turbine assessment pace-d 19sept13
TRANSCRIPT
CenPEEPCenPEEP
USAID PACE-DHEAT RATE IMPROVEMENT PROGRAMMEHEAT RATE IMPROVEMENT PROGRAMME
AT CHANDRAPUR AND PANIPAT
T bi & A ili i P f A tT bi & A ili i P f A tTurbine & Auxiliaries Performance Assessment Turbine & Auxiliaries Performance Assessment
PMI NoidaPMI NoidaPMI, Noida19.09.2013PMI, Noida
19.09.2013
CenPEEPCenPEEP
HEAT RATE IMPROVEMENT PROGRAMME
Turbine & Auxiliaries Performance AssessmentTurbine & Auxiliaries Performance AssessmentTurbine & Auxiliaries Performance Assessment Turbine & Auxiliaries Performance Assessment
ChandrapurChandrapur Unit Unit –– 6 (500 MW):6 (500 MW):44thth to 8to 8thth March, 2013March, 2013
P i tP i t U itU it 5 (210 MW)5 (210 MW)PanipatPanipat Unit Unit –– 5 (210 MW):5 (210 MW):1111thth to 15to 15thth March, 2013March, 2013
CenPEEPCenPEEP
Indian Coal Station
Impact of Efficiency
Indian Coal Station
1 kcal//kWh Coal Saving 2,37,091 Tons
CO2 Reduction 2,95,655 Tons
Cost Reduction Rs. 56.9 Crores
All data on annual basis
67 kcal//kWh1 % Eff Coal Saving CO2 Reduction
Installed Capacity 1,18,409 MW, GCV 3500 kcal/kg , Coal Cost Rs 2400 per Ton, PLF 80%, FC 34%
Cost Reduction67 kcal//kWh Improvement
1 % Eff. Improvement
Coal Saving158,85,097 Tons
CO2 Reduction 198,08,885 Tons
Cost Reduction Rs. 3813 Crores
Same as above, Heat rate 2350 kcal/kWh
Per day Coal Consumption 6,240 Tons
500 MW Unit Annual Coal Consumption
22,77,600 Tons
Annual Coal Cost Rs. 318.84
Crores
Annual CO2 Production
28,47,000 Tons
S b S ifi l i 0 65 k /kWhSame as above, Specific coal consumption 0.65 kg/kWh
5 kcal//kWh Improvement
500 MW Unit Coal Saving 5,008 Tons
CO2 Reduction 6,261 Tons
Cost Reduction Rs. 1.2 Crores
S bSame as above
CenPEEPCenPEEPMajor Heat Rate Loss Areas
Typical Major Heat Rate Loss Area
Dry FG Loss, 22%
Unaccountable, 21%
RH S 9%
Cooling Tower, 8% RH Spray, 9%8%
HPT Eff, 12%IPT Eff, 10%
Condenser Loss, 18%
CenPEEPCenPEEP
Turbine & Auxiliaries Performance Test
Performance test Carried Out:
Turbine & Auxiliaries Performance Test
• Gross Turbine Cycle Heat rate (GTCHR )• HP & IP Turbine Cylinder Efficiency Condenser Performance• Condenser Performance
• HPH performance • FW Flow validation• Cooling Tower Walk Down Survey• Cooling Tower Walk Down Survey
CenPEEPCenPEEP
Gross Turbine Cycle Heat RateyTurbine Cycle Heat rate depends upon, how much heat is
utilized for generation of one unitg
GTCHR = Heat added in the cycle / Total MW generated
• Major components affecting the Turbine Cycle ffEfficiency are
HP / IP /LP Turbine CondenserHP HeatersImproper Cycle Isolation (Unaccountable Losses)Improper Cycle Isolation (Unaccountable Losses)RH Spray
CenPEEPCenPEEPGross Turbine Cycle Heat Rate
Gross Load Gross Load MWMW FW Press HPH InletFW Press HPH Inlet Kg/cm2(abs)Kg/cm2(abs)
MS Pressure before ESVMS Pressure before ESV Kg/cm2(abs)Kg/cm2(abs) FW Temp HPH InletFW Temp HPH Inlet Deg.CDeg.CMS Temp before ESVMS Temp before ESV Deg.CDeg.C FW Press HPH OutletFW Press HPH Outlet Kg/cm2(abs)Kg/cm2(abs)
HPT Exhaust PressureHPT Exhaust Pressure Kg/cm2(abs)Kg/cm2(abs) FW Temp HPH OutletFW Temp HPH Outlet Deg.CDeg.C
HPT E h t T tHPT E h t T t D CD C M i St FlM i St Fl T/hT/hHPT Exhaust TemperatureHPT Exhaust Temperature Deg.CDeg.C Main Steam Flow Main Steam Flow (Q1)(Q1)
T/hrT/hr
HRH Steam Pressure before HRH Steam Pressure before IVIV
Kg/cm2(abs)Kg/cm2(abs) Feed Water Flow (Qf)Feed Water Flow (Qf) T/hrT/hr
HRH Steam Temp. before IVHRH Steam Temp. before IV Deg.CDeg.C CRH Flow (Q2)CRH Flow (Q2) T/hrT/hr
FW press after top heaterFW press after top heater Kg/cm2(abs)Kg/cm2(abs) S/H Spray Flow (Qs)S/H Spray Flow (Qs) T/hrT/hr
FW T t E i l tFW T t E i l t D CD C R/H S Fl (Q )R/H S Fl (Q ) T/hT/hFW Temp at Eco inletFW Temp at Eco inlet Deg.CDeg.C R/H Spray Flow (Qr)R/H Spray Flow (Qr) T/hrT/hr
HPH Ext. Steam TempHPH Ext. Steam Temp Deg.CDeg.C S/H Spray S/H Spray TemperatureTemperature
Deg.CDeg.C
HPH Shell PressureHPH Shell Pressure Kg/cm2(abs)Kg/cm2(abs) R/H SprayR/H Spray Deg CDeg CHPH Shell PressureHPH Shell Pressure Kg/cm2(abs)Kg/cm2(abs) R/H Spray R/H Spray TemperatureTemperature
Deg.CDeg.C
HPH Drip TempHPH Drip Temp Deg.CDeg.C Leak Off FlowLeak Off Flow T/hrT/hr
CenPEEPCenPEEPTurbine & Auxiliaries Performance Test
• GTCHR test was carried out on for one hour at VWO condition. • Control room parameters from DAS were averaged during the test
duration. • Online measurements of some of the Critical Parameters were
• GTCHR test was carried out on for one hour at VWO condition. • Control room parameters from DAS were averaged during the test
duration. • Online measurements of some of the Critical Parameters were• Online measurements of some of the Critical Parameters were
validated using offline instruments. • Online measurements of some of the Critical Parameters were
validated using offline instruments.
