transmission line basic presentation

Upload: somiran-das

Post on 05-Jul-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/15/2019 Transmission Line Basic presentation

    1/141

    1

    A PresentationA Presentation

    onon

    Transmission line BasicsTransmission line Basics

     

  • 8/15/2019 Transmission Line Basic presentation

    2/141

    2

    WHY A TRANSMISSION LINE?

    Transmission lines are constructed basically for transmissionof power from one point to another 

      Normal connecting points

    Interconnection between 2(two) generating stations

    Connecting generating station with substations

    Interconnection between substations

    Interconnection between substation & power sub station Interconnecting power substations

    Connection from power substation to consumers

  • 8/15/2019 Transmission Line Basic presentation

    3/141

    3

    BASIC SCHEMATIC

    G!"#TI$! % T"#!'II$! IT"I*+TI$!

    Generator 

    11 KV

    GT220 KV

    Step down

    transformer 

    Distribution

    Power plant Transmission

    systemDistribution system

    11220 !V

    220""11 !V

    110#$ !V

  • 8/15/2019 Transmission Line Basic presentation

    4/141

    ,

    POWER SYSTEM !IA"RAM

  • 8/15/2019 Transmission Line Basic presentation

    5/141

    -

    TRANSMISSION LINE CONCEPT

    Power 

    Plant 

    Consumer Home 

  • 8/15/2019 Transmission Line Basic presentation

    6/141

    .

    POWER SYSTEM COMPONENTS

    Source:

    www.howstufworks.com

  • 8/15/2019 Transmission Line Basic presentation

    7/141

  • 8/15/2019 Transmission Line Basic presentation

    8/1410

    CHOICE O# "ENERATION $ TRASMISSION

    %OLTA"E

    Generation is normally at , or 11 45

    tepped up through transformer and transmitted o5er a longdistance to the desired load centers at different 5oltages which

    depends on %  6uantum of power to be transmitted

     %  7ine length

     %  Cost of terminal e8uipments %  conomy consistent with desired reliability

  • 8/15/2019 Transmission Line Basic presentation

    9/1419

    CON!&CTOR SELECTION SCENARIOS

    cenario I : Conductor for low 5oltage lines ( , 4;< 11 4;< 33 4;)

    are selected from the point of 5iew of c'rrent carr(ing capacit( cenario II : election of conductor for =; > +=; lines where

    conductor si?e can not be increased beyond a certain limit in #CTransmission because of factors li4e in)'ctance *+L,- capacitance

    *.$+C,- corona $ RI e//ects etc Corona > "I phenomena increasesdirectly with the diameter of conductor *undle conductor<therefore< ha5e to be used for 5oltage le5el for , 4; and beyondfrom Corona > "I consideration *undle conductor can also be used

    in lower 5oltage line to increase the 8uantum of power to betransmitted

    S0in e//ect  of conductor in #C Transmission also limits si?e ofconductor where bundle conductor is more economical (both cost

    and power loss) instead of a single large diameter conductor 

  • 8/15/2019 Transmission Line Basic presentation

    10/1411

    WHAT IS CORONA?

    Transmissionline conductors are surrounded by an electric field 

    Corona discharge is generated when the electric field at the surfaceof the conductor becomes larger than the brea4down strength of thesurrounding air

    urface irregularities such as sharp points and water droplets cause

    local field concentration< enhancing corona generation Thus< during bad weather< corona discharge is more intense and losses are muchgreater 

    Corona discharge generates audible noise and 5isible lights The

    5isible light and audible noise can be obser5ed simultaneously The 5oltage at which corona begins in called the discharge inception

    5oltage Con5ersely< the 5oltage at which corona ceases is calleddischarge e@tinction

    Corona produces radio and tele5ision interference

  • 8/15/2019 Transmission Line Basic presentation

    11/14111

    CORONA !ISCHAR"E PHOTO

    Corona e5ent captured by corona camera on -4; line

    Corona Camera

  • 8/15/2019 Transmission Line Basic presentation

    12/14112

    CORONA !ISCHAR"E %I!EO

  • 8/15/2019 Transmission Line Basic presentation

    13/14113

    TRANSMISSION LINE %OLTA"E AN!

    CHOICE O# CON!&CTORS

    Normal Transmission1oltage

    T(pe o/ con)'ctor Normall( 'se)

    , 4; #C" #nt> s8uirrel

    11 4; #C" Aeasel

    33 4; #C" "acoon.. 4; #C" og

    132 4; #C" Banther> ebra

    22 4; #C" ebra> 'oose, 4; Twin #C" 'oose > *ersimis> In5ar  

    /.- 4; 6+# #C" *"I'I>In5ar  

  • 8/15/2019 Transmission Line Basic presentation

    14/1411,

    TRA!E NAME O# CON!&CTORS

    Trade name of conductors are normally 4ept after the names of

    5arious animals< birds and insects ome of the common ones are:Code !ame

    #ppro@ current carryingcapacity (#mp)

    ia ofconductor

    (mm)

    #ppo@+T

    (4g)

    #ppro@weight(4g>4m),D ambient ,-D ambient

    8uirrel 11- 1/ .33 /11 0-

    Gopher 133 123 /0 9-2 1.

    Banther -2 ,02 21 912/ 9/.

    ebra /9- /3. 20.2 1331. 1.23'oose 9 03- 31// 1.2- 22

    http://www.google.co.in/imgres?imgurl=http://blogs.warwick.ac.uk/images/rosalindhook/2005/06/04/panther.jpg&imgrefurl=http://blogs.warwick.ac.uk/rosalindhook/entry/grey_panther_induction/&h=331&w=482&sz=58&tbnid=usgk7XgE1EoJ::&tbnh=89&tbnw=129&prev=/images%3Fq%3Dpanther%2Bpicture&hl=en&sa=X&oi=image_result&resnum=1&ct=image&cd=1http://www.google.co.in/imgres?imgurl=http://blogs.psychologytoday.com/files/u26/zebra-picture.jpg&imgrefurl=http://blogs.psychologytoday.com/blog/lust-in-paradise/200803/america-zebra-nation&h=427&w=350&sz=19&tbnid=nI3czj1DAq0J::&tbnh=126&tbnw=103&prev=/images%3Fq%3DZebra%2Bpicture&hl=en&sa=X&oi=image_result&resnum=1&ct=image&cd=1http://www.google.co.in/imgres?imgurl=http://www.moose1899.com/Find-8-Moose222.jpg&imgrefurl=http://www.moose1899.com/about%2520our%2520website%2520logo.htm&h=354&w=300&sz=47&tbnid=akqAbbRd9rIJ::&tbnh=121&tbnw=103&prev=/images%3Fq%3DMoose%2Bpicture&hl=en&sa=X&oi=image_result&resnum=2&ct=image&cd=1http://www.google.co.in/imgres?imgurl=http://www.turtletrack.org/Issues04/Co01102004/Art/Gopher.jpg&imgrefurl=http://www.buzz.mn/%3Fq%3Dnode/2645&h=348&w=486&sz=45&tbnid=wuSZEXTWYqoJ::&tbnh=92&tbnw=129&prev=/images%3Fq%3DGopher%2Bpicture&hl=en&sa=X&oi=image_result&resnum=3&ct=image&cd=1http://www.google.co.in/imgres?imgurl=http://www.onlinebangalore.com/life/pets/images/squirrel.jpg&imgrefurl=http://www.onlinebangalore.com/life/pets/squirrel.html&h=253&w=304&sz=11&tbnid=29BUnPucCSwJ::&tbnh=97&tbnw=116&prev=/images%3Fq%3Dsquirrel%2Bpicture&hl=en&sa=X&oi=image_result&resnum=2&ct=image&cd=1

