    Trinity River Corridor Project Update

    Col. Charles H. Klinge

    Commander, Fort Worth DistrictUS Army Corps of Engineers

    Jill A. Jordan, P.E.Assistant City ManagerCity of Dallas

    Dallas City Council briefingAug. 21, 2013

    1

  • 7/27/2019 Trinity River Corridor Project Update

    3/95

    Purpose

    To provide an overview of the Trinity RiverCorridor Project

    To introduce the US Army Corps of Engineers

    (Corps)

    To outline next steps

    2

  • 7/27/2019 Trinity River Corridor Project Update

    4/95

    Trinity River Corridor Project Partners

    US Army Corps of Engineers (Corps) City of Dallas Dallas County North Texas Tollway Authority (NTTA)

    Texas Dept. of Transportation (TxDOT) Fed. Highway Administration (FHWA) Texas Commission on

    Environmental Quality (TCEQ) Environmental Protection Agency (EPA)

    Federal Emergency ManagementAgency (FEMA) North Central Texas Council of

    Governments (COG)

    3

    Federal, State and Local Partners

  • 7/27/2019 Trinity River Corridor Project Update

    5/95

    Trinity River Corridor ProjectNon- Profit Partners

    Trinity Trust Foundation

    Trinity Commons Foundation Audubon Society Boone Family Foundation Circle Ten Boy Scouts Dallas Camera Club Dallas Running Club

    Downtown Dallas EQUEST Groundwork Dallas Girl Scouts of Northeast Texas River Ranch Education Charities Ocean Conservancy Scottish Rite Hospital Student Conservation Association Texas Horse Park Foundation Trinity Bird Count Trinity Strand Trail The Mission Continues

    4

  • 7/27/2019 Trinity River Corridor Project Update

    6/95

    AT&T

    CVS Caremark Dallas Morning News Dr. Pepper/Snapple National Fish & Wildlife/FedEx Hilton Anatole Kroger Lukes Locker Matthews Southwest Methodist Hospital Dallas Nestle Waters NorthPark Center

    Oncor Reliant Energy Sprint Southwest Airlines Xerox

    Wells Fargo

    Trinity River Corridor ProjectPrivate Sector Partners

    5

  • 7/27/2019 Trinity River Corridor Project Update

    7/95

    Fort Worth DistrictUS Army Corps of Engineers

    Who we are: Created 1950 after 1949 Fort Worth flood

    1,200 civilian and military employees half in Fort Worth

    What we do:Military Works: Support the needs of 11 Army and 5 Air Force installations

    across Texas, New Mexico and Louisiana

    Civil Works: Ten river basins covering 53% of the state

    Levee systems in 16 Texas counties 25 lakes containing 314 parks

    Corps lakes provide 30% of Texas water supply 35 current ecosystem restoration projectsOverseas contingency response: 27 employees

    deployed to Afghanistan in MayEmergency response: District employees

    deploy nationwide for disaster relief

    6

  • 7/27/2019 Trinity River Corridor Project Update

    8/95

    930 Miles

    15 hrs Disaster Response

    HydropowerGeneration

    Land Acquisition

    Flood Protection

    MilitaryConstruction

    (Army)

    Military Construction

    (Air Force)

    Core Drilling

    MilitaryConstruction

    (Medical)

    EnvironmentalRestoration/ FUDs

    Water Supply

    Recreation

    Interagency andInternationalSupport

    Fort Worth District Mission Areas

    7

  • 7/27/2019 Trinity River Corridor Project Update

    9/95

    Overview

    8

    The Trinity River corridor projects address regionalconcerns but flood risk reduction is the cornerstone.

    4 inter-related components of the projects are:

    I. Flood Risk ReductionII. Ecosystem Restoration

    III.TransportationIV.Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    10/95

    200,000 people work or live behind the levees

    $12.2 billion in floodplain investment

    9

    1989 flood40-year event

    I. Flood Risk Reduction

  • 7/27/2019 Trinity River Corridor Project Update

    11/9510

    Corps Lakes provideflood control, watersupply andrecreation

    Benbrook Grapevine Lavon Lewisville Joe Pool Ray Roberts

    Flood Risk Reduction

  • 7/27/2019 Trinity River Corridor Project Update

    12/95

    Flood Risk Reduction

    11

    Two Corps ofEngineersprojects

    DallasFloodwayExtension

    DallasFloodway

  • 7/27/2019 Trinity River Corridor Project Update

    13/95

    Flood Risk Reduction History

    1949Fort Worth flood kills 11, flood control reservoir

    construction advances (Lewisville, Grapevine, Benbrook) 1958Corps completes major Dallas Floodway upgrade

    1989-1991Worst floods since 1908. 1998Dallas voters authorize record bond package $246

    million for Trinity flood control, transportation and recreation.

