the wide area view: synchrophasors - nysrc.org meeting material/070810... · • current wasas...
TRANSCRIPT
10/15 10/29
1/28
The Wide Area View:
SynchrophasorsAn Intelligent Utility Reality Webcast
July 8, 2010
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
The Wide Area View: Synchrophasors
Phil CarsonEditor-in-ChiefIntelligent Utility Daily
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
The Wide Area View: Synchrophasors
Tony JohnsonConsulting EngineerSouthern California Edison
Jeff Younger Assistant Manager of Electronic SystemsSalt River Project (SRP)
Chantal HendrzakProject Manager and Applied Research DirectorPJM Interconnection
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
AgendaIntroduction
• Our definition of an intelligent utility
• As the grid becomes two-way, so does the conversation
The discussion
• Tony Johnson, Southern California Edison, explains synchrophasor technology and how it applies to SCE
• Jeff Younger, Salt River Project, discusses situational awareness and wide area measurement and control
• Chantal Hendrzak, PJM Interconnection, talks about how this applies to a multi-utility project
Q&A
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
10/15 10/29
1/28
Introduction: An intelligent utility operation
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
7
© Copyright 2009, Southern California Edison
Outline
• What is a SynchroPhasor
• WASAS Design Considerations / Requirements
• WASAS System Design Overview
Join the conversation on Twitter using #IUWebcasts
and follow Intelligent Utility on Twitter @IntelUtil
8
© Copyright 2009, Southern California Edison
What is a SyncroPhasor?
9
© Copyright 2009, Southern California Edison
Keys to the success of SyncroPhasors
• Accurate time stamp
• Voltage, Current, and Frequency
• Magnitude and angle
• 30 Samples per second
• From points all over the grid
Join the conversation on Twitter using #IUWebcasts
and follow Intelligent Utility on Twitter @IntelUtil
10
© Copyright 2009, Southern California Edison
Outline
• What is a SyncroPhasor
• WASAS Design Considerations / Requirements
• WASAS System Design Overview
Join the conversation on Twitter using #IUWebcasts
and follow Intelligent Utility on Twitter @IntelUtil
11
© Copyright 2009, Southern California Edison
WASAS Design Considerations / Requirements
• Not a synchrophasor data only system – a wide-area situation awareness system primarily for use by control center operators– EMS/SCADA data
– Non-electrical data (weather, fire, traffic, earthquake, etc.)
– More will be added in the future!!!
• Not a standalone system – must interface with variety of external systems– Other SCE systems, such as EMS/SCADA, engineering database, etc.
– External data servers for weather, fire, traffic, earthquake data
– Synchrophasor data from phasor systems of other utilities (e.g. WECC member utilities)
– May interface with more SCE internal and external systems in the future
Join the conversation on Twitter using #IUWebcasts
and follow Intelligent Utility on Twitter @IntelUtil
12
© Copyright 2009, Southern California Edison
WASAS Design Considerations / Requirements (cont.)
• Will need to evolve to become a wide-area monitoring, protection
and control system (WAMPACS) over time
– Must be able to support all types of wide-area monitoring, protection
and control applications
• System expansion anticipated
– More phasor measurements from SCE and others
– Other data (e.g. IED data)
• Will be part of SCE’s overall Smart Grid deployment
– Leverage SCE existing IT infrastructure and common services
13
© Copyright 2009, Southern California Edison
WASAS Design Considerations / Requirements (cont.)
• Current WASAS deployment complete by end of 2011 as an
approved GRC project including all procurement, engineering,
deployment, installation, and testing processes
External
SCE
2-4 sec
LEGEND
External system
Data Store
Future
Functionality
WASAS system
Future System
External data
( e.g. weather, traffic,
fire, earthquake)
External Phasor data
(WECCnet/NASPInet)
External Direct P&C
(WECCnet/NASPInet)
EMS/
SCADA Other Data
Services (e.g.
