university of nigeria, nsukka · 2015. 9. 16. · university of nigeria, nsukka march, 2012 . ii...
TRANSCRIPT
i
AN APPRAISAL OF INFORMATION AND COMMUNICATION TECHNOLOGY (ICT) APPLICATION
IN NIGERIAN CONSTRUCTION INDUSTRY
BY
UGWUANYI DONALD CHIDIEBERE PG/M. ENGR/09/51317
A DISSERTATION SUBMITED TO THE SCHOOL OF
POSTGRADUATE STUDIES IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE AWARD OF
MASTER OF ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING
FACULTY OF ENGINEERING
UNIVERSITY OF NIGERIA, NSUKKA
MARCH, 2012
ii
CERTIFICATION
This is to certify that Ugwuanyi Donald Chidiebere, a postgraduate student in the
Department of Civil Engineering with registration number PG/M.ENGR/09/51317,
has successfully satisfied the requirements for the research work for the award of
Master of Engineering Degree (M.ENG) in Material and Construction. The work is
original and has not been submitted in part or full for the award in any institution.
--------------------------------------- -----------------------------
Prof. O. O. Ugwu Date
(Project supervisor)
---------------------------- ----------------------------
Prof. J. C. Agunwamba Date
(Project Supervisor)
-------------------------------- ------------------------
Engr. J. C. Ezeokonkwo. Date (Head Civil Engineering Department, UNN)
------------------------------------------ ------------------------
Engr. Prof. J. C. Agunwamba Date (Dean, Faculty of Engineering, UNN)
--------------------------------------- -------------------------
(Dean, Postgraduate School) Date
iii
DEDICATION
Dedicated to God Almighty for given me the grace and courage to execute this
research work. And to all those who love the progress of mankind.
iv
ACKNOWLEDGEMENT
I acknowledge with gratitude my supervisors Engr Prof. O. O. Ugwu and Engr
Prof. J. C. Agunwamba.
I appreciate my father Mr. Joseph M. Ugwuanyi, my mother Mrs Roseline N.
Ugwuanyi and my sister Blessing Ugwuanyi.
I remain indepted to my elder brother, Pharm Francis. O. Ugwuanyi for being a
good brother.
My profound gratitude goes to my friends Bro Michael, Engr.Christian Onu,
Engr Bartholomew Mba, Engr. Mrs Evan Ekoh and Others for their contribution
towards the realization of this research work.
May God bless you all.
v
ABSTRACT
This study is aimed at investigating the level of Information Communication
Technology (ICT) applications in the Nigerian Construction Industry; determine the
prospects with respect to benefits, costs, risks and research and development needs
and to make recommendations on possible interventions. Relevant literature on studies
done in other counties and in Nigeria as well was reviewed. A comprehensive
questionnaire was designed and administered to the respondents (construction industry
professional) for data collection and analysis. A total of 63 respondents to a
questionnaire survey most of which were construction companies provided empirical
data for the analysis. Preliminary findings indicate that Nigerian Construction Industry
has not fully appreciated the value of ICT and the impact of its use on the productivity
value chain management. This delay in ICT uptake in Nigerian construction industry
is limiting advances in construction quality, cost efficiencies and competitiveness of
local firms. However, there are indications that the construction companies in Nigeria
are beginning to realize that they would record substantial financial benefits as a result
of ICT implementation and are flexible in the case of adapting to new technology. The
survey through the questionnaire had limitations as it relates to industry best practice
in the international Arena because of varying applications of construction techniques
and methodologies. Furthermore, the survey was relatively small compare to the
target group of over 2000 industry players. This was mainly due to lack of funding
for the research. However, the study establishes a baseline for future construction
sector ICT studies and further registered the sectoral ICT competitiveness of the
Nigeria construction industry.
