tidal flood defences river arun - arcelormittal piling · tidal flood defences river arun...

2
Existing steps to be broken Voids filled with Class 1A or 1B fill Class 1A or 1B fill Class 6A modified fill Future ground level Existing structure Sand Chalk Fill Wall typically HZ 1180M D-sol.12 king piles and AZ 26 sheet piles infills Flood protection level Riverward Landward MHWN +1.35 m0D +5.0 m +4.25 m MSL +0.05 m0D MLWN -1.35 m0D MHWS +2.85 m0D HAT +3.45 m0D -0.45 TGL 3.725 +4.80 m Future ground level +0.02 MLWS -2.65 m0D LAT -3.25 m0D 750 670 = = Class 1A or 1B fill Working in partnership with Arun District Council, West Sussex Council and Littlehampton Harbour Board, the Environment Agency is improving the tidal flood defences along the East Bank of the River Arun in Littlehampton, on the South Coast of England. The work is being carried out by VolkerStevin and CH2M Hill and is budgeted at £14.1million. Completed at the end of 2014, the scheme protects 2,000 residential properties and businesses against 75 years of predicted sea level rise as well as enhancing the riverside walkway between the town and the beach. Two types of retaining wall were considered for the structure which has to withhold upto 6.9 m soil and ground water without lateral support. Initially a tubular wall in combination with AZ ® steel sheet piles was thought to be the most economical but on consideration of the long design life, the HZ ® / AZ ® combined wall system from ArcelorMittal was found to be the most economic and technically feasible solution. It utilises large HZ ® -M (HZ 1180M A-sol.12 & HZ 1180M D-sol.12) beams with welded interlocks, which are installed by panel driving techniques down to the required levels before AZ 26 sheet piles are driven to connect the beams into a continuous wall. The beams carry the vast majority of the bending moments and have the advantage that the face of the beam is small in comparison with a tubular solution. CH2M Hill had to take great care over assessing the design life of the structure, which at its most aggressive depth had to tolerate up to 7.2 mm thickness loss through the design life of the flood wall. Tidal Flood Defences River Arun Littlehampton | UK Typical cross section

Upload: others

Post on 14-Jun-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Tidal Flood Defences River Arun - ArcelorMittal Piling · Tidal Flood Defences River Arun Littlehampton | UK Typical cross section . Tidal Flood Defences River Arun Littlehampton

Existing steps to be broken Voids filled with

Class 1A or 1B fill

Class 1A or 1B fill

Class 6A modified fill

Future ground level

Existing structure Sand

Chalk

Fill

Wall typically HZ 1180M D-sol.12 king piles and AZ 26 sheet piles infills

Flood protectionlevel

Riverward Landward

MHWN +1.35 m0D

+5.0 m

+4.25 m

MSL +0.05 m0D

MLWN -1.35 m0D

MHWS +2.85 m0D

HAT +3.45 m0D

-0.45

TGL 3.725

+4.80 mFuture ground level

+0.02

MLWS -2.65 m0D

LAT -3.25 m0D

750

670

==

Class 1A or 1B fill

Working in partnership with Arun District Council, West Sussex Council and Littlehampton Harbour Board, the Environment Agency is improving the tidal flood defences along the East Bank of the River Arun in Littlehampton, on the South Coast of England. The work is being carried out by VolkerStevin and CH2M Hill and is budgeted at £14.1million.

Completed at the end of 2014, the scheme protects 2,000 residential properties and businesses against 75 years of predicted sea level rise as well as enhancing the riverside walkway between the town and the beach.

Two types of retaining wall were considered for the structure which has to withhold upto 6.9 m soil and ground water without lateral support. Initially a tubular wall in combination with AZ® steel sheet piles was thought to be the most economical but on consideration of the long design life, the HZ® / AZ® combined wall system from ArcelorMittal was found to be the most economic and technically feasible solution.

It utilises large HZ®-M (HZ 1180M A-sol.12 & HZ 1180M D-sol.12) beams with welded interlocks, which are installed by panel driving techniques down to the required levels before AZ 26 sheet piles are driven to connect the beams into a continuous wall. The beams carry the vast majority of the bending moments and have the advantage that the face of the beam is small in comparison with a tubular solution.