Chandrapur Unit – 6: Load Maintained at 480 MW Chandrapur Unit – 6: Load Maintained at 480 MW
• The Gross turbine Cycle Heat Rate (GTCHR) as per test data was 2026kcal/kWh and test corrected GTCHR value of 2033 kcal/kWh(corrected for CW inlet Temp of 28.7 0C/ Design 30 0C) at 480 MW as
• The Gross turbine Cycle Heat Rate (GTCHR) as per test data was 2026kcal/kWh and test corrected GTCHR value of 2033 kcal/kWh(corrected for CW inlet Temp of 28.7 0C/ Design 30 0C) at 480 MW as(co ected o C et e p o 8 C/ es g 30 C) at 80 asagainst design of 1965 Kcal/kWh (at VWO condition) there by havinga HR deviation of 68 kcal/kWh.
(co ected o C et e p o 8 C/ es g 30 C) at 80 asagainst design of 1965 Kcal/kWh (at VWO condition) there by havinga HR deviation of 68 kcal/kWh.
Panipat Unit 5: Load Maintained at 211 MWPanipat Unit – 5: Load Maintained at 211 MW
• The Gross turbine Cycle Heat Rate (GTCHR) as per test data was 2106kcal/kWh and test corrected GTCHR value of 2126 kcal/kWh(corrected for CW inlet Temp of 29.1 0C/Design 32 0C) at 211 MW asagainst design of 1983 Kcal/kWh (at VWO condition) there by havinga HR deviation of 143 kcal/kWh.
CenPEEPCenPEEPGTCHR Test : Chandrapur Unit – 6 (Unit Load : 480 MW)
Sl No. Description Heat Rate (Kcal / Kwh)
1 Test GTCHR (VWO) 2026
2 Test Corrected GTCHR (Corrected for CW I/L 20332 Test Corrected GTCHR (Corrected for CW I/Ltemp of 28.7°C / D‐30°C)
2033
3 Design GTCHR (VWO) 1965
4 Total Deviation in GTCHR 68
5 Condenser loss due to CW flow / Heat load 13
6 Condenser loss due to dirty tube / air ingress 27
7 HP Turbine Efficiency (83.1% / D ‐ 88.76%) 167 HP Turbine Efficiency (83.1% / D 88.76%) 16
8 IP Turbine Efficiency (91.37% / D – 91.41%) ‐
9 FW temp of Eco Inlet (252.87°C/ D ‐255.7°C) 3
10 MS Temperature (547 3°C/ D ‐537°C) ‐10
D - Design
10 MS Temperature (547.3 C/ D 537 C) 10
11 MS Pressure (165.2 Ksc / D ‐170 Ksc) 3
13 HRH Temperature (543.5°C/ D ‐537°C) ‐3
14 RH Spray flow (42 t/hr) 1014 RH Spray flow (42 t/hr) 10
15 Total accountable losses 59
16 Unaccountable losses 9
CenPEEPCenPEEPGTCHR Test : Panipat Unit – 5 (Unit Load : 211 MW)
Sl No. Description Heat Rate (Kcal / Kwh)
1 Test GTCHR (VWO) 2106
2 Test Corrected GTCHR (Corrected for CW I/Lt f 29 1°C / D 32°C)
2126temp of 29.1°C / D‐32°C)
3 Design GTCHR (VWO) 1983
4 Total Deviation in GTCHR 143
/5 Condenser loss due to CW flow / Heat load 8
6 Condenser loss due to dirty tube / air ingress 44
7 HP Turbine Efficiency (81.1% / D ‐ 87%) 18
8 IP Turbine Efficiency (86.06% / D – 90.51%) 14
9 FW temp of Eco Inlet (240°C/ D ‐240.5°C) ‐
10 MS Temperature (537.5°C/ D ‐535°C) ‐2
D - Design
11 MS Pressure (141.6 Ksc / D ‐150 Ksc) 9
13 HRH Temperature (524.5°C/ D ‐535°C) 5
14 RH Spray flow (13.5 t/hr) 4
15 Make Up Flow (7 t/hr) 20
16 Total accountable losses 120
17 Unaccountable losses 23
CenPEEPCenPEEPFW Water Flow Validation at Panipat Unit - 5
• Unit - 5 FW Flow measurements was carried out using hightemperature ultrasonic flow meter at the HPH – 5 inlet line.
• The Flow measured using ultrasonic flow meter was showing680.5 t/hr as against the online flow value on the same line of700 t/hr.
• 20 t/hr in FW Flow measurement corresponds to GTCHR of 60kcal/kWh (for typical 210 MW Unit).