vi
TABLE OF CONTENTS
Title page ---------------------------------------------------------------------------------- i
Certification------------------------------------------------------------------------------ ii
Dedication ----------------------------------------------------------------------------------- iii
Acknowledgement ------------------------------------------------------------------------- iv
Abstract -------------------------------------------------------------------------------------- v
Table of content --------------------------------------------------------------------------- vi
List of tables------------------------------------------------------------------------------- viii
List of figures------------------------------------------------------------------------------ ix
1.0 INTRODUCTION --------------------------------------------------------------- 1
1.1 Background of the study---------------------------------------------------------- 1
1.2 Significance of the study---------------------------------------------------------- 2
1.3 Aims and objectives -------------------------------------------------------------- 4
1.4 Scope of the study-------------------------------------------------------------------4
1.5 Statement of problem--------------------------------------------------------------- 5
1.6 Research questions ------------------------------------------------------------ 5
2.0 LITERATURE REVIEW -------------------------------------------------------- 6
2.1 ICT applications in the global construction industry--------------------------- 6
2.2 The development of information communication technology (ICT) in
construction --------------------------------------------------------------------------------- 7
2.3 Current information technologies for the construction sector-------------- 9
2.3.1 Computer Aided Design and Visualization------------------------------------- 10
2.3.2 Building Engineering Applications --------------------------------------- 11
vii
2.3.3 Computer Aided Cost Estimation------------------------------------------ 12
2.3.4 Planning, Scheduling and Site Management----------------------------- 13
2.3.5 Computer Aided Facilities Management---------------------------------- 13
2.3.6 Integration---------------------------------------------------------------------- 14
2.3.7 Business and information Management----------------------------------- 14
2.4 Current communication technologies for the construction sector----- 15
2.5 Review of related work --------------------------------------------------------- 19
3.0 RESEARCH METHODOLOGY ----------------------------------------- 24
3.1 Research method -------------------------------------------------------------- 24
3.2 Area of study-------------------------------------------------------------------- 24
3.3 Sources of data----------------------------------------------------------------- 24
3.4 The questionnaire--------------------------------------------------------------- 25
3.5 Data analyses technique------------------------------------------------------ 26
3.6 Analysis of data----------------------------------------------------------------- 28
4.0 RESULT AND DISCUSSION -------------------------------------------- 30
4.1 Data presentation-------------------------------------------------------------- 30
4.2 Discussion of findings -------------------------------------------------- 50
5.0 SUMMARY, CONCLUSION AND RECOMMENDATION ------- 54
5.1 Summary-------------------------------------------------------------------------- 54
5.2 Conclusion ------------------------------------------------------------------------ 57
5.3 Recommendation ----------------------------------------------------------------- 58
References ---------------------------------------------------------------------------------- 61
Appendix---------------------------------------------------------------------------------- 66
viii
LIST OF TABLES
Table 2.1: Benchmark metrics for key Enablers & Barriers to IT implementation
Table 3.1: Geographical distribution of questionnaire
Table 3.2: Extent of delivery of IT benefits
Table 4.1: Number of employees
Table 4.2: Specific IT department
Table 4.3: Persons responsible for IT planning and expenditure
Table 4.4: Percentage turnover invested on IT
Table 4.5: Organization‟s annual turnover
Table 4.6: Organization type
Table 4.7: Persons responsible for implementing IT projects
Table 4.8: Persons responsible for IT project justification
Table 4.9: Benchmark metrics for IT application areas
Table 4.10: Benchmark metrics for justification factors
Table 4.11: Benchmark metrics for motivation factors
Table 4.12: Benchmark metrics for strategic benefits
Table 4.13: Benchmark metrics for tactical benefits
Table 4.14: Benchmark metrics for operational benefits
Table 4.15: Benchmark for direct cost
Table 4.16: Benchmark for indirect cost
Table 4.17: Benchmark for risk factors
Table 4.18: IT evaluation techniques
Table 4.19: Benchmark metrics for evaluation process
ix
LIST OF FIGURES
Figure 2.1: Construction process and IT application
Figure 2.2: Evolution of internet related communication technologies
Figure 2.3: Research framework – ICT applications, success factors, barriers,
benefits and risks.
Figure 4.1: Response on number of employees
Figure 4.2: Reponses on specific IT department
Figure 4.3: Response on person responsible for IT planning and expenditure
Figure 4.4: Response on percentage of turnover invested on IT
Figure 4.5: Response on originations annual turnover
Figure 4.6: Response on persons responsible for implementing IT projects
Figure 4.7: Response on persons responsible for IT project justification
1
CHAPTER ONE
INTRODUCTION
1.1 BACKGROUND OF THE STUDY
Information and Communication Technology (ICT), also known as information
technology (IT) has radically transformed the way we live, learn, work and play
(Capron 2000). Many companies in the construction industry do not generally appear
to have appreciated the positive changes and advantages that the new technology was
providing to companies in other sectors of the economy. A major construction
process demands heavy exchange of data and information between project participants
on a daily basis (Masqsood et al., 2004). This makes the construction industry one of
the most information-intensive industries, and requires close coordination among a
large number of specialized but interdependent organizations and individuals to
achieve the cost, time, quality and sustainability goals of construction project (Ugwu
et al., 2005). ICT has been shown to be a vital tool in assisting the construction
industry to cope with the increasing complexity of its product and services as well as
the increasing demands of clients and regulators (Betts,1999), and to enhance
construction productivity (Liston et al., 2000). To asses the impact of ICT on
construction in this regard, surveys on the use of ICT in the construction industries of
various countries in different parts of the world have been carried out in recent times.
