transmission costs
DESCRIPTION
Transmission Costs. Summary. RPS Calculator Valuation Framework. The availability and cost of transmission are primary components in the Net Market Value (NMV) calculation used to rank competing resources in the RPS Calculator - PowerPoint PPT PresentationTRANSCRIPT
TRANSMISSION COSTS
Summary The availability and cost of
transmission are primary components in the Net Market Value (NMV) calculation used to rank competing resources in the RPS Calculator
They reflect the cost to deliver new renewable generation to California loads
The methodology of identifying available capacity and transmission costs in Version 6.0 is generally the same as previous version, additional updates planned
RPS Calculator Valuation Framework
Levelized Cost of Energy
Transmission Cost
Capacity Value
Energy Value
Net Resource Cost
Integration Cost*
−
=
−
+
++
*Not currently quantified in RPS Calculator
Summary Continued
Transmission availability and cost estimates for all existing CREZs will be updated in Version 6.0 of the RPS Calculator to reflect all available CAISO study information
Black & Veatch also identified new major resource areas (“Super CREZs”) for which new transmission cost estimates need to be developed (i.e. 3,000 MW new wind capacity in Sacramento River Valley)
Out of state transmission cost estimates are derived from previously vetted studies
RPS Calculator in Transmission Planning RPS Calculator receives information from and provides information
to CAISO transmission planning processes Transmission projects included in CAISO Transmission Planning
Process (TPP) are recovered through the Transmission Access Charge (TAC) levied on all users of the transmission system
TAC costs are passed on to ratepayers Generation projects accessing transmission lines in the TPP may avoid
additional delivery network upgrade (DNU) costs
Since the CAISO TPP is based on the CPUC’s RPS Calculator portfolios, it is critical the overall process shown here works
CAISO GIDAP
Transmission Inputs
Available Capacity [MW]
Delivery Network Upgrade (DNU) Costs
[$/kW-yr]
RPS Calculator
RPS Portfolios
Commercial Projects [MW]
Generic Projects[MW]
CAISO TPP
CPUC LTPP
Iterative - informs next cycle and other processes
Role of Transmission in RPS Calculator
In developing each portfolio , the RPS Calculator considers the: Availability of existing transmission Cost of building new transmission
General treatment of transmission availability and costs has not changed between Version 2.0-5.0 and 6.0
Updates have been made to inputs and additional updating required, as described in following slides
TRANSMISSION AVAILABILITY
Transmission Availability in RPS Calculator
General treatment of transmission availability has not changed between Version 2.0-5.0 and 6.0: Each zone has estimates of the amount of fully deliverable capacity (and associated
costs) available on existing transmission, minor upgrades, and major upgrades Existing transmission & minor upgrades assumptions provided by CAISO
Existing transmission capacity is allocated to (1) IOU contracts and (2) most favorably ranked generic projects
These projects have no associated upgrade costs Remaining projects are bundled together for selection on minor and major upgrades
Transmission Availability by Electrical Zone Estimates of existing capacity and minor upgrades provided by CAISO Major upgrades are assumed to represent a new transmission line
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
Avai
labl
e Ca
paci
ty (M
W)
Major Upgrades
Minor Upgrades
Existing
Note: Graph reflects old transmission cost estimates and available transmission capacity data that will be updated prior to the F15-16 TPP by Q1 2015
Reso
urce
Net
Cos
t w/o
Tr
ansm
issi
on ($
/MW
h)
MW
Minor Upgrades
Major Upgrades
Tran
smis
sion
Upg
rade
Cos
t ($
/kW
-yr)
MW
Existing Tx
Allocation of Transmission Capacity
Resources are ranked and sorted in each zone based on their net cost without accounting for transmission
Available capacity for new transmission is allocated to the most favorably ranked projects Existing transmission is
allocated to IOU contracts prior to ranking/selection process
No upgrade costs for these resources
Higher cost projects assigned minor and major upgrade costs
No Tx CostMinor
Upgrade Cost
Major Upgrade
Cost
ESTIMATING TRANSMISSION COSTS
General Methodology Interconnection Cost Delivery Network Upgrades Zone Identification Out-of-state Transmission
Transmission costs split in three categories: Interconnection Cost Delivery Network Upgrades (minor