    1908Dallas flood kills 5, leaves 4,000 homeless, citywithout power for days, massive property damage

    1928First levee system built in Dallas

    MontgomeryWard building,1949 FortWorth flood

    12

  • 7/27/2019 Trinity River Corridor Project Update

    14/95

    Flood Risk ReductionDallas Floodway Project

    2007 Water Resources Development Act (WRDA) Section 5141was authorized to raise the levees up to 2 feet, provide recreation(Balanced Vision Plan) and improve pump stations

    2009Corps tells City it has rated Dallas Floodway unacceptable;

    FEMA withdraws accreditation of levees; city begins maintenanceand construction work to re-certify levees

    2010Feasibility Study and Environmental Impact Statementprocess launched to explore what actions are needed to restorecapacity of Dallas Floodway to meet a major storm event.

    2011 Corps introduces Risk Assessment process, a cost-effectivemethod for assessing aging dams, to the Dallas Floodway Project. First of this type of study for levees in the Country

    Determines Dallas Floodway Project Levees are more resilient and providearound 1,500-year protection

    13

  • 7/27/2019 Trinity River Corridor Project Update

    15/95

    Flood Risk ReductionThe Risk Assessment Process

    14

    Method for quantifying the risk (likelihood) of various ways a leveecan fail, and the consequences of each failure type

    Identifies most cost-effective ways to reduce risk

    Overtopping with breach

    Successful result: Determined levees moreresilient than previously thought

    Narrowed the list of 13potential failure modes to two:

    Overtopping with breach ofEast or West Levee

    Overtopping of the EastLevee floodwall

  • 7/27/2019 Trinity River Corridor Project Update

    16/95

    Flood Risk ReductionRecommended Flood Risk Management Plan

    15

    Raise low spots in the levees up to 3 feet to increase flood conveyanceto 277,000 cubic feet per second. This is enough to convey floodwaters ofa major storm that has a 1/2,500 chance of happening any given year

    Cost of these two changes: $6.2 million

    Old abandonedAT&SF TrestlesProposed for Removal

    The Trestles are on 14-foot-centers and collect debris during flooding andstack up floodwaters into the floodway. The embankment acts as a weirand impedes flow down the floodway system

  • 7/27/2019 Trinity River Corridor Project Update

    17/95

    Flood Risk Reduction

    16

    Where leveelow spotswould be

    raised

    East Levee: 2.6 milesWest Levee: 1.2 miles

  • 7/27/2019 Trinity River Corridor Project Update

    18/95

  • 7/27/2019 Trinity River Corridor Project Update

    19/95

    Flood Risk ReductionInterior Drainage Plan

    18

    Expanding pump stations, such asPavaho (completed last year),reduces neighborhood flooding. ThisWest Dallas neighborhood regularly

    flooded before upgrade.

    2006 Flooding near Old Pavaho

    Pump Station

    2012 New Pavaho Pump Station

  • 7/27/2019 Trinity River Corridor Project Update

    20/95

    Concept of Able

    Flood Risk ReductionInterior Drainage Plan

    19

    More pump stations under way

    Baker Pump Station (2255 IrvingBlvd. near Design District);construction now

    28 percent complete

    Able Pump Station (600 S.Riverfront near Fuel City) Underdesign. Construction to beginwithin a year.

