 The desire to cut greenhouse gas emissions is also reflected in the aims of NPS
EN-1 which indicate that at least an 80% reduction should be achieved by 2050,
compared to 1990 levels.
5.6.6 Section 4.6 of PPW emphasises the need to recognise the strength of urban
communities, which are home to the majority of the population in Wales. It
states in paragraph 4.6.1 of PPW that:
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 113
“Development can help to arrest the decline in community facilities and
deliver environmentally-sound modernisation, re-use or replacement of
urban infrastructure.”
5.6.7 Section 4.7 of PPW sets out criteria that local planning authorities should
adhere to when allocating land. This includes locating development so that it
can be well serviced by existing infrastructure (including energy supply, waste
management and water).
5.6.8 Section 4.9 of PPW directs that there is a preference for the re-use of previously
developed land, which will promote sustainability objectives.
5.6.9 The proposed development is intended to improve efficiency and increase
product generation. This would result in a reduction in grid import by 45 MWe,
a reduction in the amount of flared gases by 3.8 PJ per annum, an increase in
operational efficiency and reliability that would secure the long-term future for
the steelworks site as a whole, and would make significant contributions to the
local and national economies. The proposed development also makes use of
an already industrialised site and is supported by existing infrastructure. In view
of this, the proposed development is considered to be fully compliant with the
objectives of the WG as outlined under the sustainability chapter of PPW.
Chapter 5 – Conserving & Improving Natural Heritage & the Coast
5.6.10 The site is note constrained by any landscape or ecological designations,
however, there are some designations within close proximity to the steelworks
site and within the 15km study area. The site is also located on the coastline
and can be viewed from a handful of areas designated for their landscape
value.
5.6.11 PPW recognises at paragraph 5.1.3 of PPW that conservation and development
can often be fully integrated. Whilst the value of the landscapes in Wales is
recognised by PPW, the policy also stresses the need to have regard to the
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 114
relative significance of designations and avoiding placing unnecessary
constraints on development.
5.6.12 Paragraph 5.5.5 advises that statutory designation do not necessarily prohibit
development, but proposal for development must be carefully assessed for the
effect on those natural heritage interests which the designation is intended to
protect.
5.6.13 In accordance with the requirements of the NPSs, and in particular the
assessment principles identified in NPS EN-1, the proposed development has
been assessed in light of all the relevant nearby designations having regard to
the features of acknowledged ecological and landscape importance. Technical
assessments have been undertaken in this regard and conclude that the
detrimental impacts of the proposed development can be suitably mitigated and,
in any case, are vastly outweighed by the benefits the scheme offers.
Chapter 6 – Conserving the Historic Environment
5.6.14 Chapter 6 of PPW places emphasis on the need to preserve or enhance the
historic environment.
5.6.15 There are no listed buildings, SAMs, or Registered Parks and Gardens within
the confines of the application site. However, within the 1km study area there
are 99 previously recorded heritage assets. Following consultation with
Glamorgan Gwent Archaeological Trust and Cadw archaeological constraints
were identified at the Margam Copper Works and the Margam Iron and Steel
Works.
5.6.16 A full impact assessment of the significance of effects on these assets is
incorporated in the ES. An overview of this has been included at paragraph
5.2.114 of this statement. Having considered the proposed development
against the setting of these features of acknowledged importance it is
considered that the detrimental impact would be minimal. In terms of the
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 115
potential impacts upon archaeology, this would be controlled by way of a
watching brief style condition, which is set out in the draft DCO.
Chapter 7 – Economic Development
5.6.17 PPW has recently been revised (February 2014) to take account of TAN 23
(Economic Development) and now places further weight on the need for the
planning system to support economic and employment growth alongside social
and environmental considerations within the context of sustainable
development.
5.6.18 In particular, paragraph 7.2.2 of PPW states that:
“Local planning authorities are required to ensure that the economic
benefits associated with a proposed development are understood and
that these are given equal consideration with social and environmental
issues in the decision-making process, and should recognise that there
will be occasions when the economic benefits will outweigh social and
environmental considerations.”
5.6.19 The proposed development offers a host of economic benefits which would be
felt by the local and national economies during both the construction and
operational phases of the development, including the long-term support the
proposed development will offer the steelworks as a whole in terms of efficiency
savings, which in turn will increase the capacity of the steelworks to continue
supporting the local economy.
