uk sbs sfs gn slotted stud deflection head detail v-2 · the slotted stud is a detail used to...
TRANSCRIPT
The Kingframe Steel Framing System (SFS) Slotted Stud Deflection Head Detail*
provides both installation and performance benefits offering up to 50% savings compared to
conventional deflection head details.
Introduction
The slotted stud is a detail used to accommodate deflection of the primary structure in the Kingframe SFS. The
concept is shown below.
Figure1: Slotted Stud Detail
Studs are cut to length and punch slotted in the factory for delivery to site. On site, the studs are set out and fixed
at base as for all other deflection details. At head, fixings are installed through both flanges of the head track
through the slots in the studs. This allows for relative deflection of the head track whilst still providing restraint for
the studs.
Ordering: When placing orders for slotted studs, the order must clearly state that slotted studs are required. This
is the responsibility of the installer. For more information please visit: www.kingspanpanels.co.uk/sbs
*Patent applied for
• Feature - Slotted hole detail to top end of SFS stud, visible beneath the base line of the head track for
ease of fixing.
• Function - To provide adequate deflection tolerance to infill wall areas between floors.
• Benefit - Increases the speed of installation, while providing cost and material savings, when compared
to conventional deflection head details.
Site Installation
General Studs: These are studs not forming openings in the SFS system and are generally set out at 600, 400 or
300mm centres across the elevation. The installation sequence is as follows:
1. The head and base tracks are installed
prior to the studs. This is carried out in
accordance with the Kingspan Steel
Building Solutions engineering
specification which indicates the setting
out requirements from grid. The drawings
also specify minimum fixing requirements.
2. Studs must be checked for length prior
to installation to ensure that a deflection
gap is left at head and the studs sit fully
inserted into the base track. The deflection
gap should be taken as 25mm unless
otherwise stated on the Kingspan Steel
Building Solutions drawings. If the studs
are cut to length on site, they must be cut
at base such that the slots remain intact at
head. Figure 2: Standard base track connection
3. Studs are set out at base according to the Kingspan Steel Building Solutions engineering specification. They
are inserted into the base track at marked locations and then plumbed for level.
4. The studs are fixed at base by driving one ø5.5mm x 25mm pan head Tek screw through each flange of the
base track and stud. Care must be taken to ensure that the stud is fully inserted into the track and that the fixings:
• are perpendicular to the flange;
• are fully driven;
• observe a minimum edge distance of 15mm; and,
• are not driven into a slot at base. Figure 3: Fixing location
5. Studs are then re-checked for level prior to fixing at
head.
6. At head, ø5.5mm x 25mm pan head Tek screws are
driven through both flanges of the head track into the slots
which are pre-punched in the studs.
For information concerning installation of Kingframe
SFS, please contact the Kingspan Steel Building
Solutions Technical Team Tel: +44 (0)121 753 7050
www.kingspanpanels.co.uk/sbs