DESCRIPTION OF APPROACH, METHODOLOGY AND WORK PLAN FOR PERFORMING THE ASSIGNMENT 4.1 Introduction Nepal, officially the Federal Democratic Republic of Nepal, is a landlocked country located in South Asia. Nepal has an area of 147,181 square kilometers and a population of approximately 27 million. Nepal is the world's 93rd largest country by land mass and the 41st most populous country. It is located in the Himalayas and bordered to the north by the People's Republic of China, and to the south, east, and west by the Republic of India. Specifically, the Indian states of Uttarakhand, Uttar Pradesh, Bihar, West Bengal, and Sikkim border Nepal, whereas across the Himalayas lies the Tibet Autonomous Region. Nepal is separated from Bangladesh by the narrow Indian Siliguri Corridor. Kathmandu is the nation's capital and largest metropolis. The mountainous north of Nepal has eight of the world's ten tallest mountains, including the highest point on Earth, Mount Everest, called Sagarmatha in the Nepali language. More than 240 peaks over 20,000 ft (6,096 m) above sea level are located in Nepal. The southern Terai region is fertile and humid. Lumbini, the birthplace of Lord Gautama Buddha, is located in this region. Lumbini is one of the holiest places of the Buddhist religion; it contains important evidence about the nature of Buddhist pilgrimages dating from as early as the 3rd century BCE. Hinduism is practiced by about 81.3% of Nepalis, making it the country with the highest percentage of Hindus. Buddhism is linked historically with Nepal and is practiced by 9%, Islam by 4.4%, Kiratism 3.1%, Christianity 1.4%, and animism 0.4%. A large portion of the population, especially in the hill region, may identify themselves as both Hindu and Buddhist, which can be attributed to the syncretic nature of Hinduism and Buddhism in Nepal. A monarchy throughout most of its history, Nepal was ruled by the Shah dynasty of kings from 1768, when Prithvi Narayan Shah unified its many small kingdoms until 2008. A decade-long Civil War involving the Communist Party of Nepal and several weeks of mass protests by all major political parties led to the 12-point agreement of 22 November 2005. The ensuing elections for the1st Nepalese Constituent Assembly on 28 May 2008 overwhelmingly favored the abolition of the monarchy and the establishment of a federal multiparty representative democratic republic. Nepal remains isolated from the world's major land, air and sea transport routes although, within the country, aviation is in a better state, with 47 airports, 11 of them with paved Technical Proposal

Upload: vijay-barrey

Post on 12-Feb-2016

219 views

Category:

Documents


0 download

DESCRIPTION

mksdnflmkandsf vknlknjlk dsfg dfsg adrg qerg dfgdr dr sdfh gsfdg dwfhfdhg sdfh sfd

TRANSCRIPT

Page 1: TIA Nepal Approach Methodology 24-11-14

DESCRIPTION OF APPROACH, METHODOLOGY AND WORK PLAN FOR PERFORMING THE ASSIGNMENT

4.1 Introduction

Nepal, officially the Federal Democratic Republic of Nepal, is a landlocked country located in South Asia.

Nepal has an area of 147,181 square kilometers and a population of approximately 27 million. Nepal is the world's 93rd largest country by land mass and the 41st most populous country. It is located in the Himalayas and bordered to the north by the People's Republic of China, and to the south, east, and   west   by   the  Republic   of   India.   Specifically,   the   Indian   states   of Uttarakhand, Uttar Pradesh, Bihar, West Bengal, and Sikkim border Nepal, whereas across the Himalayas lies the Tibet Autonomous   Region.   Nepal   is   separated   from Bangladesh by   the   narrow   Indian  Siliguri Corridor. Kathmandu is the nation's capital and largest metropolis.

The mountainous north of Nepal has eight of the world's ten tallest mountains, including the highest point on Earth, Mount Everest, called Sagarmatha in the Nepali language. More than 240 peaks over 20,000 ft (6,096 m) above sea  level  are  located  in Nepal. The southern Terai region  is   fertile and humid. Lumbini, the birthplace of Lord Gautama Buddha, is located in this region. Lumbini is one of the  holiest   places   of   the Buddhist religion;   it   contains   important  evidence   about   the  nature  of Buddhist pilgrimages dating from as early as the 3rd century BCE. 

Hinduism is practiced by about 81.3% of Nepalis, making it the country with the highest percentage of   Hindus.   Buddhism   is   linked   historically   with   Nepal   and   is   practiced   by   9%, Islam by 4.4%, Kiratism 3.1%, Christianity 1.4%, and animism 0.4%.   A   large   portion   of   the   population, especially   in the hill  region,  may identify themselves as both Hindu and Buddhist,  which can be attributed to the syncretic nature of Hinduism and Buddhism in Nepal.

A monarchy throughout most of its history, Nepal was ruled by the Shah dynasty of kings from 1768, when Prithvi   Narayan   Shah  unified   its   many   small   kingdoms until   2008.   A   decade-long Civil War involving   the Communist   Party   of  Nepal and   several  weeks   of  mass   protests   by   all  major political  parties  led  to   the  12-point  agreement of  22  November  2005.  The ensuing elections  for the1st Nepalese Constituent Assembly on 28 May 2008 overwhelmingly favored the abolition of the monarchy and the establishment of a federal multiparty representative democratic republic.

Nepal remains isolated from the world's major land, air and sea transport routes although, within the country, aviation is in a better state, with 47 airports, 11 of them with paved runways; flights are frequent and support a sizable traffic. The hilly and mountainous terrain in the northern two-thirds of the country has made the building of roads and other infrastructure difficult and expensive. In 2007 there were just over 10,142 km (6,302 mi) of paved roads, and 7,140 km (4,437 mi) of unpaved road and one 59 km (37 mi) railway line in the south.[96] There is a single reliable road route from India to the Kathmandu Valley. More than one-third of its people live at least a two hours walk from the  nearest   all-season   road;  15  out  of  75  district  headquarters   are  not   connected  by   road.   In addition, some 60% of road network and most rural roads are not operable during the rainy season.[97] The only practical seaport of entry for goods bound for Kathmandu is Calcutta in India. Internally, the poor state of development of the road system makes access to markets, schools, and health clinics a challenge.

4.2 Understanding of Project Objectives

The Civil Aviation Authority of Nepal, has invited proposals to provide the consultancy services for the,” Air Transport Project Preparatory Facility.” The RFP has been issued to the JV formed by M/s Intercontinental Consultants and Technocrats Pvt. Ltd. (ICT), India; The SAP Group LLC, USA; Snow Holdings,  UK;  Virender Khanna & Associates,   India  and Full  Bright  Consultancy (Pvt.)  Ltd,  Nepal. Based on the RFP and the clarifications furnished thereafter, the JV group is submitting the technical and financial proposals for carrying out the consultancy services for the above project.

Technical Proposal

Page 2: TIA Nepal Approach Methodology 24-11-14

Given an opportunity, the team is keen to contribute positively in carrying out the challenging task set out by the CAAN and it is hoped that our approach and interest are communicated effectively throughout our submission. This Chapter presents a description of our Approach, Methodology and Work Plan for performing the assignment keeping in view the Terms of Reference furnished by the CAAN and our appreciation of the project parameters.

In formulating the Approach and Methodology, the Consultants have given detailed consideration to the objectives of the project, Scope of Consultancy Services and all other relevant aspects. In giving final shape to this methodology, the Consultants have also drawn on the extensive international experience they have gained from similar projects undertaken during the recent years, particularly from  their   vast   experience  of  projects   in  other  African  and  Asian   countries   funded  by   various Financial Institutions.

The Consultancy assignment aims to review the current master plan ( 2010-2028) of TIA, to carryout detail engineering design and preparation of bidding documents for procurement of works and equipment, and to assist the CAAN to undertake public private partnership project in future development/ improvement projects. 

4.3 Site Appreciation to Understand the Field Situation / Description of ProjectTribhuvan   International   Airport is   an international   airport in  Kathmandu,   Nepal.   It   is   the   sole international  airport  in  Nepal  and has one domestic and one  international  terminal.  At  present, about 30 international airlines connect Nepal to destinations in Asia, Europe and the Middle East. The airport is about six kilometers from the city Centre, in the Kathmandu valley.

Airport type Public

Operator Civil Aviation Authority of Nepal (CAAN)

Serves Kathmandu, Nepal

ICAO Code VNKT

Hub for Agni Air

Technical Proposal

Page 3: TIA Nepal Approach Methodology 24-11-14

Buddha Air Nepal Airlines Sita Air Tara Air Yeti Airlines

Elevation AMSL 1339.54 m (4394.76 ft.),

Reference Temperature 27.8°C

ARP Coordinates 274149.778 N 0852128.535 E

Types of traffic permitted IFR / VFR

  

AIRFIELD DIMENSIONS:

Runway

Designation  02/20Dimensions 3050x46(m)surface Bitumenstrength 54 F/ A/W/TRunway Condition Pavement is distressed at many places.

TORA TODA ASDA LDA02 3050 3290 3050 305020 3050 3200 3050 2930

Apron surface Cement Concretestrength PCN 53 R/B/W/T

Taxiway width 23 msurface Bitumenstrength PCN 54 F/A/W/T

 Turn Pad: The RWY ends in a turn pad in both thresholds, and it is the only way for aircrafts to turn around as the parallel taxiway doesn’t reach both ends.o:.o RWY strip/RESA The RWY has a strip of 3140 x 150 Sq. m.Only northern part of the RWY has RESA. Currently it is only 90 m long from the end of the strip (as opposed to the ICAO recommended RESA length of 240 m), due to the land falling away steeply.o CWY RWY has CWY in both ends: 02 (245 x 150 m) and 20 (150 x 150 m)TaxiwayThe airfield has a parallel taxiway, but it doesn’t reach both RWY ends. Furthermore, thereare five exit taxiways (TWY1, TWY2, TWY3, TWY4 and TWY5, starting from THR20) whichlink the RWY and the TWY. They are 23 m wide and made of bituminous surface.Distance between RWY and TWY (109 m) is not enough to comply with ICAO standards,and is less than the required for any of the passenger jet aircraft operating in the airport.In the airfield there is also a decommissioned cross runway, which is being used now as ataxiway to reach the hangars.ApronThere are two civil aprons in the airport: one for domestic traffic and other for internationaloperations. Both of them are served like remote aprons, to which passengers reach by bus.The international one is located in front of the international terminal building and has 9

Technical Proposal

Page 4: TIA Nepal Approach Methodology 24-11-14

aircraft parking positions.The domestic apron is further from the domestic terminal and is located near THR20. It has enough space   to   house   25   aircrafts.   There   is   also   a  military   and  maintenance   apron,   apart   from   the previously   commented,   and   an   helicopter   apron   located   at   the   end   of   decommissioned   cross runway.The helicopter landing area is located east of the runway opposite to TWY2 and TWY3.According to AIP, apron surface is made of cement concrete.AIRPORT ACTIVITIES SUBSYSTEMNavigation and landing aidsThe airport has four radio aids: NDB (KAM), VOR/DME (KTM) and two locators, Nalinchowk(LNC)  and Thecho (LTH).There is an Approach Lighting System Cat-1 of high intensity on extended center line up to a distance of 870m for Runway- 02. Precision Approach Path Indicator (PAPI) System has been provided at both ends  of   the   runway.   The  airport  has  a  Meteorological  office   to  provide  Meteorological  Report (METAR) data to the Control Tower ( TWR), Area Control Centre ( ACC ) and Approach Control units of   Air   Traffic   Services.   Meteorological   Services   are   available   during   airport   operation   hours. Aerodrome, Aircraft Parking (Int. and Domestic), Aerodrome Ground Movement, Slope –Longitudinal Profile,   Aerodrome  Obstacle,   Visual   Aerodrome   Traffic,   Standard  Departure,   Standard   Terminal Arrival   Route,   Instrumental   Approach,   TIA   Controlled   Airspace,   Kathmandu   Terminal   Area,   IFR Holdings, VFR Holdings, Mountain Flight Route Charts are available in the AIP document.Markings and lightingCentre lines are marked in RWY and TWY. Furthermore, RWY has Designation, THR, TDZ and edge marks.  TWY has holding positions  at  all  RWY/TWY  iqqntersections marked.   In   the apron taxiing guidance signs at all intersections with TWY and RWY and at all holding positions, guide lines and nose-in   guidance   at   aircrafts   stands   are   marked.   There   are   also   stop   bars,   where appropriate.According to the AIP there are RWY end, THR and edge lights and TWY edge lights.Rescue and Fire Fighting Service According to the AIP the Category for firefighting is Category IX.Fuelling facilitiesJet A1 is available during operation hours.  It   is provided by Nepal Oil  Corporation. There are six trucks, 1, 20,000 Liters, 1000 Liters/min.Passenger facilities: Terminal building and car parkingThe airport has three terminal buildings: domestic, international and VVIP.The Domestic terminal  is  located the nearest THR20. Only passengers can enter the building,  as there is a policeman controlling it. There is a security control with two metal detectors and two X-Ray machines (men and women) and once it is crossed, there is a hall in which companies have their own counters for passengers to do the check-in. Then the passengers pass another security control to access the boarding hall, where two boarding gates can be found, apart from a restaurant and some other facilities. Boarding gates end directly in the apron, where buses take the passengers to the domestic apron and their corresponding aircraft. There is not arrival lounge in this terminal, but passengers are conducted directly to a covered shed outside the building where baggage claim is located.The international terminal is located in front of the international apron, lightly nearer to THR20than the domestic terminal. It has two entrance halls and airlines counters are distributed between both of them. In this case counters are flexible, not property of each company. Before entering this lounge,  passengers  must  pass  a  security  control   in  which  their  baggage  is  controlled (once  it   is checked   in,  not   all   the   luggage   is   controlled).   Then  passengers   go  upstairs   to   the   immigration control, where some passport controls are sited, and pass a security control to enter the boarding area. There are five international boarding gates, which access directly the apron.In the same way, arrival passengers enter the building by foot and reach the passport control, where Visa must be obtained. Once they have passed the immigration control they go downstairs to the baggage claim lounge, where there are three baggage belts. The meters and greeters waiting area is located outside the terminal building, in front of the gate for passengers to leave the building.VVIP terminal building is located just in front of the domestic apron.