  • 8/15/2019 Transmission Line Basic presentation

    15/1411-

    INS&LATE! CABLE %s O%ERHEA! LINE

    BARE CON!&CTOR 

    !ECI!IN" #ACTORS

    ;oltage le5el

    istance

    Congestion

    Cost consideration

    Geographical consideration

    #esthetic consideration

    "eliability

    #5ailable Technology

    pecial circumstances

  • 8/15/2019 Transmission Line Basic presentation

    16/1411.

    LAYIN" O# TRANSMISSION LIN2 

    I, Ins'late) ca3les

    +nderground

    $5erhead on Bylon

    upported by *ridge Girder 

    II, Bare Con)'ctor

    irect supports on Insulators

    Bylon supports

    Laying of Underground cable

  • 8/15/2019 Transmission Line Basic presentation

    17/141

    1/

    TYPES O# PYLONS

    # B$7 (tandard length: /- m> 0- m> 9/- m> 12 m)

    Aooden

    teel "ail> Channel

    Bretressed Concrete ( BC)

    "einforced Cement ConcreteWooden Pole

    Steel Tubular Pole PS Pole

  • 8/15/2019 Transmission Line Basic presentation

    18/141

    10

    TYPES O# PYLONS

    * LATTICE STEEL STR&CT&RE (Tower)

    'odular welded (self supporting or guyed)

    *olted ( built up & self supporting)

  • 8/15/2019 Transmission Line Basic presentation

    19/141

    19

    MO!&LAR TOWER ERS

  • 8/15/2019 Transmission Line Basic presentation

    20/141

    2

     TYPES O# LATTICE STR&CT&RE

    #ccording to support condition

    #ccording to number of circuits they carry:

    #ccording to tower shapes> base dimension

    E #'rt4er classi/ication

    #ccording to angle of de5iation

  • 8/15/2019 Transmission Line Basic presentation

    21/141

    21

    LATTICE STR&CT&RE CLASSI#ICATION

    ACCOR!IN" TO S&PPORT CON!ITION5  elf supporting tower 

    Guyed tower  

  • 8/15/2019 Transmission Line Basic presentation

    22/141

    22

    ACCOR!IN" TO NO O# CIRC&IT THEY CARRY  ingle circuit tower 

    ouble circuit tower 

    'ulti circuit towers 

    LATTICE STR&CT&RE CLASSI#ICATION

  • 8/15/2019 Transmission Line Basic presentation

    23/141

    23

    !ETAILS O# SIN"LE CIRC&IT TOWER 

    Cross arm at 3 le5els Cross arm at 2 le5els

    Cross arm at 1 le5el

  • 8/15/2019 Transmission Line Basic presentation

    24/141

    2,

    !O&BLE 6 M&LTI CIRC&IT TOWER 

    !OU"LE IRUIT TOWER

    MULTI IRUIT TOWER

  • 8/15/2019 Transmission Line Basic presentation

    25/141

    2-

    ACCOR!IN" TO CON#I"&RATION

    ;ertical configuration tower 

    =ori?ontal configuration tower 

    elta configuration tower

    LATTICE STR&CT&RE CLASSI#ICATION

  • 8/15/2019 Transmission Line Basic presentation

    26/141

    2.

    #CC$"I!G T$ T$A" =#B> *# I'!I$!

     !$T: To be chosen by designer on Techno economical consideration

    LATTICE STR&CT&RE CLASSI#ICATION

    WI!E "ASE! TOWER

    NARROW "ASE!

    %&'() *ts

    %&'

    +$ *ts

    #$$ %& NORMAL

    TOWER#$$ %& OMPAT

    TOWER

    400 kV Compact Single pole tower at Delhi &

  • 8/15/2019 Transmission Line Basic presentation

    27/141

    2/

    400 kV Compact Single pole tower at Delhi &

    Noida 

  • 8/15/2019 Transmission Line Basic presentation

    28/141

    20

    ACCOR!IN" TO AN"LE O# !E%IATION5

    *Tangent to+er$ s'spension to+er,

    A type tower (2 degree)

    Tension to+ers$angle to+ers:

    B type tower (1- degree)

    C type tower (3 degree)

      (#lso used for transposition)

    ! type tower (. degree) 

    LATTICE STR&CT&RE CLASSI#ICATION

  • 8/15/2019 Transmission Line Basic presentation

    29/141

    29

    TRANSPOSITION TOWER 

    W4at is transposition to+er an) its con/ig'ration? Transposition tower is normally parallel double circuit

    transmission tower to facilitate interchange of transmissionline phase conductor< where the phase conductors occupydifferent structure positions for different portions of the line

    length so that transmissionline impedances is balancedFor e@ample< conductor placement on the structures may be"* for onethird of the line length< *" for onethirdof the line length< and *" for the remaining third of theline length

    Ctype tower with modified crossarm is generally usedwith ?ero degree de5iation

  • 8/15/2019 Transmission Line Basic presentation

    30/141

    3

    WHY TRANSPOSITION?