  • 7/27/2019 Trinity River Corridor Project Update

    21/95

  • 7/27/2019 Trinity River Corridor Project Update

    22/95

    21

    Flood Risk ReductionFiscal Year 2014

    Brief the Transportation and Trinity River Project CouncilCommittee on the Dallas Floodway Project

    Environmental Impact Statement and the upcoming 2014Public Meeting

    Award the Upper Chain of Wetlands and Able PumpStation

    Open Baker Pump Station

  • 7/27/2019 Trinity River Corridor Project Update

    23/95

    II. Ecosystem Restoration

    Lower Chain of Wetlandshave dual role: New wildlifehabitat in the heart of the citythat also reduces flood risk inthe Dallas Floodway

    Fed by treated wastewater,the Lower Chain of Wetlandsthrive through drought and

    further clean water before itflows back into Trinity RiverI. Flood Risk Reduction

    II. Ecosystem RestorationIII. TransportationIV. Recreation

    22

  • 7/27/2019 Trinity River Corridor Project Update

    24/95

    Ecosystem Restoration

    Lower Chain of Wetlands highlights Native plants selected to maximize

    food supplies for birds Water levels adjusted to attractseasonal waterfowl

    125 bird species have been recordedin the Lower Chain of Wetlands

    23

  • 7/27/2019 Trinity River Corridor Project Update

    25/95

    Ecosystem RestorationPath Forward: More wetlands

    Upper Chain of Wetlands(Martin Luther King Jr.Bridge at 11th Street),Phase 1 constructioncomplete

    PavahoStorm Water

    PolishingWetlandsanticipatedconstructionstart this year

    24

  • 7/27/2019 Trinity River Corridor Project Update

    26/95

    Tire Removal, Planting andClean Up Activities

    Staff, contracts and volunteer programs such as Groundwork Dallas and

    Southwest Airlines Trinity Conservation Corps aim to remove tires and trashin and along the Trinity

    Staff, contracts and volunteer programs plant native species vegetation

    2525

  • 7/27/2019 Trinity River Corridor Project Update

    27/95

    Ecosystem RestorationFiscal Year 2014 Next Steps

    Brief the Transportation and Trinity River Project CouncilCommittee on the operations and maintenance for theLower Chain of Wetlands

    Award the construction of the Upper Chain of Wetlands

    Award a contract to remove tires in and along the TrinityRiver

    Continue planting and clean up activities at variouslocations along the Trinity River and wetlands areas

    26

  • 7/27/2019 Trinity River Corridor Project Update

    28/95

    III. Transportation

    Concept for Sylvan Bridgenow under construction

    I. Flood Risk ReductionII. Ecosystem Restoration

    III. TransportationIV. Recreation

    27

  • 7/27/2019 Trinity River Corridor Project Update

    29/95

    TransportationSylvan Avenue Bridge Under Construction

    Construction start: March 2012 Re-open to traffic: Early 2014 Completion: June 2014 6 Lanes (3 in each direction),

    6 foot-wide sidewalk, bikelanes, ramp to park area

    TxDOT cost: Approximately$42 million

    28

    Transportation

  • 7/27/2019 Trinity River Corridor Project Update

    30/95

    TransportationHorseshoe Project: I-30 (McDermott Bridge)

    and I-35E Bridges

    TxDOT awarded design-buildcontract November 2012

    Construction soil tests begun Construction complete 2017 Cost: $798 million (private,

    local, state & federal)

    Planned Margaret McDermott Bridge (I-30)

    29

  • 7/27/2019 Trinity River Corridor Project Update

    31/95

    TransportationMargaret Hunt Hill Bridge

    Opened March 2012 First Santiago Calatrava

    vehicular bridge built in the U.S. Connects downtown Dallas to

    West Dallas over the Trinity

    River (Woodall RodgersFreeway to Singleton Boulevard)

    30

  • 7/27/2019 Trinity River Corridor Project Update

    32/95

    Transportation

    Riverfront Boulevard Under Design

    Continental Ave.Phase I

    Commerce St.

    CadizSt.