Technical Proposal

Page 5: TIA Nepal Approach Methodology 24-11-14

There is a parking for vehicles in front of the international terminal building and a remote car park for the domestic terminal, so passengers have to walk under covered walkways to the terminal.Handling facilities/HangarThere are many hangars in the airport. At the end of the decommissioned cross runway there are two of them, property of Buddha Air and Yeti Airlines. Between the domestic and the international aprons there are two more hangars: a military one and a NAC (Nepal Airlines Company) maintenance hangar.Cargo handlingThe Cargo Handling is being done by the Airlines.

Operating capacity and obstaclesDue to both weather and very high and hazardous terrain around the airport, all IFR traffic lands from   the   south   and   takes   off   towards   the   south.   Normally   from   July/August   to November/December,   cases   of   bird   concentration   and   bird   strikes   at   or   in   the   vicinity   of   the aerodrome have been reported now and then. In other months stray birds may be encountered occasionally. Lots of measures have been adopted to control these birds concentrations, including driving them through guards and security personnel. According to the AIP there are 33 obstacles, which can be consulted in the AIP.

4.4 Scope of Consultancy Services

The   scope   of   the   consultancy   services   under   the   assignment   has   been   divided   in   two   stages comprising;

STAGE 1: TRAFFIC STUDY AND PRELIMINARY DESIGNS

STAGE 2: DETAILED DESIGN AND TENDER DOCUMENTS

STAGE 1: TRAFFIC STUDY AND PRELIMINARY DESIGNS

The Consultants will collect available engineering & operational data of the existing airport facilities, existing  Master  Plan,  and   the  available  development  plans  and  prepare  an   Inception  Report  & Project  Plan.  After  a  detailed   study  carryout  capacity  analysis  with  existing   facility  and prepare Preliminary Design proposals with various options for an updated Master Plan & Land use plan, improvement/ up-gradation of airside infrastructure, Terminal Building, and Landside facilities at TIA Nepal. The scope broadly will comprise the following:

Review of  existing Master Plan(  2010-2028),  carryout  capacity  analysis  with existing facility and ascertain the  current development & improvement needs,  

Review of Air Traffic analysis and update forecast for passenger and goods traffic taking into account of regional development of international airports at Bhairahawa, Pokhara and the second airport at Nijghad.  

Capacity analysis of runway and taxiways in conjunction with existing Air space and CNS system,  

Field   investigations,   topographic   surveys,   detailed   geo-technical   and   materials investigation;

Prepare Obstacle limitation surfaces,

 Preparation of Airport Master Plan (AMP) in line with the agreed traffic projections and as per ICAO requirements & SARPS, indicating land use needs, Facilities assessment, phased development programme, 

Preparation of  plans  and broad designs  with different  options   for  proposed airport development taking into consideration, shifting of Army hangars, Airline Hangars, basic 

Technical Proposal

Page 6: TIA Nepal Approach Methodology 24-11-14

strip   widening,   taxiway,   apron,   drainage,   perimeter   road,   up-gradation   of   ATM facilities, etc.

Accommodate   projected   traffic,   security   measures,   immigration   and   emigration, Customs, Health   and all functions and activities relevant to terminal building as per ICAO / IATA requirements;

Design review of phase IA of existing Master Plan,

Preparation of layout of the proposed international terminal building and improvement of  the existing passenger  and cargo terminal  building/  new buildings,  VVIP  building alongwith relevant infrastructure,/ support infrastructure such as automated baggage handling   system,   BMS,   CCTV,   FIDS,   AODB,   Access   control,   Ancillary   Buildings,   to accommodate   projected   traffic,   security   measures,   immigration   and   emigration, Customs, Health  and all functions and activities as per ICAO / IATA requirements;

Review of requirements of electrical and power supply

Hydrological study; 

Review and design of airport Drainage system;  

Review of water supply requirements,

Pavement evaluation and analysis; 

Design of Fuel Hydrant system for new international apron,

Review of safety and security services.

Review and design of all  required visual  aids for Navigation including runway lights, signage,   PAPI,   approach   lights,   windsocks,   markings,   Communication   System, Metrological Services  etc. shall be in line with the requirements of ICAO Standards and recommended practices

Cost estimates Preparation of Environmental and Social justification of the project by determining the 

Environmental   Impact  Assessment  and  Environmental  Management  Plan  and  Social Impact Assessment (SIA); 

Preparation of Preliminary Design Report with options for their technical feasibility and recommendations submitted on the most technically and economically feasible options for further consideration by the Employer for detailed design.

STAGE 2: DETAILED DESIGN AND TENDER DOCUMENTS

Following the approval by the CAAN of an option under the Preliminary Design Report, the scope of work, work under Stage 2 will comprise the following:

Preparation of detailed architectural  & structural  design for all the proposed airport infrastructure   components   (passenger   and   cargo   terminal   buildings,   VIP   facilities, hangars,   airside  works   i.e.   runway,       taxiway   and   apron,   communication  network, Navigation aids, AGL, Metrological Services, Fuel Hydrant, support services on land and airside and other support infrastructure  such as Fire station, etc.) along with detailed technical drawings; 

Detailed design to include all utilities like Power, Water and Sewerage etc.;

Detailed drainage design;

Cost estimation; 

Technical Proposal

Page 7: TIA Nepal Approach Methodology 24-11-14

Preparation of implementation schedule; 

Preparation of tender documents for the implementation of the project 

Technical Approach

Our first objective will be to make a realistic review of existing air traffic data and forecast them as required for the purpose of design of the facilities and review the master plan of the airport. It will be phased in such a manner, so as to meet the current and future operational, passenger and cargo demands. The master plan will further emphasize on the infrastructure that will promote and facilitate business and trade growth. 

Similar approach shall be followed for identifying introduction of non-aeronautical facilities, which   will   provide   services   to   the   business   community   in   connection   with   their   trade. Nevertheless,   emphasis  will   be  made   on   safe   and   smooth   terminal   operations   and   user friendliness.

The New International Terminal Building and reconfiguration of the existing Terminal building will be made environmentally friendly and acceptable to the community by proper blending with   the   local   environment   and  Architecture.   It  will   also   act   as   a   catalyst   for   economic development in the neighborhood as it generates employment opportunities. 

The Consultants will collect all the relevant information available with the CAAN, other trade and industrial bodies and analyze for their impact on passenger and cargo traffic. Any gaps shall be determined and further data collected for comprehensive analysis. A survey team for the same shall be identified and a suitable draft format devised for the collection of data.

4.4 General Approach

The   general   approach   of   the   Consultants   to   undertake   the   service   is   to   provide  multi-disciplinary  expertise each with an element of excellence,  as role of  the each discipline  is crucial for the success of the endeavor. The Consultant’s dedicated team proposed for the assignment has been drawn from a pool of several eminent engineers and professionals with extensive experience in the field of airport master planning,  architectural  planning,  airport engineering, airport logistics, airport design, navigational aids, runway lighting, E&M services, financial & economic planning, regulatory and operational aspects and environmental / social studies. The team will ensure:

The closest possible liaison between the Consultant’s team and CAAN,

That local conditions, regulations and traditions etc., are fully respected, and 

To provide high quality  services  for successful   implementation of   the project  within  the budgeted cost.

The Consultant’s approach for carrying out the services is based on their extensive experience of successful completion of similar projects. For successful and efficient rendering of services, the Consultants proposes to take a sound engineering / professional approach based on clear understanding  of   the  project,   planning  and   systems  approach.   The  Consultants   shall   give special emphasis to maintain the quality of services to be provided.

4.5 Quality Assurance Plan

Intercontinental Consultants and Technocrats Pvt. Ltd. is an ISO 9001:2008 certified firm with commitment to deliver a quality product. The Quality Assurance (QA) system will be based on the premise that at least two independent, responsible and qualified professionals agree on the correctness of each work output before it is delivered or used as input for another task. 

Technical Proposal

Page 8: TIA Nepal Approach Methodology 24-11-14

This will ensure that the final documents and design efforts in the Detailed Project Report are of high quality.

Equally important is the level of interaction between the Consultants and the CAAN During the project preparation stage, the Consultants will interact frequently with the CAAN   and hold joint reviews on various technical aspects so as to ensure high quality work covering all tasks under the scope of work.

For   preparation   of   the   project,   following   elements   are   considered   essential   to  maintain quality:

The  QA   system  will   be   developed   to  meet   the   specific   requirements   of   the   project depending upon the type of the facility, design criteria, design life   and the acceptable level of quality.

Document verification, file supervision and quality control procedures on various surveys and site investigations.

Selection of quality materials and design techniques.

Development of design standards, technical specifications and acceptance criteria.

Design verification - At every appropriate stage of design preparation, design verification will be performed to ensure that the final product, while conforming to all relevant laid-down standards and specifications, is cost effective and can be easily implemented at site. The   design   verification   will   include   tasks   such   as   performing   alternate   calculations, adoption of proven design methods / concepts etc. The QA system will be designed to achieve, sustain and improve the quality of service, and to assure the CAAN that internal controls are effective and adequate and fully conform to the requirements of the codes and   technical   specifications.  Quality  Assurance  will   be  an   integral  part  of   every  work function and will be essentially the system of planning, organizing and controlling “human skills” to assure their compliance. Accordingly, each of the significant engineering process and sequence of steps that are to be followed by the survey / investigation and design teams will be clearly spelt out. Step-by-step procedures defining clearly the responsibilities of   each   process,  will   be   evolved   for   various   surveys,   investigations   and   designs   like topographic surveys, material and geo-technical investigations, study of water and power supply,   drainage   and   sewerage   system,   inventory   and   condition   surveys   for   existing pavements,   design   of   pavement,   Environmental   and   Social   Mitigation   Management Program (ESMP), etc.

4.6 Methodology Framework

In   formulating   the  methodology,   the  Consultants   has   given  detailed   consideration   to   the objectives of the Project, background of the Project, existing airfield facilities, scope of work and all  other relevant  aspects.  The methodology to be used will   follow requisite technical requirements to ensure safety, provide adequate capacity and follow internationally accepted planning procedures, in addition to the requirements projected by the Client in the ToR for the study.  These   include  the Standards  and Recommended Practices   (SARSPs)  of   ICAO and as prescribed by the RRA. The Consultants has also used the expertise and extensive international experience which has been gained from similar projects undertaken during the recent years in various African and Asian Countries funded by various financial institutions.

Based on our understanding of the objectives and the detailed ToR, we have developed a methodology that will address the requirements of this project. Since the scope of services covers some dependent and interdependent tasks, it is proposed to follow a TASK APPROACH for feasibility study, detailed engineering design and preparation of tender documents. The entire scope of work is grouped as below:

Technical Proposal

Page 9: TIA Nepal Approach Methodology 24-11-14

STAGE 1: TRAFFIC STUDY AND PRELIMINARY DESIGNS

Task Group I  : Collection and Review of Data and Documents

Task Group II  : Traffic Analysis and Forecast 

Task Group III  : Surveys and Field Investigations

Task Group IV : Review and Updating Airport Master Plan & Airport Safety 

Task Group V  :  Standard Bidding Documents

Task Group VI  :  Environmental/Noise Contours

Task Group VII  :  Interim/Preliminary Designs   

STAGE 2: DETAILED DESIGN AND TENDER DOCUMENTS

Task Group VIII : Detailed   Engineering   Designs,   Drawings   and   Tender  Documents 

Task Group IX : Deliverables 

Each   task   is   divided   into   activities   and   the   Consultants   has   developed   and   evolved   a methodology based on Task Approach.  The list  of group of tasks and activities therein are indicated in Table below:

Table 1 : Task List

Task No. Description of Task

STAGE – 1 : TRAFFIC STUDY AND PRELIMINARY DESIGNS

TASK GROUP I: COLLECTION AND REVIEW OF DATA AND DOCUMENTS

101 Mobilization & startup meeting

102 Site Reconnaissance

103 Collection of Data / Documents, Existing Master Plan, Land Use and Development Plans etc.

104 Study and review of Architectural  and Functional  Design of Existing Terminal  and Ancillary Buildings & Hangers

105 Study and review Existing Topographical Survey and Geo-Technical Investigation data

106 Study and review of Existing Air Side Pavements

107 Study and review of existing power supply systems

108 Study of existing Engineering Data

109 Study and review of Operational Data, Navigational Aids, CNS/ATM,AGL systems etc.

TASK GROUP II: TRAFFIC ANALYSIS AND FORECAST

201 Review of Air Traffic Data and Existing Prognosis

202 Models for Forecast

203 Traffic Studies, Analysis and Projections, Capacity analysis,

TASK GROUP III: SURVEYS AND FIELD INVESTIGATIONS

301 Additional Topographical Survey

302 Additional Geo-technical Survey

303 Hydrological Surveys

Technical Proposal

Page 10: TIA Nepal Approach Methodology 24-11-14

Task No. Description of Task

304 Electrical Power Supply assessment

305 Operational and Technical Assessment of the Site

306 Obstacle Limitation Survey

307 Pavement condition Analysis

308 Assessment of Support Infrastructure

TASK GROUP IV: REVIEW & UPDATION OF AIRPORT MASTER PLAN & AIRPORT SAFETY

401 Planning Standards, Design Parameters

402 Assessment of Airside Facilities

403 Assessment of Terminal and Ancillary Building Facilities

404 Assessment of Airport safety and recommendations

405 Updating Airport Master Plan and Land use plan

406 Airport safety

TASK GROUP V: STANDARD BIDDING DOCUMENTS

501 Standard bidding document for preliminary review

502 PPP Transaction

TASK GROUP VI: ENVIRONMENTAL / NOISE CONTOURS

601 Prepare noise contour plan based on currently used aircrafts at TIA and develop land use plan considering noise contour plan.

602 Environmental Impact Assessment (EIA) and Environment Management Plan (EMP)

TASK GROUP VII: INTERIM / PRELIMINARY DESIGNS

701 Design review for existing designs for ITB,and other buildings

702 Design Review of pavements for parallel taxiway and Apron

703 Design Review of construction of new Helipad, link Taxiway.

704 Design review for taxiway edge lighting, apron flood lighting and visual aids

705 Preliminary design for new works and equipment

706 Survey & Geotechnical  Investigation reports

707 Progress of design of all components

STAGE – 2 : DETAILED DESIGN AND TENDER DOCUMENTS

TASK GROUP VII: DETAILED ENGINEERING DESIGNS, DRAWINGS AND TENDER DOCUMENTS

801. Detailed design of Nepal Army & Airlines Hangars with associated facilities

802. Detailed   design   of   Runway   strip,   perimeter/access   road,   Diversion   and reconfiguration of inner perimeter road, access road

803. Detailed  design  of  Construction of  new parallel   taxiway,  new international  apron 

Technical Proposal

Page 11: TIA Nepal Approach Methodology 24-11-14

Task No. Description of Task

along with the associated link taxiways.

