Managing mega-‐projects: comparing Heathrow Terminal 5 and the
2012 London Olympics'
Prof. Tim Brady University of Brighton, UK
Business in Built Environment Workshop May 6, 2015 Smart City Seminar Oulu, Finland.
![Page 2: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/2.jpg)
2001
![Page 3: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/3.jpg)
Page 3
2005
![Page 4: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/4.jpg)
2007
![Page 5: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/5.jpg)
2009
![Page 6: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/6.jpg)
2011
![Page 7: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/7.jpg)
2013
![Page 8: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/8.jpg)
Why do projects fail?
![Page 9: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/9.jpg)
“Projects exhibit high failure rates because senior managers and project teams underes8mate, up front, the extent of uncertainty and complexity involved in their projects and fail to adapt their management style to the situa8on.” Source: Shenhar and Dvir, 2007 Reinven8ng Project Management, Harvard Business School, Boston MA.)
![Page 10: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/10.jpg)
Is there a beYer way?
![Page 11: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/11.jpg)
Back to the 1950s
![Page 12: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/12.jpg)
Two approaches
Characterised by
Mr OpZmizer and Mr SkepZc
Page 12
See Klein, B.H. and Meckling, W. (1958), “ApplicaZon of operaZons research to development decisions”, OperaZons Research, Vol. 6, pp. 352-‐63
![Page 13: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/13.jpg)
Mr OpZmizer systemaZcally analyses and compares all the alternaZve promising final systems makes esZmates about the performance all the subsystems and components might achieve by the target date matches these alternaZves to a detailed model of the future operaZng environment then, according to some criteria for choosing the most efficient system among the alternaZves, a choice is made which end-‐product is best
![Page 14: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/14.jpg)
Mr SkepZc refuses to define what is opZmal at an early stage contracts for several prototypes to be developed in the overall programme maintains flexibility by commifng resources to the development in stages, constantly reviewing enables learning to take place which allow beYer decision-‐making at later stages
![Page 15: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/15.jpg)
Klein & Meckling’s findings If Mr OpZmizer’s assumpZons (guess) about performance of the single choice prove correct then certainly that soluZon will be more efficient But if they turn out wrong then there are serious consequences in terms of inferior quality, major cost escalaZon and schedule overruns Mr SkepZc’s strategy is ojen the most efficient
![Page 16: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/16.jpg)
Why do some megaprojects succeed?
![Page 17: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/17.jpg)
Any QuesZons?
![Page 18: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/18.jpg)
Page 18
![Page 19: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/19.jpg)
Heathrow Terminal 5
• Europe’s largest construcZon project £4.3bn
• New infrastructure – system of systems
– 2 main terminal buildings – 60 aircraj stands – baggage handling system – 600-‐bed hotel – 4,000 space car park – Road and rail extensions – Air traffic control tower – 2 rivers diversions – Major tunnelling and excavaZon
London 2012 • Large project -‐ original budget £8.1bn • New infrastructure – system of
systems – The Olympic stadium – AquaZcs centre – Velodrome + BMX track – Basketball arena – Eton Manor – Olympic village – IBC/MPC – Energy Centre + associated
underground networks for gas, electricity, water, telecoms and sewage
– Waterways, Wetlands, Green spaces/parklands, 30 bridges, underpasses, new road and rail links
![Page 20: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/20.jpg)
Challenges they faced London 2012 Olympics • Large and complex
construcZon programme • MulZple stakeholders, some
with conflicZng objecZves • Dual objecZves of delivering
the games and providing legacy benefits
• Large public sector investment
• Extremely high public profile • Huge reputaZonal risks for
government and country • An immovable deadline –
opening ceremony to take place on 27th July 2012
Heathrow Terminal 5 • Largest and most complex
project undertaken by BAA • Planning Inquiry: 700
condiZons • Project risk: cost overruns
could affect survival of BAA as a company
• T5 site: physically constrained; logisZcally challenged
• Heathrow had to remain in service while T5 was built
• Systems integraZon: many different knowledge bases and technologies
• BAA set a deadline – T5 to open end-‐March 2008
![Page 21: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/21.jpg)
• structural complexity was dealt with by breaking the project down into 4 main areas and 147 sub-‐projects and the single model environment, pre fabrica7on
• to deal with socio-‐poliZcal complexity BAA introduced the T5 agreement and integrated teams
• emergent complexity was dealt with by BAA accep7ng all the risk, re-‐imbursible contracts, incen7ves to innovate during the project and the just-‐in-‐7me logis7cs
• uncertainty was dealt with by early experimenta7on and standardisa7on of major components, by pre-‐assembly, by off site tes7ng to prove constructability, and a policy of not adop7ng untested technologies
The Heathrow T5 approach
![Page 22: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/22.jpg)
• structural complexity was dealt with by breaking the programme down into 70 projects in 6 different directorates – Infrastructure; Venues; Security; LogisZcs; Village; Transport
• socio-‐poliZcal complexity was dealt with by introducing strong governance with clear responsibili7es for assurance and repor7ng -‐the ODA appointed an experienced Delivery Partner (CLM) to oversee the whole programme and each project had its own management structure and was led by a Tier One Contractor who was accountable for delivery
• emergent complexity and uncertainty were dealt with by using familiar partners and the loose-‐7ght approach and not adop7ng new technologies
The London 2012 approach
![Page 23: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/23.jpg)
Observations from the cases • both projects/programmes were complex in all forms: structural,
socio-‐poliZcal, and emergent and subject to strict Zme constraints
• BAA was an intelligent client with in-‐house capability delivering serial projects/programmes
• London 2012 was a one-‐off but the ODA was an intelligent client that led the approach and appointed a capable delivery partner
• BAA adopted a single approach to contracts – the T5 agreement; ODA had a variety of contractual arrangements depending on the complexity of the project but both supported collaboraZve pracZce and integrated team working
• neither T5 nor London 2012 did anything radically new • both T5 and London 2012 had a long Zme to plan and prepare • both exploited learning from earlier projects • both had large adequate budgets
![Page 24: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/24.jpg)
The hybrid opZmiser/skepZc model
Strong Client leadership and involvement Strong governance – assurance and reporZng CollaboraZve working – integrated teams Flexibility – ability to have different contracZng approaches in sub-‐projects according to the situaZon Adaptability – able to respond to changes Learning
![Page 25: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/25.jpg)
![Page 26: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/26.jpg)
![Page 27: Tim Brady in the Oulu Smart City Seminar on Wed 6th May, 2015](https://reader034.vdocument.in/reader034/viewer/2022042819/55cae533bb61eb4c788b4706/html5/thumbnails/27.jpg)
The OpZc Model of Project Success
Strong Client
Strong gover-‐nance
Collab-‐oraZve working
Flexi-‐bility
Adapt-‐ability
Learn-‐ ing