CH2M Hill had to take great care over assessing the design life of the structure, which at its most aggressive depth had to tolerate up to 7.2 mm thickness loss through the design life of the flood wall.

Tidal Flood Defences River Arun Littlehampton | UK

Typical cross section

Page 2: Tidal Flood Defences River Arun - ArcelorMittal Piling · Tidal Flood Defences River Arun Littlehampton | UK Typical cross section . Tidal Flood Defences River Arun Littlehampton

Tidal Flood Defences River Arun Littlehampton | UK

Project Owner Environment Agency

Design Consultant CH2M HILL

Contractor VolkerStevin

Sheet Piles HZ 1180M A-sol.12 21.2 m S 355 GP 1 031 t AZ 26 Pairs 12.6 m S 355 GP 233 t HZ 1180M D-sol.12 21.7~22.0 m S 430 GP 971 t AZ 26 Pairs 12.2~12.6 m S 430 GP 222 t Total 2 457 tonnes of sheet piles

Photography copyright © High Camera Ltd | UK _ www.highcamera.co.uk

10

.20

16

- C

S 0

23

- L

ittle

ham

pton

- G

B

ArcelorMittal Commercial RPS S.à r.l.Sheet Piling | 66, rue de LuxembourgL-4221 Esch-sur-Alzette | LuxembourgT (+352) 5313 [email protected]

ArcelorMittal Commercial UK LtdSheet Piling | Flr 3, Fore 2, Huskisson WaySolihull B90 4SS | United Kingdom T (+44) 0121 713 6655 | F (+44) 0121 733 1299 sheetpiling-rps.uk@arcelormittal.comsheetpiling.arcelormittal.com

MLW

Shelter

COASTGUARD ROAD

Shingle

Mean H

igh

River Arun

Lighthouse

ARU

N PAR

ADE

Park

Sand

4.0mStone

(occulting white)

East Pier

Stone

Amusement Park

MLW

Amusement

Sand and Shingle

Mean Low

Water

Shingle

NN

B463457/CIVIL/103

B463457/CIVIL/103

C463457/CIVIL/103

C463457/CIVIL/103

A463457/CIVIL/103

A463457/CIVIL/103

A463457/CIVIL/103

A463457/CIVIL/103

H463457/CIVIL/103

H463457/CIVIL/103

J463457/C

IVIL/106

J463457/C

IVIL/106

M463457/C

IVIL/107

M463457/C

IVIL/107

L

MR

L

L

MR

X

X

ARU

N PAR

ADE

Promenade retaining wall

Exclusion zone forFoul Water Crossing

Steel sheet piles withreinforced concrete cap

REACH 2

Steel sheet piling

REACH 2 Steel sheet piling

REACH 1 Steel sheet piling

Promenade retaining wall

Reach 1 and 2 General Arrangement

HZ®-M template

When analysing the two solutions the HZ® / AZ® was found to be stronger after sacrificial losses in comparison with the same losses from the tubular solution. This resulted in the significant cost saving by utilising the HZ® / AZ® solution.

All of the solutions were analysed and priced with ArcelorMittal included as part of the project team with the “Early Supplier Involvement” service.

Soils typically consisted of made ground with overlying chalk of varying strength. The made ground was the result of previous port construction (and activity) and was very varied. It included obstructions and cobbles. The chalk was weak in the upper layers, but increased in strength with depth and had flints and cobbles within the matrix.

The installation was carried out by VolkerStevin. Very robust driving frames have been constructed such, that the lower frame was close to high tide level and then the wall was installed with a combination of vibratory techniques (PVE 40VN) and noise shrouded percussive techniques (BSP CX85 in 7 Tonne mode and BSP CX110 in 9 Tonne mode). All equipement was heavily shrouded with double skin acoustic shrouding to keep noise levels to a minimum.

The site worked through some very difficult conditions with the wettest winter for some years, in conjunction with long periods of gale force winds. The installation works on Reaches 1 & 2 have been successfully completed with piling work moving to higher reaches using conventional AZ® sheet pile walls.