Cambrian School District Bond Project Update March 6, 2014 Board of Trustees Meeting Dr. Debbie Blow Rick Kramer, Kramer Project Development Co. Linda Mao, Sugimura Finney Architects. TOPICS. Bond timeline review Fammatre 3 Classrooms update Solar Project update Steindorf Project update – - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: TOPICS

1

Cambrian School DistrictBond Project Update

March 6, 2014 Board of Trustees Meeting

Dr. Debbie BlowRick Kramer, Kramer Project Development Co.

Linda Mao, Sugimura Finney Architects

Page 2: TOPICS

2

Bond timeline review Fammatre 3 Classrooms update Solar Project update Steindorf Project update – Lease opportunity at DO Workshop

TOPICS

Page 3: TOPICS

3

Bond Timeline Review

We are here!

Page 4: TOPICS

4

Current status:◦ Budget: $1.65M◦ Construction documents are in the works using

pre-approved plan◦ Target DSA “over the counter” review March 16◦ Lease, leaseback with Bruns Belmont for the

building. Award March 20◦ Bid sitework and utilities. Award April 3◦ Start construction end of April◦ Complete construction mid August

FAMMATRE 3 CLASSROOMS UPDATE

Page 5: TOPICS

5

Fammatre Site Layout

3 New Kindergarten CR’s

Page 6: TOPICS

6

Fammatre Classroom Layout

Page 7: TOPICS

7

Current status:◦ Budget: $4.7M◦ Request for Proposals is being drafted by KPDC◦ Send to solar providers in March◦ Receive proposals and select solar provider in

April◦ April notice to proceed with design◦ September or October possible construction start

SOLAR PROJECT UPDATE

Page 8: TOPICS

8

Current status:◦ Budget: $16.5M◦ Committee established STEAM requirements◦ Curriculum synopsis board presentation tonight◦ Building requirements board presentation tonight◦ Proceed with Schematic Design (SD)◦ SD presentation to board on April 17◦ April – May. Pause until bond election.◦ June 2014 – April 2015 CEQA, construction

documents, permitting and bidding◦ May 2015 construction start

STEINDORF PROJECT UPDATE

Page 9: TOPICS

9

STEAM Curriculum Synopsis: School-wide focus on STEAM Curriculum

◦ Project-based learning: “Learning by doing” STEAM Labs and Makers Labs

◦ Integrated Curriculum◦ Common Core State Standards in action

More informational Text Depth of Knowledge

◦ The 4 Cs of 21st Century Skills Risk Taking

STEINDORF PROJECT UPDATE

Page 10: TOPICS

10

Putting the “A” in STEAM Four areas of the Arts

◦ Visual Arts◦ Music◦ Theater Arts◦ Dance

Integrated Curriculum Examples◦ Mathematics – Visual Arts & Music

◦ Language Arts – Theater & Digital Media

◦ Science – Visual Arts, Music, & Makers Labs◦ Physical Education – Science & Dance

STEINDORF PROJECT UPDATE

Page 11: TOPICS

11

STEAM Space Requirements:◦ Modernize existing buildings totaling 25,000 sf and

add two new buildings totaling 9,000 sf. Sustainable construction with LEED certification.

◦ 2 modernized classrooms per grade K8 = 18 CR’s (1 is new)

◦ Flexible multi-use space for dining, performing arts, PE

◦ Typical administrative support spaces and restrooms◦ Flexible Media Center◦ Flexible Makers Labs◦ Flexible Science Lab◦ Flexible outdoor learning spaces in courtyards◦ Outdoor amphitheater for performing arts◦ Parking and play areas

STEINDORF PROJECT UPDATE

Page 12: TOPICS

12

Steindorf Conceptual Siteplan

Page 13: TOPICS

13

Steindorf Conceptual Images

Page 14: TOPICS

14

Steindorf Conceptual Images

Page 15: TOPICS

15

Steindorf Space requirements

Page 16: TOPICS

16

Steindorf Space requirements

Page 17: TOPICS

17

Steindorf Space requirements

Page 18: TOPICS

18

Steindorf Space requirements

Page 19: TOPICS

19

Potential ability to accommodate some displaced Steindorf Tenants at the DO

Existing workshop 3,500 sf is underutilized. Could be quickly renovated and leased along with some of maintenance yard.

Build a new smaller workshop. 2,000 sf Expand maintenance yard into front

parking lot. Estimated cost around $1.3M

Lease opportunity at DO

Page 20: TOPICS

20

Lease Opportunity at DO

Page 21: TOPICS

21

Time for questions, discussion, opinions, direction.