804. Detailed design of Construction of a new remote aircraft parking apron  including two link taxiways     including, pavement, visual aids, signs and illumination, Provision of apron flood  light,  Apron  taxiway,  perimeter   road and  GSE park,  Provision  of  fire hydrant system

805. Detailed   design   of   Construction   of   Access   Road   to   link   between   Runway   and VOR/DME area and associated works.

806. Detailed design of Secondary power supply augmentation taking into consideration of additional load of new facilities, new sub-station for new ITB and refurbishment, expansion   of   existing   Main   Substation   and   replacement/upgrading   of   existing generators and other power appliances.

807. Detailed design of Airport security fencing related to improvement works including illumination, extension of CCTV in fence etc.

808. Detailed   design   of   New   International   Terminal   Building   (ITB),   fully   automated baggage   handling   system;   airport   operation   center   comprising   various   airport operation system such as FIDS,  AODB, PC rooms and fittings etc;  security  control system for passenger, staff and baggage; access control between various ITB areas; CCTV.  Air   side  interface will   include gates,  passenger  boarding bridges and visual docking guidance system. Landside interface will include viaduct or other option as appropriate.  A consideration will be development of new ITB under PPP.

809. Detailed   design  of   Reconfiguration  of   existing   International   Terminal   Building   to operate as domestic terminal.

810. Detailed   design   of   New   access   road   and   multi-story   car   park   for   the   new International Terminal Complex, planning and design of interface between New ITB and future MRT (Mass Rapid Transit) station

811. Detailed design of Water supply improvement for the airport and Provision of fire hydrants at air side and land side, New sewage treatment plant

812. Detailed  design  of   Fuel  hydrant   system  for  new  international  apron  and  remote aircraft parking apron.

813. Detailed design of Relocation of existing Nepal Army establishments, development of future infrastructure in available areas of TIA.

814. Detailed design of Relocation of existing and development of new VVIP Building and associated facilities.

815. Detailed design of Site development for future fuel farm, fuel  hydrant system

816. Detailed design of Expansion of Cargo Terminal

817. Review improvement on CNS/ATM  identify further improvement needs on CNS/ATM at TIA to be included in the next project; and prepare detail design of the priority improvements

818. Study   dedicated   surface   transportation   system   for   TIA   linking   with   key   road transportation nodes with appropriate options to provide dedicated airport access 

Technical Proposal

Page 12: TIA Nepal Approach Methodology 24-11-14

Task No. Description of Task

from these transportation nodes

819. Review and assess current discussion and  initiatives on Public  Private Partnership (PPP)   in   infrastructure   development   in   the   country,   review   the   reports   and assessment conducted,

820. Preparation of Engineering Drawings

821. Preparation of Bill of Quantities and Cost Estimates

822. Review and Updating of Economic Assessment

823. Preparation of Construction Schedule

824. Preparation of Tender Documents

TASK GROUP IX: DELIVERABLES

901 Inception Report 1month

902 Report on Updated Master Plan 3 month

903 Standard   bidding   documents   for   construction   and   PPP transactions

6 month

904 Interim Design report 6 month

905 Draft Final Design Report, cost estimates,3D AV presentations 15month

906 Draft Bidding documents 16 month

907 Final Bidding documents for construction and PPP transaction 17 month

908 Final   Report   and   Final   Tender   Documents,   updated  Master Plan,3D Model,3D-AV presentation

18 month

4.7 Methodology

The following paragraphs spell out the methodology proposed to be adopted for carrying out the individual task during Consultancy Services for the Feasibility Study, Detailed Engineering Design and Preparation of Bidding Documents for the Air Transport Project Preparatory Facility at TIA Nepal. However,   these  may   require  modifications  or   adjustments,  inter-alia,   for   addressing   additional issues or conditions encountered during the provision of services. Should such modifications become necessary,   they  will  be  suitably   reviewed and discussed with   the  Client  and approval  obtained. Several tasks may be started simultaneously and thus their serial numbers do not necessarily reflect a sequential order. 

STAGE – 1 : TRAFFIC STUDY AND PRELIMINARY DESIGN

TASK GROUP I COLLECTION AND REVIEW OF DATA AND DOCUMENTS

Task 101: Mobilization & startup meeting

Technical Proposal

Page 13: TIA Nepal Approach Methodology 24-11-14

The team of key professionals and other experts for carrying out the study will be mobilized as early as possible after signing of the Contract Agreement.

A Start-up meeting will be held with representatives of the CAAN  and other relevant government organizations   for   pre-planning   coordination,   establish   channel   of   communication   for   reviewing relevant reports and exchange of ideas to be familiar with the project requirement.

Task 102: Site Reconnaissance

The Consultants team in co-ordination with the Client will carry out the reconnaissance of the site of existing airport for familiarization in general and identify the requirement / inputs and critical areas in carrying out the assigned task keeping in mind the ICAO Standards and Recommended Practices. During the site reconnaissance, the following factors / conditions for the existing airports site shall be analyzed.

a) Operational: This will include review of existing features (natural and manmade) in and around the existing airports to identify obstacles within the laid down obstacle  limitation surfaces in accordance with ICAO (annex-14), hazards affecting operational safety and weather conditions. 

b) Social and Economical: This will include review of proximity, access, current land uses, study of creek portion/ Marine features affecting runway extension   and any other issue of significant implication.

c)  Techno-economical:  This will include engineering issues such as suitability of topography, soil characteristics, drainage and availability of construction material etc.

Task 103: Collection of Data / Documents, Existing Master Plan, Land Use and Development Plans etc.

All the past studies and investigations conducted for the project, as available, will be collected for review and their merits and limitations assessed. The following documents and data will be included for reference:

Existing Airport Master Plan ( 2010-2028);

Traffic data and traffic forecast carried out; if any

Topographical survey plan as available;

Geo-technical study report of existing runway, taxiways and aprons; 

Details of last pavement evaluation reports of runway / taxiway / apron carried out

Details of sanctioned / ongoing works in the vicinity of project site;

Land use plan;

Existing drainage, sewage and water supply system;

Layout of existing general and airfield lighting installations;

Availability of utilities to support the development including power supply system;

Details of existing Navigational Aids, Communication, Surveillance System and Meteorological services;

General features / characteristics of existing building and structures 

Details of landside infrastructure facilities, access network and parking;

Details of Army Hangar & Airlines Hamgar

Details of existing Army establishments for relocation,

Perimeter road;

Technical Proposal

Page 14: TIA Nepal Approach Methodology 24-11-14

Survey  and evaluation of   locally  available  construction  material,   their   suitability   in   terms of quality and quantity / leads, etc.; and

Emergency services Fire, Medical/ Health and any other data found suitable for the project.

Task 104: Study and review of Architectural and Functional Design of Existing Terminal and Ancillary Buildings & Hangers

The   Consultants   shall   study   and   review   the   land   use   compatibility   with   the   potential   new infrastructures in accordance to the following tasks:

i) Review on-site  land uses for compatibility based on ICAO norms of terminal building design setback requirements,   including building restriction  lines,  runway and taxiway obstacle  free areas, runway visibility zones and runway protection zones.

ii) Review land uses around airport and zoning for land use compatibility with ICAO norms, FAA and other applicable standards.

iii) Review the land use compatibility of the potential new infrastructures with the existing Master Plan and existing Development Plans if any.

Task 105: Study  and   review  Existing  Topographical   Survey  and  Geo-Technical   Investigation data

The available reports, data, regional maps, topographic sheets and site plans, contour maps etc. will be collected by the Consultants and reviewed. Verification on ground and review of maps will be done by the Consultants.  The boundary of the area for the proposed site  of the project  will  be identified in the maps of the area. All the maps information will be digitized so as to have all the ground details including all utilities and land use available in the digital format.

The   data  made   available   by   the   Client   on   soil   characteristics   of   the   proposed   project   site   or surroundings will be collected and studied in order to understand the basic soil characteristics, which are essential for outline design given as under:

Classification of soil including grain size distribution curve;

Bore log details;

Natural moisture content;

Safe Bearing Capacity

Atterberg’s Limits;

California Bearing Ratio values. 

Maximum dry density at OMC compaction 

Sources,  availability,   lead and  landed cost  of  materials  required for construction will  be broadly identified.   Necessary   information   from   engineering   departments   in   the   area  will   be   obtained, confirming the quality and suitability of key construction material such as good earth, coarse, fine aggregates and water for construction purposes.

The studied data will be used for identifying the gaps of the available information (and define the scope of the topographical surveys and geo-technical investigations to be undertaken) as well as for the   preliminary   identification   of   land   use   for   proposing   general   layout   alternatives   during   the preliminary design stage and for preparation of overall Airport Master Plan.

Task 106: Study and review of Existing Air Side Pavements

The Consultant shall examine the data and document furnished by CAAN on the existing pavement such as runway, taxiways, apron, perimeter road, security fencing, Airfield Lighting system  etc. All the available data such as details of last overlay done, evaluation report of last PCN if any, details of 

Technical Proposal

Page 15: TIA Nepal Approach Methodology 24-11-14

RESA, turning pads and blast pads etc. shall also be reviewed. Besides the Consultant shall conduct visual  pavement   survey   to   collect  data   related   to   pavements   distresses   such  as   cracks,   ravels, potholes, patches deformation, edge step, edge break and pavement conditions etc. These details will be used for guidance in developing the structural design of the pavement.

Task 107: Study and review of Existing power supply system

The Consultant will collect the Data & Drawings and conduct a comprehensive study and review of 

the  existing   load  patterns  and  details  of  essential  and  non-essential   loads  of   the  Terminal   and 

Ancillary Buildings, Cargo Terminal, ATC equipment operational area and the land side facilities etc. 

connected from the power sub-station. The single line diagrams (SLDs) for each of the load centres 

shall be studied and reviewed for capacities of equipment, switchgears and cables feeding the loads. 

The Consultant will conduct a critical evaluation of the existing support structure i.e. the sub-station 

building, cable ducts,  access and equipment installation etc. keeping in view the scope of works 

covered in the TOR. The sources of normal and essential power supply systems shall be reviewed for 

necessary improvements / upgradations to meet the electrical power requirements of the proposed 

augmentation works at the TIA. The Consultant’s Electrical Engineer will interact with the Client’s 

Electrical Engineers for preparing a reliable power supply network compatible with the increase in 

power requirement adopting the state of the art technology and techniques and in compliance with 

the ICAO, Annex 14, Aerodrome Design and Operations, ICAO Aerodrome Design Manual Part 5: 

Electrical Systems and the Standard and Recommended Practices (SARPs), as applicable.

Task 108: Study of Engineering Data

Consultants will review all available data pertaining to site like site plans and land plans. Relevant drawings and documents will be collected to acquire the details of existing topography, drainage and general   soil   conditions.   Sources,   availability,   lead   and   landed   cost   of   materials   required   for construction, source of electric power will be broadly identified.   Necessary information from local engineering departments and market will be obtained confirming the quality and suitability of key construction materials.

Site conditions analysis (in terms of visibility, obstructions, accessibility, etc.);

Site Maps;

Regional Maps;

Topography Sheets and Contour Maps;

Meteorological data (wind, temperature, rain, humidity etc.);

Grading, drainage, and soil characteristics;

Noise issues/ Noise contours;

Past traffic data;

Socio-economic data;

Data   regarding   existing   airports   in the vicinity;

Air traffic characteristics;

Schedule of rates

 Task 109: Study and review of Operational Data, Navigational Aids, CNS/ATM, AGL System etc.

Technical Proposal

Page 16: TIA Nepal Approach Methodology 24-11-14

The Consultant will interact with concerned aviation related agencies / departments for obtaining 

the data indicated below:

Utilization of existing runway during the day, peak hour and annual operations 

Existing safety and security measures during operations and non-operational time

Existing CNS / ATM system and their status 

Existing visual aids and their status 

Restricted area, if any within operational area 

Daily flight schedule to assess the time available for runways, taxiways and other associated 

works without significantly affecting the operations 

Identification   of   sites   for   installation   of   plants   and   equipment   and   access   roads   for 

movement of vehicles and equipment for construction purposes within the operational area 

and their parking place during operations of aircraft. 

The Consultant  shall  study and review the details  and plan the  improvements / upgradations  in 

consultation with  the Client.  These data will  also be utilized  for   identification of   required  input 

parameters for structural design of pavement, working out the available time for construction works 

and planning stacking of materials, installation of equipment, movement of vehicles, machineries 

etc. during construction without creating any operational hazard. The data would also helpful for 

working out the other work packages. 

Visual Aids for Navigation and Apron Flood Lighting

Consequent upon the study and review of the existing Aeronautical Ground Lighting (AGL) and apron 

flood lighting systems and the materials and equipment in use, the Consultant will prepare designs 

for   the proposed new taxiways and aprons  under  the  project  work.  The sizes  and capacities of 

isolating transformers, constant current regulators, routes of series cables, pipe duct location, CCR 

hall location etc. will be duly examined for their adequacy to meet the additional requirements. The 

Consultant   shall   also  examine   the  present  power   supply   system  including   switchover  time and 

determine the augmentation / improvement required. New taxiways shall be provided lighting with 

LED lamps  in consultation with the Client.  Apron flood  lighting shall  be provided with polygonal 

galvanized high masts with lowering lantern .all apron service area, with a minimum glare to the 

pilots of aircraft in flight and on the ground to aerodrome and apron controllers and personnel on 

the apron. The design will cover both normal and emergency lux levels and the uniformity rations as 

per   ICAO   requirements.   The   normal   lighting   shall   be   with   high   efficiency   HPSV   lamps   while 

emergency lighting shall  be with instant glowing  induction / halogen lamps. The designs for the 

visual aids and apron lighting shall conform to the following and the Standard and Recommended 

Practices (SARPs) with latest state-of-the-art technology and techniques.

