traffic report - sandy point quarry
TRANSCRIPT
BENEDICT INDUSTRIES
TRAFFIC REPORT FOR PROPOSED MODIFICATIONS TO THE EXISTING SANDY POINT QUARRY, HEATHCOTE ROAD, SANDY POINT
MARCH 2012
COLSTON BUDD HUNT & KAFES PTY LTD ACN 002 334 296 Level 18 Tower A Zenith Centre 821 Pacific Highway CHATSWOOD NSW 2067
Telephone: (02) 9411 2411 Facsimi le: (02) 9411 2422 Email : [email protected]
REF: 8358/2
Attachments to Report to Increase Tonnages at EPL 1924 Page 61 of 11 2
Colston Budd Hunt & Kafes Pty Ltd
3. We confirm that this report addresses the Director General's req.u1rements. We understand that you are preparing plans of the internal layout.
4. We- trust this letter provides the information you require. If you have any queries, please co~tact us.
Yours fai_thfully, COLSTdN BUDD HUNT & KAF-ES PTY L TD
--IL'~ tJ~ T. Rogers Director
-2
Attachments to Report to Increase Tonnages at EPL 1924 Page 60 of 112
Colston Budd Hunt & Kafes Pty Ltd
TABLE OF CONTENTS
TABLE OF CONTENTS
1. INTRODUCTION .................. .. ... .............................................................................................1
2. EXISTING CONDITIONS ...................................................... .. .............................................. 2
3. IMPLICATIONS OF PROPOSED DEVELOPMENT .............. .. ...................................... ..... 9
Attachments to Report to Increase Tonnages at EPL 1924 Page 62 of 112
Colston Budd Hunt & Kafes Pty Ltd
CHAPTER 1
1. INTRODUCTION
1.1 Colston Budd Hunt and Kafes Pty Ltd has been commissioned by Benedict
Industries to prepare a report examining the traffic implications of proposed
modifications to the operation of the existing Sandy Point quarry, located on
Heathcote, Sandy Point. The site location is shown in Figure 1.
1.2 The existing quarry operates six days a week and has been the subject of a
number of approvals:
o Planning Consent 900/67 issued 14 July 1967- No limit on extraction;
o Previous EPL licence limit on extraction, crushing, grinding and milling
200,000 tonnes per annum.
1.3 lt is proposed to import material (some 180,000 to 240,000 tonnes per annum)
into the quarry to be processed into a substitute for naturally quarried materials.
This would bring the cumulative activity to some 380,000 to 440,000 tonnes per
annum.
1.4 This report assesses the traffic implications of the proposed development through
the following chapters:
o Chapter 2- describing the existing conditions; and
o Chapter 3- assessing the transport implications of the proposed
development.
Attachments to Report to Increase Tonnages at EPL 1924 Page 63 of 112
Colston Budd Hunt & Kafes Pty Ltd
CHAPTER2
2. EXISTING CONDITIONS
Site Location and Road Network
2.1 The existing quarry is located on the eastern side of Heathcote Road, Sandy Point
(with the site access located approximately one kilometre south of St George
Crescent). The site has access from Heathcote Road with all turning movements
permitted. The site access is a sealed two lane road with a wide sealed area
adjacent to Heathcote Road. Within the site, gravel roads and dirt tracks provide
access to the various quarry areas. A weighbridge and associated facilities are
located several hundred metres within the site. Employees generally park in an
informal car park located adjacent to the weighbridge. The current quarry
operates six days a week with trucks collecting extracted material between 6.00
am and 4.00 pm.
2.2 Heathcote Road adjacent to the site is a two way rural road with one traffic lane in
each direction and unsealed shoulders. lt has a posted speed limit of 80 km/h .
Sight lines from the site access to the south along Heathcote Road are good being
500 metres. To the north, Heath cote Road bends to the northwest, and sight
lines are some 150 metres. Heathcote Road is an arterial road that connects
Liverpool with Sutherland.
Traffic Flows
2.3 In order to gauge traffic conditions, counts were undertaken during Tuesday
morning (6.30am to 9.30am) and afternoon (3 .00pm to 6.30pm) in late October
Attachments to Report to Increase Tonnages at EPL 1924 Page 64 of 112
2
Colston Budd Hunt & Kafes Pty Ltd
CHAPTER 2
2011 at the intersection of the site access and Heathcote Road. The results of
the surveys are displayed in Figures 2 and 3 and found that:
o Heathcote Road carries some 1 ,800 vehicles per hour (two way) in the peak
periods; and
o the site generated some 15 trucks (two way) in the morning peak hour. In the
afternoon peak hour the site generated some 5 trucks (two way).
