TOWN HALL STATION COMMUNITY REFERENCE GROUP
CROSS YARRA PARTNERSHIP
FRIDAY 29 JANUARY 2021
![Page 2: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/2.jpg)
TOWN HALL STATION COMMUNITY REFERENCE GROUP
Jodie Barrington, CBD Precinct Communications and Stakeholder Engagement Lead, CYP D&C
Blythe Chidgey, Town Hall Station Stakeholder Engagement Manager, CYP D&C
Kate Kearns, Business Support and Engagement Lead, CYP D&C
Ryan Martin, Senior Tunnels Engineer - West Precinct, CYP D&C
![Page 3: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/3.jpg)
AGENDA
1. City Square acoustic shed art installation
2. Project overview
3. Town Hall Station update
4. Business support update
5. TBM Tunnelling update
![Page 4: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/4.jpg)
CITY SQUARE ACOUSTIC SHED ART INSTALLATION
Presenter Emma Coulter
![Page 5: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/5.jpg)
PRACTICE INTRODUCTION.
ADHOC, GERMANY.
RICHMOND TOWN HALL. MUSEUM OF BRISBANE, BRISBANE.
LINDEN NEW ART, ST KILDA.
VCA, MELBOURNE.
BSA, BYRON BAY. WILLIAM JOLLY BRIDGE, BRISBANE.
HOTEL WINDSOR, MELBOURNE. CHASM, NEW YORK.
ANNA PAPPAS GALLERY, MELBOURNE.
INSTALLATION ARTWORK.
![Page 6: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/6.jpg)
OPPORTUNITY.METRO TUNNEL ACOUSTIC SHED.
SITE ANAYLSIS.
CONTEXT – TIME + PLACE.
FLINDERS LANE.
VIEWS DOWN
FLINDERS LANE
SWANSTON ST.
PEDESTRIAN, + TRAM
COMMUNTERS
VIEWS TO ARTWORK
WESTIN HOTEL
ST PAULS CATHEDRAL
ADELPHI HOTEL
COLLINS ST
STREET VIEWS FROM
FEDERATION SQUARE
PRIVATE COLLEGE
NICHOLAS
BUILDING
![Page 7: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/7.jpg)
WARP.INITIAL SKETCH.
![Page 8: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/8.jpg)
SWANSTON ST.FLINDERS LANE.
ARTIST CONCEPT MODEL SPATIAL DECONSTRUCTION #23 (resilience).3D view corner Flinders Lane + Swanston st
![Page 9: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/9.jpg)
SWANSTON ST. FLINDERS LANE.
ARTIST BUILDING ELEVATIONS SPATIAL DECONSTRUCTION #23 (resilience).
![Page 10: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/10.jpg)
ARTIST CONCEPT MODEL SPATIAL DECONSTRUCTION #23 (resilience).3D view corner Swanston + Collins St
![Page 11: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/11.jpg)
![Page 12: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/12.jpg)
PROJECT OVERVIEW
Presenter: Jodie Barrington
![Page 13: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/13.jpg)
AR D E N n
PAR K V I L L E n
S TAT E L I B R ARY
T O W N H AL L n
AN Z A C n
![Page 14: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/14.jpg)
ARDEN
Arden Station site
• Station box construction ongoing, including
installation of precast platform panels
• Construction of western station building (above
ground)
• Ongoing TBM/tunnelling support and cross
passage construction
• Realignment of Laurens Street in February 2021
to enable service relocations and construction of
the Arden Station entrance
Western Portal
• Ongoing construction of egress building
Platform construction
![Page 15: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/15.jpg)
PARKVILLE
• Permanent structure works are ongoing at Grattan Street east
in the main station box. Secondary box excavation is
progressively transitioning into structure works
• Tunnel ventilation shaft and goods lift works have commenced
from site establishment at the Grattan Street east site
• Preparatory works at Grattan Street west are ongoing to
facilitate station entrance construction adjacent to The
Royal Melbourne Hospital in February 2021
Grattan Street East
![Page 16: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/16.jpg)
STATE LIBRARY
• In late-December 2020 TBM Joan
broke through into the State Library
Station Precinct
• Top-down construction works are
continuing at the La Trobe and Little
La Trobe Street sites
• Structure and lining works are
continuing below ground, as the team
continue to install the permanent
architectural elements of the future
State Library Station.