weather)
Historian
Database
DFR/PMU
Direct P&C
(e.g. IEDs)
Advanced WAMPAC
Applications
WASAS
Real-time
Database
14
© Copyright 2009, Southern California Edison
SCE’s vision about WASAS
• Separate presentation,
application, and data interface
parts with interfaces between
– Presentation and application
– Application and data input
adapter
• Work with NASPI to make
interfaces to become open
standards
Presentation
Applications
(include direct data pass thru)
Electrical Non-electrical
Data Input Adapter
Control
(future)
Join the conversation on Twitter using #IUWebcasts
and follow Intelligent Utility on Twitter @IntelUtil
15
© Copyright 2009, Southern California Edison
Outline
• What is a SyncroPhasor
• WASAS Design Considerations / Requirements
• WASAS System Design Overview
Join the conversation on Twitter using #IUWebcasts
and follow Intelligent Utility on Twitter @IntelUtil
16
© Copyright 2009, Southern California Edison
WASAS as part of SCE Smart Grid Vision
OSB Adapters
External Interfaces
Cell Relay
Field Area Network
Ca
p B
an
ks
Sto
rag
e
Tra
nsfo
rme
r
Oth
ers
ITRON Cell Relay
Da
tab
ridg
e fo
r exte
rna
l
acce
ss to
M&
V d
ata
DMS
Dis
tribu
tion
Co
ntro
l
Lo
ad
Co
ntro
l
eD
NA
His
toria
n
EMS
Ph
aso
r Ga
tew
ay
Tra
nsm
issio
n/
Su
bsta
tion
Co
ntro
l
Data Nodes
UI
Co
mm
on
Use
r
Inte
rface
Human Machine
Interface (HMI)
HM
I-1
Re
lays
AV
VC
PC
PM
U
Devices
HM
I-2
OMSGIS
Operational Service Bus (OSB)
WiMax
WiMAX
Ba
ttery
Mo
nito
ring
Dig
ital F
au
lt
Re
co
rde
r
Le
ga
cy D
evic
es
(Typical) Distribution Substation
Protection
and Control
URCI Network
UR
CI
UR
CI
UR
CI
UR
CI
SCE Grid Control Center
AMI Network
Management
System
AMI MDMS
AMI Event
Services
GE Inet II
61850 (GOOSE)
61850 61850DNP3IEEE
C37.118 Comtrade
SCE Fiber NetworkWiMax
SCE Fiber Network
OSB Adapter
IP (61850)ANSI C12.19 / Smart
Energy Profile
OSB Comm/Security
Adapter
Home Area Network
Smart Appliances
HAN Devices
Electric Vehicles
PCT
MeterZ
igb
ee
OSB Adapter
Exte
rna
l Inte
rface
s
California ISO
WECC Utilities
Others
SCE Fiber Network
Comtrade DNP3Modbus/
Modbus+IEC 61850
ANSI
C12.19
IEEE
C37.11860870/
TASE2Smart Energy
Profile
External Users of Measurement
and Validation Data
OSB Comm.Security Adapters
Comtrade DNP3
Modbus/Modbus+
IEC 61850 ANSI C12.19 IEEE C37.118
60870/TASE2 Smart Energy Profile
Wide Area Fiber Network
(VPN - Future)
Wide Area Fiber Network (VPN)
CR
AS
Co
ntro
ller
(Typical)
Transmission
Substation
61850 (GOOSE)
OSB Adapter
IEEE
C37.118
SCE Fiber Network
© Copyright 2009, Southern California Edison
Re
lays
61850
Other Common
Services
Smart Grid
Services
OSB Core
Security Services
Admin
Auditing
Encryption
Authentication
DF
R
PM
U
Ph
as
or D
ata
Ga
tew
ay
60
87
0/T
AS
E2
IEE
E C
37
.11
8
17
© Copyright 2009, Southern California Edison
WASAS System Design Views – Network/Comm
SCEnet2 Conceptual Architecture
18
© Copyright 2009, Southern California Edison
WASAS System Design Views – logical
Legend
NASPInet
EMS/SCADA
Applications
External
Intelligent Alarm &
Event Management
Real-Time
WASAS Apps
Weather
Traffic
Fire
Earthquake
EMS Applications
Network Model
SCADA
WAMPAC Applications
SCE Security
Perimeter WASAS/WAMPAC
EMS Historian
Data
System & Data
Management
Global Event Mgmt
Phasor Data
Concentrator
Substation
Other SCE Data
IEDs
DFR / PMU
Edge Security
Engineering
Historian
Visualization
Visualization & Event/
Alarm Processing
Authoring &
Configuration
Non-Real-Time
WASAS Apps
GIS … ...