    Phase 2

    Phase 1 construction late this year(lasting 19 months)

    Phase 2 construction to beginSpring 2014 (lasting 24 months)

    6 traffic lanes, cycle track,

    bioswales, landscaping Cost: $42.5 million City, County,COG

    31

    TransportationRiverfront

  • 7/27/2019 Trinity River Corridor Project Update

    33/95

    TransportationCadiz Street

    (FromRiverfrontTo Lamar)

    Est. Total Cost $4.8 M (funded)Design completed in November 2012

    Begin roadway const. by February 2014Complete roadway const. in August 2015

    Begin Sump A bridge const. late 2015Complete Sump A bridge const. late 201632

    T t ti

  • 7/27/2019 Trinity River Corridor Project Update

    34/95

    TransportationBeckley/Commerce Intersection Improvements

    33

    Design completed in July 2013 Estimated total cost - $3.6M Construction scheduled to begin in December 2013 (15-18 month

    duration)

  • 7/27/2019 Trinity River Corridor Project Update

    35/95

    TransportationTrinity Parkway Under design

    34

  • 7/27/2019 Trinity River Corridor Project Update

    36/95

    TransportationTrinity Parkway Need and Purpose

    1994-1996Trinity River Corridor CitizensCommittee recommended a levee couplet parkway

    TxDOT conducted the Major TransportationInvestment Study from 1996-1998:

    Looked at over 35 different scenarios for traffic relief inthis corridor

    Looked at vehicular, mass transit, bicycle andpedestrian options

    Recommended a variety of solutions including theTrinity Parkway

    35

  • 7/27/2019 Trinity River Corridor Project Update

    37/95

  • 7/27/2019 Trinity River Corridor Project Update

    38/95

  • 7/27/2019 Trinity River Corridor Project Update

    39/95

    Transportation

  • 7/27/2019 Trinity River Corridor Project Update

    40/95

    39

    TransportationTrinity Parkway Toll Road

    Reunion Overlook View of the Parkwayfrom the Lake

  • 7/27/2019 Trinity River Corridor Project Update

    41/95

  • 7/27/2019 Trinity River Corridor Project Update

    42/95

  • 7/27/2019 Trinity River Corridor Project Update

    43/95

  • 7/27/2019 Trinity River Corridor Project Update

    44/95

    IV. Recreation

    43

    I. Flood Risk ReductionII. Ecosystem RestorationIII. Transportation

    IV.Recreation

    43

  • 7/27/2019 Trinity River Corridor Project Update

    45/95

    RecreationBalanced Vision Plan

    In 2003 City of Dallas writes long-range Balanced VisionPlan to reclaim Trinity River as a great natural resource andunique public domain and a model of environmentalstewardship that embodies the spirit of the Kessler Planidea of nearly a century before.

    44

    Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    46/95

    45

    RecreationBalanced Vision Plan

    Lakes

    River meanders Playing fields Multipurpose trails Canoe/kayak loop Amphitheater

    Restore/expand ripariancorridor Improve aquatic habitat Riffle pool complexes Wetlands Pedestrian bridges Promenade Concession pads Boat/canoe access Picnic areas

    Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    47/95

    46

    RecreationPossible Phase I Urban Lake Under Study

    Construction could begin in late 2014

    Approx. 23 acres

    Near MargaretMcDermott Bridge andCommerce Bridge

    For reference, Lake Cliff isabout 13 acres and BachmanLake is about 120 acres

    Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    48/95

    47

    RecreationPossible Phase I West Dallas Lake Under Study

    Construction could begin in late 2014

    About 21 acresNear Westmoreland

    For reference, Lake Cliff is 13 acresBachman Lake is 120 acres

    Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    49/95

    48

    RecreationContinental Avenue Bridge and West Dallas Gateway

    Construction began June2013

    Completion estimated inMay 2014

    Amenities includeparking, landscaping,

    bocce, chess, kids playarea and meditationzones

    $10.6M ($8M donationand $2.6M from 2006bond funds)

  • 7/27/2019 Trinity River Corridor Project Update

    50/95

    BUILDING STRONG

    Elm Fork Greenbelt Masterplan

    49

    Masterplan isfunded by theBoone FamilyFoundation

    Study beginsSpring 2013

    Amenities beingconsideredinclude publicaccess,Interpretationopportunities,wildernessopportunities, anddestinations