![Page 17: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/17.jpg)
ANZAC
• TBM Millie and Alice are both on their way to Town Hall
Station. Millie has completed over 600 metres of tunnel, and
Alice has completed 50
• Works to construct the Shrine of Remembrance station
entrance is underway
• Excavation continues for the tram interchange station
entrance, with the team now excavating beneath the
suspended roof slab
• In the south box, 6 of 10 concrete pours to construct the
concourse level slab are now complete.
Tram interchange excavation
![Page 18: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/18.jpg)
TOWN HALL STATION UPDATE
Presenter: Blythe Chidgey
![Page 19: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/19.jpg)
ROADHEADER TUNNELLING UPDATE
Activity Jan Feb Mar Apr May Jun
Roadheader tunnelling
Preparation for platform rail
tunnel excavation
Platform rail tunnel excavation
Platform rail tunnels
Roadheader tunnelling
• 24 hours, Monday to Sunday
![Page 20: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/20.jpg)
ROADHEADER TUNNELLING
Platform rail tunnels Completed
excavation
City Square
Flinders
Quarter
Federation
Square
![Page 21: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/21.jpg)
PLATFORM CONSTRUCTION
The structures and lining team
are continuing the construction
of the underground station
platform
Ground beam installation works
![Page 22: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/22.jpg)
FLINDERS QUARTER
![Page 23: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/23.jpg)
Basement one construction works – January 2021
![Page 24: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/24.jpg)
FLINDERS QUARTER
Activity Jan Feb Mar Apr May Jun
Shaft construction
works
(Formwork installation,
excavation, concrete
pours) Basement one slab Basement one walls
Basement two slab
Basement two walls
![Page 25: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/25.jpg)
FLINDERS QUARTER CONCRETE POUR
LARGE CONTINUOUS CONCRETE POUR
• 24 hours, 9 February 2021
• Basement one level, 500 cubic metres
Flin
de
rs S
tree
t
Swanston Street
Shaft A
![Page 26: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/26.jpg)
FLINDERS QUARTER – OUT OF HOURS WORKS
Deliveries (ongoing)
• Monday to Saturday, 5am to 7am
• Monday to Friday, 6pm to 10pm
Shaft construction
• Monday to Friday, 7am to 10pm
• Sundays, 8am to 4pm
Permanent concrete structure works
• Monday to Friday, 7am to 12am (concrete pours, as required)
• Monday to Fridays, 6pm to 7am (concrete finishing works, as required)
• 24 hours, 9 February 2021
Excavation
• Monday to Friday, 7am to 8pm
• Saturdays, 7am to 5pm
• Low noise works will continue between 8pm and 10pm (Monday to Saturdays)
Excavated material removal
• Monday to Sunday, 6:30am to 10pm
![Page 27: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/27.jpg)
FLINDERS LINK
![Page 28: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/28.jpg)
FLINDERS LINK WORKS UPDATE
Activity Jan Feb Mar Apr May Jun
Wall and roof
construction
Breakthrough
Footpath
reopening –TBC
Q1 2021
Service
relocations, roller
door, gantry and
pedestrian gate
installation works
Backfill works
![Page 29: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/29.jpg)
FEDERATION SQUARE
![Page 30: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/30.jpg)
FEDERATION SQUARE WORKS UPDATE
Activity Jan Feb Mar Apr May Jun
Shaft excavation (Shaft A)
Support tunnelling works
• 24 hours, Monday to Sunday
Federation Square excavation and tunnelling support
![Page 31: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/31.jpg)
CITY SQUARE
![Page 32: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/32.jpg)
CITY SQUARE WORKS UPDATE
Activity Jan Feb Mar Apr May Jun
Shaft excavation
Tension pile installation
Permanent concrete structure
works
South and central Northern end of
shaft
Bottom up construction sequence in
the shaft including the construction of
the base slab, walls and suspended
slabs
![Page 33: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/33.jpg)
CITY SQUARE– OUT OF HOURS WORKS
Excavation and tension pile installation
• Monday to Sunday, 24-hours
![Page 34: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/34.jpg)
OTHER WORKS
Groundwater well decommissioning –Swanston Street (between La Trobe and Collins streets)
• 10pm to 5am, two nights between
Tuesday 9 and Thursday 11 February
2021
Service investigations - Flinders Street
• 1am to 5am, between Wednesday 27
January and Saturday 6 February 2021
![Page 35: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/35.jpg)
QUESTIONS
![Page 36: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/36.jpg)
BUSINESS SUPPORT UPDATE
36Presenter: Kate Kearns
![Page 37: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/37.jpg)
37
2020
• 2020 tough year for most
Melburnians, particularly difficult for
businesses in the CBD
• Many businesses forced to close their
doors during lockdown, CYP-DC
continued to support those
businesses that remained open (in
and around our construction sites.
