topaz jacktopaz jacket installationet installation
TRANSCRIPT
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
1/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
TOPAZ JACKET INSTALLATION
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
2/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
1. Rig up slings on jacket to main hook of HLV 2. Raise up the hook to 30% of designedload, then cut seafastening
The installation of TOPAZ jacket will contain below steps:
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
3/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
3. Lift the jacket off the cargo bargearound 3m from top of grillages
4. Cast off the barge from HLV
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
4/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
5. Lower down the jacket into water 6. Adjust cranes hooks to upend the jacket
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
5/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
7. Adjusting and preliminary leveling forjacket by using auxiliary hook of HLV
8. Jacket set down to the seabed
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
6/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
9. Pile lifting and place on upending clamp 10. Pile upending and stabbing into jackets leg
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
7/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
11. Release ILT, deploy hammer to startpile driving
12. Driving piles to its target penetration
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
8/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
13. Completed driving of 1st segment of pile,perform jacket leveling by using leveling tool
14. Cut off 1st segment, stab 2nd segment into1st pile and weld
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
9/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
15. Completion of pile driving and leveling, pilecut off, then weld crown shims to connect pilesto the jacket
16. Installation of transition piece on top of piles
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
10/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
17. Lifting, upending and stabbing conductorsinto conductors guides
18. Driving conductors to its target depth
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
11/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
19. Installation of boat landing No. 3 20. Installation of boat landing No. 2
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
12/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
21. Installation of boat landing No. 1 22. Installation of riser guard
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
13/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
INSTALLATION COMPLETION
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
14/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
THANK YOU FOR YOUR
ATTENTION!
-
7/27/2019 Topaz JackTopaz jacket installationet Installation
15/15
PTSC OFFSHORE SERVICES
T&I PROJECT INTERNAL TRAINING
QUESTION & DISCUSSION??