CenPEEPCenPEEP
Impact of Turbine Efficiency on HR/Output
Description Effect on Effect on
Impact of Turbine Efficiency on HR/Output
pTG HR KW
1% HPT Efficiency 0 16% 0 3%1% HPT Efficiency 0.16% 0.3% (app 3 kcal)
1% IPT Efficiency 0.16% 0.16%( )(app 3 kcal)
1% LPT Efficiency 0.5% 0.5%(app 10 kcal)Impact of Turbine Efficiency on HR/Output ( pp )
Output Sharing by Turbine CylindersHPT 28%
p y pneeds to be calculated on Unit specific basis
IPT 23%LPT 49%
CenPEEPCenPEEP
Turbine Isentropic Efficiency
Used EnergyTurbine Isentropic Efficiency =
Available Energy
hin - hout=
h hMajor Issues: hin – hisen
Whereh = Enthalpy at Cylinder Inlet conditions
Major Issues:
• Turbine Efficiency Test to be carried out at VWO Condition• Turbine Offline Testing to be carried out twice in a year & pre-post COHhin = Enthalpy at Cylinder Inlet conditions
hout = Enthalpy at Cylinder Outlet conditionshisen = Isentropic Enthalpy
• Turbine Offline Testing to be carried out twice in a year & pre post COH• Retention of PG Test Points for new units• Water leg correction to be incorporated in online pressure measurements• Calibration/upkeep of offline instrumentsp p
CenPEEPCenPEEPTurbine Efficiency Gap
Breakup Of Turbine Efficiency Losses (%)
Leakage Loss - 50%
Surface Roughness - 36%
Others - 14%
CenPEEPCenPEEPTurbine Seals Loss break up
OTHERS SHAFT OTHERS6% SEALS
15%INTER
STAGE27%
TIP SEALSSEALS52%
CenPEEPCenPEEPSeal Leakage
DIAPHRAGM
TIPSPILL STRIPS
TIPLEAKAGE
TENON
STEAM FLOW
ROOT
ROTATINGBLADE
STATIONARYBLADESTAGE
PRESSURE
ROOT LEAKAGE
COVER ORSHROUD
Impulse Wheel andSPILL STRIPSDOVETAIL
Impulse Wheel and Diaphragm
Construction
BALANCE HOLE
WHEELPACKING
INTERSTAGE PACKING LEAKAGE
BALANCE HOLEFLOW
SHAFT
INTERSTAGE PACKING LEAKAGE
CenPEEPCenPEEPSeal Leakage
BLADECARRIER
TIP SPILLSTRIPS TENONTIP
LEAKAGECOVER
STATIONARYBLADE
ROTATINGBLADE
TRAILINGEDGE
LEADINGEDGE
Reaction Drum Rotor Construction
INTERSTAGEPACKING
ROTOR
CenPEEPCenPEEPTurbine Surface Roughness
• Surface finish degradation:
- Deposits
Corrosion- Corrosion
- Solid Particle Erosion
- Mechanical damage
• Roughness up to 0.05 mm can lead to decrease in efficiency by 4%
CenPEEPCenPEEPTurbine Seal DamageTurbine Seal Damage
MISSING SEAL STRIPSMISSING SEAL STRIPS
Tip seal strips : missing, slots washed out
CenPEEPCenPEEPHP/IP Turbine – Chandrapur Unit - 6
• The HP Turbine Efficiency test was carried out in VWO condition.The HPT efficiency as per test data is 83.1 % as against design value(VWO) of 88.76 %.There is a deterioration of about 5 66 % in HPT efficiency This
• The HP Turbine Efficiency test was carried out in VWO condition.The HPT efficiency as per test data is 83.1 % as against design value(VWO) of 88.76 %.There is a deterioration of about 5 66 % in HPT efficiency This• There is a deterioration of about 5.66 % in HPT efficiency. Thiscorresponds to a HR loss of 16 Kcal/kWh.
• There is a deterioration of about 5.66 % in HPT efficiency. Thiscorresponds to a HR loss of 16 Kcal/kWh.
Description HPT Exhaust Pressure Throttle Pressure HPT Exh. / Throttle Pr.pKg/cm2( a) Kg/cm2( a)
/
HBD 47.02 170 0.2766
Test Data 48.8 165.2 0.2953
The increase in pressure ratio indicates increase in turbine clearances.• It is suggested that the gland seal / inter‐stage seal strips condition as well
it l b h k d t th t il bl t it
The increase in pressure ratio indicates increase in turbine clearances.• It is suggested that the gland seal / inter‐stage seal strips condition as well
it l b h k d t th t il bl t it
• The IPT efficiency as per test data is 91.37 % as againstdesign value (VWO) of 91.41 %.
• There is a no deterioration in IPT efficiency.as its clearances may be checked at the next available opportunity.• It is proposed to trend the HPT efficiency at VWO (to track the degradation).
• It is suggested that the pressure ratio of HPT exhaust to throttle pressure
as its clearances may be checked at the next available opportunity.• It is proposed to trend the HPT efficiency at VWO (to track the degradation).
• It is suggested that the pressure ratio of HPT exhaust to throttle pressure
y
It is proposed to trend the Efficiency at VWO (to track the degradation)It is proposed to trend the Efficiency at VWO (to track the degradation)
gg p pshould also be monitored, trended and analyzed for correlating with changein Turbine clearances/deposits.
gg p pshould also be monitored, trended and analyzed for correlating with changein Turbine clearances/deposits.
CenPEEPCenPEEPHP Turbine – Panipat Unit - 5
• The HP Turbine Efficiency test was carried out in VWO condition.The HPT efficiency as per test data is 81.1 % as against design value(VWO) of 87 %.There is a deterioration of about 5 9 % in HPT efficiency This
• The HP Turbine Efficiency test was carried out in VWO condition.The HPT efficiency as per test data is 81.1 % as against design value(VWO) of 87 %.There is a deterioration of about 5 9 % in HPT efficiency This• There is a deterioration of about 5.9 % in HPT efficiency. Thiscorresponds to a HR loss of 18 Kcal/kWh.
• There is a deterioration of about 5.9 % in HPT efficiency. Thiscorresponds to a HR loss of 18 Kcal/kWh.