Technical Proposal

Page 17: TIA Nepal Approach Methodology 24-11-14

ICAO Annex 14 - Aerodrome Designs and Operations 

ICAO – Aerodrome Design Manual Part 4- Visual Aids 

ICAO – Aerodrome Design Manual Part 5 – Electrical System

ICAO – Aerodrome Design Manual Part 6 – Frangibility 

Federal Aviation Administration (FAA) – Advisory Circulars

Task 110: Inception Report / Project Plan

The   report,   consisting  of   initial  findings,  project   schedule,  design   criteria   and   staff  mobilization schedule will be presented two months from the project commencement to the Client.

Based on the information collected above, we will prepare Project Procedures and Guidelines for planning,   designing   and   tendering,   standard   specifications,   QA/QC,   environmental,   O&M,   risk management etc. documents to be used during the course of the project.

This report shall briefly describe the mobilization and establishment status of the Consultant, the specific staffing plan, the updated work plan the Consultant proposes to follow in carrying out the assignment based on the Consultant’s initial findings, details of any constraints or inputs required from the employer and such remarks as are deemed appropriate including the works done so far. 

TASK GROUP II: TRAFFIC ANALYSIS AND FORECAST

Task 201: Review of Air Traffic Data and Existing Prognosis

The Consultants shall study and review the existing air traffic data of the airport and forecast them, as  necessary   for   the  purpose  of  pavements  and  building  designs   for   the  design  aircraft  or   for infrastructure dimensions as per ICAO requirement. The air traffic shall be projected for the next 20 years.  The Consultants would obtain the current data from CAAN pertaining to the following for assessing the adequacy of the existing facilities and for preparation of development plans: 

Passenger Data

Domestic Passengers

International Passengers

Peak hour passengers

Seasonality of air traffic movement 

Major origins and destinations 

Busy hour rates 

Cargo Data

Export Cargo

Import Cargo

Domestic Cargo

Aircraft Movement

Data on Aircraft Types, Movement and Aircraft Fleet

Day and week analysis 

Time of day analysis 

Overnight parking 

Technical Proposal

Page 18: TIA Nepal Approach Methodology 24-11-14

Peak period aircraft mix

Other movements 

The information on the following vital aspects will also be obtained and reviewed with the traffic data collected as above:

Current Economic Development Plans for the country,

Government Policy Decisions,

Supply and demand of air transport services,

Economic growth and per capita income,

Tourism Development Plans

Task 202: Models for Forecast

Applicable  models   for   forecasts  will   be   selected   and   applied,   and  may   include   trend   analysis, multiple regression analysis and econometric models,  etc.  as well  as feedback from the industry sources. 

The model  to be applied to the development of the traffic prognosis  will  be discussed with the CAAN. 

Task 203: Traffic Studies, Analysis and Projections, Capacity Analysis

The existing traffic trends at Tribhuvan International Airport, Nepal, the catchment areas served and economic factors which are driving current and expected to drive future growth (Market drivers) in the region will  be studied.  The sources will  be existing data made available by the Government sources, the Client and other public sources and supplemented with interviews with leading travel agencies and airlines. 

Keeping in focus the IATA guidelines and ICAO, Airport Planning Manuals regarding traffic analysis, the  Consultants  will   carry  out   the   traffic projection.  Study  of   the  peak  profiling  of   activity  and production of relevant key data, to be agreed with the Client, but expected to include peak day and peak hour passengers, ATM and cargo tonnes.  In the process the following specific tasks will  be undertaken:

Overview of airport and aircrafts fleet market trends: A review of the environment in which the airport operates will be conducted. The review will gather data on regional economic trends, existing transport infrastructure (surface and air) and other issues including:

- Various Airlines

- Airport congestion; 

- Cargo market developments

• Market Assessment of Aviation Demand

An assessment of the airport’s market characteristics and potential demand for air travel will be assessed. Areas to be examined by the consultants will include:

- Projections  of  population and  income growth  in   that   catchment  area  and the air   travel demand resulting from that growth

- The   present   service   characteristics   and   future  operating   strategies   of   airlines   presently providing service 

- Key niche and market segments 

- The competition from other  airports   in   the  region based on development  plans  of  new airports and enhancement in existing facilities would also be taken into account for working out the future traffic flow pattern

Technical Proposal

Page 19: TIA Nepal Approach Methodology 24-11-14

- The diversion of passenger and cargo traffic from other airports, over a period of time, due to various factors, including attaining saturation levels of operations, would be considered while estimating the horizon year traffic;

• Long - term traffic forecast will be based on:

- Passenger levels by type 

- International, domestic or other relevant segmentation

- Scheduled, charter

- Cargo tonnage throughputs 

- Air Traffic Movements by year and for peak week and peak day

• Generation and growth of traffic would depend on various factors like:

- Catchment area served by the airport;

- Existing population characteristics, land-use and economic, agriculture activities within the influence area of the airport;

- Economic indicators, e.g. GDP and its growth;

- Development envisaged in the region and its hinterland;

- The likely shift in traffic from other airports in the region due to increased facilities at the proposed airport;

- The development of other airports in the influence region, including the existing airport; and

- The policy decisions of the Government in the overall economic and sector growth during the  horizon  period.   The  developments  envisaged   in  commercial,   industrial,   tourism and other key sectors within the influence area of the airport would be taken into account while working out the horizon year traffic.

- Drivers of traffic patterns, business, tourism and transit traffic;

- Customs Passenger levels by year and for peak week and peak day: International, domestic, transit, transfer and other relevant segmentation such us Scheduled, charter

- Air Traffic Movements by year and for peak week and peak day

- Aircraft fleet expected to use the Airport and classification by ICAO type (A,B,C,D,E,F)

- Design aircraft for pavements calculations and building dimensions.

• Traffic Projections & Capacity Analysis

The Consultants will carry out the capacity analysis of the existing facilities and   shall carryout the traffic projection for  the next  20 years and discuss with the Client.  Thereafter the peak design hour of passengers and aircraft movements for International and Domestic traffic and aircraft movements will be calculated, using current traffic relationships as the baseline. They calculations will be presented as:

- Annual forecasts of Air carrier passengers (domestic and International)

- Low cost, Charter and Corporate operations

- Enplaned  and  deplaned  domestic   and   international   airfreight,  bulk   freight   and   air  mail tonnage carried by air cargo aircraft and passenger aircraft as belly cargo.

- Operations   (scheduled   passenger   air   carrier,   charter   passenger,   scheduled   commuter, unscheduled air taxi, all-cargo, general aviation)

Technical Proposal

Page 20: TIA Nepal Approach Methodology 24-11-14

- Base general aviation aircraft

- Mix of tourism and business related traffic

For designing city side access, parking requirements etc. the assessment of vehicular traffic will also be made based on the mix of vehicular modes used to visit the airport.

TASK GROUP III: SURVEYS AND FIELD INVESTIGATIONS

Task 301: Additional Topographical Survey

The existing topographical surveys  carriedout in earlier studies shall be obtained and reviewed. The additional topographical survey shall be carriedout for the all new developments work of ITB, VVIP building,  Cargo  extension,  new  location  of  Army  hangar,   relocation Army establishment/  camp, Airline Hangar,  parallel taxiways, international/ remote apron, extension & widening of basic strip, Helipad, link taxiway  and perimeter roads etc.The basic objective of topographical survey is to capture three dimensional positions of all ground features in the Airport premises in the form of x, y and z coordinates with respect to a defined reference system of coordinates to generate accurate digital terrain model  of the airport area  for designing and working out improvement, rehabilitation, and up-gradation of infrastructure facilities. The coordinates of Airport Reference Point  (ARP) will  be used as reference for establishment of temporary bench marks and subsequent detailed topographical survey. All control points and survey of the airport will be based on National Datum.Before  carrying  out  detailed   topographical   survey  of   the  area,  Temporary  Bench Marks  will  be established along the strip at an interval of 200-300 with the help of Total Station Traverse in a close loop to fix X and Y coordinates of the bench marks. The Z coordinates will be fixed by auto/digital levels based on the RL of the ARP. The major activities to be undertaken are:

Fixing of temporary bench marks Detailed topographic survey will be been carried out using Total Station

Various natural   features  like drains,  creeks,  man-made features  i.e.  runway edge  lights,   internal perimeter fencing, buildings, roads etc., as existing on ground within the operational area of the airport shall be picked up with the help of Total Station. 

Besides   the   above   mentioned   requirements,   the   survey   of   obstructing   objects   like   hills, towers/chimneys within a radius of 15 km will be carried out by taking x and y coordinates of the object by navigational GPS and the height component (top height) added to the ground height. 

Task 302: Additional Geo-technical Survey and Materials Investigation

The existing geotechnical surveys  carriedout in earlier studies shall be obtained and reviewed. The additional geotechnical   survey shall be carriedout for the all new developments work of ITB, VIP building,  Cargo extension,  Army hangar/  Airline  Hangar,  parallel   taxiways,   international/   remote apron, Helipad, Link taxiway and perimeter roads etc.

The additional geo-technical and Material investigation will be carried out as per the standard code approved by ICAO or any other code as approved by CAAN and its scope will mainly comprise the following:

1. Investigation of new pavement of parallel taxiway, international apron, remote apron etc.2. Detailed   Geotechnical   Investigation   for   the   New   International   Terminal   Building,   VIP 

Building, extension of existing cargo/ other buildings / structures,  New Location of Army Hangar/ Airline hangar etc.

3. Material SurveySubgrade Investigation

Technical Proposal

Page 21: TIA Nepal Approach Methodology 24-11-14

For determining the strength characteristics of the sub-grade soil   in the proposed   apron(s) and taxiway(s) pavement area, the investigation will include both field and laboratory testing. The soil samples shall  be collected at  about 100 m  intervals  and also at  such other  places necessary  to determine changes in the soil type. The samples collected from each test pit will be tested for the following:

In-situ density and moisture content  Sieve Analysis and Atterberg limits 

Laboratory moisture – density characteristics (modified AASHTO compaction) 

Laboratory CBR (unsoaked and 4-day soaked compacted at three energy levels) and swell

Bore log details

Safe Bearing Capacity

Boreholes shall be drilled up to a maximum depth of 10 m at the locations of proposed structures (new and expansion). If rock is encountered, then drilling into soft rock shall extend up to 5m and in hard rock up to 3 m. 

Materials Investigation

A   detailed  material   survey   for   terminal   building,   VIP,   Cargo     and   other   anticipated   accessory structures and pavement construction will be carried out. Potential sites sources will be identified and shown on the engineering plans. To ascertain the quantity and quality of material at potential borrow pits and quarry sited test pits of adequate depth and drilling shall be carried out (at least 4 tests   /   hectare).   Analysis   and   testing   shall   be   carried   out   and   provided   as   required   on   the construction materials, in accordance with standard practice provided in the CML’s Testing Manual, 2000. Tests are to include; soil / moisture / density relationships and CBR values and any test on special methods of soil stabilization. The Consultant shall make adequate tests to prepare alternative designs for sub-base, base courses and wearing courses with different materials, such as naturally occurring grave, gravel stabilized with cement and / or crushed stone. 

In addition, soils samples will be collected from borrow areas and tested to assess their suitability for use in earthwork filling. 

Construction  materials   samples   shall   be   tested  where  necessary   for  mechanical   characteristics. Potential gravel shall be tested for the following material properties:

• Grading

• Atterberg’s limits and

• Moisture / density relationship (AASHTO T180)

• California Bearing Ratio (CBR)

For materials like coarse aggregates, the following tests will be carried out for their suitability for use in the pavement: (i) Los Angles abrasion value test; (ii) Aggregate crushing value; (iii) Flakiness index test  (iv)  Stripping value test;  (v)  Water absorption test  (vi)  Sodium Sulphate Soundness test (vii) Specific  gravity  and   (viii)  Chloride  and  Sulphate  content.  Gravel   sources   shall  be   tested   for   the material properties: (i) Grading (ii) Atterberg limits (iii) Moisture/density relationship (AASHTO T180) and (iv) C.B.R. (4 days soaked).

The Consultants shall prepare Soil and Material Plans (scale 1:5000) for approval of CAAN showing test pit location / sample locations of all construction materials available and investigated with an indication of their quantities. 

Technical Proposal

Page 22: TIA Nepal Approach Methodology 24-11-14

The Consultants  shall   identify  the  possible  causes   for   failure of  existing pavements  and suggest measure   to  prevent   similar   failure   in   future   including   sections  with  plastic   soils   that  would  be determined and appropriate corrective measures shall be recommended. 

The lead and landed cost of materials required for construction. Location of possible quarries will be identified for supply of aggregates, sand and water, etc. and leads ascertained. Sources of supply of cement,   steel   and   bitumen  will   be   identified.  While   selecting   quarry   locations,   environmental restrictions, if any, and feasibility of availability of these sites to prospective civil work contractor will be duly considered.

Following   review   of   existing   sources,   the   Consultants   shall   identify   additional   supplies   of construction water, if required, such as boreholes and shallow ponds ahead of the rainy season and identify associated costs to ensure that all water to be used in implementation of the project is not provided from the public source. 

Task 303: Hydrological Surveys

The  Consultant   shall   study  and  make  an  assessment  of   the   structural   conditions  and  hydraulic properties of all the existing drainage system, pipe and box culverts, if any including inlet and outlet structures and prepare the design of their remedial works or replacement while designing of a storm water drainage system for the entire airport. For all new drainage structures or existing structures which require major  repairs,  expansions or  replacement,  the Consultant shall  carry  out  relevant hydrological and geo-technical analysis for preparing the system designs

Consultants will  prepare a hydrological assessment and drainage pattern for the project site and determine the location of waterway and construction of drainage facilities, cross-drainage works and the  design of  such  facilities.  For   the regular  study data  such as  rainfall,   temperature  and other dichotic features of importance shall be considered. Cross-sections and gradients of watercourses shall  be   surveyed  to  determine   the  design  of  proper  drainage.  All  hydrological   studies   shall  be carried out as per International Standards and Codes of Practices.

Task 304: Electrical Power Supply assessment

The Consultant will conduct a comprehensive study of the existing sources of power supply and the load distribution pattern from the sub-station. Keeping  in view the scope of new developments covered in the TOR, a critical evaluation of the demand for power for the existing and the proposed developments,   the   support   structures,   such   as   sub-station   buildings,   cable   ducts,   access   and equipment installation etc. shall be make. 