Enterprise
Common Svcs
Device Mgmt
System and
Application Mgmt
Data Mgmt
Data BusSecurity
WECC
BPA PDC
CAISO PDC
[Other] PDC
Gateway
Gateway
Gateway
SCE Phasor
Gateway
Central Security
External Data
Proxy Servers
Existing or
Out-of-Scope
In Scope,
Near Term
In Scope,
Long Term
Analyticnal
(Real-time)
Operational
(Real-time)
19
© Copyright 2009, Southern California Edison
WASAS System Design Views – Data Flow
LEGEND
External system
Existing
Data Store
Future Functionality
WASAS
Application
Servers
DFR
External PDCs
(WECC members)
PDC
External Data
Proxy Server
WASAS System &
Data Management
Visualization
Server
RT
PM
U d
ata
stre
am
Exte
rna
l P
MU
da
ta,
an
d
SC
E P
MU
da
ta r
eq
ue
st
PDC data stream
Data R
equest
Requested data
Data R
equests
Data requests
DF
R L
ocal tr
ig n
otificationWASAS
Historian DB
WASAS
Operational DB
Data
request
Ext
erna
l PM
U d
ata
requ
est/
SCE P
MU d
ata
EMS &
Historian DB
(eDNA)
Exte
rna
l P
MU
da
ta R
eq
ue
st/
SC
E P
MU
da
ta
SCE
Phasor Gateway
Exte
rnal P
MU
data
Request/
SC
E P
MU
data
Ext
erna
l PM
U d
ata/
SCE P
MU d
ata
requ
est
Exte
rnal P
MU
data
/
SC
E P
MU
data
request
Data request
Requested EM
S
& eDNA data
Request
ed d
ata
WASAS system
External P
MU data R
equest/
SCE P
MU data
Exte
rnal P
MU
data
Request/
SC
E P
MU
data
WECC
Phasor Gateways
(WECC members)
External P
MU data/
SCE P
MU data request
Exte
rnal P
MU
data
/
SC
E P
MU
data
request
Glo
bal R
ecord
ing T
rig R
equests
Requested data
EM
S &
eD
NA
Data
Weath
er,
eart
hquake,
fire
, and tra
ffic
Data
Requested applications
output data (analog, messages,
alarms/warnings, etc.)
External PMUs
Ext
erna
l PM
U d
ata
External Data
Source
Real-Time and/or archived
external data (weather,
earthquake, fire, traffic)
Real-time or archived
External data RequestsWASAS
Data Store
PMU
NASPInet Data Bus
(Future)
Future System
Request
ed H
isto
rian D
ata
His
torian D
ata
Request
DFR
Reco
rded d
ata
Historian D
ata Requests/
Data for long term
store
DFR
Reco
rded D
ata
Request
Sele
cte
d a
pplic
atio
ns
outp
ut d
ata
(analo
g, m
essages,
ala
rms/w
arn
ings, e
tc.)
Weath
er, e
arth
quake,
fire, a
nd tra
ffic d
ata
Engineering
& Other DBs
PDC data stream
Data
request
Request
ed d
ata
Data
request
Reg Info from SDM
Apps output Reg. Info
Re
g. in
fo r
eq
ue
sts
(De
vic
e,
Ap
ps, e
tc. R
eg
. In
fo)
Re
g In
fo fro
m S
DM
Valid
ate
d P
DC
data
Reg. info request
Reg. info request/PDC Reg. Info
Requested Reg Info
Requested H
istorian Data
PM
U d
ata
retr
ansm
issio
n r
equest
Requeste
d m
issin
g P
MU
data
Requeste
d H
isto
rian D
ata
EM
S &
eD
NA d
ata
Dat
a re
ques
t
Data
request
Requeste
d d
ata
WASAS
Analytical DB
Requeste
d d
ata
Data
Requests
20
© Copyright 2009, Southern California Edison
WASAS System Design Views – Network/Comm (cont.)