2.4 In order to assess the cumulative impacts of quarry and ancillary operations,
particularly in the morning and afternoon peak periods, a review of truck
movements associated of quarry operations (based on the running sheet) was
undertaken. On the Tuesday of the traffic surveys (October 2011) it was found
that there were some 100 truck movements (50 in/50 out) between 6.00am and
3.00pm. The surveys found that over 90% of trucks arrived from or departed to
the north along Heathcote Road . Based on five and half days a week, 50 weeks
per year operation, with loads of 32 tonnes per truck, this is equivalent of an
extraction of 440,000 tonnes per year.
Intersection Operations
2.5 The capacity of the road network is largely determined by the capacity of its
intersections to cater for peak period traffic flows. The intersection of the site
access and Heathcote Road has been analysed using the SIDRA program. SIDRA
simulates the operations of intersections to provide a number of performance
measures. The most useful measure provided is average delay per vehicle
expressed in seconds per vehicle. Based on average delay per vehicle, SI ORA
estimates the following levels of service (LOS) :
Attachments to Report to Increase Tonnages at EPL 1924 Page 65 of 112
3
Colston Budd Hunt & Kafes Pty Ltd
CHAPTER 2
o For traffic signals, the average delay per vehicle in seconds is calculated as
delay/(all vehicles), for roundabouts the average delay per vehicle in seconds is
selected for the movement with the highest average delay per vehicle,
equivalent to the following LOS:
0 to 14 "A" Good
15 to 28 "B" Good with minimal delays and spare capacity
29 to 42 "C" Satisfactory with spare capacity
43 to 56 "D" Satisfactory but operating near capacity
57 to 70 "E" At capacity and incidents will cause excessive
delays. Roundabouts require other control mode.
> 70 I! F." Unsatisfactory and requires additional capacity
o For give way and stop signs, the average delay per vehicle in seconds is
selected from the movement with the highest average delay per vehicle,
equivalent to following LOS:
0 to 14 -"A" Good
15 to 28 "B" Acceptable delays and spare capacity
29 to 42 "C" Satisfactory but accident study required
43 to 56 "D" Near capacity and accident study required
57 to 70 "E" At capacity and requires other control mode
> 70 "Fn Unsatisfactory and requires other control mode
2.6 lt should be noted that for roundabouts, give way and stop signs, in some
circumstances, simply examining the highest individual average delay can be
misleading. The size of the movement with the highest average delay per vehicle
Attachments to Report to Increase Tonnages at EPL 1924 Page 66 of 112
4
2.7
Colston Budd Hunt & Kafes Pty Ltd
CHAPTER2
should also be taken into account. Thus, for example, an intersection where all
movements are operating at a level of service A, except one which is at level of
service E, may not necessarily define the intersection level of service as E if that
movement is very small. That is, longer delays to a small number of vehicles may
not justify upgrading an intersection unless a safety issue was also involved .
The SI ORA analysis found that the Heathcote Road and the site access intersection
operates with average delays of some 38 seconds per vehicle in the peak periods.
This represents level of service C, a satisfactory level of intersection operation.
Outside of peak periods delays are less as traffic flows are lower along Heathcote
Road.
Attachments to Report to Increase Tonnages at EPL 1924 Page 67 of 112
5
Colston Budd Hunt & Kafes Pty Ltd
ATTACHMENT
3. IMPLICATIONS OF PROPOSED DEVELOPMENT
3.1 lt is proposed to import material (some 180,000 to 240,000 tonnes per annum)
into the quarry to be processed into a. substitute for naturally quarried materials.
This would bring the cumulative activity to some 380,000 to 440,000 tonnes per
annum. To accommodate the importation of material, a number of changes to
stockpiling and blending of material are proposed. These are shown on Figure 4 . .
This chapter assesses the implications of the proposed development through the
following sections:
o parking provision;
o access and internal layout;
o traffic effects; and
o summary.
Parking Provision
3.2 Parking for employees will be accommodated in the informal parking area located
in the vicinity of the weigh station. There is ample room to accommodate parking
for any additional employees within the 38.12 ha site.
Access and Internal Layout
3.3 Vehicular access will be maintained from Heathcote Road via the existing sealed
access road. Within the site, new roads will be constructed as required to access
the new activity areas. These new roads will be designed to accommodate the
design vehicles that will use them (trucks or loaders).
Attachments to Report to Increase Tonnages at EPL 1924 Page 68 of 112
6
Colston Budd Hunt & Kafes Pty Ltd
ATTACHMENT
Traffic Effects
3.4 lt is proposed to import up to 240,000 tonnes of material per year and mix this
with 200,000 tonnes extracted, which will then be transported off site (tota.l of up
to 440,000 tonnes). lt is understood that a proportion of trucks (some 50%)
bringing material into the site will depart with a load of blended material. Based
on five and half days a week, 50 weeks a year operation and 32 tonne load trucks,
the following number of truck movements are estimated:
o trucks bringing material to the site- 28 trucks per day;
o trucks departing empty (after bringing material in) - 14 per day; ·
o trucks departing with material (after bringing material in) - 14 per day;
o trucks arriving empty to collect material - 9 per day; and
o trucks departing with material (after arriving empty) - 9 per day.