The appropriate power supply network for the airport shall be prepared in consultation with the Client.   The   standby   power   supply   system   for   the   critical   loads   such   as   navigational   aids, communication systems, AGL facilities, terminal essential loads, etc. shall also be firmed up as per ICAO   requirements.   The   existing   brands   of   HT   /LT   power   equipment   like   switchgear,   cables, transformers,  generators    etc.   together  with   their   ratings   shall  be  collected  and considered   for planning and designing of a sound and reliable power supply system for the airport in compliance with the ICAO norms and standards and recommended practices. 

Task 305: Operational and Technical Assessment of the Site

Factors which restrict operational requirements, e.g. bird hazards and any other natural or man-made conditions that may impact on operational safety shall be studied along with present land use of the airports, habitation and surrounding area to minimize socio-economic impacts. The reports of the geo-technical characteristics of the sites, suitability of the sites for the provision of facilities such as approach lights and radio navigation aids, security considerations etc. shall be studied.

Technical Proposal

Page 23: TIA Nepal Approach Methodology 24-11-14

Task 306: Obstacle Limitation Survey

Airport zoning and obstruction restrictions are of paramount importance in order to ensure safe landing,  take off and maneuvering  of aircraft  in the surrounding airspace.  Consultant will  advise CAAN of the requirements with reference to the ultimate development plan to prevent, or remove, dominant obstacles in the vicinity of the airports. The topography of the area around the airports will  be studied to identify the obstacles / obstructions in the vicinity and the approaches to the proposed expansion of runways. The study will be conducted taking into account ICAO laid down SARP   in  Annex   14,   Vol.   I.   Natural   terrain   and  man-made   structures   forming   obstacles  will   be identified for removal or to be suitably marked to ensure safety of aircraft operations. An obstacle limitation surface plan will be prepared. Following detailed work is proposed to be carriedout : 

Review the established baseline and grid system for defining the coordinates of the various areas covered by survey work , survey work shall be  carried-out  with reference to existing Airport Reference Point ( ARP), all existing features& fixtures shall be marked with coordinates, elevation. Height etc, Geographical coordinates for the project shall  be in WGS-84 System.

All radio navigational aids and communication facilities linked to the aerodrome located within the aerodrome and outside the aerodrome will be surveyed and their location and elevation (Top & base)will be shown in the map. Super structures installed over nav-aids such as obstruction light, additional antenna, lightening arrester etc. will  also be shown with height and location details in the map

Approach surface areas in both the directions of the runway will  to be surveyed. The survey will include identification of all man-made as well as natural structures / features (Roads, buildings, high ground, electric/telephone lines, towers / chimneys, nallahs / water streams / rivers, hills etc.) falling in the approach area on both sides of existing runway and establishing their location and elevation (Top & base) on a plan. The objects shall be shown along with their location and elevation (Top & base) in the following Manner. 

The   following   charts   shall   be   prepared   and   the   data   on   CD.   The   Charts   shall   be   prepared   in accordance with the ICAO Annex-14  : 

Grid Map, Aerodrome Chart, Approach Charts, Take Off Climb Surface Chart, Aerodrome Obstacle Chart, OLS Chart, Nearby Aerodromes, Rescue & Fire Fighting Chart (RFF Chart):, 30 NM Chart, and, Aircraft Parking and Docking Chart / Aerodrome Ground Movement Chart.

Task 307: Pavement Condition Analysis

The inventory of the existing pavement at the airport will be prepared in terms of length, width, type and   condition,   uneven  profile   (both   longitudinal   and   transverse)   and   geometrics  of   junctions   / intersections dimensions and conditions of curves and fillets, etc. Distress pavement conditions like cracking, potholes and patching, rutting, raveling, edge step, edge break and pavement condition etc. will be recorded.. The general drainage condition and submergence or subsidence of any section will   be   recorded.  Data   related   to   the   pavement   composition   shall   be  obtained   from CAAN.   If required,   the   Consultant   shall  make   trial   pits   at   the   edges   or   other   suitable   locations   of   the pavement in consultation with the CAAN and ascertain the pavement composition.

The Consultant shall carry out:

Pavement  evaluation  as  necessary   to  elicit   the   residual   strength  of   the  airport   runway, taxiway and apron including tests such as Standard Falling Weight Deflectometer (SFWD) or use of other alternatives by determining the CBR and Resilient Modulus of the undisturbed subgrade soil samples collected from the test pits and the Resilient modulus of the existing pavement layers including Asphaltic Concrete cores to be collected from site. 

Technical Proposal

Page 24: TIA Nepal Approach Methodology 24-11-14

Identification of priorities for rehabilitation, including application of recycling techniques and resealing; 

DCP tests for determination of Sub-grade CBR properties;

Determine, where necessary, failure mechanisms and provide adequate basis for the design of remedial measures;

Examination   of   the   airport   drainage   system   and   pavement   elevations   relative   to   the surrounding areas, in particular to ascertain what, if any, detrimental effects they may have had on the structural capacity of the pavements.

The interval of the tests shall depend on pavement condition but no inferior to 50 m spacing in areas of severe damage.

For  unpaved sections  of  runway,   taxiway  and apron,  the Consultant  will  carry  out  all  necessary pavements   evaluation   including   coring   along   the   center   line  of   the   runway,   at   the   apron   and taxiway, DCP tests for determination of in-situ density, sub-grade CBR properties and layer thickness for the pavement.

Task 308: Assessment of Support Infrastructure

After review of  the existing support   infrastructure  at  the airport  such as surface access system, surrounding  land uses,  available  utility,  socio-economic   issues etc.,   the  Consultant  will  plan and design for their improvement and meetings will be held all the concerned agencies for arriving at an integrated plan for support infrastructure such as power, water and sewerage etc

TASK GROUP IV: REVIEW & UPDATION OF AIRPORT MASTER PLAN & AIRPORT SAFETY

Task 401: Planning Standards, Design Parameters

The Consultant would adopt the following standards in planning and designing of the improvements at the airport:

Aircraft Pavement Geometry  - ICAO Annex 14 Airport Pavement Structure  - As per International / Local Standards 

conforming to ICAO norms  Road Specifications  - CAAN Standard Specifications 

Testing Procedures  - Central Material Laboratory latest testing 

                                                    Manual 

Structures  - British / European Standards 

Based  on  study  of   the   various  data   collected   through  field   investigations  and  as  per   the   ICAO Manuals,  planning and design  parameters  and type  of  materials  and their  specifications for  the following aspects shall be fixed. 

Dimensions of the existing runway, extension area, shoulders, fillets etc.

Geometrics design of the runway, taxiway, and apron (existing and new)  

Design value of the soil parameters for design of the terminal building

Material type and specifications of airport pavements and terminal building

Design value of the traffic and mix of various types of aircraft movements to determine the annual departures for the thickness design of airfield pavements

Technical Proposal

Page 25: TIA Nepal Approach Methodology 24-11-14

Task 402: Assessment of Airside Facilities

Passenger and cargo forecast demand together with the operation of design aircraft shall form the prerequisite for planning the requirement of extension of runway, taxiway, apron, parking stands, modification of the existing terminal building and other ancillary building such as power station, fire station, maintenance building etc. besides ground support equipment parking areas, aeronautical ground lighting & isolated parking positions. For planning the airside facilities ICAO SARPs contained in Annex 14 will be complied. Navigational aide will be designed in accordance with ICAO guidelines given in Annex 10 and ICAO SARPs contained in Annex 17 shall be considered for AVSEC related services. 

The airside facilities broadly will include:

Extension & widening of Runway basic strip to meet requirements for code E. 

Parallel Taxiways

Apron : The apron in front of the international terminal building. Remote apron & cargo apron shall be sized as per the requirement 

New Helipad with associated taxi-link,

Navigational Aids and Communication system: It will include both radio and visual aids, ground to ground and air to ground communication facilities will also be planned in the control tower. 

Ground marking as per ICAO standards 

Rescue and Firefighting facilities 

Apron Flood Lighting 

Operational Roads 

Fuel Hydrant system for international and remote apron

Security Fencing and Gates 

General Parking and Ground Handling Areas and Facilities (Landside and Airside)

Site development for new fuel farm

Task 403: Assessment of Terminal and Ancillary Building Facilities

It   is   important   to  be   aware   that   the  modifications  etc.  will   be   carried  out  within   the  existing operational areas of airport. It is therefore imperative to design and phase the construction activities in such a way that would least disturb the flow of airport users and compromise the security aspect.

Construction of New International Terminal Building, reconfiguration of existing Terminal Building for use as Domestic Terminal Building, relocation of VIP Building, shifting of Army Hangar/ Airlines Hangar to new location, relocation of Army establishment  and expansion of Cargo terminal etc, shall be  planned  based  on  the  realistic   forecast  of  annual  passenger  and peak  hour  passenger   load, different departure areas inside the terminal building. The cargo forecast both import and export shall   be   taken   into   consideration   for   planning   the   requirement   of   the   terminal   area.   The augmentation   and   facility   planning   of   the   terminal   building   shall   comply  with   requirement   of Chapter VI of Annex 9, ICAO, FAA Advisory Circular No. 150/5360-13 and IATA’s Airport Terminal Reference Manual (ATRM). 

The Passenger Terminal Building will cater for:

Kerb side facilities

Passenger entry and exit.

Concourse area 

Check in area

Technical Proposal

Page 26: TIA Nepal Approach Methodology 24-11-14

Baggage   processing   both   incoming   and outgoing   with   automated   baggage handling system, online X-ray etc.

User requirements for regulatory agencies and airport administration

Passenger amenities

Processing equipment layout

Security 

The Cargo Terminal Building will cater for

Both landside and airside passenger interface facilities for loading and unloading operations

The processing area for export cargo comprising of receipt areas, weighing, export inspection, if any, sorting and storage.

Import processing area will be comprised of receipt of cargo from airside, storage, customs and narcotics inspection areas and delivery to consignee on the landside.

Ancillary Buildings shall cover 

Administrative Building 

Army Hangar & Airlines hangar

Fire Station

Hangar including Customs Clearing Facilities 

The buildings will be located and sized as per the requirement in consultation with the Client.

For the above, the Consultant shall take into consideration modification/additions of all interlinked support facilities such as access roads, car park, landscaping and other non- aeronautical facilities that may generate revenue. The Consultant would examine the existing building and structures to determine their suitability and structural  integrity for the predicted passengers and cargo usage. Appropriate recommendations for alternative arrangement and space shall be made. The Consultant shall also make alternative proposals for their refurbishment or replacement as required. 

Task 404: Assessment of Airport safety and recommendations

Task 405: Updating Airport Master Plan and Land use plan

The aim of the Airport Master Plan is to achieve the required capacity for aircraft, passenger, cargo and vehicular movement with maximum passenger, operator and staff convenience at lowest capital and operating cost at each stage of  its  implementation.  The airport  master plan  is to be drawn defining very clearly the ultimate development needs and the role of the airport. 

The primary goal of the Master Plan update will  be to create a current and future development program that  will   create and sustain  safe,  efficient,  economical  and environmentally  acceptable airport facilities for the region. It is to achieve the most optimum and effective movement of the following at the lowest operating and maintenance cost:

• Aircraft of different mix

• Passenger, cargo and vehicular movement

• Airport staff

Technical Proposal

Page 27: TIA Nepal Approach Methodology 24-11-14

The  master  plan   is  prepared   to  define  ultimate  development  needs  of   the  airport   and   can  be executed in phases as per the Client prerogative. It must identify predetermined ‘trigger points’ for initiating each stage leading to the ultimate development. Further, it is required to prepare a  land use plan based on noise contour.

 The Consultants will prepare the Airport Master Plan including an Airport Layout Plan (ALP) set in accordance with ICAO Airport Planning Manual Doc 9184-AN/902 Part 1 and Annex 14 Aerodrome Design and Operations. The FAA Advisory Circular 150/5070-6A Airport Master Plans and 150/5300-13 including chapter 5 Airport Design will also be utilized and cross referenced to ensure the airport complies with more stringent of the planning guidelines. The location of each component facility will be guided by its functional requirement,  separation stipulation by ICAO and proposed expansion requirements. The area of each component facility will be arrived at using the planning parameters and   established   planning   practices.   The   emphasis   will   be  made   on   safe   and   smooth   aircraft operation and user friendliness. AMP will be prepared based on the foregoing demands estimates and   sectoral   needs   defined   earlier.   It   indicates   sizing   of   project   components   based   on   traffic projections. 

The Consultant shall prepare a noise contour plan based on the currently operating aircrafts and accordingly prepare a land use plan.

By achieving this goal, the document will provide the guidance to satisfy the aviation demand in a financially feasible and responsible manner. In support of this goal, the following objectives will be realized.

Identify   airside,   landside,   and   airspace developments   and   improvements,   and recommend options  to   further  optimize  the economic   aspects   of   the   airport   while enhancing   the   safety   and   operational capacity;

Establish   an   implementation   schedule   for short,   intermediate,   and   long-term improvements   and   insure   that   they   are financially feasible;

Ensure   that   short-term   actions   and recommendations do not preclude long-term planning options;

Incorporate   the   interests   of   the   public, airport   users   and   government   agencies into the planning process; and

Make recommendations as to compatible land   uses   and   the   appropriate   steps necessary   to   ensure   proper   zoning   and minimum noise impacts.

Optimum   site   requirements   for   all significant airport functions

Identify   constraints,   if   any   and   their mitigation

Consultants   shall   prepare   the   layout  plans  of   the  airport   facilities  based  on   foregoing  demand estimates and sectoral needs defined earlier and evolve a layout plan for expansion of the airport. The plan shall include sizing of project components as listed above, based on demand projections and a most feasible layout shall be prepared.

The Airport Master Plan will determine the optimum sites and respective site area requirements for all significant airport functions and shall comprise the following major airport facilities:

Airside  development:  Widening   and   expansion   of   basic   strip   of   runway,   configurations     of taxiways  & apron,  parking  bays,  operational   roads,  perimeter   road,   isolated  aircraft parking position, fire station, AGL and navigational aids etc.

Terminal interface: Passenger and Cargo Terminals, control tower and allied structures 

Landside   development:   Main   approach   road,   Multi-level/   ground   level   Car   parking   and Commercial Development

Dedicated road transport system consisting of roads or via duct, as appropriate, to airport from main nodal points of Kathmandu, Patan and Bhakatapur. 