    Spans fromRoyal Lanesouthward to theconfluence

    49

  • 7/27/2019 Trinity River Corridor Project Update

    51/95

    50

    RecreationElm Fork Athletic Complex

    Construction completion estimated inmid- to late 2013

    Estimated open for management by

    FC Dallas and open for play April 1 Amenities include 10 internationalsoccer fields (lighted), 4 internationalsoccer fields (unlighted), 5 youthsoccer fields, 2 pavilions with openplay space and potential concession

    areas Construction cost about $18 million

    from various bond and grant funds

    R ti

  • 7/27/2019 Trinity River Corridor Project Update

    52/95

    RecreationDallas Wave Under Construction

    Located off 8th Street & Corinth, under the

    Santa Fe Trestle Trail crossing of the TrinityRiver

    Construction of Wave Complete Construction of bypass channel pending

    additional work 100s of kayakers currently use this feature Amenities include parking lot, main wave

    and bypass channel

    5151

    R i

  • 7/27/2019 Trinity River Corridor Project Update

    53/95

    Recreation

    Construction award September2012

    Located at 1825 CaliforniaCrossing Rd.

    Provides portage locationsabove and below the low waterdam

    Construction is estimated to becomplete in October 2013(weather permitting)

    52

    California Crossing Canoe Launches

    Under Construction

  • 7/27/2019 Trinity River Corridor Project Update

    54/95

  • 7/27/2019 Trinity River Corridor Project Update

    55/95

    RecreationMoore Park Expansion Completed in June

    54

    (Adjacent to Santa Fe Trestle Trail and Corinth DART rail station)

    Pavilion, amphitheater, pedestrian bridge over Cedar Creek and parking

  • 7/27/2019 Trinity River Corridor Project Update

    56/95

    Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    57/95

    56

    Construction could begin in fall 2013

    (pending land acquisition) at SouthCentral Park on Fellows Lane

    Amenities could include: Expansion of existing park to

    connect to the Trinity River Lower

    Chain of Wetlands to theneighborhood Mini spray area Upgrades to the existing

    basketball court Two open play areas

    Additional walkway Off-street parking area

    $800,000 to $900,000construction budget from2006 Bond Funds

    South Central (Joppa) Gateway

    Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    58/95

    400-acre formerlandfill

    PGA quality 18-hole course

    9-hole shortcourse, practicefacility

    Partnership ofAT&T, SMU, city,

    SMU Golf Team,First Tee ofGreater Dallasyouth group andothers

    57

    RecreationTrinity Forest Golf Course

    Anticipated construction start: 2013; opening 2016

    PGA tour site for the Byron Nelson by 2019

    Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    59/95

    Located at 811 Pemberton Construction started Summer 2013 Estimated finish: Summer 2014 Non-profit phase includes a

    therapeutic center, arenas, a camphouse and trail ride opportunities

    $12 million cost from 1998 & 2006bond funds and HillcrestFoundation grants

    Partners include:Equest Therapeutic Horsemanship River Ranch Educational Charities Texas Horse Park Foundation

    RecreationTexas Horse Park

    58

    Recreation

  • 7/27/2019 Trinity River Corridor Project Update

    60/95

    Location: I-20 at Dowdy Ferry Road Opened in June Pavilion, fishing piers, bathrooms,

    hike/bike/equestrian trails $1 million from 1998 bond funds

    RecreationGreat Trinity Forest Gateway and Horse Trails

    59

  • 7/27/2019 Trinity River Corridor Project Update

    61/95

    Trinity Trails Network Background

    Trinity Trails Network is a subset of the Citys

    Trail Network System

    Extends from Royal Lane near Luna in the North

    to I20 & Dowdy Ferry in the South Hard surface trails 62.7 miles planned

    (8 miles in service)

    Soft surface trails 18.8 miles in service

    60

    Elm Fork Greenbelt Trails

  • 7/27/2019 Trinity River Corridor Project Update

    62/95

    Elm Fork Greenbelt Trails

    61

    Trinity Forest Trails

  • 7/27/2019 Trinity River Corridor Project Update

    63/95

    Trinity Forest Trails

    62

    Santa Fe Trestle Trail

  • 7/27/2019 Trinity River Corridor Project Update

    64/95

    Santa Fe Trestle Trail Two trailheads: 2295 S. Riverfront

    Blvd, Dallas TX 75207 and 1837E. 8th Street, Dallas TX 75203

    (DART overflow parking lot)

    Trail length - .86 miles from westentrance at Moore Park (underconstruction as a separate project)to east parking lot inside floodway