3.5 Thus the proposed change in operation will result in an average of 7 4 truck
movements per day (37 in/37 out) . Based on the survey of existing quarry
operations some 15% of daily truck movements occur in the weekday morning
peak hour and some 5% in the weekday afternoon peak hour. Using these rates
peak mur traffic generation would total some 12 and 4 Vehicles per hour in
weekday morning and afternoon peak hours respectively.
3.6 lt is likely that material being brought to the site will be more evenly split between
east and west compared to the distribution of material (mainly to/from the west).
On this basis the increase in traffic movements on Heathcote Road as a result of
the proposed development would be some 5 to 1 0 vehicles per hour (two way) in
the weekday morning peak hour, with a smaller increase in the weekday
Attachments to Report to Increase Tonnages at EPL 1924 Page 69 of 112
7
Colston Budd Hunt & Kafes Pty Ltd
ATTACHMENT
afternoon peak hour. These are minor increases (one vehicle every 7 to 15
minutes) and would not change the operation of traffic flows along Heathcote
Road (which carries some 1 ,800 vehicles per hour in the weekday morning and
afternoon peak hours).
3.7 The operation of the Heathcote Road/site access intersection was reanalysed
using SIDRA with development traffic in place. The analysis found that it operates
with average delays of some 39 seconds per vehicle in the peak periods. This
represents level of service C, a satisfactory level of intersection operation.
Outside of peak periods delays are less, as traffic flows are lower along Heathcote
Road.
3.8 As noted in Chapter 2 sight lines at the access to Heathcote Road are some 500
metres to the south and some 150 metres to the north. AS2890.2-2002 suggests
a minimum sight distance requirement of 111 metres for an 80 km/h speed
environment. Thus the available sight lines at the site access satisfy the
requirements of AS2890.2-2002.
Summary
3.9 In summary, the assessment of the traffic effects of the proposed development has
found that it would result in a minor increase in traffic generation. The operation
of the site access would continue to operate at a satisfactory level of service in the
peak periods. Sight lines comply with the requirements of AS2890.2-2002.
Attachments to Report to Increase Tonnages at EPL 1924 Page 70 of 112
8
8358 - Sandy Point Quarry
ol
GEORGE$ R!VEA NATIDNA_L PARK
I . I
!j
.. .. .~~-~· · ;·~·- .... ,. .. 1 .. .. 4·•···· ; I :_...-...-
G!"liw~l : 1 ' n •• ' ,/rlt j
- .
,,
·"__.,
\
k' ( !I
1-. ~ '·
.. ~
. j
_...!
Location Plan
Colston Budd Hunt & Kafes Ply Ltd
DRA\M>I BY CBHK Ply Ltd_hs Ref: 8358 21 December 2011 Figure 1
Attachments to Report to Increase Tonnages at EPL 1924 Page 71 of 112
8358 - Sandy Point Quarry
......... ('i)
0
ll .__.l{) +
<.0 1'
lJ ea 0rr: CD 0 -u
..&::
ea -CD :I:
Tl 0 0 .........<.0 l{)"<'""" "<'""" -:!:.
.~~i ov.
e'!ilil ~eo
ANorth
LEGEND tOO • Exlltlng P••k Huur Tr•Hic FIIIWI
(+10) - AddlllotiBI Oevalilpnl81'1t Trafllc
Existing weekday morning peak hour traffic flows plus development traffic
Co l s t o n Budd Hunt & Ka f es Ply Ltd
DRA\MI BY CBHK Ply Lld_hs Ref: 8358 21 December 2011 Figure 2 Attachments to Report to Increase Tonnages at EPL 1924 Page 72 of 112
8358 - Sandy Point Quarry
......... 0
e.t<'i0.\):
e'b,.1'- "'""" 0 '--' ...~l~0"'"""
"'C ll +
ea 0
r:r= (:)Cl)
~ ()\!:~0 -t) .c ~ ea 0Cl)
:I: 11 0 0 0 ......... 1' N
+'--'
ANDrlh
LEGEND 100 • Exhltlng PNk Hour Tfll"lc; Flcnn
(+10) - AdciiiiOr'IIAI Dllllvelapmlllll'lt Trafflt::
Existing weekday morning peak hour traffic flows plus development traffic
Co/ston Budd Hunt & Kafes Ply Ltd
DRA\Ml BY CBHK Ply ltd_hs Ref: 8358 21 December 2011 Figure 3 Attachments to Report to Increase Tonnages at EPL 1924 Page 73 of 112
8358 - Sandy Point Quarry
50 100 150
Sandy Point Quarry
N ~
0 ~
j:! Q) Cl Cll Cl.