    Bower transmission lines are transposed primarily forimpedance balance so as to eliminate or reducedisturbances in the neighboring communicationcircuits produced by geometric imbalances of power

    line Transposition tower are re8uired for a line length

    H 2 4ms why

    #rrangement of transposition tower is shown below

    LINE TRANSPOSITION

  • 8/15/2019 Transmission Line Basic presentation

    31/141

    31

    LINE TRANSPOSITION

    WITH 7C8 TYPE TOWER 

    R

    '

    "

    R

    '

    "

    R

    '

    "

    R

    '

    "

    T( T)T*

  • 8/15/2019 Transmission Line Basic presentation

    32/141

    32

    SIN"LE %s B&N!LE CON!&CTOR 

    ingle Conductor   : !ormal +se

    *undle Conductors:

    eciding Factors

    Capacity nhancement

    Technical reasons ( =andling & rection easiness< Corona> "adioInterference ( "I) consideration 

    *undle conductor Configuration

    Twin *undle

    6uad *undle

    pecial Burpose *undle (=e@agonal> $ctagonal etc)

  • 8/15/2019 Transmission Line Basic presentation

    33/141

    33

    TOWER SI9ES

    TOWER HEI"HT IS !ECI!E! BASE! ON

    pan : 7onger the span< more is the height 'inimum Ground clearance (#) re8uired to be

    maintained

    Conductor sag (*) Insulator assembly length (C) to maintain

    re8uired electrical

    ;ertical separation of Cross arms ()

     !umber of cross arm and its configuration

    Bea4 =eight for fi@ing earth wirecorresponding to shield angle ()

     A

    "

    !

    E

    !

    S+ield angle

  • 8/15/2019 Transmission Line Basic presentation

    34/141

    3,

    WHY EARTH WIRE?

    To protect conductor against lightning flasho5ers

    To pro5ide a path for fault current

    !irect #las4o1er

    $ccurs due to shielding failure with lightning on the conductor<flasho5er ta4ing place across the insulator string from conductorto ground

    Bac0 #las4o1er

    $ccurs due to high tower footing resistance with a high 5oltage atthe grounded tower cross arm compared to conductor< resulting ina flasho5er across the insulator string from ground to conductor

  • 8/15/2019 Transmission Line Basic presentation

    35/141

    3-

    WHY EARTH WIRE?

    'a@imum allowable fault current (I) through earth wire mainlydepends on

    #rea of earth wire (#)

    'a@imum permissible temperatureTime of short circuit (t)

    I 5aries proportional to # and in5erse proportion to s8rt (t)

  • 8/15/2019 Transmission Line Basic presentation

    36/141

    3.

    SHIEL! AN"LE

    arth wire is placed on top of the structure to

     pro5ide a shied angle for protection againstlightning o5er power conductors< therecommended angle being 3 degree with the5ertical in case of 5ertical formation of powerconductors

    7ocation where iso4eraunic le5els are high< lowerangle of shielding may be adopted

    #s cross arm width increases< hori?ontal spacing

    of conductor increases To protect the conductorswith specified shield angle< earth wire has to be

     placed at a higher ele5ation in such cases Toreduce the tower pea4 height< double pea4 with

    double earth wire are used in those cases

  • 8/15/2019 Transmission Line Basic presentation

    37/141

    3/

    STAN!AR! NORMAL SPAN

    #OR %ARIO&S %OLTA"E CLASSES

    %OLTA"E SPAN RAN"E *METERS,

    11 4; /-1

    33 4; 103- ( 913- o5er poles)

    .. 4; 2,32

    132 4; 3-3.-

    22 4; 3230

    , 4; 3- ,-

    /.- 4; ,,-

  • 8/15/2019 Transmission Line Basic presentation

    38/141

    30

    MINIM&M "RO&N! CLEARANCE

    %OLTA"E MINIM&M "RO&N! CLEARANCE

    IN METERS *IS :;.

  • 8/15/2019 Transmission Line Basic presentation

    39/141

    39

    NO O# CROSS ARMS

    AN! ITS CON#I"&RATION

    3 for single circuit line

    . for double circuit line

    12 or more for multi circuit lines

      Cross arms can be of =ori?ontal > ;ertical or Triangularconfiguration

    MINIM&M PHASE TO PHASE

  • 8/15/2019 Transmission Line Basic presentation

    40/141

    ,

    MINIM&M PHASE TO PHASE

    ELECTRICAL CLEARANCE

    %OLTA"E MINIM&M PHASE CLEARANCE*APP=, MM * IS :;.

  • 8/15/2019 Transmission Line Basic presentation

    41/141

    ,1

    WHAT IS "ALLOPIN"?

    "alloping *)ancing o/ con)'ctor,  is ;ery low fre8uency< high

    amplitude 1i3rations induced by: =igh 5elocity steady winds on conductors with asymmetrical

    ice deposit

    Ahen ice on a portion of ice co5ered conductor melts and

    suddenly drops off  Ahen a floc4 of birds perching together on a conductor

    suddenly ta4es off< lea5ing the conductor Jumping in loops

    Ot4er +in) in)'ce) 1i3rations are5

    #eolian 5ibrations : =igh fre8uency< low amplitude 5ibrationsinduced by low< steady & laminar wind

    Aa4e induced 5ibrations: 7ow fre8uency< medium amplitude5ibrations induced by high 5elocity steady winds on bundleconductors

  • 8/15/2019 Transmission Line Basic presentation

    42/141

    ,2

    CON!&CTOR SA"

    Conductor sag depends on

    Type of conductor 

    pan length

    Aeight of conductor 

    Conductor tension Sag 7SK L A72 > 0T

    A L conductor weight per meter 

    7L span length ( tower spacing)TL Conductor Tension

    !e1elope) Lengt4 7!KL 7M A2 73

      2,T2

    L, -.an

       S  ,

      -  a  g

    !

  • 8/15/2019 Transmission Line Basic presentation

    43/141

    ,3

    INS&LATOR ASSEMBLY LEN"TH

    %oltage Appro>imate Stan)ar) ins'lator assem3l(lengt4- single s'spension string

    11 4; 2 mm

    33 4; -- mm.. 4; 9.-mm

    132 4; 1.3 mm

    22 4; 23, mm, 4; 3/, mm

    /.- 4; -- mm

  • 8/15/2019 Transmission Line Basic presentation

    44/141

    ,,

    MINIM&M TOWER HEI"HT

    MINIM&M TOWER HEI"HT IS "O%ERNE! BY

    Minim'm gro'n) clearance *A,

    Ma>im'm sag *B,

    Ins'lator assem3l( lengt4 * C,

    */or s'spension to+er onl(,

    Cross arm spacing

    *1ertical con)'ctor separation, * !, 

    Eart4 +ire pea0 )istance /rom top most

    cross arm point * E,

     A

    "

    !

    E

    !

  • 8/15/2019 Transmission Line Basic presentation

    45/141

    ,-

    CROSS ARM SI9E *WI!TH,

    %oltage Minim'm Bo)(clearance * mm,

    11 4;

    33 4; 33

    .. 4; .1

    132 4; 1/

    22 4; 1./-, 4; 10.

    /.- 4;

    'inimum electrical clearance of conductor> Jumper from Tower body

      (I -.13)

    LOA!S ON TOWER

  • 8/15/2019 Transmission Line Basic presentation

    46/141

    ,.