5.6.20 In addition, to the economic benefits of the proposed development are the vast
reductions in carbon emissions, which are supported by paragraph 7.4.1 of
PPW that recognises the shift towards a low carbon economy and encourages
the development of eco-industrial networks.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 116
Chapter 8 - Transport
5.6.21 Paragraph 8.1.1 of PPW states that:
“The Welsh Government aims to extend choice in transport and secure
accessibility in a way which supports sustainable development and helps
to tackle the causes of climate change by: encouraging a more effective
and efficient transport system, with greater use of the more sustainable
and healthy forms of travel, and minimising the need to travel.”
5.6.22 PPW aims to achieve sustainable transport through the implementation of a
number of key objectives. Paragraph 8.7.1 relates to development
management and transport, and provides a list of those matters that should be
considered when determining applications. Paragraph 8.7.2 recognises that the
provision of a TA is an important mechanism for setting out the scale of
anticipated impacts of a proposed development.
5.6.23 This DCO Application is accompanied by a TA which has considered the traffic
and transport implications associated with the proposed development. This has
concluded that the additional traffic generation would not result in a significant
detrimental impact upon the highway network or local amenity. Moreover, a TP
has been prepared which would seek to minimise single occupation trips and
encourage sustainable modes of transport.
Chapter 11 – Tourism, Sports and Recreation
5.6.24 PPW identifies tourism as being vital to economic prosperity and job creation
within Wales, which the WG consider to be a significant and growing source of
employment and investment.
5.6.25 The proposed development sits within the confines of the existing Port Talbot
site and, therefore, would be seen against the backdrop of the existing
structures and buildings that form the steelworks. The impacts of the proposed
development on tourism have been considered in the ES, of which there are
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 117
positive and negative influences. However, the positive influences (i.e. the
need for accommodation for construction workers or visitors) are considered to
significantly outweigh the negative impacts (i.e. visual harm) given that the
proposed development will be consumed by the existing steelworks buildings
and would therefore not cause significant undue harm to visual amenity of the
area as a whole. This is qualified by the LVIA, contained within the ES.
Chapter 12 – Infrastructure & Services
5.6.26 This chapter of PPW deals with infrastructure and services, that is the issues of
water supply and waste water management, waste management, energy supply
from renewable and low carbon sources, and telecommunications. Paragraph
12.1.4 states that:
“The Welsh Government aims to secure the environmental and
telecommunications infrastructure necessary to achieve sustainable
development objectives, while minimising adverse impacts on the
environment, health and communities.”
5.6.27 PPW supports the use of existing infrastructure in order to achieve sustainable
development. The proposed development comprises an extension to the
existing steelworks operations that would improve efficiency, reduce energy
consumption and contribute to the economy.
5.6.28 Section 12.8 of PPW relates to renewable and low carbon energy and was
updated in February 2014 to take account of the UK Renewable Energy
Roadmap: 2013. This sets the path for the delivery of renewable energy
schemes to meet the target of 15% of electricity to come from renewable
sources by 2020, introduced in 2009 in the European Union Renewable Energy
Directive. In addition, emphasis is given to the WG’s Energy Policy Statement –
Energy Wales: A Low Carbon Transition (2012), which outlines the commitment
to the delivery of the energy programme in order to contribute to reducing
carbon emissions.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 118
5.6.29 The Energy Wales: A Low Carbon Transition document has been given
additional weight following its insertion into national planning policy for Wales.
This document reinforces the importance of energy, which is said to underpin
our entire way of life. It makes it clear that there is a need to ensure Wales is in
the best possible position to not only create new jobs and supply chain
opportunities, but also to take advantage of the potential to export energy
expertise, goods and services to other nations seeking to make the transition to
a low carbon economy.
5.6.30 Paragraph 12.8.2 of PPW states that:
“The Welsh Government is committed to playing its part by delivering an
energy programme which contributes to reducing carbon emissions as
part of our approach to tackling climate change.”