Technical Proposal

Page 28: TIA Nepal Approach Methodology 24-11-14

Airport   support   elements:   Airport   operations   and   support   facilities,   aircraft   maintenance facilities, air freight facilities, flight catering, airline support facilities, airport administration and maintenance, Fire and rescue services, Air and ground navigational and traffic control aids.

The schematic development plan would include development of airside facilities such as runway, runway strips and safety areas, taxiways, apron, isolated bay, terminal facilities including passenger terminal complex, Fire Fighting building, administrative office buildings, fuel farms, electrical sub-station,   air-conditioning   plant   room,   car   park,   roadway   access   system,   other   airport   support facilities,   utilities   and   infrastructure,   land   use   plans   and   other   commercial   developments supplementary to the airport. The location of each component facility will be guided by its functional requirement, separation stipulation by ICAO and future expansion requirements. The area of each component   facility  will   be   arrived   at   using   the   planning   parameters   and   established   planning practices.   The  master  plan  will   essentially   include  a  descriptive   report  explaining   logic  of   each provision of the master plan for quick and efficient decision-making.

Operational   constraints  and  measures   for   their   removal  would  be   included   in   the  master  plan. Suitable provisions towards communication, navigational and ground visual aids will be incorporated in the Master Plan based on prevailing meteorological conditions. Through discussions with airline operators and understanding of their future plans, requirement of space for aircraft maintenance and hangar facilities would also be included in the Master plan.

In summary,   the  Airport  Master  Plan  document will  detail   the  land use  plan  showing  taxiways, aprons, Air and ground navigation and traffic control aids at and near the airport,  service roads, rescue and firefighting requirements  as they pertain  to Airport  Master Plans on the airside.  For landside development, a variety of facilities will be examined. The document will provide the sizing of   the  passenger   terminal  building  and  its  capacities,   identify  the  operating concept,  develop a layout concept and identify the equipment to be included. The security and operational areas walls to be provided will be located on the plan. Operating concept for other landside facilities e.g. main access road, supporting services roads, administration and maintenance building, general aviation facilities etc., the utilities- water, power, sewerage and drainage requirement will be identified. The Master  Plan document  will  provide the phasing  of  the project,   the related capital  cost  and the economic analyses.

The draft Airport Master Plan will be presented and discussed with CAAN and then the final Airport Master Plan will be prepared.

Task 406: Airport safety

TASK GROUP V: STANDARD BIDDING DOCUMENTS

Task 501: Standard bidding document for preliminary review

The Consultant shall  prepare standard bidding documents  incorporating   the general and special specifications for the project works as per the scope of work based on ICAO and FAA guidelines, sound engineering practices and manufacturer’s specifications. Based on the design and drawings approved by the CAAN, the Consultant shall prepare necessary conceptual drawings for standard bidding documents. 

The Consultant shall prepare the bid documents for the project package wise. The tender documents will comprise the following:

Technical Proposal

Page 29: TIA Nepal Approach Methodology 24-11-14

Invitation to Tender, 

Instructions to Bidders, Bidding Data, 

Forms of Bid and Qualification Information, 

Form of Agreement and Appendix 

Form of Performance Guarantee 

Tender Surety 

Special and General Conditions of Contract 

The Standard Bid Documents shall indicate that documents are “for information only and not part of tender documents”  with a preamble in the text stating that this  report   is  only  representing the investigation and findings of the Consultant and shall be bidders responsibility for any source and quality of material etc. without binding the Client. 

Task 502: PPP Transaction

Capacity Development Support for PPP Projects

The ICT Consortium will provide engineering and design services to upgrade Tribhuvan International Airport and implement an appropriate mode of Public Private Partnership. Our aim is to improve the quality of service, maximize airport capacity, enhance operational safety and satisfy stakeholders. we  will   collect   data   from  Government/CAAN,  National  Planning  Commission,  Nepal   Investment Board, and line ministries the laws; acts; policies; plans; regulations, best international and national practices, financial and investor issues. Broadly we shall carryout following activities :

a. Understand the regulations and institutions relevant to CA sector.b. In   discussion   with   CAAN   and   stakeholders,   we   will   identify   facilities   that  may   be 

considered for PPP and those that will be kept out.c. Of facilities that may be kept in PPP we will do a qualitative SWOT analysis. This will also 

reflect international experience available in the public domain. d. Varying combinations of the facilities available for PPP will be listed.e. Based on financial  modeling,   including broad costs  and expected  revenues   from the 

facilities, we will identify the optimum PPP mode that may be introduced. f. The   analysis   will   identify   the   factors   of   management,   contractual   and   financial 

arrangements, risk assessment, and future role of CAAN and other issues applicable to introduce PPP.

g. We will assist in conducting stakeholders meetings at specific stages of the project and include CAAN officials for purposes of training.

h. In discussion with CAAN we will develop documents and set the procedures for selection of the PPP concessionaire. 

i. To align with airport best commercial practices, models applied at comparable airports may be used as benchmark for design of business activities.

TASK GROUP VI: ENVIRONMENTAL / NOISE CONTOURS

Task 601: Prepare noise contour plan based on currently used aircrafts at TIA and develop land use plan considering noise contour plan.

Technical Proposal

Page 30: TIA Nepal Approach Methodology 24-11-14

The Consultant  shall  collect field data and prepare a noise contour plan based on the currently operating aircrafts and accordingly prepare a land use plan.

Environment and Social Impact Assessment and Management Plan (ESIA & EMP) will address various environment   and   social   issues   associated   with   the   project.   The   Consultants   will   adopt   the requirements   of   the   Govt     of   Nepal   and   the   CAAN   and   Regulations   governing   environment management and ADB guidelines for preparation of Environment and Social Impact Assessment. It will help in assessing the probable changes in environment and social structure and taking suitable measures to offset/ minimize adverse effect.

The Consultant will suggest means of promoting public / NGO participation during implementation

Task 602: Environmental Impact Assessment (EIA) and Environment Management Plan (EMP)

Based   on   the   Preliminary   Design,   following   activities   will   be   undertaken   for   assessment   of environmental impacts:

Identification of impacts

- Reconnaissance Survey.  The Consultants will  carry out reconnaissance survey of the area and identify potential environment issues associated with the project.

Evaluation Models

- Prediction and evaluation of Impact. The impacts which may be positive & negative, short term & long term, reversible & irreversible, Direct & indirect on the existing environment like ecology, Air and Water quality, Noise levels, Soil erosion, due to location, construction and operation of airport will be identified assessed and predicted using various models and techniques like simple matrix, BEES technique etc. The quantified evaluation will be done as far as possible where quantification is not possible qualitative judgment will be used. Based on the analysis of different alternatives, the engineering design with the least environmental impact will be selected. The ESIA and EMP will take in to consideration of the following:

a) Consideration for natural resources and environment in the greater airport area;

b) Establish a sustainable balance between air-traffic systems and infrastructure on one side and the ecological and social systems on the other;

c) Improving   safety   through   better   separation   of   air-traffic   approach   and   departure corridors and the surrounding natural habitation of both people and animals;

d) To  provide   an   environmental   framework   for   the   future  planning,   development  and investment;

e) Assess all relevant aircraft related activities at the airport, including but not limited to, fuel farms and supply, fueling procedures, noise, emissions, etc… against international, regional and national requirements;

f) Assess   and   revise,  where   necessary,   relevant   airport   operations,   including   but   not limited to, maintenance procedures, waste handling and disposal, contamination etc.

g) Assess all risks associated with bird strikes and stray animals along the glide paths

h) Assess all activities associated with the runway, taxiway and apron systems, including but not limited to, herbicides, energy usage, spillages, surface water contamination etc.

Technical Proposal

Page 31: TIA Nepal Approach Methodology 24-11-14

i) Assess all relevant activities associated with the use of the terminal building including, but   not   limited   to,   water   supply   system,   energy   system,   waste   and   solid   water management etc.

j) Assess all aspects of social impact associated with future developments like economic effects  of   the  airport,   the   impact  of   the  airport  on  local   communities   (employment prospects, HIV/AIDS, noise pollution, loss of arable land etc.)

Possible deterrents

Based on the outcome of the study, the Consultants will prepare the Environmental Management Plan (EMP) which involves the implementation of environmental protection and mitigation measures and monitoring of significant environmental impacts. Environmental protection measures are taken to   (i)  mitigate  environmental   impacts,   (ii)   provide   in-kind   compensation   for   lost   environmental resources,  or  (iii)  enhance environmental  resources.  These measures will  be set  out   in an EMP, which covers all phases of the project from pre-construction through operation phases, and outlines mitigation and other measures that will be undertaken to ensure compliance with environmental regulations and reduce or eliminate adverse impacts. The EMP will include suitable cost-effective, technically feasible, environmentally friendly mitigation measures to offset any adverse impact on the   environment,  work   program   and   cost   estimates   for   implementing  mitigation  measures   in discussion with concerned authorities and practices in Nepal.

TASK GROUP VII: INTERIM / PRELIMINARY DESIGNS

Task 701: Design review for existing designs for ITB,and other buildings

The existing available designs carried-out during Air Transport Capacity Improvement Project 2010 shall be reviewed and shall undertake preliminary designs for new works and equipment. Quality of service, e.g. IATA LOS factors will be considered in the new, and modifications proposed for existing, terminal designs.

Norms on processing area per peak hour pax., potential for commercial area development etc. will be used in the design development of the passenger terminals. For cargo terminals the norms will be based on area/ton of cargo, type of cargo, regulatory procedures, extent of mechanization and IT processing involved etc.

Task 702: Design Review of pavements for parallel taxiway and Apron

As per Terms of Reference, it is planned to construct parallel taxiway from junction of taxiway “B” upto New International  Apron phase  II,  Apron for NITB,  new remote aircraft parking apron and extension of parallel taxiway between “E” to runway end 02. The plans prepared earlier under    Air Transport   Capacity   Improvement   Project   2010   shall   be   reviewed   in   terms   of   the   reviewed   / proposed new Master Plan and ICAO guidelines, the geometrics shall be rechecked in view of the current   category of airport and the future growth plans. The structural designs shall be reviewed with reference to the latest geotechnical surveys.

Task 703: Design Review of construction of new Helipad, link Taxiway.

The proposed Helipad with  linking taxiway shall  be reworked out and reviewed  in terms of the proposed new Master Plan and  ICAO guidelines   .  The structural  designs shall  be  reviewed with reference to the latest geotechnical surveys

Technical Proposal

Page 32: TIA Nepal Approach Methodology 24-11-14

Task 704: Design review for taxiway edge lighting, apron flood lighting and visual aids

Based on the New Master Plan and field data collected in the  surveys conducted in the foregoing tasks, the complete system for taxiway edge lighting   and illumination of the Aprons area, Hangar area , shall be reviewed and redesigned for  illumination level /  lux level as per ICAO guide lines.

Task 705: Preliminary design for new works and facilities

As per the Terms of Reference, it  is proposed to deliver the technical document that will be the Preliminary Design Report. This document shall allow CAAN to make decisions, (with the Consultants advisement),   about   the   planning   premises,   design   parameters   and   functional   design   of   the modified / extended / new terminal areas, as well as about the preferred geometrical design option from those presented by the Consultants for the whole infrastructures, particularly:

• International Passenger Terminal Building, VIP Building, reconfiguration of existing terminal building to be used as domestic terminal, and expansion of cargo terminal

• Airside (runway basic strip, taxiways, apron , perimeter road drainage etc)

• Ancillary buildings including Hangars 

• Accesses Network, MRT interface  and Parking Areas

• Dedicated airport access road.

This document shall permit taking decisions on other important and more detailed matters, such us type of engineering systems, intakes for utilities, approach to the architectural concept etc. but over a  final  selection for   the geometrical  design.  The target  of  this  proposal   is   to  get   the maximum efficiency   and   quality   of   the   assignment,   saving   time   and   allowing   a   fluent   and   collaborative relationship between CAAN and the Consultants.

The structure of this report will be as follows:

Executive   summary  describing   the   inventory  of   existing   conditions  and   indicating   laws   and regulations to be applied during the design, summarizing the main conclusions for Traffic Data and Documents (Landside vehicular study, passengers and aircraft operations and type, cargo), planning (design parameters, functional uses etc. ) and options for geometrical design (accesses network, terminal building and urbanism and associated airside)

Annexes for each discipline: that will include all the necessary calculations (traffic analysis and prognosis, design parameters based on IATA Manuals etc.) or other deep studies attached to the main report, such us the compliance with the ICAO regulations regarding Obstacle Limitation Surfaces or compatibility of the selected materials with NAVAIDS signals)

Support Drawings, showing the geometrical options, layout proposed as well as other technical aspects (inventory of existing conditions etc.)

Task 706: Surveys & Geotechnical Investigations reports

Findings of surveys will be utilized for design preparation based on Design Criteria. These in turn will be on the basis of functional Requirement and the various procedures developed during the planning stage. We shall also give due consideration to the following: 

“Value Engineering” practices 

Technical Proposal

Page 33: TIA Nepal Approach Methodology 24-11-14

Integrated planning to avoid conflicts during construction  

Various topographic ,geotechnical surveys and investigations carried out under earlier task shall be summarized & documented and submitted to clients with consultants specific recommendations of findings for implementation.

Task 707: Progress of design of all components

The consultants after having completes all field data collection and preparation of preliminary design shall submit an executive summary for review by the clients.

STAGE – 2: DETAILED DESIGN AND TENDER DOCUMENTSTASK GROUP VII : DETAILED ENGINEERING DESIGNS, DRAWINGS AND TENDER DOCUMENTS

Task 801: Detailed design of Nepal Army & Airlines Hangars with associated facilities

The Consultants shall carry out layout and physica design of the Army hangar and Airline Hangars 2 nos, alongwith associated facilities such as apron, link taxiways, visual aids, illumination, fire safety protection system and apron flood lighting. The detailed design shall include structural design of all components  and shall     involve  production  of   relevant  drawings   including   site  plan,  floor  plans, sections and elevations using the Main scale of 1:500, or as decided in discussion with CAAN. The pavement design shall be as per ICAO laid down norms as depicted in Aerodrome Design Manual, Part - 3

Building   codes   and   standards   used   for   the   safety   of   users   of   the   terminal  will   be   based   on International Standards as applicable  in Nepal /  the  UK Building Regulations guidance document Approved Document  (ADB) supported by the BS 7974 suite of fire engineering documents; or other Internationally recognized building fire codes. The Codes to be followed in all cases will be discussed with the Client and local authorities and concerned regulatory bodies.