    LOA!S ON TOWER 

    ;"TIC#7 7$# ead weight of Tower  ead weight of conductor & arth wire 7i5e weight of wor4ing personal<

    hoisting tools & tac4les etc now loading (where5er applicable)

    Transient loads  =$"I$!T#7 7$#For the purpose of con5enience weconsider all hori?ontal loads in two perpendicular a@es

    $ne in Trans5erse direction wrt crossarm $ne in longitudinal direction wrt cross

    arm

  • 8/15/2019 Transmission Line Basic presentation

    47/141

    ,/

    ORIENTATION O# TOWER +@r@t CROSS ARM

    Su-.en-ion to/er .o-ition-

    Line align0ent

    Line align0ent

    ro-- ar0 orientation 1.lan2

    # uspension Tower Longitudinal direction

    Longitudinal direction

       T  r  a  n  -  3

      e  r  -  e

       d   i  r  e  c   t   i  o  n

  • 8/15/2019 Transmission Line Basic presentation

    48/141

    ,0

    ORIENTATION O# TOWER +@r@t CROSS ARM

    * #ngle Tower  

     Angle of

    de3iation

     Angle of

    de3iation

    "i-ector 

     Angle To/er Po-ition-

    ro-- Ar0 Orientation of Angle to/er 1.lan2

  • 8/15/2019 Transmission Line Basic presentation

    49/141

    ,9

    TRANS%ERSE LOA! ON TOWER 

    $n account of wind pressure on tower body

    $n account of wind pressure on conductor< earth wire &insulator string

    $n account of conductor > earth wire pull

    Wind load on to/er , wind 

    pressure 4 .ro5ected area

    Wind load on conductor6eart+

    /ire , wind pressure 4

    .ro5ected area

    onductor 

    TRANS%ERSE LOA! ON TOWER ON A$c O#

  • 8/15/2019 Transmission Line Basic presentation

    50/141

    -

    TRANS%ERSE LOA! ON TOWER ON A$c O#

    CON!&CTOR $ EARTHWIRE P&LL

    7 , angle of !e3iation

    T-in 86*

    *Tco- 86*

    T-in 86*

    T

    T

    T

    T

    8 , (#$9 : ;

  • 8/15/2019 Transmission Line Basic presentation

    51/141

    -1

    LON"IT&!INAL LOA! ON TOWER ON ACCO&NT

    O# CON!&CTOR$ EARTHWIRE P&LL

    Longitudinal direction

    Tran-3er-e direction

  • 8/15/2019 Transmission Line Basic presentation

    52/141

    -2

    LON"IT&!INAL LOA! ON TOWER 

    # $n account of conductor > arth wire pull

    In normal case< 7ongitudinal load due to conductor pull canceleach other e@cept for bro4en wire condition (*AC) where therewill be imbalanced pull on the cross arm

    # ! T$A" which are used for termination of a line atswitch yard end are subJected to se5ere pull by conductor whichare strung on one side only

    * $n account of unbalanced Tension of conductor > earth wire ontwo sides of towers which may happen due to error during final

    tensioning & temperature 5ariation which may cause unbalancetension due to linear e@pansion> contraction when section lengthon either side of the tower are different

    C +nder *ro4en wire condition (*AC)

  • 8/15/2019 Transmission Line Basic presentation

    53/141

    -3

    !ead End To/er 

    S/itc+ yard gantry

    onnection to S/itc+ yard gantry i-done at a later -tage and /it+ -lac%

    -.an only

    LON"IT&!INAL LOA! ON TOWER 

  • 8/15/2019 Transmission Line Basic presentation

    54/141

    -,

    CONCEPT O# WEI"HT SPAN

     Ahat is weight span

    It is the span length (length of conductor or earth wire)which contribute to the 5ertical load on tower

    Weig+t -.an Weig+t -.an

    Weig+t -.an

    1left2

    Weig+t -.an

    1rig+t2

    W( W*

  • 8/15/2019 Transmission Line Basic presentation

    55/141

    --

    WHY NE"ATI%E WEI"HT SPAN OCC&RS ?

    $n steeply inclined spans< the low point of sag may fall beyond the

    lower support This indicates that the conductor in the uphill span ise@erting a negati5e or upward force on the lower tower The amountof this upward force is e8ual to the weight of the conductor from thelower tower to t4e lo+ point in t4e sag@ I/ 'p+ar) pull of the uphillspan is greater t4an t4e )o+n+ar) loa) o/ t4e ne@t adJacent span<

    actual uplift will 3e ca'se)

  • 8/15/2019 Transmission Line Basic presentation

    56/141

    -.

    NE"ATI%E WEI"HT SPAN

    R"

    L"

    1:2R A

    L A

     A

    "

    Total weight span of tower # L 7# % " #

    Total weight span of tower * L 7* M " *

    THEORETICAL #ORM&LA #OR CALC&LATION

  • 8/15/2019 Transmission Line Basic presentation

    57/141

    -/

    O# WEI"HT SPAN BETWEEN TOWERS AT

    !I##ERENT ELE%ATION

    !i-tance of Null .oint or Lo/ .oint of conductor fro0 t+e center of -.an

    i- gi3en by t+e for0ula

  • 8/15/2019 Transmission Line Basic presentation

    58/141

    -0

    THEORETICAL CONCEPT O# O#

    NE"ATI%E WEI"HT SPAN

    L*

    L(

    T*

    T(

    ;*

    ;(

    ;*

    T*

    T

    /L(

    T(

    T*

    T,T*OS;* , T( co- ;( 

    T*SIN ;* , /L*

    T* OS ;( , T(OS ;(

    T*SIN ;*@/L(,T(SIN ;(

    /1L(@L*2,T(SIN ;(

  • 8/15/2019 Transmission Line Basic presentation

    59/141

    -9

    SI"NI#ICANCE O# NE"ATI%E WEI"HT SPAN

     !egati5e weight span will mean that conductor> earth wire in

    such a location will produce a 5ertically upward load instead of5ertically down in normal cases

    ;ertically upward load L () weight span @ weight per unitlength of conductor> earth wire

    E##ECT O# NE"ATI%E WEI"HT SPAN

    ffect of negati5e weight span is that suspension tower can not be used at location with negati5e weight span as it will lift up

    the suspension insulators #ngle towers are therefore< to beused for such locations e5en if angle of de5iation is ?ero

  • 8/15/2019 Transmission Line Basic presentation

    60/141

    .

    CONCEPT O# WIN! SPAN

    WHAT IS WIN! SPAN?