and major upgrades) Out-of-state Transmission
Unit costs based on: IOU Per Unit Costs B&V WECC methodology Previous E3 RPS calculator
estimates CAISO Delivery Network Upgrades
Methodology Overview
Gen-tie line Substation costs
New switching station New breaker position at existing substation
Interconnection Facility Costs
Gen-tie lines Costs vary depending on interconnecting utility
UtilityVoltage Class (kV) – Cost/mile
< 100 kV 115 kV 230 kV 500 kV
PG&E $1,400,000 $1,400,000 $1,690,000 $4,610,000
SCE $1,559,000 $1,606,000 $2,276,000 $3,796,000
SDG&E $1,922,000 $3,981,000 $4,431,000 $4,559,000
VEA N/A $1,590,000 $1,770,000 N/A
From 2013 PTO Per Unit Cost Information
Interconnection Facility Costs
Note: Costs will be updated with 2015 estimates prior to the F15-16 TPP by Q1 2015
Two substation options based on project location. Example: Project A is within reasonable gen-tie distance –
new breaker position Project B is not within reasonable gen-tie
distance, but can connect to the 115 kV line – new switching station
Project A 20 MW
Project B20 MW
Sub A 115 kV
Sub B 115 kV
115 kV Line
Interconnection Facility Costs
New Breaker Position (Existing BAAH Substation)
New Switching Station (Ring Bus)
UtilityVoltage Class (kV)
< 100 kV 115 kV 230 kV 500 kV
PG&E $1,400,000 $1,550,000 $2,100,000 N/A
SCE $878,000 $919,000 $2,170,000 $5,232,000
SDG&E $528,000 $680,000 $2,036,000 $3,940,000
VEA N/A $603,000 $1,004,000 N/A
From 2013 PTO Per Unit Cost Information
UtilityVoltage Class (kV)
< 100 kV 115 kV 230 kV 500 kVPG&E $10,800,000 $12,000,000 $16,000,000 N/ASCE $3,222,000 $3,471,000 $17,767,000 $36,715,000SDG&E $4,233,000 $7,377,000 $13,509,000 $40,610,000VEA N/A $4,602,000 $6,170,000 N/AFrom 2013 PTO Per Unit Cost Information
Interconnection Facility Costs
Note: Costs will be updated with 2015 estimates prior to the F15-16 TPP by Q1 2015
Delivery Network Upgrade (DNU) Costs
DNU costs consist of minor and major upgrades Worked with CAISO to determine best way to incorporate
DNU in analysis Proposed method is to use costs for upgrades based on
interconnection studies for projects in Competitive Renewable Energy Zones (CREZ)
Three categories: Available transmission capacity with no upgrades Available transmission capacity with minor upgrades Available transmission capacity with major upgrades
Delivery Network Upgrade (DNU) Costs
Example DNU Costs:
Delivery Network Upgrade (DNU) Costs
MW of Available Capacity in 2020
on Existing Transmission (No Upgrades)
MW of Available Capacity in 2020
on Existing Transmission
(Minor Upgrades)
Cost of Minor Upgrades ($M)
Major Upgrade Segment Size
(MW)
Major Upgrade Segment Capital Cost ($ millions)
Riverside East (Riverside East, Palm Springs) 350 350 2,400 955Tehachapi 3,774 4,774 100 Westlands 0 2,590 1,512
CAISO has not studied all areas and so transmission availability and costs for minor and major upgrades in several areas have not been established
Currently use costs estimated by E3 in previous version of the RPS Calculator.
CPUC and CAISO have developed a proposed approach to update the costs (see following slides)
Estimates will be updated in time for the F15-16 TPP by Q1 2015
Updated resources need to be assigned to zones. Many are outside original boundaries.
Proposed method and new Super CREZ described in “California Renewable Energy Resource Potential and Cost Update” presentation
Delivery Network Upgrade (DNU) Costs - Key Issues
1. The 2010 estimates would be used as an initial starting point for the 6.0 Version of the Calculator
2. The Calculator would be run with the initial estimates, and the most economical Super CREZs would be identified
3. These Super CREZs would then be examined by the CAISO to update the major and minor transmission costs estimates for each area
4. The calculator would be re-run with the updated costs, and the most economical Super CREZs would be identified again
5. If there are any changes in the list of most economical Super CREZs, these would be sent to the CAISO for re-study, returning to step 3
6. This process would continue until the list of most economical Super CREZs does not change after updating the transmission cost estimates. These costs would be incorporated into Version 6.1 of the RPS Calculator, which would then be vetted by stakeholders.
Proposed Approach for Updating Transmission (DNU) Cost and Availability
Proposed Approach for Updating Transmission (DNU) Cost and Availability
2. RPS Calc Run
3. Special CAISO Study of Tx for Selected Super
CREZ
4. RPS Calc Run
New Super CREZ
Identified?