Description HPT Exhaust Pressure Throttle Pressure HPT Exh. / Throttle Pr.pKg/cm2( a) Kg/cm2( a)
/
HBD 40.36 150 0.2690
Test Data 37.9 141.6 0.2676
The decrease in pressure ratio indicates of deposits in HP turbine. • It is suggested to check for deposits in HP Turbine at the next
il bl t it
The decrease in pressure ratio indicates of deposits in HP turbine. • It is suggested to check for deposits in HP Turbine at the next
il bl t itavailable opportunity.• It is proposed to trend the HPT efficiency at VWO (to track thedegradation). • It is suggested that the pressure ratio of HPT exhaust to throttle
available opportunity.• It is proposed to trend the HPT efficiency at VWO (to track thedegradation). • It is suggested that the pressure ratio of HPT exhaust to throttlegg ppressure should also be monitored and analyzed for change inTurbine conditions
gg ppressure should also be monitored and analyzed for change inTurbine conditions
CenPEEPCenPEEPIP Turbine – Panipat Unit - 5
• The IPT efficiency as per test data is 86.06 % as against design value(VWO) of 90.51 %.
• There is a deterioration of about 4.5 % in HPT efficiency. This
• The IPT efficiency as per test data is 86.06 % as against design value(VWO) of 90.51 %.
• There is a deterioration of about 4.5 % in HPT efficiency. Thisycorresponds to a HR loss of 14 Kcal/kWh.
ycorresponds to a HR loss of 14 Kcal/kWh.
Description IPT Exhaust PressureKg/cm2( a)
IPT Inlet PressureKg/cm2( a)
IPT Exh. / IPT Inlet Pr.g/ ( ) g/ ( )
HBD 7.07 34.31 0.2060
Test Data 7.64 34.7 0.2202
The increase in pressure ratio indicates the increase in turbine clearances. • It is suggested that the gland seal / inter-stage seal strips condition
ll it l b h k d t th t il bl
The increase in pressure ratio indicates the increase in turbine clearances. • It is suggested that the gland seal / inter-stage seal strips condition
ll it l b h k d t th t il blas well as its clearances may be checked at the next availableopportunity.
• It is suggested to provide online measurement of IPT Exhaustpressure and temperature which is presently not available.
as well as its clearances may be checked at the next availableopportunity.
• It is suggested to provide online measurement of IPT Exhaustpressure and temperature which is presently not available.p p p y
• It is suggested that the pressure ratio of IPT exhaust to IPT inletshould also be monitored and analyzed for change in Turbine clearances.
p p p y• It is suggested that the pressure ratio of IPT exhaust to IPT inlet
should also be monitored and analyzed for change in Turbine clearances.
CenPEEPCenPEEPCondenser Performance Monitoring
Parameters to be Monitored
• Condenser Back Pressure
• CW Inlet TemperatureCW Inlet Temperature
• CW Outlet Temperature
• Condensate temperature
• Air-steam mixture temperature
• Water box differential pressurep
• CW flow (Using Pitot Tube)
CenPEEPCenPEEP
NON-CONDENSABLE
Condenser Performance MonitoringNON-CONDENSABLE
OUTLETSTEAM INLET
NON-COND. REMOVAL SYSTEM
FT
P
AIR/VAPOR OUTLET
CW Inlet Temp : 2CW Outlet Temp : 8Condensate Temp: 2
PPP
OUTLET
WW
Condensate Temp: 2Back Pressure: 2CW Waterbox dP: 2 Air/steam Mixture
TWCONDENSATE LEVEL
P
Temp: 2
IRC
UL
AT
ING
A
TE
R O
UT
LE
T
CIR
CU
LA
TIN
G
WA
TE
R IN
LE
T
P
T
DO S
CONDENSATE
(Δ P)(Δ P)
P
CI
WA C W
F
T
F = FLOW MEASUREMENTW = WATER LEVEL MEASUREMENTP = PRESSURE MEASUREMENT
PERF. TEST CONNECTION
SUPPLEMENTAL TEST CONNECTION
T = TEMPERATURE MEASUREMENTDO = DISSOLVED OXYGEN MEASUREMENTS = SALINITY MEASUREMENT
CONDENSATE LEVEL
4 Nos.
TYPICAL CONDENSER INSTRUMENTATIONTYPICAL CONDENSER INSTRUMENTATION
P PRESSURE MEASUREMENT S SALINITY MEASUREMENT
CenPEEPCenPEEPTypical Condenser Calculations
S.NS.N ParameterParameter UnitUnit TestTest
Measured ParametersMeasured Parameters
LoadLoad MWMW PP 21021011 Condenser Pressure Condenser Pressure mm Hgmm Hg PcPc 120.8120.822 CW In TempCW In Temp Deg CDeg C TiTi 34 1634 1622 CW In Temp CW In Temp Deg.CDeg.C TiTi 34.1634.1633 CW Out Temp CW Out Temp Deg.CDeg.C ToTo 45.0945.0944 Condensate Condensate
TemperatureTemperatureDeg.CDeg.C TconTcon 5555
TemperatureTemperature55 Air suction TempAir suction Temp Deg.CDeg.C TaTa 48.9/50.0448.9/50.04
Calculated ParametersCalculated Parameters
66 Saturation TempSaturation Temp Deg.CDeg.C TsatTsat 55.5655.56
77 Expected Back Pressure * Expected Back Pressure * mm Hgmm Hg PxpPxp 8585
* Expected BP to be derived from design BP after applying corrections for Load
and CW inlet temperature during test
CenPEEPCenPEEPTypical Condenser Calculations
S.NS.N ParameterParameter UnitUnit TestTest
88 Design CW Temp RiseDesign CW Temp Rise Deg CDeg C dTdT 101088 Design CW Temp RiseDesign CW Temp Rise Deg.CDeg.C dTdT 1010
99 Design TTDDesign TTD Deg.CDeg.C TTDTTD 2.52.5
1010 Back Pressure due to CW InletBack Pressure due to CW Inlet mm Hgmm Hg Ti+dT+TTDTi+dT+TTD 7979Back Pressure due to CW Inlet Back Pressure due to CW Inlet Temperature Temperature
mm Hgmm Hg Ti dT TTDTi dT TTD 7979
1111 Back Pressure due to CW Flow Back Pressure due to CW Flow mm Hgmm Hg To+TTDTo+TTD 8181
1212 Variation due to CW Inlet Variation due to CW Inlet TemperatureTemperature
mm Hgmm Hg 77--1010 --66
1313 V i ti d t CWV i ti d t CW HH 1111 1010 221313 Variation due to CW Variation due to CW Flow/Heat LoadFlow/Heat Load
mm Hgmm Hg 1111--1010 22
1414 Variation due to air/Dirty Variation due to air/Dirty TubesTubes
mm Hgmm Hg 11--1111 39.839.8TubesTubes
1515 Total variation Total variation mm Hgmm Hg 11--1010 41.841.8
CenPEEPCenPEEP
Condenser Performance MonitoringFactors affecting Condenser BP deviation
T b f li
Co de se e o a ce o to g
• Tube foulingDeposits in tubesMonitor the Waterbox dp
• Air ingress into the systemMonitoring sub cooling of the air steam mixtureAir flow measurementAir flow measurement
• High Condenser heat loadImproper Cycle isolationImproper Cycle isolationHigh MS flow