    It is the span length ( length of conductor & arth wire) which contributeto the trans5erse hori?ontal load on the tower 

    B( B*

    Wind -.an , 1 B( @ B*2 6 *

    Wind load on conductor6 Eart+ /ire , /ind .re--ure 4 .ro5ected area

    TOWER SPOTTIN"

  • 8/15/2019 Transmission Line Basic presentation

    61/141

    .1

    TOWER SPOTTIN"

    Tower spotting is the process of choosing right type of Tower

    along the line routeTB I!;$7;

    Choosing Techno economical line route

    Fi@ing of #ngle ( de5iation point) to a5oid> minimi?e obstaclesenroute

    Ta4ing le5els at intermediate points for drawing of profile between #ngle points ( igital instruments li4e total stations arenow a days used)

    rawing of Brofile ( lectronic soft wares are now a days usedusing data from digital instruments

    TOWER SPOTTIN"

  • 8/15/2019 Transmission Line Basic presentation

    62/141

    .2

    Tower spotting is done either manually using sag templatecur5es or through electronic soft ware li4e B7C#

    To/er -.otting on .rofile

    TOWER SPOTTIN"

    SA" TEMPLATE C&R%E

  • 8/15/2019 Transmission Line Basic presentation

    63/141

    .3

    SA" TEMPLATE C&R%E

    Conductor & arth wire when strung between towers normally

    ta4es shape of a catenary cur5e Catenary cur5es of conductordrawn at the wor4ing tension forms the sag template cur5e

    Blastic sagtemplates are made for the purpose of manualtower spotting and also for random chec4ing of spotting done

    through electronic soft ware

    TOWER SPOTTIN" !ATA

  • 8/15/2019 Transmission Line Basic presentation

    64/141

    .,

    TOWER SPOTTIN" !ATA

    $nce the technical parameters li4e angle of de5iation< weight

    span< wind span etc are tabulated< the ne@t step is to choose thecorrect type of towers at 5arious locations after comparing thefield parameters with the design parameters In case of hilllyterrains< towers with 'ne'al leg e>tension are also used This

    is mainly adopted to reduce benching wor4 in a particularlocation The design parameters are contained in a documentcalled Tower spotting ata

    &NE&AL LE" E=TENSIONS

  • 8/15/2019 Transmission Line Basic presentation

    65/141

    .-

    &NE&AL LE" E=TENSIONS

    Leg 1 @ CD 0tr E4tn2

    Leg ! 1 @ 0tr E4tn2

    1"2 !V Badarpur K-lie-riat /ine

    /oc# o# 1 /3 4"5 "5 "5 +6

     1 @ 0tr E4tn2

     1 @ ) 0tr E4tn2

  • 8/15/2019 Transmission Line Basic presentation

    66/141

    SAMPLE TOWER SPOTTIN" !ATA

  • 8/15/2019 Transmission Line Basic presentation

    67/141

    ./

    SAMPLE TOWER SPOTTIN" !ATA

    SAMPLE TOWER SPOTTIN" !ATA

  • 8/15/2019 Transmission Line Basic presentation

    68/141

    .0

    SAMPLE TOWER SPOTTIN" !ATA

    TOWER SCHE!&LE

  • 8/15/2019 Transmission Line Basic presentation

    69/141

    .9

    TOWER SCHE!&LE

    Loc

    No

    Angle o/

    !e1iation

    Weig4t Span Win) Span Recommen)e)

    to+er t(peLe/t Rig4t Total Le/t Rig4t Total

    "ENERAL I!EA ON WIN! PRESS&RE

  • 8/15/2019 Transmission Line Basic presentation

    70/141

    /

    "ENERAL I!EA ON WIN! PRESS&RE

    Aind pressure is proportional to wind 5elocity

    Aind pressure ?onesIndia is di5ided in . ( i@) wind ?ones based on wind speed

      ;b is based on pea4 gust 5elocity a5eraged o5er a short timeinter5al of about 3 ( Three) seconds

     !ote: Aind as per I 02 and Aind ?one as per I 0/-

    Aind one *asic wind speed (;b) m>sec

    1 33

    2 393 ,,

    , ,/

    - -

    . --

    WIN! 9ONES O# IN!IA

  • 8/15/2019 Transmission Line Basic presentation

    71/141

    /1

    WIN! 9ONES O# IN!IA

    WIN! 9ONES 6 BASIC WIN! SPEE!S O# NER

  • 8/15/2019 Transmission Line Basic presentation

    72/141

    /2

    WIN! 9ONES 6 BASIC WIN! SPEE!S O# NER 

    Name o/ states Win) Done Basic +in) spee) * %3,m$sec

    #ssam .>->,>2 -->->,/>39

    'eghalaya .>->, -->->,/

    #runachal Bradesh ->3 ->,,

     !agaland ,>3 ,/>,,

    'anipur .>->3 -->->,,

    'i?oram . --

    Tripura . --

  • 8/15/2019 Transmission Line Basic presentation

    73/141

    WIN! 9ONE MI9ORAM

  • 8/15/2019 Transmission Line Basic presentation

    74/141

    /,

    WIN! 9ONE MI9ORAM

    WIN! 9ONE MANIP&R

  • 8/15/2019 Transmission Line Basic presentation

    75/141

    /-

    WIN! 9ONE MANIP&R 

    WIN! 9ONE ME"HALAYA

  • 8/15/2019 Transmission Line Basic presentation

    76/141

    /.

    WIN! 9ONE ME"HALAYA

    WIN! 9ONE AR&NACHAL PRA!ESH

  • 8/15/2019 Transmission Line Basic presentation

    77/141

    //

    WIN! 9ONE AR&NACHAL PRA!ESH

    WIN! 9ONE TRIP&RA

  • 8/15/2019 Transmission Line Basic presentation

    78/141

    /0

    WIN! 9ONE TRIP&RA

    WIN! SPEE!

  • 8/15/2019 Transmission Line Basic presentation

    79/141

    /9

    WIN! SPEE!

    METEOROLO"ICAL RE#ERENCE WIN! SPEE! * %R ,

    ;"  is e@treme 5alue of wind speed o5er an a5eraging period of 1( ten) minutes duration

    ;" L ; b> N 

    N  is ta4en as 13/- to con5ert 3 seconds pea4 gust speed in to 1minutes a5erage

    !ESI"N WIN! SPEE! * %),

    ;d L ;" @ N 1 @ N 2

    N 1L "is4 coefficient

    N 2 L Terrain "oughness coefficient

    SELECTION TABLE #OR 2

  • 8/15/2019 Transmission Line Basic presentation

    80/141

    0

    SELECTION TABLE #OR 2 .

    Aind ones1 2 3 , - .