Task 802: Detailed   design   of   Runway   strip,   perimeter/access   road,   Diversion   and reconfiguration of inner perimeter road, access road

The Consultant shall formulate the design criteria and performance standard based on the standards laid down by ICAO for operations and safety. Design the transverse profiles of the runway basic strip so that effective drainage is achieved. The characteristics of basic strip shall meet the requirements of ILS / CAT –II/ III  operations etc.

Diversion of perimeter roads as per new master plan, relocation of access control, security gates shall be designed to meet optimum efficiency with all latest equipment.

Task 803: Detailed design of Construction of new parallel   taxiway,  new international apron along with the associated link taxiways

The Consultant shall formulate the design criteria and performance standard based on the standards laid down by ICAO for operations and safety. An optimum design would be evolved for the design of, parallel taxiways, international apron, GSE parking and perimeter road. The pavement design shall be as per ICAO laid down norms as depicted in Aerodrome Design Manual, Part - 3. Pavement design will be carried out to carry traffic over 25 years life of the proposed project as described below: Establishment of sub-grade strength and characteristics

Technical Proposal

Page 34: TIA Nepal Approach Methodology 24-11-14

Design the components of pavement structure such as sub-base and base by ACN-PCN method using   gross   weight   of   the   aircraft,   tyre   pressure,   gear   configuration   and   sub-grade characteristics.

Earthwork   for  pavement  design  by  using   the   result  of  soil   and  material   tests   to  determine gradients of slope, compaction and pave design 

Study the fillet geometrics to ensure that fillet radius is compatible to the taxiing speed and design aircraft requirements and there is no accumulation of rain water.

Ground Support Equipment  parking area,

Apron flood lighting

Visual aids, docking  and bay identification markings

Fuel hydrant facilities at the international apron

Access roads 

Material designing for various layers is an integral part of pavement design. This will take into consideration the stresses imposed by design aircraft, design life and functional requirement of layer. Marshall’s method will be used for asphalt mix design.

Task 804: Detailed design of Construction of a new remote aircraft parking apron   including two link taxiways   including, pavement, visual aids, signs and illumination, Provision of apron flood light, Apron taxiway, perimeter road and GSE park, Provision of fire hydrant system

The Consultant shall formulate the design criteria and performance standard based on the standards laid down by ICAO for operations and safety. An optimum design would be evolved for the design of remote aircraft parking bays with two link taxiways, GSE parking  and perimeter road. The pavement design shall be as per ICAO laid down norms as depicted in Aerodrome Design Manual, Part - 3. Pavement design will be carried out to carry traffic over 25 years life of the proposed project as described below: Establishment of sub-grade strength and characteristics

Design the components of pavement structure such as sub-base and base by ACN-PCN method using   gross   weight   of   the   aircraft,   tyre   pressure,   gear   configuration   and   sub-grade characteristics.

Earthwork   for  pavement  design  by  using   the   result  of  soil   and  material   tests   to  determine gradients of slope, compaction and pave design 

Study the fillet geometrics to ensure that fillet radius is compatible to the taxiing speed and design aircraft requirements and there is no accumulation of rain water.

Ground Support Equipment  parking area,

Firefighting hydrant system

Apron flood lighting

Visual aids and bay identification markings

Material designing for various layers is an integral part of pavement design. This will take into consideration the stresses imposed by design aircraft, design life and functional requirement of layer. Marshall’s method will be used for asphalt mix design.

Task 805: Detailed   design   of   Construction   of   Access   Road   to   link   between   Runway   and 

Technical Proposal

Page 35: TIA Nepal Approach Methodology 24-11-14

VOR/DME area and associated works.

The Consultant shall formulate the design criteria and performance standard based on the standards laid down by ICAO for operations and safety. 

Consultant shall carry out detailed design of access road as per new master plan, to meet optimum efficiency and serviceability of the VOR/DME.

Task 806: Detailed design of Secondary power supply augmentation taking into consideration of additional load of new facilities, new sub-station for new ITB and refurbishment, expansion   of   existing   Main   Substation   and   replacement/upgrading   of   existing generators and other power appliances

Based  on  the  present   load  pattern,   the  Consultant   shall  work  out   the  appropriate  peak  power 

requirement keeping in view the proposed improvements / upgradation works and the same shall be 

firmed   up   in   consultation   with   the   Client.   The   power   sources   for   the   primary,   standby   and 

uninterrupted power supply (UPS) shall  also be detailed by the Consultant.  The electrical  power 

requirement for the following components of the project shall also be assessed for preparing the 

detailed designs both for essential and non-essential systems.

Relocation of hangars 

Relocation of VIP building and Cargo Terminal 

Relocation of Army infrastructure 

New International Terminal Building 

Reconfiguration of existing international terminal building 

CNS / ATM systems 

New taxiways / apron flood lighting 

Roads and car park lighting 

After essential of the maximum demand of power requirement and the source, the Consultant will 

develop the detailed designs of the power supply and distribution to meet the requirements of 

normal essential and uninterrupted power systems. This will include sizing of switchgear, cables and 

distribution panels, installation designs, expansion of existing main substation/ provision of new sub 

station as appropriate to site requirements etc. The design of the systems shall be based on the IEC 

standards and best industry practices, beside ICAO Standards and Recommendations contained in 

the  Annex  14  and   ICAO Aerodrome Design  Manuals  Part  5-  Electrical   Systems,  with   respect   to 

locations, capacities, sizes and the operating requirements. The system design shall also cover fault 

levels, voltage drops, capacity, loading at various points, insulation levels, current rating metering, 

protections etc. so that a design is evolved for a reliable power system for the vital installations at 

the airport.

Technical Proposal

Page 36: TIA Nepal Approach Methodology 24-11-14

Task 807: Detailed design of Airport security fencing related to improvement works including illumination, extension of CCTV in fence etc.

The  layout  plans  of   the  airport  security   fencing  shall  be  prepared taking  into  consideration the revised Master Plan and   the security scenario at the airport in line with the accepted procedures and practices. The guidelines / requirements of ICAO’s safety SARPs and CAAN’s Notifications and guidelines   regarding  airport  security  shall  be kept   in view while  finalizing  the  specifications  and design of the airport security fencing.

Due care shall be taken for improvement of security by illuminating the perimeter fence and by proving CCTV cameras on strategic places of perimeter security fence & entry gates.

Task 808 Detailed   design   of   New   International   Terminal   Building   (ITB),   fully   automated baggage   handling   system;   airport   operation   center   comprising   various   airport operation system such as FIDS, AODB, PC rooms and fittings etc; security control system for passenger, staff and baggage; access control between various ITB areas; CCTV. Air side interface will   include gates, passenger boarding bridges and visual docking guidance system. Landside interface will include viaduct or other option as appropriate.  A consideration will be development of new ITB under PPP.

The  Consultants   shall   carry  out   layout  and  physical  design  of   the  New  International     Terminal Building, The Detailed Design shall involve production of relevant drawings including site plan, floor plans, sections and elevations using the Main scale of 1:500, or as decided in discussion with CAAN.

Building codes and standards used for the safety of users of the terminal will be based on British Standards / the UK Building Regulations guidance document Approved Document B (ADB) supported by the BS 7974 suite of fire engineering documents; or other Internationally recognized building fire codes. The Codes to be followed in all cases will be discussed with the Client and local authorities and concerned regulatory bodies. The finishes for various components shall be discussed with CAAN and finalized.

The multi-level terminal with provision of specialized equipment at the terminal will be identified. The equipment to be considered for such items will include Automated Baggage Handling systems with online baggage scanning system Lifts, Flight Information Display systems, IT systems, Airport Operations Database ( AODB), PC rooms, Building security systems, access control/ swipe cards/ biometric systems, Passenger Boarding Bridges, and Visual Docking System  etc  in keeping with the security requirements and threat perception and meeting ICAO Annex 17 security SARPs. 

Passenger   departure   hall,   arrival   hall,   security   /   transit   hall,   navigational   /   communication installations, airlines offices, shall be provided with air conditioning. Public areas & offices at Cargo complex shall also be covered. Central air conditioning plant with environment friendly refrigerant shall be proposed which consumes comparatively less power. Air-conditioning plant capacity shall be worked out based on ambient conditions, occupancy and type of construction after detailed heat load calculations. 

Being a public utility building it is essential to provide fire detection & alarm. Fire fighting equipment, first   aid  and   sprinkler   system shall  meet   the   requirements  of   local   regulations  and   shall   be  of international standards.

The   systems   shall   be   designed   to   meet   the    Energy   saving   and   Environment-friendly requirements :Lighting system for the building  including exterior  lighting, Power distribution and Lightning protection, and  Irrigation network in Corporate and green areas, 

Task 809: Detailed  design  of  Reconfiguration  of  existing   International   Terminal  Building   to 

Technical Proposal

Page 37: TIA Nepal Approach Methodology 24-11-14

operate as domestic terminal.

The   consultant   shall   undertake   review  of  existing  designs  and   carryout  preliminary   designs   for reconfiguration  works and equipment. Quality of service, e.g. IATA LOS factors will be considered in terminal designs. Facelift of the existing building with use of modern finishing items shall be decided in consultation with CAAN.

Norms on processing area per peak hour pax., potential for commercial area development etc. will be used in the design development of the passenger terminals. The equipment to be considered for such items will include Automated Baggage Handling systems with online baggage scanning system Lifts, Flight Information Display systems, IT systems, Airport Operations Database ( AODB), PC rooms, Building   security   systems,   access   control/   swipe   cards/   biometric   systems,   Passenger   Boarding Bridges,  and Visual  Docking  System   etc     in  keeping  with   the  security   requirements  and  threat perception and meeting ICAO Annex 17 security SARPs. 

Task 810: Detailed   design   of   New   access   road   and   multi-story   car   park   for   the   new International Terminal Complex, planning and design of interface between New ITB and future MRT (Mass Rapid Transit) station

The following type of roads will be planned to meet the traffic needs of the airport.  Access Road  Service Roads Car Parks

The Multi-level car park shall be designed with associated utilities, electrical & mechanical systems, lifts,   escalators,   security   systems,  CCTV,   IT   systems,   structural  designing,   interior  designing  and commercial exploration aspects etc.The proposed site of ITB shall be connected to existing road network, multi-level car park/ proposed MRT station ( conceptual design)  in such a way that resultant network provides an efficient access to and from the airport. The entire road network will be planned and designed (geometric design and pavements), drainage, trees and landscape, markings and road signs etc. 

Task 811: Detailed design of Water supply improvement for the airport and Provision of fire hydrants at air side and land side, New sewage treatment plant

Based   on   data   collected,   the   Consultant   shall   identify   following   with   respect   to   support infrastructure at the proposed airport:

Water Supply: So As per TOR , existing water supply system is to be shifted to North West of the airport. The existing water supply source, quantity and quality of treated water available shall be studied in detail and , scheme for off-take of water, specification and cost estimate will be prepared. Detailed   scheme will   include     additional  bore  wells,  water   treatment  plant,    water  distribution system  and  requirements of fire hydrants etc. shall be catered.

Waste Water Disposal: New sewage treatment   plant facility shall be designed for the increased requirement   considering   the   capacity   of   New   ITB,   refurbished   domestic   terminal   ,   cargo,VVIP Building and other ancillary buildings alongwith scheme for management (disposal and/or reuse) of untreated / treated waste water, specification, cost estimate etc.

Technical Proposal

Page 38: TIA Nepal Approach Methodology 24-11-14

Fire Hydrant System: Fire hydrant system for NTB, air side apron of NTB shall be provided as per safety requirements.

Task 812: Detailed design of  Fuel  hydrant  system for  new  international  apron and remote aircraft parking apron.

The   fuel  hydrant   system  for   the   international   apron  and   remote  aircraft  parking  bays   shall   be designed and proposed to be connected to the existing  fuel depot .

The existing fuel depot shall be assessed and need for expansion shall be established. Accordingly site development plan for new fuel depot shall be prepared. The proposed new  fuel depot shall be designed and divided into three categories:

Inbound or receiving system, Storage system Dispensing or delivery system

The system shall comprise of underground piping for hydrants, hydrant pits, hydrant vehicles/ hydrant carts, storage tanks, pumps, filters, cathode protection system and other safety devices/ safety procedures. While developing the system, care shall be taken to provide following safety and working parameters:

Health, Safety and Environmental (HSE) Policy Safety Plan Hazard and Risk Analysis Quality Assurance Policy (QAP) and Procedures Project execution plan Detailed specifications

Task 813: Detailed design of Relocation of existing Nepal Army establishments, development of future infrastructure in available areas of TIA.

As per New Master Plan Nepal Army Hangar is to be shifted to  eastern side of runway and existing Nepal Army establishment is to be relocated to provide more area for airport operations.

Detailed design as per international standards shall be carriedout including architectural designing, structural designing, interior works, electrical and mechanical equipment/ utilities  designing, wiring lighting illumination , etc. 

Task 814: Detailed design of Relocation of existing and development of new VVIP Building and associated facilities.

As per New Master Plan VVIP facilities are to be relocated out of existing terminal building which is to be redesigned for use as Domestic Building.

New VVIP Building with associated facilities shall be designed in detail as per international  standards including architectural designing, structural designing, interior works, electrical and mechanical equipment/ utilities  designing, wiring lighting/ illumination , etc. 

Task 815: Detailed design of Site development for future fuel farm, fuel  hydrant system

Technical Proposal

Page 39: TIA Nepal Approach Methodology 24-11-14

Fuel hydrant system for new international apron & remote aircraft parking apron bays shall be designed  and details worked-out accordingly.

Site development for new fuel farm shall be provided in detail along with design details. The fuel hydrant system below the apron pavement shall be connected to the fuel depot The fuel depot shall be designed and divided into three categories:

Inbound or receiving system,

Technical Proposal

Page 40: TIA Nepal Approach Methodology 24-11-14

Storage system Dispensing or delivery system

The preliminary cost of the system shall be worked out giving details of expansion program in a phased manner to meet the current requirements and future growth as the air traffic increases. 