MPLS Resource Sharing (backbone)
21
© Copyright 2009, Southern California Edison
WASAS System Design Views – Security
22
© Copyright 2009, Southern California Edison
WASAS System Design Views – Deployment
• Four environments: Operation (OP), Production Test (PT), Development (DEV), and Training (TR)– Full redundancy for OP and PT
– PT is exactly the same as OP
• External access of WASAS data is through WASAS external historian databases– Data are pushed from OP environment to external historian – no direct access from external
Firewalls and security boundary
TRN
=OP+Sim
DEV
=OP
Local
redundant
No local
redundant
OP
OP PT
=OP
PT
=OP
GCC-Main
GCC-Backup
Legend
Historian
WASAS
Historian
WASASMirrored
Historian
SCE Admin
23
© Copyright 2009, Southern California Edison
Additional information
SCE’s Wide Area Situational Awareness
SystemAnthony Johnson
Office: 626-308-6936
Cell: 661-803-4499
www.sce.com/smartgrid
23
Join the conversation on Twitter using #IUWebcasts
and follow Intelligent Utility on Twitter @IntelUtil
SRP
Synchrophasor Activities
Jeff Younger
SRP Electronic Systems
07/08/2010 J. Younger
3rd largest public power utility
~940,000 electric customers
2,900 sq miles of service territory
90% Residential + 10% C&I
Salt River Project (SRP)n
Phoenix
Flagstaff
Tucson
Chandler
Gilbert
MesaTempe
Glendale
Peoria
Miami
GlobeScottsdale
SRP electric
SRP resale - utility
SRP resale
Not served by SRP
SRP’s irrigated area
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
SI
AX
AF
WT
RUD
OR
AN
KY
BD
PB
PP
WD
CL
KNX
ST
TS
ROS GF
SI
BRG
HAA
JOA
KY
BRG
CO
APS
CH
500kV
230kV APS
OCO
SCR
SRP Existing & FY11-FY13 Planned
RUD
PL
SCE
DEV
DIR
APS
WWG PES
PWT
WAPA
MD
SUF
APS
DVY
APS
SRA
APS
WPX
WAPA
LIB
APS
PAY
SDGE
NGA
APS
GLD
APS
ELS
APS
WWG
APS
WT
WAPA
CDG
WAPA
PPK
APS
PPK
(not all lines are shown)
TEP
SPVPAN
GRV
FY13
FY11
FY1x
FY11
FY12
FY13
FY12
FY11
FY12
FY13
FY11
Existing w/future
PMU on-line today
Future SRP PMU
Adjacent
utility
07/08/2010 J. Younger
Why Synchrophasors
• Instantaneous view of the state of the electric system
• Once you have the data, there are a variety of applications:o Enhanced state estimation
o Operator visualization
o Black Start visibility
o Line impedance derivation
o Post-disturbance analysis
o Island phase angle studies
o Power network model validation
o Oscillatory mode detection & damping
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
Synchrophasor Data Flow – Concerns
• IRIG-B failure
• Communication channel failure
• PDC Software lockup
• Inter-vendor operability issues
• Different C37.118 interpretations
• Inter-utility data-sharing issues
• Data archiving concerns
• Security
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
Industry Trends
• IEEE C37.118 now widely available
o Common platform, minimum performance standard
• Ethernet availability
o Increased bandwidth for wide area control applications
• Software advances
o Improved operator displays, on-line/real-time analysis
• Government & University R&D
o Optimal placement of PMUs
o State Estimation enhancement
• More DFR & relay-embedded PMUs
o Hathaway, GE, SEL, ABB
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
Industry challenges
• Inter-operability
o Can brand G really talk to brand S? Reliably?