![Page 38: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/38.jpg)
FQ WEBSITE
38
• 2020 highlighted the importance of having a strong online presence
• CYP-DC & RPV launched the Flinders Quarter website in November 2020
www.flindersquarter.com
• Site showcases the diverse and unique businesses of the area along with upcoming events and
activations
• Also, strengthens the brand/FQ ‘look and feel’ that we’ve developed over the past two years
![Page 39: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/39.jpg)
FQ CHRISTMAS CAMPAIGN
• Digital Campaign – 14-26 Dec
• Organic social posts
• Paid social campaign
• Influencer collaboration
• Area photo shoot and promotional video
• 178K people reached across both Facebook and Instagram (paid and organic)
39
![Page 40: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/40.jpg)
USER GENERATED CONTENT
• Good level of user-generated content throughout the campaign, particularly around the augmented reality art walls and the Electric Confetti installation in Scott Alley.
• FQ businesses also posted during this time and tagged Flinders Quarter, enabling us to share the content via FQ stories.
40
![Page 41: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/41.jpg)
PAID SOCIAL CAMPAIGN
• Facebook & Instagram:
• 2 x weeks of promoted posts
• Centred around a “Shop Local this Xmas” message
• Most engaged audience:
• Women 25-39
• Live within 20km of Melb CBD
• Interest in boutiques, markets and shopping malls
41
![Page 42: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/42.jpg)
INFLUENCER COLLABORATION
• @tothotornot@melbournesights @melbournemadness
1 x Feed Post
1 x Story(Note – Augmented Reality Walls were not set up when they visited)
2 x Feed Posts26 x Stories
2 x Feed Posts7 x Stories
![Page 43: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/43.jpg)
DEGRAVES STREET SOUTH
• Greening – 15 x trees and planter boxes
• Augmented Christmas Decals
43
![Page 44: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/44.jpg)
FQ AUGMENTED ART WALK
44
• May 2021, 6 x weeks
• Build on the success of FQAAW2019
• 12 x artworks, local artists
• Attract new and repeat local visitation
to the area with a unique, creative
experience
• Incentivise visitors to engage and
support businesses through gamification
of the user journey
![Page 45: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/45.jpg)
WHAT’S NEW
45
• New gamification element
• Visitors will be lead through FQ, activating key artwork at selected locations and unlocking offers and incentives from businesses (or ‘treasures’) along the journey.
• EyeJack app will feature:
➢ Google map of the art locations
➢ enable customisation of ‘treasures’ to support businesses
➢ capture visitor contact details at the end of their experience for redemption details, marketing and feedback opportunities, and report on user metrics.
![Page 46: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/46.jpg)
QUESTIONS
46
![Page 47: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/47.jpg)
TBM TUNNELLING UPDATE
Presenter: Ryan Martin
![Page 48: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/48.jpg)
TBM PROGRESS
Presenter: Ryan Martin
TBM Joan
• Broke through at Parkville Station 27 August 2020
• Relaunched from Parkville Station 15 October 2020
• Broke through at State Library Station 20 December 2021
• Scheduled to relaunch from State Library Station end February 2021
TBM Meg
• Broke through at Parkville Station 19 September 2020
• Relaunched from Parkville Station 4 November 2020
• Has currently completed approximately 790m (of 970m)
![Page 49: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/49.jpg)
STATE LIBRARY BREAK THROUGH
![Page 50: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/50.jpg)
VIDEO
TBM Joan breakthrough at State Library Station December 2020 on Vimeo
![Page 51: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/51.jpg)
CROSS PASSAGE CONSTRUCTION
• Cross passage 10 (Church Street) – break in and excavation programmed to commence early February
• Cross passage 11 (Canada Lane) – break in and excavation programmed to commence early February
• Cross passage 12 (south west corner of Queensberry and Swanston streets) - break in and excavation programmed to commence mid February
• Cross passage 13 (south of Lonsdale Street) - break in and excavation programmed to commence August 2021
• Cross passage 14 (between Little Bourke and Bourke streets) - break in and excavation programmed to commence August 2021
Presenter: Ryan Martin
Permanent lining works complete (CP4)
![Page 52: TOWN HALL STATION COMMUNITY REFERENCE GROUP](https://reader031.vdocument.in/reader031/viewer/2022012301/61e1a6f0819ce675804fe6aa/html5/thumbnails/52.jpg)
QUESTIONS