Turnout 229 Installation
24-02-2016
Turnout 229 lifted & placed on sleepers prior to shut
Cut of rail on existing mainline and
removing rails with TLB.
Removal of sleepers on
mainline
Removal of ballast with TLB on
mainline
Compacting ballast bed with Mini-Roller
Place mini rollers on skid rails under turnout
Slide turnout into position
Slide turnout into position
Slide turnout into position
Align turnout with mainline rails
Place ballast from stockpile Using TLB;
Clean excess ballast and tamp by hand
Welding of SRJ Welds
Installation of signal rodding, points machine
and signal pole
Welding of ES Welds
Tamping Machine
1st Train traversing over turnout