• Security
o Data sharing among utilities can be difficult
o More hooks into substation, relays
• Operator acceptance
o Must turn data into information
o Efficient visualization is key
• Cohesion among utilities
o Need for a common forum & standards
• Catch-22 application cycle
o Developer needs installed PMU base
o Installing PMUs requires a business need
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
Western Interconnection Synchrophasor Program
(WISP)
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
WISP High-Level Scope
1. Synchrophasor Infrastructure
o Deployment of 250+ plus PMUs and phasor data concentrators (PDC)
throughout the Western Interconnection, data and wide-area network
communication infrastructure, IT infrastructure, and the NASPI
integration infrastructure
2. Synchrophasor Applications and Tools
o Real-Time Applications
Situational awareness for operators
Wide-area controls for automatic safety nets
o Offline Applications and Tools
Power system performance and disturbance evaluation
System-wide model validation
3. RC Reliability Improvement Processes
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
SRP Synchrophasor Team
• An ongoing, multi-departmental effort
o Computer Applications – EMS, SE
o Communications Engineering – network
o Communications C&M – field installation
o Transmission Planning – model validation &
disturbance analysis
o System Protection – PMU design, settings
o System Operations – visualization
o Control Engineering – EMS, SE integration
o Relay Shop – field installation, maintenance
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
Team Milestones
• Used real-time PMU data during Black Start exercise
• Installed permanent PMUs for Black Start path
• Installed permanent, redundant PDC network
• Initiated EIPP/NASPI & WISP involvement
• Evaluated GE N60 & L90 & Hathaway DFR PMU capabilities
• Published papers at WPRC, Texas A&M, NAPS, ETEP
• Funding research with Arizona State University
o Optimal placement of PMUs
o State estimator enhancement
o Line impedance verification
o Tools for operator situational awareness
o Generator dynamic parameter validation
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
SRP Future Efforts
• Hardware
o 230kV & 500kV expansion plan is underway
o Evaluating Arbiter 1133A PMU device
o Hathaway DFR upgrades
• Software
o State Estimator & EMS integration
o Evaluating visualization packages (RTDMS)
• Industry Involvement
o Increased WECC WISP & JSIS involvement
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
07/08/2010 J. Younger
For Additional Information:
Steve Sturgill
602-236-4387
SRP Synchrophasor Contact
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©2010www.pjm.com
PJM SynchroPhasor Technology
Deployment
Chantal Hendrzak
General Manager – Applied Solutions
PJM Interconnection
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201039www.pjm.com
PMU Installations in the U.S.
Source: NASPI, April 2010
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201040www.pjm.com
Pre-Grant SynchroPhasor Deployment
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201041www.pjm.com
PJM SynchroPhasor Deployment Project
Production Quality System to
Support 80+ Monitored Substations
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201042
Voltage Stability
Monitoring
SynchroPhasor Applications
1-2 years 2-5 years >5 years ?
Disturbance Analysis
Determination of Accurate
Operating Limits
Angle & Frequency
Monitoring
Real-time Control of
wide-area network
System
Restoration
Improve State
Estimation
Wide-area
monitoring
Model Derivation
& Validation
Detection of
imminent Cascading
Real-time control
of corridors
Dep
loym
en
t C
hallen
ge
Ready to deploy
Needs moderate development
Requires more research
Inter-area
Oscillation
Detection & Analysis
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©2010www.pjm.com
PJM©201044
When Visibility is Lacking
-170-160-150-140-130-120-110-100-90-80-70-60-50-40-30-20-10
0
15:05:00 15:32:00 15:44:00 15:51:00 16:05:00 16:06:01 16:09:05 16:10:38
Time (EDT)
Re
lati
ve
Ph
as
e A
ng
le
Cleveland West Michigan
Normal Phase Angle is approx. -25º
Phase
Angles
Diverged
Prior To
Blackout
August 14, 2003 Blackout
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201045
Voltage Stability
Monitoring
SynchroPhasor Applications
1-2 years 2-5 years >5 years ?