They include surveys conducted in Canada in 1999 (Rivard, 2000), South Africa in
2000 (Arif & Karam, 2001), Sweden in 2000, Denmark in 2001(Samuelson, 2002),
Malaysia in 2001 (Lim et al, 2002). Turkey in 2001 (Sarshar & Isikdag, 2004) and
Singapore in 2003, (Goh, 2005).
2
While most of these surveys have been carried out in highly developed
European countries and Asian economics, only the South African survey by Arif &
Karam (2001) represent an emerging economy in Africa. Oladapo (2007) has also
carried out a survey into the use of ICT in the Nigeria construction industry. However,
his survey apart from it being limited to South West Nigeria, focused more on the
level of computer literacy of construction industry professionals and mode of
acquisition. Oyediran (2005) studied the awareness and adoption of information and
communication technology (ICT) by Architectural, Engineering and Construction
industry educators in Nigeria. Adejimi and Iyagba (2007) compared E-construction
technology for integrating building processes between Nigeria, Canada and the Nordic
countries. Their study however revealed that the digital divide between Nigeria and
the developed world is closing up as more and more computer facilities are becoming
accessible. However, they also indicated that modern and advanced information
technology facilities such as internet, intra/extranet, virtual reality tools, tele/video
conferencing, construction robots etc are grossly inadequate.
The intent of this research work is to ascertain the level of use of ICT in the
Nigeria construction industry and also to determine the prospects with respect to the
benefits, cost, risks and research and development needs.
1.2 SIGNIFICANCE OF THE STUDY
The construction sector contributes significantly to the GDP of a nation. In
developed countries such as Japan and Korea, construction contributes up to 12 to 14
percent of GDP (Gann, 2000). In the developing countries (according to Dharwadker,
3
1979) investments in construction projects could be as high as 50 to 60 percent of
national budgets.
In Nigeria, the construction industry was the dominant contributor to the
nation‟s GDP in the 1980s, accounting for about 70 percent of the GDP (Planning
committee on the National Construction Policy, 1989). This made the industry very
strategic to Nigeria‟s development efforts. Unfortunately, however, the industry has
been bedeviled by a combination of low demand and consistent low productivity and
poor performance over the years (Manshued et al 1994; Olomolaiye, 1987; Aniekwu,
1995; Okuwoga, 1998; Adeyemi et al, 2005). This has reduced its contribution to the
national economy to a mere 1 percent of the GDP in 2002 (AFDB/OECD, 2004).
The industry is made up of an organized formal sector and an unorganized
informal sector. The formal sector comprises small, medium and large scale according
to their level of capitalization and annual turnover. The few large firms (mostly
foreign), which constitute just about 5 percent of the total number of contractors in the
formal sector, control about 95% of the construction market, giving the small firms
just about 5 percent share of the market. The results of this study will impact the
Nigerian construction industry in the following ways;
Delineate the ICT application areas and the level of adoption.
Highlight the benefits of ICT application in construction at the strategic,
tactical and operational levels.
Serve as a guide to construction organizations in the area of the cost of ICT
adoption (both direct and indirect cost); and the risks involved.
Research and development.
4
1.3 AIMS AND OBJECTIVES
Oladapo (2006) had reported that the construction industry in Nigeria has
during the past few years increased its use of ICT. However, very little is known about
the impacts of the technology on the industry and the prospects for its widespread
penetration of the industry. This is because very few reports exist of research in ICT in
developing countries, including Nigeria (Pamulu & Bhuta, 2004). Against this
background, the objectives of the study are to:
Assess the impact areas and the level of used of ICT by construction
companies in Nigeria.
Evaluate the benefits (strategic, tactical and operational) of adopting ICT in
construction.
Evaluate the cost implication of adopting ICT in construction.
Assess the risk factors.
It also intends to bring to the fore the current direction of development of ICT and to
determine the prospects for research and development needs in the Nigerian
construction industry.