    "eliability 7e5el

    7e5el 1 (up to , 4;) 1 1 1 1 1 1

    7e5el 2 (abo5e , 4;)Mtriple & 6uad c4t up to ,

    4;

    10 11 111 112 113 11,

    7e5el 3 (Tall "i5er crossing& special tower)

    11/ 122 12- 12/ 120 13

    SELECTION TABLE #OR 2 

  • 8/15/2019 Transmission Line Basic presentation

    81/141

    01

    Terrain Categor( %al'e o/ 2  

    Cat .5 @posed terrain with few or no obstructionswith a5erage height of obJects less than 1- m li4eopen sea coast> water stretch< deserts< flat tree lessterrain

    10

    Cat 5 $pen terrain with well scattered obstructionsha5ing height between 1-m to 1 m li4e normalcountry with 5ery few obstacles

    1

    Cat < 5  Terrain with numerous closely spaced

    obstructions li4e built up & forest area

    0-

    Note? For line- encountering ill-6 ridge-> K* -+ould be ta%en a- ne4t

    +ig+er 3alue

  • 8/15/2019 Transmission Line Basic presentation

    82/141

  • 8/15/2019 Transmission Line Basic presentation

    83/141

    %AL&E O# !RA" COE##ICIENT C)t 

  • 8/15/2019 Transmission Line Basic presentation

    84/141

    0,

    #OR TOWER 

    Soli)it( Ratio !rag Coe//icient C)

    +p to - 3.

    1 3,2 29

    3 2-

    , 22

    - and abo5e 2

    SOLI!ITY RATIO

  • 8/15/2019 Transmission Line Basic presentation

    85/141

    0-

    SOLI!ITY RATIO

    olidity ratio L Brotected area of all members

      #rea of frame

     !$T: rag coefficient ta4es in to account the shielding effects ofwind on the leeward face but if leeward members are not shielded

     by the windward face< proJected area of the leeward members shallalso be considered in the calculation

    %AL&ES O# "&ST RESPONSE #ACTOR #OR

  • 8/15/2019 Transmission Line Basic presentation

    86/141

    0.

    TOWER * "T, AN! INS&LATOR * "I,

    WIN! LOA! ON CON!&CTOR

  • 8/15/2019 Transmission Line Basic presentation

    87/141

    0/

    6 "RO&N! WIRE

    Fwc

     L Bd @ Cdc

     @ 7 @ d @ Gc

    Bd L esign wind pressure in !>m2

    Cdc L rag coefficient (1 for conductor and 12 for ground wire> earth wire)

    7 L Aind span L =alf of sum of adJacent span

    d L iameter of conductor> arth wire in meter 

    Gc

    L Gust response factor 

    %AL&ES O# "&ST RESPONSE #ACTOR "C

    #OR CON!&CTOR 6 EARTH WIRE

  • 8/15/2019 Transmission Line Basic presentation

    88/141

    00

    #OR CON!&CTOR 6 EARTH WIRE

    WIN! LOA! ON INS&LATOR STRIN"

  • 8/15/2019 Transmission Line Basic presentation

    89/141

    09

    WIN! LOA! ON INS&LATOR STRIN"

    Fwi

     L Bd @ Cdi

     @ #i @ GiBd L esign wind pressure in !>m2

    Cdi L rag coefficient to be ta4en as 12

    #i L - Q proJected area of insulator stringGi L Gust response factor 

     !ote: !o mas4ing effect will be considered in case of multiple >; insulator strings

    TENSION LIMIT O# CON!&CTOR 6 E$WIRE

    * R / IS FG P t I$S I .:,

  • 8/15/2019 Transmission Line Basic presentation

    90/141

    9

    * Re/5 IS FG Part I$Sec I- .:,

    Conductor >arth wire tension at e5eryday temperature and withoute@ternal load< should not e@ceed the following:

    Condition I

    Initial unloaded tension : 3- Q of ultimate tension strength ( +T)Final unloaded tension: 2-Q of +T ( for 5oltage le5el upto 22 4;)

      22Q for conductor & 2 Q for arth wire

      ( for , & 0 4; le5el)

  • 8/15/2019 Transmission Line Basic presentation

    91/141

    #ORM&LA #OR CALC&LATIN" CHAN"E IN

    TENSION O# CON!&CTOR$ E$WIRE !&E TO

  • 8/15/2019 Transmission Line Basic presentation

    92/141

    92

    TENSION O# CON!&CTOR$ E$WIRE !&E TO

    CHAN"E IN TEMP 6 PRESS&RE *RE#5 IS :;< PART I,

     T22

    S T2 % (T1 l2

    w2

    812

    U)> 2,T12

    VtUWX L l2

    w2

    822

    U > 2,where

    T2 L Tension at temp t2 R C in 4g

    T1 L Tension at temp t1 R C in 4g

    l L pan length in meter AL Aeight per meter 

    81 L Y( w2 Mw12 )>w w1 L wind load in 4g> m

    ZL #

    L oung modulus in 4g> cm2#L Cross section area ( m2)

    V L Coefficient of linier e@pansion per RC

    62 L loading factor

    t L (t2 % t1) R C

    SA" TENSION CHART

  • 8/15/2019 Transmission Line Basic presentation

    93/141

    93

    SA" TENSION CHART

    Aith change in ambient temperature< tension on conductor and

    earth wire shall also change in the following pattern because ofthermal e@pansion> contraction in the following manner

    Temperature increases : Tension decreases

    Temperature decreases : Tension increases It is therefore important that correct tensions are maintained

    during stringing of conductor > earth wire corresponding toambient temperature so that design tension and sags are

    maintained during worst loading conditions as alreadye@plained earlier 

     

    SA" TENSION CHART

  • 8/15/2019 Transmission Line Basic presentation

    94/141

    9,

    For this purpose< tension and sags at different ambient

    temperatures are calculated corresponding to base wor4ingtension at e5ery day temperature and with no wind & usingformula already discussed earlier

    The results are than tabulated in a con5enient way for reference

    SA" TENSION CHART

    SA" TENSION CHART

  • 8/15/2019 Transmission Line Basic presentation

    95/141

    9-

    SA" TENSION CHART

    METHO! O# MAINTAININ" CORRECT

    TENSION AT THE TIME O# STRIN"IN"

  • 8/15/2019 Transmission Line Basic presentation

    96/141

    9.

