ALASKA’S FIRST UNIVERSITY UAF Deferred Maintenance & Renewal February 2010

Upload: deiondre

Post on 24-Feb-2016

50 views

Category:

Documents


2 download

DESCRIPTION

UAF Deferred Maintenance & Renewal. February 2010. Why is Deferred Maintenance a concern to UAF?. Majority of facilities built between 1958 and 1972. The oldest facility, Eielson Building, was built early 1930’s Average age of facilities: Fairbanks campus = 35 years - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

UAF Deferred Maintenance & Renewal

February 2010

Page 2: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Majority of facilities built between 1958 and 1972.The oldest facility, Eielson Building, was built early 1930’sAverage age of facilities:

Fairbanks campus = 35 years Community campus = 25 years

Why is Deferred Maintenance a concern to UAF?

2

Page 3: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

UAF FactsBuildings: 267Campus Sq. Feet: 3,470,408 GSFRoads: 8.28 milesWalkways: 8.81 milesExterior lights: 1,000Exterior stairways: 164Exteriors steps: 1,700Roof: 31 acresParking spaces: 5,137Parking lots: 24 acresUtilidor: 8 miles

Approximately 3 million square feet of campus is heated and powered by UAF's combined heat and power plant

3

Page 4: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

UAF 1969

4

Page 5: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Deferred Renewal:Correction of deficiencies from the cumulative effect of major repair, renewal and replacement, and renovation projects that have not been carried out; special consideration should be given to identification and completion of deferred renewal projects that will result in further deterioration of a facility if not completed. (Regents’ Policy 05.12.020.D)

Maintenance & Repair:Recurrent day-to-day work required to preserve or immediately restore a facility or fixed equipment to such a condition that it can effectively be used for its designated purpose. (Regents’ Policy 05.12.020.F)

Definitions

5

Page 6: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

1920's 1930-1939 1940-1949 1950-1959 1960-1969 1970-1979 1980-1989 1990-1999 2000-Present

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

1,600,000

Year

Sq. F

eet

Campus GrowthBy date facility acquired or construction completion

6

Page 7: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Construction Age Renovation Age

Age GSF** % of Total GSF GSF % of

Total GSF % Change

Less than 10 167,979 5% 695,117 22% 314%

10-25 528,291 17% 607,006 19% 15%

25-50 2,021,589 64% 1,517,356 48% -25%

Over 50 437,146 14% 335,526 11% -23%

3.1 M 100% 3.1 M 100%

Construction Age vs. Renovation Age*

*Renovation Age: • Construction age is reset to newer age when an investment greater than 50% of adjusted value is

invested in the facility.• Construction age reset due to major renovations on the following buildings:

• Brooks Building – 2003• Duckering Building – 2002• Rasmuson Library – 2004• Fine Arts Davis Concert Hall – 2004• Fine Arts Building – 2008• Museum of the North – 2007• Tanana Valley Campus Center - 2008

7

** GSF includes UAF main campus, TVC, and Fairbanks Agricultural & Forestry Experiment Station

Page 8: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Plumbing Roofs Exteriors HVAC0

10

20

30

40

50

60

70

80

90

100

National Average System Life Cycle

UAF's Average System Age

UAF's Maximum System Age

UAF's Minimum System Age

Major Building System

Age

(yea

rs)

Life-cycle of major building systemsBunnell House

-Fine Arts Building Renovation-Bioscience Research & Diagnostic Facility

Page 9: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

November December January $-

$1.00

$2.00

$3.00

$4.00

$5.00

$6.00

$7.00

20082009

Cost

of S

team

/ H

eatin

g De

gree

Day

(HDD

)

TVCC Steam CostsCost savings achieved from exterior replacement at TVCC

-56%change

-63%change

-36%change

Estimated Annual Cost Savings FY10: $43,000

Page 10: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY10

Page 11: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY11

Page 12: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

ADA $1,200,000Campus-Wide Residential $850,000Critical Electrical $5,185,908Elevators $1,355,000Fire Alarms, Sprinklers $876,392Road, Paths & Lights $550,000Sewer $3,507,219Utilities $5,238,000

Other R&R AppropriationsState & Non-State

FY97 – FY10

12

Page 13: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

$1.3 M

$6.3 M

$4.7 M

$14.5 M

$4.4 M

Community Campus R&R AppropriationsState & Non-State

FY97 – FY10

13

Page 14: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Overview of Total UAF R&R AppropriationsFY1997-FY2010

State $133.5 MNon-State $47.4 M

Non-State Category: Federal Receipts $13.4 M

Non-State Category: University Receipts $34 M

TOTAL $180.9 M

Average FY97-FY10 $12.9 M

14

Page 15: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Overview of R&R AppropriationsFY1997-FY2010

74%

19%

7%

StateUniversity ReceiptsFederal Receipts

15

Page 16: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

DRAFT

16

Page 17: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

$1.2M State GF Funding. Installed code compliant fire sprinkler system throughout building.

Irving I Fire Sprinklers

17

Page 18: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

$1.0M State GF. Renewal of 2,500 sf. of space in the Gruening building to serve the new doctoral program in Psychology.

Before

After

Gruening Revitalization for PhD in Psychology Program

18

Page 19: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

$7.7M ($5.7M GF, $2M UA Non-GF) Revitalization, code corrections, and renewal of 19,800 gsf of lab and office space. Funded in 2006, completed in 2008.

Before

After

Arctic Health Laboratory Revitalization Phase 1

19

Page 20: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Wood Stave Pipe

50 year old wood stave pipe - shows only the "bands“. The sewer flow was holding the wood staves up, and once the sewer flow was stopped, they fell to the bottom of the line.

20

Page 21: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Critical Electrical Distribution Phase 1A Vault 1 top slab construction. Vault 1 is located at

the intersection of the new utilidor and the utilidor that goes to the West Ridge

New utilidor (8' x 8') located on the North side of Alumni Drive near the Atkinson Power Plant.

Interior of Vault 2 - boxes and switches will be located on the left hand wall.

21

Page 22: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

TVCC Revitalization Phase 3 Exterior Envelope

Before

AfterBefore

After

TVCC Thermography Photos TVCC Thermography Photos

22

Page 23: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Skarland Hall Shower Repairs

Corrosion at galvanized shower base pans. This results in water leaking to floor below.

Plumbing shower waste line from the use of showers for over 40 years.

23

Page 24: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY24

UAF Contracts AwardedContractors & Design Consultants

2004-2009

*Note:Fairbanks contractors were awarded $54.9M and Fairbanks consultants were awarded $4.2M out of the total contracts awarded to Alaska contractors/consultants.

*Alaska: Contractor/Consultant Out of State: Contractor/Consultant -

10,000,000

20,000,000

30,000,000

40,000,000

50,000,000

60,000,000

70,000,000

ContractorsConsultants

Location

$ Va

lue

Page 25: UAF  Deferred  Maintenance & Renewal

ALASKA’S FIRST UNIVERSITY

Saving & efficiencies from consistent funding

1. Allows a two stage funding of projects.

• Small initial allocations allow design to be performed with follow up allocation funding construction

• Minimizes large appropriations not being used for construction while design is being completed

2. Allows large projects to be funded over two or three years

• Follows the actual cash flow of the projects.

• Campus can see the benefits of R&R funding earlier than waiting until a large project can be designated as worthy to receive all of the R&R funding for one or two years.

3. Potential to minimize volatile construction market pricing. A predictable and consistent volume of work from UAF should contribute to consistent pricing.

25