1.4 SCOPE OF THE STUDY
The research covers a review of ICT adoptions and applications by some
construction companies in Nigeria. The companies under study are both foreign
companies (Julius Berger, Costain, RCC, CCECC, Bulletin, Hitech, PW, Setraco etc)
and indigenous (Ferotex, Master holdings, Maloon, Amec, Jukok, Amumco global,
Horoda Ltd, Richgold, Tetratech etc) operating in Nigeria. Appropriate quantitative
techniques were employed in analyzing the data gathered.
5
1.5 STATEMENT OF PROBLEM
Numerous problems are being encountered by the construction companies in Nigeria.
Most of these problems are ICT related. The problems range from low level of ICT adoption
to incompetence in the use of the ICT as follows;
Inefficiency
Low profitability
Low quality production
Poor management of business process
Poor supply chain management
Inability to satisfy client needs
Increased cost of business process
Lack of standardization.
1.6 RESEARCH QUESTIONS
Owing to the numerous problems encountered by construction companies
from non adoption or low adoption of ICT to the problems encountered even when it
is adopted, the following research question were formulated.
What are the ICT application areas and the level of adoption of ICT by
construction companies in Nigeria?
What are the benefits obtained as a result of ICT adoption?
What are the costs implications of ICT adoption?
What are the risk factors of ICT adoption?
Does the benefit derived from ICT implementation justify its investment?
6
CHAPTER TWO
LITERATURE REVIEW
2.1 ICT APPLICATIONS IN THE GLOBAL CONSTRUCTION
INDUSTRY
During the 1980s PCs were only used in few construction companies. Throughout
the 1980s, although most building firms were using computer technology for many of
their core functions such as accounting, wages and salaries, very few of them evolved
formal polices or strategies concerning the use of information and communication
technology.
By the latter part of the 1980s, about eight years after the introduction of
reliable PC equipment, some companies had reached a situation in which their staff on
many of their larger projects were experiencing the advantages of the new technology
through the use of planning, drawing, spreadsheet and word-processing software
packages.
Today, a large number of software packages are available to all the disciplines
of the construction team at every stage of the construction process. They provide
support for a broad range of activities such as computer aided design and drafting,
building visualization, design appraisal, project management, information storage and
retrieval, cost estimation, structural analysis, on-site management, facilities
management etc.
7
2.2 THE DEVELOPMENT OF INFORMATION AND COMMUNICATION
TECHNOLOGY IN CONSTRUCTION
The use of information and communication technologies (ICTs) in the
construction industry is generating new opportunities for collaboration, coordination
and information exchange among organizations that work on a construction project.
Complex technical systems do not evolve fully formed, but rather as localized
developments. In the development of automated systems for transfer and
transformation of materials, this unbalanced evolution leads to the problem of “Islands
of automation”, where highly automated materials flow is mixed with completely
manual ones. The same problems exist in the development of computerized
information systems. The development of computing technology has meant that tools
for analysis involving data manipulation have tended to develop earliest and in
isolation. These tools show the enormous strengths of computer in the rapid analysis
of complex data sets-analysis which is frequently impossible if manually attempted.
Thus standalone applications dependent on numerical analysis, ranging from finite
element analysis to critical path analysis, had been developed by the 1960s.
Information flows between these types of applications continued to use traditional
information technologies such as the paper-based engineering drawing.
During, the 1970s, a new form of graphical manipulation was developed to aid
the creation of engineering drawings-computer aided design (CAD). Again, the output
from these systems largely relied on traditional technologies for communication
between different applications. The construction industry was at the forefront of these
developments. By the fourteenth century scaled technical drawing, probably the most
8
important information technology of the last millennium after the printed book itself
were well established for use on religious and royal building projects.
During the 1970s, large public sector projects-usually relying on extensive
standardization and prefabrication offered the opportunity to develop CAD system.
However, the demise of the large public sector construction programmes which have
been essential to the development of ICT applications in every industrial sector meant
that this initial momentum was lost (Howard 1998).
The 1980s saw the development of the personal computer (PC) which
dramatically reduced the cost of computing power, and enabled a much wider
diffusion of computers within the industry, while the processing power of computers
continued to grow exponentially. Most importantly, site offices could now be
equipped with computers. The development of communication technologies has taken
an independent path. In comparison with computer technologies, developments were
earlier and more profound. The telegraph and, more importantly, the telephone,
greatly improved communication capabilities. The fax and photocopier are more
recent innovations which have had a significant impact. Nonetheless, these
communication technologies did not allow any further manipulation of the received
data. It was not until 1970s that they began to be connected to computers to provide
integrated systems for the direct communication of information between computer
systems. The development of Local and Wide Area Networks (LANs and WANs)
proceeded steadily, but interconnectivity between computers was transformed by the
breathless diffusion of the internet during the 1990s.