6. No Costs and availability to Version 6.1 of RPS Calculator
5. Yes: re-study new areas
Updated Major/MinorTx Cost Estimates
for Super CREZ
Selected portfolio of most economic
Super CREZ from RPS Calc Supply Curve
1. Starting Tx Cost and Availability(Past CAISO Studies +
E3 Estimates)
Most Economic Super CREZ
Largely based on previously vetted initiatives:
RETI 2B (2010) B&V work for WECC on
transmission costs (2012-2014)
WREZ Generation and Transmission Cost Model (2009-2013)
Out Of State Transmission Costs
Out-of-state transmission costs Cost basis: 500 kV single-circuit ac transmission, 1500 MW
capacity, $1.8 million/mile, federally financed, Delivered to “gateway CREZs” (e.g., Mountain Pass) From WREZ Generation and Transmission model Line utilization based on resource capacity factor
In-state transmission costs: Added CAISO DNU costs to OOS costs using same approach
as California projects
Out-of-state (OOS) Transmission Cost Approach
Note: Costs will be updated with 2015 estimates prior to the F15-16 TPP by Q1 2015
Focus is on highest quality OOS resources for CA
Pacific Northwest > Round Mountain
Northern & Central Nevada > Owens Valley
Southern Nevada, Utah and Wyoming > Mt. Pass
Arizona, New Mexico > Riverside East
Baja California > Imperial Valley South
OOS Resources Delivered To California Gateway Substations / CREZs
COB
MIDWAY
MONA AULT
STORY
BURLINGTON
LAMAR
VILAS
MONTROSEPONCHA
SAN LUIS
WEST CEDAR
GONDER
TRACY
Owens Valley AMARGOSA
NEW 11
ANTELOPE
SERRANO
PISGAH
DEVERS MOUNTAIN
BLYTHE
BELLOTA
VACA DIXON
LUNAHILDAGO
WESTWING
SANTA ROSAGREENLEE
CHOLLA
FOUR CORNERS
RIO PUERCO
NEW 28
TOME
NEW 26
CALIENTE
ARROYOCPO
SN FELIPE
TORTOLITA
LOS COCHES
WALSENBURG
GLADSTONE
MONROE
OLYMPIA
J OHN DAY
NEO
BELL
NEW92
GARRISON
NEW39
NEW93
HAVRE
CONRAD
BRADY
MIDPOINT
NEW 19
BOISE
G COULEE
NEW 15
MIRACLE MILE
CASPER NORTH
YELLOWCAKE
NEW 35
LARAMIE RIVER
ARCHER
STERLING
BETHEL
BROADVIEW
FLAMING GORGE
RUPERT
ENDAKO
WILLISTON
GORDON M SHRUM
TUMBLER
PORT MCNEIL
INDEGLOW
NEW 53
NICOLA
SELKIRK
J ANET
KELLY LAKE
NEW56
NEW42
WEST BROOKS EMPRESS
RED DEERBIG KNIFE CREEK
SLAVE RIVER
GOLDSTREAM
ESMERALDA
BRIDGE
DENVER
TERMINAL
IV South HARQUAHALA
Mt. Pass
Rd. Mtn.
NEW 12
MEAD
Riverside East
• Notes: Costs are for 500 kV single-circuit ac line. In many cases other options may be more cost effective, particularly HVDC for long distance transmission
• Costs include the line, necessary substations, and right of way. Do not include overhead and AFUDC, estimated as an additional 17.5%. Operations and maintenance and losses need to be separately considered.
• Portions of the BJ_NO zone are very close to the California border. As such, this average cost for the zone is likely to overestimate the costs for certain resources that might directly interconnect across the border.
Estimated Transmission Capital Costs For OOS Zones, 500 kV Single-circuit
Zone Tx Capital Costs (Millions)
AZ_NE $ 734 AZ_NW $ 267 AZ_SO $ 699 AZ_WE $ 236 BC_CT $ 2,598 BC_EA $ 1,711 BC_NE $ 2,899 BC_NO $ 2,707 BC_NW $ 3,107 BC_SE $ 1,711 BC_SO $ 1,875 BC_SW $ 1,890 BC_WC $ 1,805 BC_WE $ 2,095 BJ_NO $ 205 BJ_SO $ 488
Zone Tx Capital Costs (Millions)
ID_EA $ 1,411 ID_SW $ 1,015 NM_EA $ 1,621 NM_SE $ 1,889 NV_EA $ 719 NV_NO $ 539 NV_SW $ 399 NV_WE $ 699 OR_NE $ 1,022 OR_SO $ 232 OR_WE $ 794 UT_WE $ 553 WA_SO $ 1,066 WY_EA $ 2,208 WY_EC $ 1,690 WY_NO $ 1,956 WY_SO $ 1,989
Note: Costs will be updated with 2015 estimates prior to the F15-16 TPP by Q1 2015
RPS Calculator Guide
• The parameters that affect Transmission can be found on the following tabs:– Tx_Inputs: cost and availability of transmission for each SuperCREZ
• Includes existing capacity and minor & major upgrades