Task 816: Detailed design of Expansion of Cargo Terminal

On the basis of the updated air traffic forecast and analysis thereof, the Consultant shall prepare plans,   designs   and   drawings   for   carrying   the   augmentation   in   the   existing   Terminals   or   new construction   of   the   terminal   building   to   facilitate   smooth     goods   flow   conforming   to   the international standards/ IATA / ADRM norms. 

The terminal  building will  be provided with all  facilities required for security,  Surface movement guidance   and   control   system,   public   address   system,  CCTV   system,   Fire   safety   systems   (water sprinkler, smoke detectors, water hydrants, fire hoses etc.), electrical and mechanical systems for cargo   handling   like   ASRS   and   appropriate   signage.   Offices   for   airlines,   airport   operators   and regulatory agencies will also be provided. 

Task 817: Review   improvement   on   CNS/ATM     identify   further   improvement   needs   on CNS/ATM at TIA to be included in the next project; and prepare detail design of the priority improvements

Keeping in view the meteorological data, Aerodrome Reference Code, operational requirement, the site   surveys   and   the   surroundings,   the   Consultants   shall   review   the   existing   facilities,   or   the proposed Radar project    and determine the  appropriate  navigational  aids  for  safe,  secured and trouble free airport operations in consultation with the CAAN. The siting and locations will be subject to actual ground conditions and site characteristics. Based on the requirements, the Consultant shall design the navigational aids such as DVOR/DME, ILS/DME, etc. in conformity with the Annex 10, ICAO   and   the   latest   market   trends   and   technologies.   The   Consultant   will   also   detail   the communication facilities for the Airport such as Air to Ground and Ground to Ground as per ICAO requirements. 

The Consultant shall also prepare detailed plans that will establish the site and the development program for the Airport Air Traffic Control in the future for monitoring of Navaids, AGL systems, communication and other relevant Airport operational facilities. The Consultant shall examine the existing   instrument   landing   facilities   i.e.  NDB and  other   related   facilities  and   suggest  necessary measures for changes/augmentations. The Air-conditioning requirements and other electrical loads shall also be detailed in the design. Each facility shall be provided with UPS of required capacity.

Task 818: Study   dedicated   surface   transportation   system   for   TIA   linking   with   key   road transportation nodes with appropriate options to provide dedicated airport access from these transportation nodes

A dedicated road transport system consisting of roads or via duct, as appropriate, to airport from main nodal points of Kathmandu, Patan and Bhakatapur shall be planned & designed with  full detailing of intersections , via ducts,  toll plaza, security systems including CCTV, IT systems etc. and structural designing/ cost estimates.

Task 819: Review and assess current discussion and initiatives on Public Private Partnership (PPP)   in   infrastructure   development   in   the   country,   review   the   reports   and assessment conducted,

Technical Proposal

Page 41: TIA Nepal Approach Methodology 24-11-14

Review   and   assess   current   discussion   and   initiatives   on   Public   Private   Partnership   (PPP)   in infrastructure development in the country, review the reports and assessment conducted, Assist  in assessing future development/improvement  plan of TIA under PPP in consultation with CAAN,   taking   into   account   feasible   PPP   modes,   management,   contractual   and   financial arrangements, risk assessment, context of future role of CAAN.

Based   on   detailed   design   and   costing,   identify   airport   works/sub-projects   potential   for   PPP undertaking.  Assess  financial   regimes   (investment,   return);   conduct  financial   analysis   to  project financial implications for potential PPP projects. Prepare pre-qualification documents, expression of interest, terms of reference, bidding/contract documents, concession agreements for PPP project.

Finalize recommended action plans for the priority PPP projects including implementation steps, timelines and key issues to be addressed for successfully implementation of the project. Support CAAN to implement the action plans.

Task 820 Preparation of Engineering Drawings

The design  development  will  establish   the   structural   system proposed  for   the  execution of   the project and integration of the civil,  mechanical, electrical and other systems into the design. The design development drawings will include the following:

Topographic plans, scale 1:2000

Plans and profiles, scale 1:2000/1:200 

Typical cross sections for pavement, scale 1:50 

Culvert and open drains 

Auxiliary works

Maintenance of Traffic Plans 

Architectural / Interior Design of Terminal Building 

Structural details of Terminal Building 

Mechanical details of Terminal Building 

Electrical details of Terminal Building 

Security fence in the operational areas 

Airside pavements including review of drainage 

Runway lights for airside pavements 

Landscape on city side of Terminal Building 

Utilities associated with Terminal Building 

IT and Terminal / Support Facilities

The  design  development  drawings  of  all   the  work  packages   shall   be  prepared   to   the   scales   as indicated in TOR in a manner and to such detail that insure the pricing and subsequent construction by qualified contractor(s)  without  any ambiguity  or misinterpretation,  and without  the need  for further design services.

Technical Proposal

Page 42: TIA Nepal Approach Methodology 24-11-14

Task 821: Preparation of Bill of Quantities and Cost Estimates

The cost estimates will be prepared and the final estimates of quantities as well as the unit rates based on market rates for the inputs will be furnished. For the unit rate analysis, due consideration will be given to the various inputs and their basic rates, proposed location of plants and respective lead distances for mechanized construction. The unit rate for each item of work will be worked out in terms of manpower, machinery, materials, overheads, profiles etc. The taxes (direct or indirect, duties, levies, and fees) shall be indicated separately. 

With the unit costs derived as explained above and the quantities developed by detailed engineering design activity, the project base costs will be worked out and shall be accurate to within +/-10%. A firmed-up cost estimate and bill of quantities (BOQ) will thus be prepared on these considerations. The cost estimate shall be broken down by main work items into foreign and local components as under:

i) For foreign currency 

Imported equipment, materials and supplies 

Identifiable   foreign   components   of   domestic   manufactured   equipment,   materials   and supplies 

Salaries of expatriate personnel, and 

Profit and overheads of foreign firms where appropriate 

ii) For local currency 

Right of way acquisition 

Local materials, supplies and services

Salaries and wages of local employees both skilled and unskilled 

RAP & EMP

Task 822: Review and Updating of Economic Assessment

The Consultants will review and update the economic assessment prepared under Stage I, taking into account the latest traffic data and the final estimated cost as per detailed design for the Project.

Task 823: Preparation of Construction Schedule

In   order   to   facilitate   project   implementation,   the   Consultants   will   develop   an   appropriate procurement procedure which will  indicate the required construction period and forward budget needs etc. The Consultants shall carry out a network analysis of the project using suitable software showing, inter alia:-

Major activities and their duration

A “network” showing the proposed ordering or sequencing of the major activities.

Duration of the entire project in the form of a bar chart

Monthly cost of each activity

Anticipated monthly expenditure presented in form of an S-curve.

Works  time scheduling   if  night   shifts  are  mandatory   to  allow continuous  airport  operations during rehabilitation period.

Technical Proposal

Page 43: TIA Nepal Approach Methodology 24-11-14

In carrying out this analysis, due account shall be taken of the climatic conditions in the project area.

Task 824: Preparation of Tender Documents

The Consultant shall prepare the general and special specifications for the project works as per the scope of work based on ICAO and FAA guidelines, sound engineering practices and manufacturer’s specifications.  Based  on   the  design  and  drawings   approved  by   the  CAAN,   the  Consultant   shall prepare necessary construction drawings for tender purpose and execution. 

The Consultant shall prepare the bid documents for the project package wise. The tender documents will comprise the following:

Volume I: Invitation to Tender, 

Instructions to Bidders, Bidding Data, 

Forms of Bid and Qualification Information, 

Form of Agreement and Appendix 

Form of Performance Guarantee 

Tender Surety 

Special and General Conditions of Contract 

Bill of Quantities  

Volume II:  Technical Specifications (General and Special Specifications)

Volume III: Drawings (A3 size)

Volume IV: IV (A) Materials Report and IV (B) Hydrological / Hydraulics Report 

The Tender Documents shall indicate that Volume IV (A) & (B) are “for information only and not part of tender documents” with a preamble in the text stating that this report is only representing the investigation and findings of the Consultant and shall be bidders responsibility for any source and quality of material etc. without binding the Client. 

TASK GROUP IX: DELIVERABLES

Task 901: Inception Report

The   report,   consisting  of   initial  findings,  project   schedule,  design   criteria   and   staff  mobilization schedule will be presented one month from the project commencement to the Client.

Based on the information collected, we will prepare Project Procedures and Guidelines for planning, designing and tendering, standard specifications, QA/QC, environmental,  O&M, risk management etc. documents to be used during the course of the project.

This report shall briefly describe the mobilization and establishment status of the Consultant, the specific staffing plan, the updated work plan the Consultant proposes to follow in carrying out the assignment based on the Consultant’s initial findings, details of any constraints or inputs required from the employer and such remarks as are deemed appropriate including the works done so far. 10 copies of the Inception Report shall be submitted not later than 60 calendar days from the date of commencement of services. 

Task 902: Report on Updated Master Plan

Technical Proposal

Page 44: TIA Nepal Approach Methodology 24-11-14

Following the Inception Report, environmental and social impact assessment, the Consultant shall proceed with establishment of the financial and economic justification of the project, analysis of the study shall include calculations of the Internal Rates of Return (IRR) and the Economic Rate of Return (ERR), Cost Benefit analysis etc. The Consultant shall submit the Preliminary Feasibility Report (10 copies) in hard copy and one editable soft copy of spread sheets showing all calculations  within 6 months   of   commencement   of   services.   The  feasibility   study   report   shall   include   findings   on environmental and social impact assessment. 

Task 903: Standard bidding documents for construction and PPP transactions

Report   on   updated   master   plan;   conceptual   designs   and   standard-bidding   documents   for construction works and standard bidding document   that for facilities that may be considered for PPP and with  varying combinations of the facilities available for PPP proposed will be discussed with the Client and the stakeholders within six months from the commencement of the study.

Task 904: Interim Design report

Review of existing designs and undertake preliminary designs for new works and equipment. Quality of  service,  e.g.   IATA LOS  factors  will  be  considered   in  the  new,  and modifications  proposed for existing, terminal designs.

Norms on processing area per peak hour pax., potential for commercial area development etc. will be used in the design development of the passenger terminals. For cargo terminals the norms will be based on area/ton of cargo, type of cargo, regulatory procedures, extent of mechanization and IT processing involved etc.

Environmental   and   Social   Issues   -   Identification   of   Environmental   and   Social   issues   will   be undertaken as a parallel exercise with the Interim Design, in order to minimize major engineering, economic, social or environmental impacts and develop practicable EMPs.

Prioritization and sequencing of the development works will be undertaken and finalised with CAAN and stakeholders, to ensure minimum discomfort during further development.

The likely capital costs for the facilities would be calculated using local construction cost rates, and lump sum cost bids for vendor supplied equipment. 

Interior design and landscape design will be done and costed.

Findings of surveys will be utilized for design preparation based on Design Criteria. These in turn will be on the basis of functional Requirement and the various procedures developed during the planning stage. We shall also give due consideration to the following: 

a) “Value Engineering” practices b) Integrated planning to avoid conflicts during construction  

Report on updated master plan; conceptual designs and standard-bidding documents and containing an executive summary will be discussed with the Client and the stakeholders within six months from the commencement of the study.

Task 905: Draft Final Design Report, cost estimates,3D AV presentations

Technical Proposal

Page 45: TIA Nepal Approach Methodology 24-11-14

Draft Final Design Report, Draft Final Design Report will be submitted by the Consultant  within 15 months of commencement of services. This report shall cover all aspects of the Final Reports.  The objective of these reports shall be providing the Client with the opportunity for a final crosscheck of all  documents  before preparation of   the  final  version.  The report  shall   summarize   the findings, analysis, results and recommendations of the detailed engineering design, and shall consist of the following volumes:  

i) Design Report –Main Report

The design  report  describing  the  salient   features  of   the  design  for   the airport,  which  shall include all the assumptions and criteria used in the analysis and design of the works, together with all details and standards used. The report shall include an executive summary followed by the main report. All design calculations for pavements and structures shall be enclosed in the form of annexes.

ii) Materials Report

A report summarizing all geotechnical findings and adoption of those findings to the design, quantities and qualities of materials to be available with the corresponding excavation depths, test results and any other related information in respect of material quarries.

iii) Hydrological - Hydraulic Report

The report summarizing all Hydrological and hydraulic analysis/calculations together with the assumptions and criteria used for the design of drainage structures, water way opening, major water courses, 

iv) Engineering Drawings

The  Consultant   shall   prepare  A1  size  contract  Engineering  Drawings,  which   shall  be  photo reduced to A3 size and submitted as bound sets. The drawings shall include locations of the proposed   pavement   treatment,   typical   Sections,   typical   treatment   details,   layouts   plans, elevations and constructional details of buildings. The consultant shall forward to CAAN one (1) complete set of originals of all drawings in A1 size and five bound sets in A3. In additional an electronic copy of the drawings should be submitted to CAAN.

v) Confidential Cost Estimate (5 copies)

The confidential cost estimate for works and services shall be in the form of completed Bills of Quantities. The estimate shall be submitted together with other reports

Draft Final design report will  be presented to the client  in 3DAudio -visual     presentation for all packages

Task 906: Draft Bidding documents

On approval of the standard bidding documents for all works and equipment packages, draft bid documents   will   be   prepared   and   submitted   to   the   employer   within   16   months   from   the commencement date. 

We will recommend the Project’s environmental indicators, the data to be collected and evaluated to measure the effectiveness with which the environmental mitigation and monitoring measures are implemented, in these documents.

Task 907 Final Bidding documents for construction and PPP transaction  nts

The    final  bid  document   for  all  works  and equipment  packages   shall  be  finalized   incorporating Employers and ADB’s comments including specifications, BOQ/ cost estimates and design and will be submitted to the employer within 17 months from the commencement date.

Technical Proposal

Page 46: TIA Nepal Approach Methodology 24-11-14

Task 908: Final  Report and Final  Tender Documents,  updated Master Plan,3D Model,3D-AV presentation

A report comprising of all deliverables including updated Master Plan, 3D model and 3D audiovisual presentation will be submitted to the employer within 18 months from the commencement date. The Final Report (10 copies) shall be submitted which shall include all related Tender Documents. This report shall incorporate compliance of all comments received from the Client.