  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    1/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    TOPAZ JACKET INSTALLATION

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    2/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    1. Rig up slings on jacket to main hook of HLV 2. Raise up the hook to 30% of designedload, then cut seafastening

    The installation of TOPAZ jacket will contain below steps:

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    3/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    3. Lift the jacket off the cargo bargearound 3m from top of grillages

    4. Cast off the barge from HLV

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    4/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    5. Lower down the jacket into water 6. Adjust cranes hooks to upend the jacket

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    5/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    7. Adjusting and preliminary leveling forjacket by using auxiliary hook of HLV

    8. Jacket set down to the seabed

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    6/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    9. Pile lifting and place on upending clamp 10. Pile upending and stabbing into jackets leg

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    7/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    11. Release ILT, deploy hammer to startpile driving

    12. Driving piles to its target penetration

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    8/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    13. Completed driving of 1st segment of pile,perform jacket leveling by using leveling tool

    14. Cut off 1st segment, stab 2nd segment into1st pile and weld

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    9/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    15. Completion of pile driving and leveling, pilecut off, then weld crown shims to connect pilesto the jacket

    16. Installation of transition piece on top of piles

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    10/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    17. Lifting, upending and stabbing conductorsinto conductors guides

    18. Driving conductors to its target depth

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    11/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    19. Installation of boat landing No. 3 20. Installation of boat landing No. 2

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    12/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    21. Installation of boat landing No. 1 22. Installation of riser guard

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    13/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    INSTALLATION COMPLETION

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    14/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    THANK YOU FOR YOUR

    ATTENTION!

  • 7/27/2019 Topaz JackTopaz jacket installationet Installation

    15/15

    PTSC OFFSHORE SERVICES

    T&I PROJECT INTERNAL TRAINING

    QUESTION & DISCUSSION??