5.6.31 The proposed development would provide an enhanced on-site energy
generation project that would allow for the production of a sustainable form of
electricity for use on the site, enabling a vast reduction in imported electricity
from the grid, together with decreased volumes of flared gases. By generating
power through the reuse of process gases, it is estimated that the reduction in
electricity imports to the steelworks from the national grid would equate to an
off-set of approximately 400,000 tonnes per annum of CO2 (based on a fossil
fuel generating station). The proposed development is therefore considered to
comply with the aspirations of Chapter 12 of PPW.
Chapter 13 – Minimising & Managing Environmental Risks & Pollution
5.6.32 The WG has defined two objectives within this chapter of PPW: (1) maximise
environmental protection for people, natural and cultural resources, property
and infrastructure; and (2) prevent or manage pollution and promote good
environmental practice.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 119
5.6.33 The ES submitted in support of this DCO application has sought to address
such matters and concludes that the impacts of the proposed development on
the environment can be acceptably managed.
5.6.34 Paragraph 13.1.14 of PPW states that special attention should be given to
minimising the risks associated with climate change. The proposed
development will reduce the steelworks’ overall carbon footprint and has clear
benefits which will help to reduce climate change. The proposed development’s
resilience to the effects of climate change is set out in more detail above at
paragraph 5.2.35.
5.6.35 Chapter 13 advises that NRW and other bodies with an interest in managing the
environment should advise planning authorities as to where climate change will
increase the specific risks to areas proposed for development. The proposed
development has evolved through consultation with NRW and various other
bodies that share an interest in the features applicable to the application site.
The matters raised in the specific consultation responses have been suitably
addressed as part of this submission.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 120
6 DCO Requirements
6.1 Overview
6.1.1 It is a requirement of the PA 2008 for all DCO applications to be accompanied
by a draft of the DCO, together with an explanatory memorandum explaining
the purpose and effect of each provision in the draft order. Accordingly, a draft
DCO has been prepared and submitted in support of this Application. This has
been written in the form of a Statutory Instrument and is accompanied by
explanatory notes for each provision.
6.1.2 The Applicant has made every effort to set all components / scheme
requirements as far as possible. The level of consultation undertaken on the
lead-up to this submission has enabled the evolution of this proposed
development. .
6.1.3 An overview of the considerations applicable to the proposed development has
been provided in this statement. Further detail on these matters is provided in
the ES, which outlines any mitigation proposed as part of the proposed
development in order to ensure that the proposed development is acceptable
and does not result in significant detriment. Securing mitigation will be pertinent
to any decision being issued, the requirements for which are provided in the
draft DCO.
6.2 Planning Requirements
6.2.1 The draft DCO includes provisions which give the developer the authority to
take actions necessary for the proposed development to be implemented
satisfactorily. One such provision is known as the ‘Requirements’ to which the
development authorised by the DCO is to be subject. Requirements are similar
to conditions that are imposed on planning permissions granted under the Town
and Country Planning Act 1990, insofar as they specify matters for which
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 121
detailed approval needs to be obtained before the development can be lawfully
commenced / completed.
6.2.2 It is necessary to control some aspects of the proposed development by way of
suitably worded requirements given that it will not be possible to design-in all
mitigation at this stage. The first draft of the requirements are included at
Schedule 2 of the draft DCO submitted with the Application. The specific
wording for the proposed requirements will be developed in consultation with
NPTCBC, who will be the authority responsible for ensuring the requirements
are discharged.
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 122
7 Conclusion
7.1.1 The proposed development of an Internal Power Generation Enhancement
Project at the existing Port Talbot Steelworks site has been devised in order to
improve the energy efficiency, increase electrical generation and reduce the
flaring of the process gases on-site, allowing for the Applicant to remain cost
competitive and enable an increased production of iron per annum from 4.1
million tonnes to 4.7 million tonnes. This is crucial to support the viability of the
steelworks site as a whole and secure the longevity of the site operations, which
need to be competitive in this global market.
7.1.2 The principle of constructing an extension to this existing operational facility is
clearly acceptable from a planning policy perspective – at national and local
levels. The aspirations of the proposed development meet the Government’s
objectives for reducing carbon emissions and contributing to the European
Union’s Energy Directive, introduced in 2009, together with the WGs Energy
Policy Statement – Energy Wales: A Low Carbon Transition (2012), which
outlines the commitment to the delivery of the energy programme in order to
contribute to reducing carbon emissions.