9
It is this rapid development of the interconnection between communication and
information technologies that has both opened up tremendous new opportunities and
posed new technical challenges.
2.3 CURRENT INFORMATION TECHNOLOGIES FOR THE
CONSTRUCTION SECTOR.
Information technologies or software application are available to support most
aspects of a construction project. These applications can be grouped into the following
categories (Sun & Howard, 2004):
Computer Aided Design and Visualization
Building Engineering Applications
Computer Aided cost Estimation
Planning, Scheduling, site Management
Computer Aided Facilities Management
Integration
Business and Information Management
Figure 2.1 is a roadmap showing where and when these applications are being
used along the construction process. The main purpose of the diagram is to
indicate the main application areas for the existing discrete software package in
the construction supply chain.
10
Figure 2.1: Construction Process and IT application (adapted from, Life
Cycle management system for construction. 2000)
2.3.1 Computer Aided Design and Visualization
Computer Aided Design (CAD) software is widely used by design professionals
and AutoCAD has the largest share of the CAD market (Howard 1998). Other popular
CAD software includes Microstation, ArchiCAD, MiniCAD, FastCAD, Autodesk
Revit etc. These CAD programs have largely replaced the traditional drawing board at
the production information stage. The basic function of CAD tools is allowing the user
to build up drawings by manipulating lines, circles, rectangles and texts interactively
on the screen. The clear advantage of CAD software is the ability to allow „editing‟,
which means delete, move, copy, rotate, scale, mirror etc. Furthermore, since the
11
drawing can be saved at any stage, the designers are able to keep various versions of
the building layout for later study. Once the geometrical information of the building
design is stored in a CAD package, different views of the building can easily be
produced. Visualization and animation systems, like 3D studio, can produce photo-
realistic, static and moving images, so that the clients can view the final appearance of
the building at the design stage. Virtual reality technology even allows the user to
interact with the design model and experience the building in simulated reality
settings, including simulated construction sequence.
2.3.2 Building Engineering Applications
Nowadays, construction industry clients have ever higher expectations. They
want their buildings to look good, to be safe, to provide comfortable living
environment for their occupants, to consume less energy in operations, etc. The ever
more complex demands on the building design process have given rise to the need for
a new approach to building engineering design based on computer software. Once a
building is constructed, it is very costly to correct any design defects. It is, therefore,
important to simulate accurately the building performance at the design stage so that
problems can be identified and solved. Over the years, a variety of methods and
algorithms have been developed to predict building performance in thermal, lighting,
acoustics, and structural aspects. Because of the complex and tedious calculation that
involve these simulations, it was nearly impossible to carry them out before
computers. During the last two decades a range of building engineering applications
have been developed for energy analysis, HVAC design, structural analysis, lighting -
simulation, etc. The benefit of these applications is that they allow designers to
12
evaluate alternative design. Examples of this software are: ATEAN from carrier, and
CARGASW from climasoft, that offer comprehensive range of software options for
climatic energy design; CALCULUX from lighting and building services design,
CYPE INGENIEROS S.A. for structural design, cosmos for finite element analysis,
DUCTSIZE from Elite software for electricity and water net design.
2.3.3 Computer Aided Cost Estimation
Controlling cost is one of the most important requirements during a
construction project. To achieve this, contractors and subcontractors must first make
accurate cost estimation. Rigorous project accounting must then be used to control the
spending. Today, there are sophisticated computer software packages, such as Esti-
Mate, Manifest, FBS-Estimator, and Presto from soft, GO from star, ITEC and ARQ
from AM2, which allow project managers to make estimations and to keep track of
project spending. Other software can help to measure, count, compute and tabulate
quantities, lengths, areas, volumes etc, of objects found in plans and specifications.
Furthermore, most cost estimating programs can be integrated with databases of cost
for labour, materials and equipment. The advantage is that cost data do not need to re-
entered, thus improving the clearity in estimating and avoiding errors. Computer
based estimation of costs archives and retrieves large volumes of resource, cost and
productivity information, makes fast and accurate calculations and presents results in
an organized, neat and consistent manner.
