the team lincoln cummings (ie) – project manager joe calkins (me) – chief engineer mark fazzio...

28
R I T R I T 05002 05002 Micro Turbine III Senior Micro Turbine III Senior Design Design

Post on 19-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

R I TR I T

0500205002Micro Turbine III Senior DesignMicro Turbine III Senior Design

Page 2: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

The Team

Lincoln Cummings (IE) – Project Manager

Joe Calkins (ME) – Chief Engineer

Mark Fazzio (ME) – Technical Writer

Allison Studley (ME) – Minutes Taker

Dr. Kozak – Faculty Advisor

Dr. Walter – Faculty Coordinator

Sponsor – RIT Mechanical Engineering Dept.

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 3: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Team Assignments

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

05002 Micro-Turbine ProjectLeader – Cliff CummingsMentor – Prof. Jeff Kozak

Fuel SystemsLead – MarkAsst. - Cliff

PDR/CDR

PaperLead – Mark

PresentationLead - Joe

Turbine and HousingLeads – Joe/Allison

Page 4: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Mission StatementWe will design and build a micro-turbine/generator that can be integrated onto a micro-air-vehicle airframe and power the vehicle’s accessories. The micro-turbine will be a continuation of the previous team’s project with the application of their design to be used for MAV power production.

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 5: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Background• Current battery technology causes the

battery to be up to half of the weight of the MAV.

• Research into lighter weight power generation methods led to micro-turbine generators.

• Third generation RIT Senior Design project

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 6: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Primary Objectives• Produce a constant 5 watts of power• Overall weight of less than 45 grams• Integrated into the MAV airframe• Minimum flight time of 3 minutes

Additional Objectives• Drive the propeller of the plane• Increase efficiency of the system

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 7: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Previous Design

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 8: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Previous Turbine Design

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Senior Design Team 04013

Page 9: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Concept Considerations

• Smaller housing needed to integrate into MAV airframe

• Compressed gas containers must be integrated into MAV airframe

• Components capable of high rotational speeds• Containment of high pressures within the system• Minimum 3 minute run time• Overall system weight goal of 45 grams

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 10: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Research Methods

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

• Preliminary Research

• Review of last year’s design

• Additional Research

Page 11: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Feasibility Assessment

Last Year's Design 2 Inlet 2 Outlet ConceptCost 3 2Size 3 2Weight 3 3Availability 3 3Manufacturability 3 2

Average 3.00 2.40Normalized Average 1.00 0.80

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

• 2 Options – Direct Comparison

• >2 Options – Weighted ComparisonWeighting Air Bearings Magnetic Bearings Axial Bearings Radial Bearings

Cost 0.2 4 4 3 2Size 0.1 5 5 2 2Weight 0 3 3 3 3Availability 0.35 5 5 2 2RPM Rating 0.35 2 2 3 3

Weighted Average 3.75 3.75 2.55 2.35Normalized Average 1.25 1.25 0.85 0.78

Page 12: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Feasibility AssessmentConsiderations

• Ability to meet the objectives

• Overall Size

• Total Weight

• Availability of procured items

• Ease of Manufacture

• Cost of procurement/manufacture

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 13: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Turbine Concepts

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

3-D Pelton Wheel Turbine

2-D Pelton Wheel Turbine

Francis Turbine

Axial Impulse Turbine

Page 14: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Turbine Feasibility

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 15: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Turbine Feasibility

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

3-D Pelton Wheel Turbine

2-D Pelton Wheel Turbine

Francis Turbine

Axial Impulse Turbine

?

Page 16: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Housing Concept• Cross flow design• 2 Inlets – 2 Outlets• Tight tolerances to

prevent flow from going around the turbine.

• 30% Fiberglass reinforced Nylon material

• Overall Size: 1.25” OD

0.6” Depth

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 17: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Housing Feasibility• Smaller OD• Lighter weight• O-Ring seal vs.

Gasket seal• Inlet/Outlet redesign• Designed for

manufacturability

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 18: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Housing Analysis

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 19: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Propellant System Concepts

Fuel• Compressed CO2 Cartridges• Compressed N2 Cartridges• Compressed Air TanksTubing• Flexible plastic lines• Rigid metal linesRegulator• Bellows regulator to decrease the inlet pressure• Micro nozzle to decrease the inlet pressure

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 20: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Propellant System Feasibility

Fuel• Compressed CO2 Cartridges• Compressed N2 Cartridges• Compressed Air TanksTubing• Flexible plastic lines• Rigid metal linesRegulator• Bellows regulator to decrease the inlet pressure• Micro nozzle to decrease the inlet pressure

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 21: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Other Design Concepts/Considerations

• Bearings: Sealed Air Shielded Magnetic

• Seals: O-Ring Gasket

• Use outlet flow in rear of wings/plane to reduce pressure drag

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 22: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Other Design Concepts/Considerations

• Bearings: Sealed Air Shielded Magnetic

• Seals: O-Ring Gasket

• Use outlet flow in rear of wings/plane to reduce pressure drag

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 23: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Test Setup

• Test initially using

laboratory supplied

compressed nitrogen.

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

• Canister compressed gas testing will be performed after concept is proven

Page 24: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Financial Analysis

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

05002 Micro-Turbine III Project

Component Description Price per Qty Line PriceHousing Turbine $96.00 1 2 $192.00

Nylon rod $5.97 foot 1 $5.97machining $10.00 1 1 $10.00fittings $1.00 1 4 $4.00bearings $40.00 10 10 $40.00coupling $14.09 10 10 $14.09Mini Stainless Steel Shaft $3.93 1 1 $3.93O-Ring $4.00 100 100 $4.00Nylon cheese head screw $5.60 100 100 $5.60black nylon 6/6 nut $10.00 100 10 $1.00

Fuel Systems Ni Canisters $20.00 1 2 $40.00Connector $0.62 1 2 $1.24O-Ring $7.50 1 2 $15.00Puncture components $20.00 1 2 $40.00Jets $100.00 50 50 $100.00

Electrical Generator $200.00 1 1 $200.00

Overall Cost $676.83

Page 25: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Final Design

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 26: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Design Limitations• Propellant cartridge & piercing device weight is

24x higher than the design target weight

• Means of reducing the pressure of the propellant are inefficient

• Finding a generator to meet the high speed requirements

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 27: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Schedule

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design

Page 28: The Team Lincoln Cummings (IE) – Project Manager Joe Calkins (ME) – Chief Engineer Mark Fazzio (ME) – Technical Writer Allison Studley (ME) – Minutes

Questions?

05002 Micro Turbine III Senior Design05002 Micro Turbine III Senior Design