    TENSION AT THE TIME O# STRIN"IN"

    *y measuring sag

    *y measuring tension

    TB

    tepI : 'easure ambient temp

    tep II: Calculate a5erage ruling span of the section using thefollowing formula

    tep III : Consult ag Tension chart and note sag and tension5alue corresponding to ambient temp and corresponding

    to a5erage ruling spantep I; : elect the span whose length is nearest to the ruling span

    & adJust sag or tension so as to attain the re8uired 5alue before final tensioning (clamping on tower)

    TOWER LOA!IN" CON!ITIONS

  • 8/15/2019 Transmission Line Basic presentation

    97/141

    9/

    7oadings shall be determined for the Two loading conditions

    Combination I : Corresponding to ma@imum wind at meanannual temperature

    Combination II : Corresponding to 2>3 rd ma@imum wind at

    the minimum temperature

    TOWER LOA!IN" TRANS%ERSE LOA!S

  • 8/15/2019 Transmission Line Basic presentation

    98/141

    90

    WIN! LOA!S NORMAL CON!ITION BRO2EN WIRE CON!ITION

    $n conductors andground wires onfull proJected areas

    Corresponding to full windspan of bundledconductors & ground wire

    Corresponding to -Q of intactspan and 1Q of bro4en span of bundled conductor> ground wire

    $n Tower $n 1- times the proJected

    areas of members on thewindward face of towers

    $n 1- times the proJected areas

    of members on the windwardface of towers

    $n insulator strings1) uspension

    2) Tension

    1 4g

    3 4g

    1 4g

    3 4g

    TOWER LOA!IN" TRANS%ERSE LOA!S

  • 8/15/2019 Transmission Line Basic presentation

    99/141

    99

    !E%IATION

    LOA!S

    NORMAL

    CON!ITIONS

    BRO2EN WIRE

    CON!ITIONS

    Trans5erse componentstension of bundledconductors and groundwire

    a) uspension tower   Trans5erse components

    corresponding to -Q ofthe tension of bundled

    conductors or 1Q of thetension of ground wire

     b) Tension tower 

      Trans5erse componentcorresponding to 1Q ofthe tension of bundledconductor> ground wire

    TOWER LOA!IN" %ERTICAL LOA!S

  • 8/15/2019 Transmission Line Basic presentation

    100/141

    1

    !&E TO

    CON!&CTOR 

    NORMAL

    CON!ITIONS

    BRO2EN WIRE

    CON!ITIONS

    uspensiontower 

    8ual to the ma@imum>minimum weight span of bundled conductors

      .Q of ma@imum>minimum weight span of bundled conductors

    Tension Tower 8ual to ma@imum weightspan of bundledconductors ( downward orupward)

      .Q of ma@imum weightspan of bundledconductors ( downward orupward)

    TOWER LOA!IN" %ERTICAL LOA!S

  • 8/15/2019 Transmission Line Basic presentation

    101/141

    11

    !&E TO"RO&N! WIRE

    NORMALCON!ITIONS

    BRO2EN WIRECON!ITIONS

    uspension tower 8ual to the ma@imum>minimum weight span ofGround wire

      .Q of ma@imum>minimum weight span ofGround wire

    Tension Tower 8ual to ma@imumweight span of Groundwire ( downward orupward)

      .Q of ma@imum weightspan of Ground wire( downward or upward)

    ue to Insulator &conductor#ccessories

    8ual to the weight ofInsulator strings< spacers<dampers etc

    8ual to the weight of Insulatorstrings< spacers< dampers etc

    TOWER LOA!IN" LON"IT&!INAL LOA!S

  • 8/15/2019 Transmission Line Basic presentation

    102/141

    12

    !&E TO POWER

    CON!&CTOR 

    NORMAL

    CON!ITIONS

    BRO2EN WIRE CON!ITIONS

    uspension Towers !I7 - Q of the tension of bundledconductors

    Tension Towers 8ual to the tension of bundled power

    conductors for deadend towers only

    8ual to the components of tensionof the bundled power conductors

    corresponding to the rele5ant anglesof de5iation

    ue to Groundwire

     !ormal conditions *ro4en wire conditions

    uspension Towers !I7 8ual to the tension of Ground wire

    Tension Towers 8ual to the tension ofGround wire fordeadend towers only

    8ual to the components of tensionof the Ground wire corresponding tothe rele5ant angles of de5iation

    TOWER LOA!IN" ERECTION LOA!S

  • 8/15/2019 Transmission Line Basic presentation

    103/141

    13

    NORMALCON!ITIONS

    BRO2EN WIRECON!ITIONS

    'an with Tools !I7 8ual to the tension ofGround wire

    7oads due to liftingtac4les< line car etc(to be considered atconductor cross armand lifting points)

    8ual to thetension ofGround wire fordeadend towersonly

    8ual to the componentsof tension of the Groundwire corresponding tothe rele5ant angles ofde5iation

     !ote: The design of towers shall be based on loading combinationand condition which is more stringent for the particular member 

    #O&N!ATION LOA!IN"S

  • 8/15/2019 Transmission Line Basic presentation

    104/141

    1,

     Calculated from Tower 7oadings

     Typical Tower 7oading tree is indicated below

    #O&N!ATION LOA!IN"S

  • 8/15/2019 Transmission Line Basic presentation

    105/141

    1-

    7oads transmitted to Foundation through tower legs

    Two types of loads act on foundation

    # ;"TIC#7 ( M )* =ori?ontal or side thrust

    &N!ER %ERTICAL LOA!

  • 8/15/2019 Transmission Line Basic presentation

    106/141

    1.

    &N!ER HORI9ONTAL LOA!

    A@ O%ERT&RNIN"

  • 8/15/2019 Transmission Line Basic presentation

    107/141

    1/

    O%ERT&RNIN"

    &N!ER HORI9ONTAL LOA!B@ SLI!IN"

  • 8/15/2019 Transmission Line Basic presentation

    108/141

    10

    SLI!IN"

    %ERTICAL LOA! ON #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    109/141

    19

    &L/ &LM&L/&LM

    FSTFST

    L

    WIN!

    FORE

    LOA! ON #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    110/141

    11

    On acco'nt o/ gra1it( /orce *+eig4t, on to+er

    If A L Total gra5ity force ( weight)

    Then 5ertical load (;7) on account of A on each leg<

    ;7w L A>, which acts downward (down thrust)

    On acco'nt HoriDontal /orces *trans1erse $ longit')inal , on to+er

    Ahich produces turning moment at the base of tower 

     !et 'oment 'T L [ F= @ h

    Ahere F= L =ori?ontal force at a particular height

      h L corresponding height from foundation top 

    LOA! ON #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    111/141

    111

    @ternal 'oment ' produces restoring moment in the form of upward &downward thrust at leg> foundation

    "estoring 'oment

    '"  L 2(upward> downward thrust in each leg @ leg to leg dist)

      ie '" L 2 ;7' @ 7

    For stability: !et turning moment L !et "estoring moment

    ie 'T L '"  \ ie 'T L 2;7' @ 7 \ ie  ;7' L 'T>27

     !et down thrust on 2 legs on one side  L M( ;7A M ;7') 