• Boundary ConditionsBoundary ConditionsCW Inlet temperatureCW Flow
CenPEEPCenPEEPCondenser : Corrective Actions
Fouling: Soft deposits –
1. On Line Tube Cleaning (OLTC)(OLTC)
2. Back washingHard deposits: opportunity l i b
Major Issues:
cleaning by1. High pressure jet2. Hydro-powered Mech
scrappers (CONCO)
• Absolute Pressure measurement for condenser back pressure• Retention of PG Test Points for new units• Trending of Condenser performance parameters
scrappers (CONCO)3. Chemical cleaning
Pro-active action: water treatment of cooling water
• Availability of OLTC• Proper Chemical Treatment• Identification of Air-in-gress Points
Opportunity cleaningAppropriate maintenance for air-in-leak reductionAppropriate maintenance of cooling towerTube leak: tube plugging & replacement
• Opportunity cleaning• Operational optimisation based on calculation
Tube leak: tube plugging & replacement Proper operationProper cycle isolation
CenPEEPCenPEEPCondenser : Use of Multiple Technology
H l i th CRH t i d i liHole in the CRH strainer drain line Hole fixed up using clamp
Temperature difference taken by the IRT Camera around the hole
Benefits of Testing:1. Improvement in condenser vacuum by 16 mm Hg2 Stoppage of one vacuum pump there by reducing in APC
Temperature difference taken by the IRT Camera around the hole
2. Stoppage of one vacuum pump there by reducing in APC and increased operational reliability
3. Unit Heat rate improvement : 32 Kcal / KWHr
CenPEEPCenPEEP
At 480 MW d i ti i C d b k f t dAt 480 MW d i ti i C d b k f t d
Condenser – Chandrapur Unit - 6• At 480 MW, deviation in Condenser back pressure from expected
value, after necessary corrections was around 31 mm Hg• 10 mm Hg is on account of CW flow/heat load and 21 mm Hg is on
account of dirty tube / air ingress loss. It corresponds to a loss in
• At 480 MW, deviation in Condenser back pressure from expectedvalue, after necessary corrections was around 31 mm Hg
• 10 mm Hg is on account of CW flow/heat load and 21 mm Hg is onaccount of dirty tube / air ingress loss. It corresponds to a loss iny g pHeat Rate of about 40 kcal/ kWh
y g pHeat Rate of about 40 kcal/ kWh
Air-ingress & High Heat Load Losses
• The air suction depression was found to be 4.6 deg C which is slightlyhigher than design value (3.5 deg C).
• Two vacuum pumps are in service with air flow of 68 & 28 kg/hrti l
• The air suction depression was found to be 4.6 deg C which is slightlyhigher than design value (3.5 deg C).
• Two vacuum pumps are in service with air flow of 68 & 28 kg/hrti lrespectively.
• The two high energy drain valves found passing (MS line strainer drainvalve before ESV – 2 & Drain before HPCV – 4)
respectively.• The two high energy drain valves found passing (MS line strainer drain
valve before ESV – 2 & Drain before HPCV – 4)
• It is suggested to stop one vacuum pump and observe the condenser back pressure to confirm any air‐ingress in condenser.
• In case of air‐ingress, IRT , Acoustic and Helium leak detection test
• It is suggested to stop one vacuum pump and observe the condenser back pressure to confirm any air‐ingress in condenser.
• In case of air‐ingress, IRT , Acoustic and Helium leak detection testmay be used to identify air‐ingress location.
• It is suggested to provide thermocouples at the down streams location of high energy drain valves for online monitoring of valve passing if any.
may be used to identify air‐ingress location.• It is suggested to provide thermocouples at the down streams location
of high energy drain valves for online monitoring of valve passing if any.
CenPEEPCenPEEPCondenser – Chandrapur Unit - 6
• High solid deposits in condenser tubes. High dissolved solids• High solid deposits in condenser tubes. High dissolved solids
Dirty Tube & CW Flow Losses
g p gand slush observed in Cooling Water due to ash ingress fromnearby Silos
• The Condenser water box dp was 0.88 & 0.76 ksc which is
g p gand slush observed in Cooling Water due to ash ingress fromnearby Silos
• The Condenser water box dp was 0.88 & 0.76 ksc which ishigh as compared to design value of < 0.6 ksc indicatingchoking in condenser tubeshigh as compared to design value of < 0.6 ksc indicatingchoking in condenser tubes
• It is suggested to clean the condenser tubes duringopportunity (deposits need to be analysed) and optimize thechemical dozing in CW system to avoid hard deposits
• It is suggested to clean the condenser tubes duringopportunity (deposits need to be analysed) and optimize thechemical dozing in CW system to avoid hard deposits
• It is suggested to revive the operation of condenser online tubecleaning system (COLTCS) after hard deposits are removedfrom condenserI i l d dd b d
• It is suggested to revive the operation of condenser online tubecleaning system (COLTCS) after hard deposits are removedfrom condenserI i l d dd b d• It is also suggested to carry out eddy current tubes andreplacement of tubes as per recommendation
• It is also suggested to carry out eddy current tubes andreplacement of tubes as per recommendation
CenPEEPCenPEEP
Condenser – Panipat Unit - 5
• At 211 MW, deviation in Condenser back pressure fromexpected value after necessary corrections was around 26
p
expected value, after necessary corrections was around 26mm Hg
• 4 mm Hg is on account of CW flow/heat load and 22 mm Hg is4 mm Hg is on account of CW flow/heat load and 22 mm Hg ison account of dirty tube / air ingress loss. It corresponds to aloss in Heat Rate of about 52 kcal/ kWh
• High dirty tube losses due to deposits in condenser tubes
• The Condenser water box dp was 0.83 & 0.81 ksc which ishigh as compared to design value of < 0.6 ksc indicatingchoking in condenser tubes
High Make p ma be d e to blo do n operation from boiler• High Make up may be due to blow down operation from boiler.