    63

    Trinity Forest Trails

  • 7/27/2019 Trinity River Corridor Project Update

    65/95

    Trinity Forest Trails

    Phase 1completefrom JoppaPreserve toEco Park

    Phase 2 complete linking Joppa Preserve to Trinity River Audubon Center

    Trailheads, 12 wide hard

    surface trail, parking and kiosks

    Phase 1 Trail length 2 miles Phase 2 Trail length 2 miles

    64

  • 7/27/2019 Trinity River Corridor Project Update

    66/95

    William Blair Jr. Park Gateway Trailhead

  • 7/27/2019 Trinity River Corridor Project Update

    67/95

    66

    3000 Municipal Street, Dallas, TX 75215

    AT&T Trails (Trinity Trails Phase IIIA)

  • 7/27/2019 Trinity River Corridor Project Update

    68/95

    AT&T Trails (Trinity Trails Phase IIIA) Under Construction

    67

    Starts at the

    Audubon andloops underGreat TrinityForest Way,ending at ElamRoad

    Construction

    will begin inSummer 2013

    Could open inWinter 2014

    Constructioncostapproximately$1.9M from

    AT&T Donation

    Trinity Forest Spine

  • 7/27/2019 Trinity River Corridor Project Update

    69/95

    Trail

    68

    Trinity ForestSpine Trail

    Study funded through a grant

    from the Trinity Trust to becompleted in 2014

    Connecting the southern mostboundary of the Great TrinityForest to the Dallas Arboretum

    Trailheads locations include theGreat Trinity Forest Gateway &Horse Trails, Audubon Center,Bruton/Scyene DART Station,and Dallas Arboretum

    Construction estimated to beapproximately $17M; Fundrasingcampaign kick off by The TrinityTrust in May 2013

    Trinity Strand Trail Phase I

  • 7/27/2019 Trinity River Corridor Project Update

    70/95

    Trinity Strand Trail Phase I

    69

    Trinity Strand Trail

    Phase I from OakLawn to MedicalDistrict Drive,connecting atSylvan Avenue

    Construction couldbe complete Spring2014

    Amenities includeplaza at TurtleCreek, 12 concrete

    trail Trinity Strand Trail

    Phase II from OakLawn to Inwoodfunded through2012 BondProgram

  • 7/27/2019 Trinity River Corridor Project Update

    71/95

    Trinity Floodway Trails

  • 7/27/2019 Trinity River Corridor Project Update

    72/95

    Trinity Floodway Trails

    71

    2012 Bond Program included $6,418,400 for design & construction of Trinity Trails

    Katy/Trinity Strand Trail

    Connection$18M

    (includes amenities)

    Proposed Alignment for All Weather Joint

  • 7/27/2019 Trinity River Corridor Project Update

    73/95

    To advance this trail ahead of the Corps EIS,the 2012 Bond Program proposed alignmentcould be modified and constructed as an allweather joint use maintenance road for:

    Maintenance trucks and other equipment

    Pedestrians

    Cyclists

    72

    Proposed Alignment for All Weather JointUse Maintenance Road / Trinity Floodway Trails

    Proposed Alignment for All Weather Joint

  • 7/27/2019 Trinity River Corridor Project Update

    74/95

    Proposed Alignment for All Weather JointUse Maintenance Road / Trinity Floodway Trails

    In June 2013, the Trinity River Corridor ProjectCommittee requested staff brief City Council in August:

    Provide a refined, proposed alignment

    Show safety recommendations

    Request a recommendation to proceed with theconstruction of this alignment

    Safety measures will be in place to address pedestrian,bicycle and maintenance vehicle traffic

    73

  • 7/27/2019 Trinity River Corridor Project Update

    75/95

    Joint-Use All Weather Facility

  • 7/27/2019 Trinity River Corridor Project Update

    76/95

    75

    Joint Use All Weather FacilityAlignment

    Proposed Alignment for All Weather Joint

  • 7/27/2019 Trinity River Corridor Project Update

    77/95

    Funds would be reserved to complete: Connections crossing outfalls following the Dallas

    Floodway EIS (could begin in late 2014)

    Connections to the Coombs Creek Trail at IH30 (assoon as IH30 is complete)

    Connection between IH30 and IH35 followingcompletion of Horseshoe Project (2017)