7.1.3 Furthermore, and as demonstrated in detail in each of the technical
assessments and the ES (submitted with this DCO application), the proposed
development is fully compliant with the aims and objectives of the relevant
NPSs (EN-1, EN-2, EN-4 & EN-5), PPW and the adopted UDP.
7.1.4 In summary, this Internal Power Generation Enhancement Project provides the
following benefits:
the proposed development would result in a total on-site generation
capacity of up to 245 MWe of electricity to power the on-site operations
and for export to the national grid;
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 123
the proposed development would allow for an off-set of approximately
400,000 tonnes per annum of CO2 through a reduction in electricity
import from the national grid;
the proposed development would result in a direct investment by the
applicant of in excess of £200 million into the County Borough of Neath
Port Talbot and the Welsh economy; and
the proposed development would utilise existing infrastructure, the use
of which is encouraged by Neath Port Talbot, and will constitute
development on an existing industrial site that will secure the continued
operation of the steelworks into the future.
7.1.5 The proposed development is considered to be acceptable and policy compliant
for the following reasons:
the proposed development would not result in any detrimental impact on
highway capacity or safety in the surrounding network;
the proposed development has been assessed having regard to the
potential for noise and vibration, which would be minimal and can be
suitably controlled by appropriate mitigation;
an air quality assessment has been undertaken for the proposed
development having regard to pollutant concentrations and sensitive
receptors in the vicinity of the site. This demonstrates that the
maximum long-term impacts in the worst case scenario are well below
the requirements of the Neath Port Talbot Local Air Quality Strategy –
there is therefore no demonstrable harm to local air quality;
the proposed development would not have a significant detrimental
impact on the ecological resource, which can be suitably managed;
The Port Talbot Steelworks (Power Generation Enhancement) Order Planning Statement 10.01
July 2014 124
the proposed development would not result in detriment to features of
acknowledged importance in respect of archaeological resource of
cultural heritage assets;
the visual effects of the proposed development on the surrounding
landscape character would generally be minor and negligible and not
significant, largely due to the scale of the proposed development which
would sit well within the existing Port Talbot site;
the proposed development has been assessed in accordance with the
requirements of TAN 15 and it has been demonstrated that the risks
from with flooding can be acceptably managed; and
the proposed development is in accordance with principles of the
relevant NPSs and the relevant strategies of the WG and does not
conflict with the Development Plan, both extant and emerging for Neath
Port Talbot.
7.1.6 The findings of the Environmental Impact Assessment are reported in the ES,
which supports this DCO Application. Whilst, inevitably, the proposed
development would result in impacts on the local environment, none of these
are considered to be significantly detrimental and can be acceptably managed
through appropriate mitigation.
7.1.7 The proposed development complies with all aspects of planning policy, and will
not result in any significant detrimental environmental impacts that would not be
outweighed by the benefits of the proposed development. In this light, the
proposed development is considered to be acceptable and clear justification
exists for Development Consent to be granted.
The Port Talbot Steelworks (Power Generation Enhancement) Order
10.01 Planning Statement
Appendices
The Port Talbot Steelworks (Power Generation Enhancement) Order
10.01 Planning Statement
Appendix A: Existing Site Layout Plan (inclusive of the “Order Limits”)
#*#*
#*
#*
#*
Margam B, Mitchell Boiler
Margam C, Boilers 6&7
Margam A , Boiler 5
Service Boilers 4&5
GrangeSubstation
No.3 Boiler
Cefn Gwrgan Substation
Ogmore Vale Railway Line
Site Access Road
©Crown copyright. All rights reserved. License Number 0100031673
This document has been prepared by AECOM for the sole use of our Client (the "Client") and in accordance with generally accepted consultancy principles, the budget for fees and terms of reference agreed between
Drawn:
Date:
Checked:Scale at A3:Revision:
Drawing Reference:
AECOM and the Client. Any information provided by third parties and referred to herein has not been checked or verified by AECOM, unless otherwise expressly stated in the document. No third party may rely upon this document without the prior and express written agreement of AECOM.