CenPEEPCenPEEPCondenser – Panipat Unit - 5
• It is suggested to clean the condenser tubes duringopportunity and optimize the chemical dozing in CW system toavoid hard deposits
• It is suggested to clean the condenser tubes duringopportunity and optimize the chemical dozing in CW system toavoid hard deposits
• It is suggested to revive the operation of condenser online tubecleaning system (COLTCS) after hard deposits are removedf d
• It is suggested to revive the operation of condenser online tubecleaning system (COLTCS) after hard deposits are removedf dfrom condenser
• It is also suggested to carry out replacement of tubes as perrecommendation of eddy current test and hard deposits
from condenser
• It is also suggested to carry out replacement of tubes as perrecommendation of eddy current test and hard depositsrecommendation of eddy current test and hard deposits.
• It is suggested to keep one ejector in service (which wasdemonstrated during test period)
recommendation of eddy current test and hard deposits.
• It is suggested to keep one ejector in service (which wasdemonstrated during test period)demonstrated during test period)
• The weekly changeover schedule to be practiced to ensure thereliability of the standby ejector
demonstrated during test period)
• The weekly changeover schedule to be practiced to ensure thereliability of the standby ejectory y j
• It is suggested to provide online cation conductivitymeasurement at condensate line
y y j
• It is suggested to provide online cation conductivitymeasurement at condensate line
CenPEEPCenPEEPHP Heater – Chandrapur Unit - 6
• The Temperature rise across HPH – 5A/5B is 39.9/40.1 deg C asagainst design value of 45.1 deg C. There is shortfall in
• The Temperature rise across HPH – 5A/5B is 39.9/40.1 deg C asagainst design value of 45.1 deg C. There is shortfall intemperature rise in HPH 5A/5B by 5 deg C.
• It is observed that DCA of HPH 5A/5B are maintaining 13/12.7 degC i t d i l f 7 d C It i t d t ti i
temperature rise in HPH 5A/5B by 5 deg C.
• It is observed that DCA of HPH 5A/5B are maintaining 13/12.7 degC i t d i l f 7 d C It i t d t ti iC against design value of 7 deg C. It is suggested to optimizeheater level to improve the performance of HPH – 5A/5B.C against design value of 7 deg C. It is suggested to optimizeheater level to improve the performance of HPH – 5A/5B.
• The Temperature rises across HPH – 6A/6B are 44.1/45.4 deg C asagainst design value of 44.3 deg C. There is no shortfall intemperature rise in HPH 6A/6B.
• The Temperature rises across HPH – 6A/6B are 44.1/45.4 deg C asagainst design value of 44.3 deg C. There is no shortfall intemperature rise in HPH 6A/6B.temperature rise in HPH 6A/6B.
• The Final Feed water temperature after HPH‐6 was around 252.87deg C as against the design value of 255.7 deg C. Thus there is
temperature rise in HPH 6A/6B.
• The Final Feed water temperature after HPH‐6 was around 252.87deg C as against the design value of 255.7 deg C. Thus there isg g g gshortfall of around 3 deg C on Final Feed water temperature.
g g g gshortfall of around 3 deg C on Final Feed water temperature.
CenPEEPCenPEEP
• The Temperature rise across HPH 5 is 27 deg C as against• The Temperature rise across HPH 5 is 27 deg C as against
HP Heater – Panipat Unit - 5• The Temperature rise across HPH – 5 is 27 deg C as against
design value of 33 deg C. There is shortfall in temperature rise inHPH 5 by 6 deg C
• The Temperature rise across HPH – 5 is 27 deg C as againstdesign value of 33 deg C. There is shortfall in temperature rise inHPH 5 by 6 deg C
• It is observed that HPH – 5 TTD / DCA are maintaining 13.4/26.0deg C as against design value of 2.9/6.9 deg C
• It is observed that HPH – 5 TTD / DCA are maintaining 13.4/26.0deg C as against design value of 2.9/6.9 deg C
• It is suggested to inspect the HPH – 5 for any parting plate/ bypassvalve passing during opportunity and to optimize heater level toimprove the performance of HPH – 5
• It is suggested to inspect the HPH – 5 for any parting plate/ bypassvalve passing during opportunity and to optimize heater level toimprove the performance of HPH – 5
• The Temperature rises across HPH – 6 are 49 deg C asagainst design value of 43 deg C. There is no shortfall in
• The Temperature rises across HPH – 6 are 49 deg C asagainst design value of 43 deg C. There is no shortfall ing g gtemperature rise in HPH 6
• The Final Feed water temperature after HPH-6 was around 240
g g gtemperature rise in HPH 6
• The Final Feed water temperature after HPH-6 was around 240deg C as against the design value of 240.5 deg Cdeg C as against the design value of 240.5 deg C
CenPEEPCenPEEPCritical Parameters – Turbine Performance
A list of critical parameters that need to be cross checked for accuracyA list of critical parameters that need to be cross checked for accuracyA list of critical parameters that need to be cross checked for accuracyA list of critical parameters that need to be cross checked for accuracy
Sl. No Parameters
1 MS Temperature before Strainer Water leg correction maybe incorporated in onlineWater leg correction maybe incorporated in online2 MS Pressure before Strainer
3 HPT Exhaust Temperature
4 HPT Exhaust Pressure
be incorporated in onlinecritical pressuremeasurements used forperformance assessment
be incorporated in onlinecritical pressuremeasurements used forperformance assessment
5 HRH Temperature before Strainer
6 HRH Pressure before Strainer
7 IPT Exhaust Pressure
8 IPT Exhaust Temperature
9 Condenser Back Pressure
10 Condenser Water box dP10 Condenser Water box dP
11 Feed Water Flow
12 SH/RH Spray Flow
13 CW inlet/o tlet Temperat re13 CW inlet/outlet Temperature
14 Hotwell Temperature
15 All Extraction Pressures & Temperatures
CenPEEPCenPEEPDetermination of CT Performance
Importance of Tower Capability over Effectiveness
Acceptance Test Code for Water- Cooling Towers: CTI ATC - 105.