     !et upward thrust on 2 legs on other side L ( ;7' % ;7A) !ormally ;7' HH;7A and therefore there is net upward thrust on 2 legs

    of a tower which also acts on the foundation and this is called uplift onfoundation

    #O&N!ATION LOA!IN" WIN! 9ONEII *

  • 8/15/2019 Transmission Line Basic presentation

    112/141

    112

    * ,

    #OR GG 2% !$C TOWER WITH TWIN MOOSE CON!&CTOR 

    TOWER TYPE COMPRESSION*2g,

    &PLI#T *2g, SI!E THR&ST*TRANS, *2g,

    SI!E THR&ST*LON", *2g,

    # M -9 -3

  • 8/15/2019 Transmission Line Basic presentation

    113/141

    113

    B@ HORI9ONTAL LOA! ON #O&N!ATION

    =ori?ontal forces on tower also produces side thrust onfoundation

    ide Thrust F&T L [ F= > ,

    arth8ua4e forces

  • 8/15/2019 Transmission Line Basic presentation

    114/141

  • 8/15/2019 Transmission Line Basic presentation

    115/141

    TOWER #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    116/141

    11.

    c) # footing with an under cut generally de5elops uplift

    resistance of two to three times that of an identical footingwithout undercut +ndercut foundations are normally

     pro5ided in fissured & soft roc4 foundations

     TOWER #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    117/141

    11/

    Failure .lane Soil S+ear Stre--

    Undercut

    Foundation

    F$+!#TI$! TB

    TOWER #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    118/141

    110

    F$+!#TI$! TB

    BROA! CLASSI#ICATION :

    $pen Cast % 'ost commonly used

    #ugured under reamed pile (where open e@ca5ation is Broblematic)

    Bile foundation

    Aell foundation $n pecial 7ocations: "i5er *ed< !earby ri5er< prone to erosion< Aea4 soil

    OPEN CAST #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    119/141

    119

    A&"&RE! &N!ER REAME! PILE

    #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    120/141

    12

    PILE #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    121/141

    121

    WELL #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    122/141

    122

    PILE #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    123/141

    123

    PILE #O&N!ATION CONSTR&CTION

    LI#TIN" O# CA"E

  • 8/15/2019 Transmission Line Basic presentation

    124/141

    12,

     

    P7/3 8&9DAT7& &ST%9T7&

    /owerin, of reinforcement ca,e in pile bore

  • 8/15/2019 Transmission Line Basic presentation

    125/141

    12-

    , , p

    P7/3 8&9DAT7& &ST%9T7&

    /owerin, of reinforcement ca,e in pile bore

  • 8/15/2019 Transmission Line Basic presentation

    126/141

    12.

    , , p

    P7/3 8&9DAT7& &ST%9T7&

    7nstalled pile

  • 8/15/2019 Transmission Line Basic presentation

    127/141

    12/

     

    http://us.f347.mail.yahoo.com/ym/ShowLetter?box=Inbox&MsgId=7316_5371269_958_2182_4736217_0_145619_6254142_4149395225&bodyPart=2&tnef=&YY=76524&y5beta=yes&y5beta=yes&order=down&sort=date&pos=1&view=a&head=b&VScan=1&Idx=29http://us.f347.mail.yahoo.com/ym/ShowLetter?box=Inbox&MsgId=7316_5371269_958_2182_4736217_0_145619_6254142_4149395225&bodyPart=2&tnef=&YY=76524&y5beta=yes&y5beta=yes&order=down&sort=date&pos=1&view=a&head=b&VScan=1&Idx=29

  • 8/15/2019 Transmission Line Basic presentation

    128/141

    P7/3 8&9DAT7& &ST%9T7&

    3rected tower on pile foundation

  • 8/15/2019 Transmission Line Basic presentation

    129/141

    129

     

    WELL #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    130/141

    13WELL FOUN!ATION

    WELL #O&N!ATION &N!ER CONSTR&CTION

  • 8/15/2019 Transmission Line Basic presentation

    131/141

    131

    OPEN CAST #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    132/141

    132

    'ost commonly used< Con5enient & 8uic4 in e@ecution wherethere is no high water table and soil collapse problem

    COMMON TYPE O# OPEN CAST #O&N!ATION:

    !epen)ing on t(pe o/ materials 'se)  

    teel Grillage Type foundation

    BCC > "CC foundation !epen)ing on e>tent o/ e>ca1ation  

    Indi5idual footing

    Chimney % frustrum type

    Chimney % Bad type

    *loc4 type

    pread type footing

    STEEL "RILLA"E TYPE #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    133/141

    133

    PCC $ RCC #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    134/141

    13,

    CHIMNEY PA! TYPE #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    135/141

    13-

    BLOC2 TYPE #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    136/141

    13.

    SPREA! TYPE #O&N!ATION

  • 8/15/2019 Transmission Line Basic presentation

    137/141

    13/

    OPEN CAST #O&N!ATION *Cont)@,

    !epen)ing on t(pe o/ soil

  • 8/15/2019 Transmission Line Basic presentation

    138/141

    130

    !epen)ing on t(pe o/ soil  

     !ormal dry soil foundation ry fissured roc4 (with under cut) "oc4 Foundation (#nchored) *lac4 Cotton soil foundation< commonly 4nown as Aet

    *lac4 Cotton (A*C) type !epen)ing on )ept4 o/ +ater ta3le  

    ry Foundation: Aater table below footing depth Aet Foundation: Aater table 1- ' from ground surface

    Bartially ubmerged (B): Aater table between 1- to /- mfrom ground surface

    Fully ubmerged (F): Aater table abo5e /- m

    WHY CLASSI#ICATION

    BASE! ON WATER TABLE?

  • 8/15/2019 Transmission Line Basic presentation

    139/141

    139

    Aeight of soil and concrete is less when submerged in water because of buoyancy effect and therefore offers lessresistance to uplift then in dry condition

    #ngle of internal friction (]) is less for wet soil and

    therefore 5olume of frustum of soil abo5e footing pad is lessin wet condition & therefore offers less resistance to uplift

    conomy in cost is therefore achie5ed in classifyingfoundations based on water table instead of adopting one

    type considering worst condition (F type)

    #O&N!ATION %OL&ME

  • 8/15/2019 Transmission Line Basic presentation

    140/141

    1,

    Comparison of foundation 5olume for different fdn classification:

     !ame of 7ine : , 4; >C 'isa *alipara

    TOWERTYPE

    CONCRETE %OL&ME *C&M,

    !RY WET P@S #@S

    # 9.0 133 12.9 1-/,

    * 2,9, 20-1 3,99 ,29

    C 2/0. ,3-31 -3,9 .3.2

    3,-. -219 -03- 1330,

  • 8/15/2019 Transmission Line Basic presentation

    141/141

    T=#!N $+