2.3.4 Planning, Scheduling and Site Management
Construction works require careful planning and skilful management of human
and physical resources. Computer system can assist on-site managers to plan ahead,
13
evaluate different options and adopt and execute the most efficient construction
operation. Besides the widespread use of planning packages such as Microsoft project,
primavera, Power project, etc, to plan and schedule detailed construction activities,
some applications like Job Master, ICON, GEST, and Presto Control, are designed to
log and track internal processes during the construction phase. Site operation
simulation programs can emulate what happens in a real construction site by
representing workers, machines, and materials, and computing the cycle of each step
taking into consideration many uncertain factors (Paulson 1995).
2.3.5 Computer Aided Facilities Management
Facilities management is a discipline that emerged in the early 1980s. It is
based on the operation, maintenance and impact of the building operations on the life
cycle cost. The available software for facilities management is a combination of CAD
and database management system. Special routines enable blocking and stacking
studies to be carried out to explore different layouts or to reflect organizational
changes. Databases are the most important part of facilities management software. It
holds data from people and their services so that when they move, their services can
follow them. ITE (Inspeccion Tecnica de Edificios), for example, is a tool that makes
it possible to create a report of the state of the building.
2.3.6. Integration
From the first software applications many different tools were developed. They
use their own data formats, which are not compatible with each other. As a result, data
cannot be electronically exchanged between them. In recent years, there is an
increasing awareness of the need for integrated construction processes and many are
14
investigating related issues. During the last two decades, advances in object oriented
programming, database systems and product data modeling technologies have
provided a solid platform for integration. Data standards are being developed first by
the international standards being developed by the international standards
organizations (STEP), and then by the International Alliance for Interoperability
(IFC). At present, these standards are still evolving. An integrated project database
that cover the whole life cycle of construction projects remains a future prospect.
2.3.7 Business and Information Management
The construction process is an information intensive one during which a huge
amount of information is generated and consumed by all the professional involved.
The common type of information includes site survey, cost analysis, design drawing,
documents, correspondence, fax, computer files or e-mails. Electronic Document
Management System can create an environment in which disparate forms of
information can be linked together, within the context of a project or organization, to
achieve easy access and control. All the previous tools and software for cost
estimating, planning, scheduling, etc, are generated in a specific stage of the project.
Sometimes this information is updated, modified, consulted, etc, at any moment of the
project. Consequently, Document Management Systems are tools that comprise
whatever information throughout the life cycle of the project, from the conception of
the need to the maintenance. Electronic Document Management Systems are
applications that can be linked to Web Based Project Management Systems to
improve communication among partners and between them and the management of
15
the project. In addition, Web Based Project Management Systems have other
functionalities like project coordination, scheduling, etc.
2.4 CURRENT COMMUNICATION TECHNOLOGIES FOR THE
CONSTRUCTION SECTOR
Communication technologies are the technologies dealing with the
transmission of information. They support the process by which information is
exchanged. Figure 2.2 shows the evolution of some information technologies (main
communication technologies) in construction. They are positioned according to their
complexity (Vertical axis) and construction specifics (horizontal axis). It is noted that
the most specific services tend to use or rely upon the generic ones, and that the most
complex service tends to integrate simpler ones.
The first services were generic and included networked file archives, e-mail
communications and text-based group conferencing. The web provided a much
friendlier navigation and presentation of the files on remote machines. It was at the
time when first construction related content appeared. Out of the first 100 websites
only two were related to construction. The first construction specific services used the
web to publish information such as scientific papers, building codes, product
specifications, etc. the next generation services were starting to use the internet as a
collaboration platform for the companies involved in a construction project (Turk &
Cerovsek, 2008).
16
Figure 2.2: Evolution of Internet Related Communication Technologies
(Adapted from, Life Cycle management system for construction. 2000)
Since 1998, however, construction has been following trends of general service
supplied on the internet. A business model of the providers of various kind of internet
related software (e.g. For managing mailing lists, discussion forums, help desk, photo
albums, etc) has evolved from the sale of software for the users to install on their
servers, to the offering of a service on their website, that offers the same functionality
to the end user. In the construction context there are now dozens of companies
providing collaboration tools such as document managing tools, project coordination
and scheduling.
E-Business/Commerce: This is modern business methodology that addresses
the needs of organization to cut cost while improving the quality of products and
services and increasing the speed of service delivery. It can be viewed from multiple
17
dimensions including communications and business processes. From communication
perspective, E-commerce is the electronic delivery of services and information. From
a business process perspectives, it is the automation of business transactions and
process.