~ C1l ~
__J
Cl. w 05 Q) Cl "' Cll c c 0 I Q)
Cll "' ~ (.)
E .8 t 0 Cl. Q)
c:: .8 $ c Q)
E .r: (.)
Cll
~
Colston Budd Hunt & Kafes Pty Ltd
DRAWN BY CBHK Ply Ltd_hs Ref: 8358 21 December 2011 Figure 4
Colston Budd Hunt & Kafes Pty Ltd as Trustee for C & B Unit Trust
ABN 27 623 918 759
Transport Planning Our Ref: TR/8358/jj
Town Planning Retail Studies
22 July, 2013
Benedict Industries PO Box 431 FRENCHS FOREST NSW 1640
Attention: David White Email: [email protected]
Dear Sir,
RE: SANDY POINT QUARRY RESPONSE TO TRAFFIC MATTERS
1. As requested, we have reviewed the traffic matters raised the
Department of Planning and Infrastructure's letter dated 9 July 201 3. Our response also addresses the traffic matters raised by Council and RMS. The traffic matters raised and our response is set out in Table 1 (attached).
2. We previously prepared a traffic report (1) in support of the proposed development.
O> 'Traffic Report for Proposed Modifications to the Existing Sandy Point Quarry, Heathcote
Road, Sandy Point': Prepared for Benedict Sands March 2012
Suite 1801/Tower A, Zenith Centre, 821 Pacific Highway, Chatswood NSW 2067 P.O. Box5186WestChatswood NSW1515Tel: (02)94112411 Fax· (93)9H12122 Directors - Geoff Budd - Lindsay Hunt - Stan Kafes - Tim Rogers - Joshua Hollis ACN 002 334 296 EMAIL: [email protected]
- 1
Attachments to Report to Increase Tonnages at EPL 1924 Page 75 of 112
Colston Budd Hunt & Kafes Pty Ltd as Trustee for C & B Unit Trust
ABN 27 623 918 759
Transport Planning Our Ref: TR/8358/jj
Town Planning
Retail Studies 22 July, 2013
Benedict Industries PO Box 431
FRENCHS FOREST NSW 1640
Attention: David White Email: [email protected]
Dear Sir,
RE: SANDY POINT QUARRY RESPONSE TO TRAFFIC MATTERS
1. As requested, we have reviewed the traffic matters raised the
Department of Planning and Infrastructure's letter dated 9 July
201 3. Our response also addresses the traffic matters raised by
Council and RMS. The traffic matters raised and our response is
set out in Table 1 (attached).
2. We previously prepared a traffic report (1) in support of the
proposed development.
(ll "Traffic Report for Proposed Modifications to the Existing Sandy Point Quarry, Heathcote
Roact Sandy Point': Prepared for Benedict Sands March 2012
Suite 1801/Tower A, Zenith Centre, 821 Pacific Highway, Chatswood NSW 2067 P.O. Box 5186 West Chatswood NSW 1515 Tel: (02) 9411 2411 Fax· IQ?) OH 1 ?CO? Directors - Geoff Budd - Lindsay Hunt - Stan Kafes - Tim Rogers - Joshua Hollis ACN 002 334 296 EMAIL: [email protected]
- 1
Attachments to Report to Increase Tonnages at EPL 1924 Page 77 of 112
Colston Budd Hunt & Kafes Pty Ltd
3. We have reviewed the report and note that there is miscalculation in the number of trucks arriving empty to collect blended
material. This was estimated to be 9 trucks per day and should have been 36. This increases the daily truck movements per day from 74 to 128 (64 in/64 out). Based on the survey of existing quarry operations some 15% of daily truck movements occur in the weekday morning peak hour and some 5% in the weekday afternoon peak hour. Using these rates, peak hour traffic generation would total some 20 and 6 vehicles per hour in weekday morning and afternoon peak hours respectively. The response to traffic matters is based on the updated estimate of additional truck movements.
4. Thus the proposed modifications to the existing Sandy Point Quarry will result in a only a minor increase in traffic movements (some 6 to 20 truck movements per hour, two-way, in the weekday morning and afternoon peak hours). Such a minor increase (one truck every 3 to 10 minutes) will not change the operation of Heathcote Road (which carries some 1,800 vehicles per hour (two way) in the peak periods, or the operation of the site access on Heathcote Road.
5. We trust this letter provides the information you require. If you
have any queries, please contact us.
Yours faithfully, COLSTON BUDD HUNT & KAFES PTY LTD
~~tr T. Roqers
Director
-2
Attachments to Report to Increase Tonnages at EPL 1924 Page 76 of 112