    76

    Proposed Alignment for All Weather JointUse Maintenance Road / Trinity Floodway Trails

  • 7/27/2019 Trinity River Corridor Project Update

    78/95

  • 7/27/2019 Trinity River Corridor Project Update

    79/95

  • 7/27/2019 Trinity River Corridor Project Update

    80/95

    Appendix A - History of TrinityRiver Corridor

    79

  • 7/27/2019 Trinity River Corridor Project Update

    81/95

  • 7/27/2019 Trinity River Corridor Project Update

    82/95

  • 7/27/2019 Trinity River Corridor Project Update

    83/95

    History (continued)1998 Cit B d P i l d P iti 11 f th T i it Ri

  • 7/27/2019 Trinity River Corridor Project Update

    84/95

    83

    1998 City Bond Program includes Proposition 11 for the Trinity RiverCorridor Project for $246M with multiple components

    First and foremost is Flood Protection: Dallas Floodway Extension Project ($24.7M) Elm Fork Improvements, including Soccer Complex ($30M)

    Other Project Components: Recreation

    Chain of Lakes concept ($31.5M) Athletic fields, trails and Gateway Parks ($41.5M)

    Transportation Trinity Parkway ($84M) Woodall Rodgers Extension (Margaret Hunt Hill Bridge) ($28M) Beckley/Commerce Intersection Improvements ($6M)

    Environmental Restoration

    Forest restoration and mitigation (part of DFE) Wetlands (part of DFE) Air Quality

    Sustainable development and reinvestment in the heart of Dallas 2006 City Bond Program includes funding for flood control,

    transportation and recreation projects 2007 Voters reconfirm support for the Trinity Parkway inside the

    levees

    2009Corps Periodic Inspection #9 occurs 2011Corps Risk Assessment determines levees are more

    resilient and actually provide 1500-year flood protection 2012 City Bond Program includes funding for flood control and

    trails

  • 7/27/2019 Trinity River Corridor Project Update

    85/95

    Appendix B - Historical FundingPartnership City / Corps

    84

    1998

  • 7/27/2019 Trinity River Corridor Project Update

    86/95

    Trinity RiverCorridor Project

    Elm Fork Dallas FloodwayExtension (DFE)

    Upper TrinityFeasibility Study

    (Dallas Floodway)

    Levee alongLuna Rd.

    Chain of Wetlands Lamar Levee Cadillac Heights

    Levee

    Flood Control- Levee Raise- Levee Fattening

    Recreation/Lakes

    85

    2006

  • 7/27/2019 Trinity River Corridor Project Update

    87/95

    MiscellaneousSmall DrainageImprovements.

    Elm Fork Dallas FloodwayExtension (DFE)

    Upper TrinityFeasibility Study

    (Dallas Floodway)

    Chain of Wetlands Lamar Levee Cadillac Heights

    Levee

    Flood Control- Levee Raise- Levee Fattening

    Recreation/Lakes

    Trinity RiverCorridor Project

    Interior DrainageProjects

    2006 BondProgram- Able Pump

    Station

    - Baker PumpStation- Pavaho Pump

    Station

    86

    2007

  • 7/27/2019 Trinity River Corridor Project Update

    88/95

    MiscellaneousSmall DrainageImprovements.

    Elm Fork Dallas FloodwayExtension (DFE)

    Chain of Wetlands Lamar Levee Cadillac Heights

    Levee

    Trinity RiverCorridor Project

    Interior DrainageProjects

    2006 BondProgram- Able Pump

    Station

    - Baker PumpStation- Pavaho Pump

    Station

    FeasibilityStudy/EIS

    Flood Control Recreation/Lakes Interior Drainage

    87

  • 7/27/2019 Trinity River Corridor Project Update

    89/95

  • 7/27/2019 Trinity River Corridor Project Update

    90/95

  • 7/27/2019 Trinity River Corridor Project Update

    91/95

  • 7/27/2019 Trinity River Corridor Project Update

    92/95

    F nding S mmar

  • 7/27/2019 Trinity River Corridor Project Update

    93/95

    Funding Summary

    Federal funds directed to the projectapproximately $225M

    Private donations approximately $60M

    Public Bond Programs supporting floodprotection, ecosystem restoration, transportationand recreation