The main E-commerce application areas include
Company/product promotion
E-procurement through search engines and Web directories
Project management/online project collaboration.
Future trends in E-commerce include
M-Commerce: Technology has now matured and makes it possible to connect,
mobile devices such as mobile phones, and Personal Digital- Assistants
(PDAs). Thus current researches are investigating the opportunities in mobile
electronic commerce or M-commerce in infrastructure delivery and mega
project management.
Wireless Communication (Bluetooth Technology): Bluetooth is a form of
wireless technology that removes the need for cables connecting computer
equipments. This should enable remote connectivity and distributed
collaborative working.
Agent–Based Procurement of Goods and Services: Agent and Multi-Agent
Systems (MAS) have been deployed in collaborative working to automate
some tasks. In this situation, artificial agents representing their owners,
execute delegated functions on their owner‟s behalf. Several potential
application areas in construction include: Collaborative design,(Ugwu et al
1999; 2003; 2005;) negotiation, claims management, e-procurement, ( Ren et
18
al 2005) information searching and retrieval, supply chain coordination, and
standards processing (Udeaja et al 2005). Such state- of-the art applications
mark fundamental shift from software-as-tool to software-as-assistant.
Anumba et al (2005) discussed details of applications of intelligent agents and
multi-agent systems in construction.
WWW & Web Portals: This is the major trend in collaborative working with
several applications in several sectors. It is now part of routine daily lives for
business process improvement especially in developed economies that can
provide the supporting infrastructure. This has also resulted in a bipolar digital
divide (BDD) between rich and poor nations with significant impacts on ICT
applications in the construction sector in different countries.
Peer-to-peer (P2P) computing: Peer-to-peer is a communication model in which
each party has the same capabilities and either party can initiate a communication
session. In some cases, peer-to-peer communication is implemented by giving each
communication node both sever and client capabilities. In recent usage, peer-to-
peer has come to describe applications in which users can use the internet to
exchange files with each other directly or through a mediating server [URL2P2P].
One potential advantage of P2P is that it could be used by corporations to enable
their employees to share files through the internet network, without the expense
involved in maintaining a centralized server. This means that employees (or more
specifically their machines) are able to exchange business information with each
other directly on a peer-to-peer basis. The technology has potential huge
applications in integrating seamlessly, the construction supply chain, starting from
19
product order receipt and configuration to manufacture and delivery (Ugwu
2005b).
Service-Oriented Architectures (SOA) & Web services: Service-oriented
Architecture (SOA) takes the WWW and Enterprise Integration Application (EIA)
solutions to the next level. At the basic level, it involves mapping business
processes to objects that are wrapped in software systems and not visible to the
users. The objects are dedicated to solving specific business process problems e.g.
retrieve document, upload document, send message, search for information,
compute sustainability index, etc. These functions are called services because they
enable each application to call up other‟s services. The application‟s services are
made available through the web interface, and are broadcast on WWW as web
services. Consequently, any application can call up the services as long as the
applications all adhere to defined protocols for service request and delivery. SOA
applications rely on eXtensible Mark-up language (XML) to address
interoperability problems. Additional information on the application of SOA
concepts to sustainability appraisal and knowledge management can be found in
(Ugwu 2005b).
2.5 REVIEW OF RELATED WORK
Studies have been carried out to determine the critical success factors, the
barriers and enablers to ICT application in construction projects to harness the
technology and streamline business process in emerging economies. The general
problem addressed is what are the critical success factors, (CSFs), and barriers that
impact the implementation, adoption, usage and diffusion of ICT in the construction
20
industry? Such a framework should enable identification of at-risk IT projects during
the early stages of project evaluation and facilitate formulation of appropriate risk
mitigation measures. Ugwu et al (2006) discuss further details on the research.
There is an abundance of documented literature that describes various projects in
construction, which focus on IT-driven construction process innovation. However,
while the majority of the research focuses on developing improved products, process
and computational models, there is a noticeable dearth of research that focuses on
issues and factors that impinge on the uptake of IT systems in construction, including
stakeholders‟ perceived benefits cost and risks of IT systems in practice Ugwu et al
(2006). An adequate understanding of perceived and expected benefits would
facilitate an unambiguous understanding of user requirements and subsequent
translation into system functional specification during development. IT
implementation in construction results in significant changes and potential
improvements in design and management processes within the organization. It is
therefore necessary to investigate critical success factors as well as inhibiting factors.
