Transfer Pilots Kick off

Baseline and final report

Page 2: Transfer Pilots Plenary - Baseline Presentation (29.01)

Baseline study

1. General context / State of the art in relation with the policy area of the practice

2. Detailed description of the good practice to be transferred (for Giving Cities)

3. Baseline situation in Receiving cities and results expected from the transfer for each partner

4. Methodological framework to ensure a successful transfer

5. Evaluation framework to measure what has been accomplished through the transfer

Page 3: Transfer Pilots Plenary - Baseline Presentation (29.01)

Context and state of the artBriefing paper aimed at city partners

Broad picture of the practice and related policy area

Accessible document

Not academic

Audience of practitioners

Page 4: Transfer Pilots Plenary - Baseline Presentation (29.01)

Detailed description of good practice

Modelled on approach developed in EU 50 urban case studies [go to link]

4 parts – • 4 line google summary• Half page summary• 3 page account with photos• 8 page template

1) Background information (including project title, beneficiary, etc)

2) Project description

3) Political and strategic context

4) Implementation framework

5) Innovative elements and novel approaches

6) Funding

7) Project Assessment

8) Conclusions: key success factors, lessons learned and condition for transfer

9) Additional information (bibliography, useful references, etc.)

Title of presentation I Tuesday 26 March 2013 I Page 4

Page 5: Transfer Pilots Plenary - Baseline Presentation (29.01)

Go to urban 50

http://ec.europa.eu/regional_policy/activity/urban/goodpracticemap_en.cfm

Title of presentation I Tuesday 26 March 2013 I Page 5

Page 6: Transfer Pilots Plenary - Baseline Presentation (29.01)

Baseline in receiving cities

Six sections

• Background information• Project description• Political and strategic context• Implementation arrangements• Funding• Success factors, learning and conditions for transfer

Title of presentation I Tuesday 26

Page 7: Transfer Pilots Plenary - Baseline Presentation (29.01)

Methodological framework for the transfer process

Transnational exchange and peer review of the practice to be exchanged.

Local activities of transfer and adaptation in each receiving cities

Communication activities

Title of presentation I Tuesday 26 March 2013 I Page 7

Page 8: Transfer Pilots Plenary - Baseline Presentation (29.01)

7 steps to high quality case studies

1. Familiarisation phase: getting to know the case study approach used in this study – understanding the templates that will be used;

2. Preparatory and Verification phase: desk research and preparing the verification template;

3. Planning phase: organising the field visit deciding on interviewees and making initial contact;

4. Fieldwork phase: study visit and stakeholder interviews; photographs

5. Analytical phase: organising and analysing collected information in the template;

6. Writing phase: Writing the journalistic summary.

7. Reviewing the texts and getting sign off for quotes and photos

Title of presentation I Tuesday 26 March 2013 I Page 8

Page 9: Transfer Pilots Plenary - Baseline Presentation (29.01)

Deadline for baseline to Secretariat is 15th March

Title of presentation I Tuesday 26 March 2013 I Page 9

Page 10: Transfer Pilots Plenary - Baseline Presentation (29.01)

Evaluation framework: How to measure the results that will be achieved

expected results and indicators against which you will measure achievements after 12 months (meaning providing baseline figures on these indicators and target figures to be reached in 12 months time),

 

the process of monitoring and evaluation (who does what, the timeline, the main tools used, etc.)

 

Title of presentation I Tuesday 26 March 2013 I Page 10

Page 11: Transfer Pilots Plenary - Baseline Presentation (29.01)

Final report at end of project (2015)

• Transfer logs in each city.

 • Description and assessment of the main results

achieved in each receiving city

 • Redefined (or enhanced) good practice.

Title of presentation I Tuesday 26 March 2013 I Page 11

Page 12: Transfer Pilots Plenary - Baseline Presentation (29.01)

Food for thought

• Preparation is key

• Context is everything

• Look from different vantage points

• The art of timing

• Max out trusted relationships

• Feed your inner curiosity

Title of presentation I Tuesday 26 March 2013 I Page 12

Page 13: Transfer Pilots Plenary - Baseline Presentation (29.01)

Capturing the Transfer Process

• Transfer diaries: written accounts, videos, social media

• Knowledge transfer workshops

• Transfer logs

Title of presentation I Tuesday 26 March 2013 I Page 13