1 Callaghan SquareCardiffCF10 5BT
Tel +44 (0)29 2067 4600Fax +44 (0)29 2067 4699
www.aecom.com
Ü
Regulation:
A3
Project:
Title:
0 490 Metres
EXISTING SITE LAYOUT PLAN
GM5(2)(o)
CM
AUGUST 20142.02 - Existing Layout Plan
KEY:#* Existing Chimney Stacks
Harbour Way (opened October 2013, not shown oncurrent OS map)Order Limits
1:10,000Client:
THE PORT TALBOT STEELWORKS (POWER GENERATION ENHANCEMENT) ORDER01
The Port Talbot Steelworks (Power Generation Enhancement) Order
10.01 Planning Statement
Appendix B: Site Location Plan
GF
©Crown copyright. All rights reserved. License Number 0100031673
This document has been prepared by AECOM for the sole use of our Client (the "Client") and in accordance with generally accepted consultancy principles, the budget for fees and terms of reference agreed between
Drawn:
Date:
Checked:Scale at A3:Revision:
Drawing Reference:
AECOM and the Client. Any information provided by third parties and referred to herein has not been checked or verified by AECOM, unless otherwise expressly stated in the document. No third party may rely upon this document without the prior and express written agreement of AECOM.
1 Callaghan SquareCardiffCF10 5BT
Tel +44 (0)29 2067 4600Fax +44 (0)29 2067 4699
www.aecom.com
Ü
Regulation:
A3
Project:
Title:
0 10,000 Metres
LOCATION PLAN
GM5(2)(o)
CM
JULY 20142.01 - Site Location
KEY:GF Site Location
1:250,000Client:
THE PORT TALBOT STEELWORKS (POWER GENERATION ENHANCEMENT) ORDER01
The Port Talbot Steelworks (Power Generation Enhancement) Order
10.01 Planning Statement
Appendix C: Sites of Landscape Importance
©Crown copyright. All rights reserved. License Number 0100031673
This document has been prepared by AECOM for the sole use of our Client (the "Client") and in accordance with generally accepted consultancy principles, the budget for fees and terms of reference agreed between
Drawn:
Date:
Checked:Scale at A3:Revision:
Drawing Reference:
AECOM and the Client. Any information provided by third parties and referred to herein has not been checked or verified by AECOM, unless otherwise expressly stated in the document. No third party may rely upon this document without the prior and express written agreement of AECOM.
1 Callaghan SquareCardiffCF10 5BT
Tel +44 (0)29 2067 4600Fax +44 (0)29 2067 4699
www.aecom.com
Ü
Regulation:
A3
Project:
Title:
0 1,000 Metres
SITES OF LANDSCAPE IMPORTANCE
GM5(2)(l)
CM
AUGUST 20142.07.2 - Sites of Landscape Importance
KEY:Conservation AreaLandscape of Outstanding Historic InterestOrder Limits
1:25,000Client:
THE PORT TALBOT STEELWORKS (POWER GENERATION ENHANCEMENT) ORDER01
The Port Talbot Steelworks (Power Generation Enhancement) Order
10.01 Planning Statement
Appendix D: Nature Conservation Sites, Habitats and Diversity Features
©Crown copyright. All rights reserved. License Number 0100031673
This document has been prepared by AECOM for the sole use of our Client (the "Client") and in accordance with generally accepted consultancy principles, the budget for fees and terms of reference agreed between
Drawn:
Date:
Checked:Scale at A3:Revision:
Drawing Reference:
AECOM and the Client. Any information provided by third parties and referred to herein has not been checked or verified by AECOM, unless otherwise expressly stated in the document. No third party may rely upon this document without the prior and express written agreement of AECOM.
1 Callaghan SquareCardiffCF10 5BT
Tel +44 (0)29 2067 4600Fax +44 (0)29 2067 4699
www.aecom.com
Ü
Regulation:
A3
Project:
Title:
0 1,000 Metres
NATURE CONSERVATION SITES, HABITATS AND DIVERSITY FEATURES
GM5(2)(l)
CM
AUGUST 20142.07.1 - Conservation Sites
KEY:National Nature ReserveSpecial Areas of ConservationSite of Special Scientific InterestLocal Nature ReservesAncient WoodlandWoodlandSurface WaterOrder Limits
1:25,000Client:
THE PORT TALBOT STEELWORKS (POWER GENERATION ENHANCEMENT) ORDER01