Effectiveness Capability►► Effectiveness is the ratio of range, to Effectiveness is the ratio of range, to the ideal range, i.e., difference between the ideal range, i.e., difference between
li t i l t t t dli t i l t t t d
►► Capability is as per CTI ATC Capability is as per CTI ATC –– 105 code.105 code.►► Capability is defined as the percentage of water that the tower Capability is defined as the percentage of water that the tower
cooling water inlet temperature and cooling water inlet temperature and ambient wet bulb temperature.ambient wet bulb temperature.
►► Effectiveness is the function of Range Effectiveness is the function of Range and Approach onlyand Approach only
can cool to the design cold water temperature when the can cool to the design cold water temperature when the parameters are all at their design value.parameters are all at their design value.►► Capability is function of inlet air WBT, Range, CW flow, fan Capability is function of inlet air WBT, Range, CW flow, fan power, wind velocity.power, wind velocity.
C bilit M d fl { D i KW f f }0 333and Approach onlyand Approach only
►► Effectiveness = Range / (Range + Effectiveness = Range / (Range + Approach). Approach). ►► Missing Factors:Missing Factors:
► Capability = Measured flow x { Design KW of fans}0.333
Predicted CW flow x {Test KW of Fans}0.333
►► Predicted CW flow is calculated from Manufacturer curves.Predicted CW flow is calculated from Manufacturer curves.►► CW Flow measurement : 3CW Flow measurement : 3--hole hole pitotpitot tube / Ultrasonic flow tube / Ultrasonic flow
tt►► Missing Factors:Missing Factors:•• Inlet air WBT• CW Flow• Wind velocity
F P
metermeter►► Multiple functional variables of independent nature.Multiple functional variables of independent nature.►► Comparability of CT Performance Comparability of CT Performance ►► Single Cell CT Capability as complementary measurement for Single Cell CT Capability as complementary measurement for P f E l tiP f E l ti• Fan Power
Effectiveness is used where ever Effectiveness is used where ever accurate CW Flow measurement is a accurate CW Flow measurement is a constraint.constraint.
Performance EvaluationPerformance Evaluation
42
CenPEEPCenPEEPImpact of Cooling Tower Performance
Cold water temperature expected to improve by 2-3 deg C by improving Tower performance Cold water temperature expected to improve by 2-3 deg C by improving Tower performance
This will improve Condenser Vacuum by 6 – 9 mm Hg This will improve Condenser Vacuum by 6 – 9 mm Hg
Improvement in Heat Rate 12 – 18 kcal/kwhImprovement in Heat Rate 12 – 18 kcal/kwh
Reduction in fuel consumption of the order of 13524 - 20286 tons per year for one 500 MW unitReduction in fuel consumption of the order of 13524 - 20286 tons per year for one 500 MW unityear for one 500 MW unityear for one 500 MW unit
Reduction in CO2 emission of the order of 16905 - 25357 tons per year for one 500 MW unitReduction in CO2 emission of the order of 16905 - 25357 tons per year for one 500 MW unit
Annual savings of Rupees 18.8 – 28.2 million for one 500 MW unitAnnual savings of Rupees 18.8 – 28.2 million for one 500 MW unit
Assumptions : PLF ‐ 80%, GCV ‐ 3500 kcal/kg, Coal cost ‐ Rs. 1400 per ton
43
CenPEEPCenPEEP
25
CT Capability vs HR Loss (200 MW)Impact of Cooling Tower Performance
15
20
25
/kw
hr) No standard curve was
l bl h / f
5
10
15
HR
Lo
ss
(Kc
al/
Seri…available with OEM / CTI for CTCapability vs Heat rate
0
5
96.7 92.5 88.7 85.1 81.8 78.8 76 72.5 70 67.9 65.8 63.8 62Capability (%) 25
CT Capability vs HR (500 MW)
15
20
Kca
l/kw
hr)
Typical curves were developed
5
10
LO
ss in
HR
(K
Series1for 200 MW & 500 MW units toassess the heat rate loss due topoor CT performance
440
5
97.4 95 91.6 88.4 85.4 82.7 80.1 77.6 75.3 73.2 71.1 69.2 67.3 65.6 64Capability (%)
CenPEEPCenPEEPOptimization of CT Performance
Concrete Splash Bars got damaged affecting the heat transfer. Complete splash bars replacement with concrete or PVC type improved the performance.
Choking of Film type fills due to airborne or waterborne dusts or silts. Mechanical cleaning or In-situ cleaning with water improved the performance. Replacement of 17 mm flute by 19 mm flute film packs also reduced choking.
45Nozzles getting choked due to balls coming from OLTC. Screens provided in hot water basin and the OLTC screens have been repaired.
CenPEEPCenPEEP
Falling of nozzles is repeated causing unequal water distribution
Optimization of CT Performance
Falling of nozzles is repeated causing unequal water distribution.