Disturbance Analysis
Determination of Accurate
Operating Limits
Angle & Frequency
Monitoring
Real-time Control of
wide-area network
System
Restoration
Improve State
Estimation
Wide-area
monitoring
Model Derivation
& Validation
Detection of
imminent Cascading
Real-time control
of corridors
Dep
loym
en
t C
hallen
ge
Ready to deploy
Needs moderate development
Requires more research
Inter-area
Oscillation
Detection & Analysis
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©2010www.pjm.com
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201047
TO
PJM
PJM SynchroPhasor Deployment: System Overview
Super
PDCEvent & Alarm
Processor
Displays
Phasor
Data
Archive
PJM Displays
PDCPMU
PMUPMU
Data
Processing
Data
Processing*
Other Monitoring Entities
(FERC/NERC, etc.)
EMS/
SCADA
* TOs can optionally receive
phasor data from PJM
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201048
SynchroPhasor Redundant Network
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201049
Metrics / Benefits
1-3 years
Eco
no
mic
Reli
ab
ilit
y
3-5 years
• Situational Awareness - Visualization
& Alerting/Alarming
• Event Capture & Tracking
• Model Validation & Improvements
• Post-Distribution Event Analysis
• Transmission Assets Monitored &
MW Flows
• Reduced Congestion Costs
• Infrastructure Investment
• Construction & Electric
Infrastructure Assets (80+ PMUs /
17 PDCs)
• Job Creation
• Reduced Wide Area Outages
and Faster Restoration
• Improved Voltage Stability
Tools
• Inter-Area Oscillation Tools
• Lower equipment failures
• Reduced Congestion Costs
• Optimized Operations
Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
PJM©201050
For Additional Information on
PJM’s SynchroPhasor Deployment
Chantal Hendrzak
Office: 610-666-4635
www.pjm.com
50Join the conversation on Twitter using #IUWebcasts and follow Intelligent Utility on Twitter @IntelUtil
To submit a question . . . Use the interface question box
to the right of your screen.
The magazine for building a smart grid and delivering
information-enabled energy. FREE subscriptions
available at www.intelligentutility.com/SUBSCRIBE
Q&A
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Go to where the power industry gathers
for news, information, and analysis, visit
www.energycentral.com
Q&A
Energy CentralContact Information:
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Q&A
Leading website and newsletter covering
the business of renewable and sustainable energy.
Go to www.RenewablesBiz.com
Energy CentralContact Information:
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Get the inside scoop with Energy Central
Professional News Service. Start your FREE trial at
http://pro.energycentral.com/professional
Energy CentralContact Information:
Q&A
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Q&A
Join the discussion, raise your question,
and voice your opinion at www.energyblogs.com
Energy CentralContact Information:
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Q&A
Join our community of innovators who are
transforming smart grid vision into reality.
Go to www.IntelligentUtility.com
Energy CentralContact Information:
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Q&A
Be a thought leader in the power industry
with insight, analysis and commentary.
Go to www.energypulse.net
Energy CentralContact Information:
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Q&A
Connecting job seekers and employers in the power
industry. Go to www.EnergyCentralJobs.com
Energy CentralContact Information:
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Q&A
Leading website and newsletter covering
the business of renewable and sustainable energy.
Go to www.RenewablesBiz.com
Energy CentralContact Information:
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Closing Remarks
November 8-10, 2010 – Scottsdale, AZ
INFORMATION TECHNOLOGY –
CUSTOMER SERVICE – OPERATIONS
If you are a senior executive at a utility/ISO/RTO and
have ultimate responsibility for enterprise-level decisions,
you should not miss this one-of-a-kind summit.
Go to www.knowledgesummits.com
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil
Phil CarsonEditor-in-ChiefIntelligent Utility Daily
Upcoming Webcasts
• August 5 – Transmission Brain and Brawn
• September 9 – Smart Meters
• October 7 – Preparing Personnel
www.energycentral.com/events/audio
Join the conversation on Twitter using #IUWebcastsand follow Intelligent Utility on Twitter @IntelUtil