Plant and wild grass growth in Cooling Tower area obstructing the air flow.
Heavy algae growth on splash bars and tower structure affecting the performance.Heavy algae growth on splash bars and tower structure affecting the performance. Proper chemical treatment has improved the performance.
46
Reduced air flow through the tower affecting the performance. Air flow optimization done by adjusting the blade angle based on air flow or Fan power measurement.
CenPEEPCenPEEPOptimization of CT Performance
Inefficient air path that do not pass through the fill i.e. heat transfer zoneInefficient air path that do not pass through the fill i.e. heat transfer zone
Improper Sealing of shaft hole of fan.Improper Sealing of shaft hole of fan.
Improper Sealing of door openings of fan chamber.Improper Sealing of door openings of fan chamber.
Improper Sealing of the fan hub area.Improper Sealing of the fan hub area.
Increased blade tip clearancesIncreased blade tip clearances
Increased drift handled by fan due to damaged or missing drift eliminators. Replacement of drift eliminators has been done.Increased drift handled by fan due to damaged or missing drift eliminators. Replacement of drift eliminators has been done.drift eliminators has been done.drift eliminators has been done.Mud/slime deposit in the hot water basin resulting choking/ damage of nozzles. Cleaning of hot basins has been done. Mud/slime deposit in the hot water basin resulting choking/ damage of nozzles. Cleaning of hot basins has been done. Failure of gear boxes has decreased the availability of Cooling Tower fans i.e. failure of i t / t t h ft f il f b i f il f h l tFailure of gear boxes has decreased the availability of Cooling Tower fans i.e. failure of i t / t t h ft f il f b i f il f h l tinput / output shafts, failure of bearings, failure of worm wheels etc.input / output shafts, failure of bearings, failure of worm wheels etc.Mud or ash deposits in cold water basins. Two stage screening of CW water at CT outlet and proper cleaning of cold water basin have improved the performance.Mud or ash deposits in cold water basins. Two stage screening of CW water at CT outlet and proper cleaning of cold water basin have improved the performance.
Improper Chlorination & Shock dozing to maintain required FRCImproper Chlorination & Shock dozing to maintain required FRC
47
Improper Chlorination & Shock dozing to maintain required FRCImproper Chlorination & Shock dozing to maintain required FRC
Air recirculation from one tower to other Air recirculation from one tower to other
CenPEEPCenPEEPCooling Tower Thermal Performance Testing
Grid setup for Cold Water Temp. measurement
Arrangement of three RTDs in Actual measurement of CWArrangement of three RTDs in a single pipe
Actual measurement of CW temperature at CT outlet channel
48
CenPEEPCenPEEPCooling Tower Thermal Performance Testing
Grid setup for Cold Water Temp. measurement of single cell
Cold water temperature is being measured before it falls on basin
49
CenPEEPCenPEEPCW Flow Measurement
CW Flow measurement using 3 hole pitot tube on
underground CW header
CW Flow measurement using
50
CW Flow measurement using ultrasonic flow meter
CenPEEPCenPEEPSingle Cell Air Flow measurement
The Anemometer is to be tied with rod (light in weight) with length equal to at least thein weight) with length equal to at least the radius of CT fan top portion. The length of cable connected to anemometer should also be more than the radius of CT fan top portionportion.
• Specific Power Consumption of CT Fan willindicate the Fill Condition
The Platform for proper approach for air flow measurement (at the top of
• Use of FRP blades in place of GRP bladesreduce Specific Power consumption
air flow measurement (at the top of the CT fan) with wheels at the bottom for mobility is to be made
51
CenPEEPCenPEEPCooling Tower Survey - Chandrapur
• The condition of splash bars to be assessed and repair/replacement isto be carried out as per condition.
• The capability test of cooling tower should be carried out
• The condition of splash bars to be assessed and repair/replacement isto be carried out as per condition.
• The capability test of cooling tower should be carried out• The airflow measurement at cooling tower fan outlet may be measured
along with fan power measurement. The high specific powerconsumption of CT fan indicates the choking of fills of cooling tower
• Design CW O/L Temp of CT is 34 deg C vis‐à‐vis design CW I/L to
• The airflow measurement at cooling tower fan outlet may be measuredalong with fan power measurement. The high specific powerconsumption of CT fan indicates the choking of fills of cooling tower
• Design CW O/L Temp of CT is 34 deg C vis‐à‐vis design CW I/L toDesign CW O/L Temp of CT is 34 deg C vis à vis design CW I/L tocondenser is 30 deg C
• Impact of 4 deg C increase in CW I/L Temp to Condenser is around 20kcal/kWh in GTCHRO ti f ibl d ti f li t b l d
Design CW O/L Temp of CT is 34 deg C vis à vis design CW I/L tocondenser is 30 deg C
• Impact of 4 deg C increase in CW I/L Temp to Condenser is around 20kcal/kWh in GTCHRO ti f ibl d ti f li t b l d• Options for possible up‐gradation of cooling tower may be exploredincluding upgradation of concrete splash bars to PVC splash bars inconsultation with CT vendors
• Options for possible up‐gradation of cooling tower may be exploredincluding upgradation of concrete splash bars to PVC splash bars inconsultation with CT vendors
CenPEEPCenPEEP
Th bili f li h ld b i d
Cooling Tower Survey - Panipat
• The capability test of cooling tower should be carried outincluding CW flow measurement to assess the performanceof cooling tower and to assess the heat rate loss due tocooling towercooling tower
• The CW flow measurement should be done using anultrasonic flow meter or by a pitot traverse preferably at CTultrasonic flow meter or by a pitot traverse preferably at CTinlet where sufficient straight length is available
• The condition of splash bars & nozzles to be assessed andprepair/replacement is to be carried out as per condition
• It is suggested to optimize the chlorine dozing in CW systemto avoid algae formation in cooling tower
• The cooling tower requires to be cleaned of deposits andl t th d it hi h i th h idit ff tiplant growth around it, which increases the humidity affecting
the performance of the cooling towers