Some research in mainstream computing and software development have investigated
the socio-technical aspects of systems development and application in organization
(Barrow, 1999), Bingi et al (1999), Holland and light (1999), Bourque et al (1999),
Hondeshel and Watson (1990), Watson et al (1991), Watson and Frolic (1993). Other
researches reported in literature have focused on investigating the various basic and
niche application areas of IT in construction. Such studies have been conducted in
Singapore (Hua, 2005), Norway (Samuelsom, 2002) Scandinavia (Howard et al 1998),
New Zealand (Doherty 1997), UK (Egbu & Botterill (2002)), (Ugwu et al 1999). The
21
proliferation of research on IT barometers in construction on national and cross
national basis indicates increasing interest to investigate socio-technical aspects of
software development and use in the Architectural, Engineering and Construction
(AEC) sector.
The research model was designed to investigate various related questions
outlined. The research instrument includes a combination of structured open-ended
interviews, questionnaires and evidence based research used for further validation.
Several research methods were adopted in the multistage research. The first stage used
a combination of pilot questionnaire survey, structured interviews with senior
personnel of leading construction organizations, and deductive analysis techniques for
interview protocol analysis (Ugwu et al, 2003a). The second stage used a
questionnaire-based survey and case-study/evidence-based research techniques.
Figure 2.3: Research framework – ICT applications, success factors, barriers,
benefits and risks. (Source: Ugwu et al 2007)
22
Fig.2.3 shows the research model used to investigate the various related questions.
The research framework was broad and covered different dimensions of information
and communication technology (ICT) in architecture, engineering and construction
(AEC) sector. These include; current applications of IT in construction, success and
inhibiting factors, perceptions of IT application areas in solving construction
problems, and organization strategic directions in IT application.
Ugwu et al (2006, 2007), discussed detailed analysis of the results of research
and case study projects that identified the key enablers and barriers to ICT application
in construction projects in Hong Kong, and then posited several lessons for emerging
economies of which the Nigerian construction industry is one of them. Table 4.23
shows the rankings using the computed IT- benchmark indices. From the table, the top
ten ranks in descending order are: Cost of development, Top management support
(leadership), Appropriate hardware technology, Appropriate software (off the shelf),
Ease of use, Development team knowledge and understanding of construction
processes &business environment, Clear definition & understanding of user
requirement, Clear communication of IT objectives to management, End-user
involvement, and IT competence of in-house team. Further analysis of the responses
reveals that contractors ranked “Ease of use” and “Change management at
organizational level” as the first and second most significant success factors
respectively, while the whole group of respondents collectively rank these as 5 and 6
respectively. Ease of use is a major issue that system developers must address in any
ICT project to minimize training requirements and the associated operational cost.
Change management is a wider issue to address by the management to ensure that
adequate measures are taken to cushion the impact on the work force, often
engendered by change in business process that result from introducing ICT systems.
Table 4.23 summarizes their Hong Kong construction industry studies.
23
Table 2.1: Benchmark metrics of key Enablers & Barriers to IT implementation
(Source: Ugwu et al 2006, 2007)
24
CHAPTER THREE
RESEARCH METHODOLOGY
3.1 RESEARCH METHOD
A research method in the form of questionnaire was adopted for the purpose of
generating data. The work reviewed and analyzed the various aspects of ICT-
applications in construction. The themes and issues covered in the research include:
ICT application areas, strategic, tactical and operational benefits, ICT implementation
costs (both direct and indirect costs) and ICT implementation risks. Data analyzed
were both descriptive and quantitative. The result was used to establish rankings of the
benchmark indices among various issues.
3.2 AREA OF STUDY
The research work studied ICT applications in construction companies in
Nigeria. To this effect, effort was made for the study to cover construction companies
domiciled in each of the six geo-political zones in the country. This is to make the
work as representative as possible.
3.3 SOURCES OF DATA
To realize the objectives of this study, the following two main types of data
were employed; primary and secondary data.
a. Primary Data: Primary data were derived from questionnaire, which were
distributed to engineers and managers of different construction companies. This
was designed to gather valid and reliable information through the response of
the interviewee to a planned sequence of questions. The structured interview
was to gather valid and reliable response while the unstructured interview was
used in desiring more precise generalization.
25
b. Secondary Data: Secondary data were collected mainly from review of
published and unpublished materials including relevant textbooks journals and
magazines.
3.4 THE QUESTIONNAIRE
A comprehensive questionnaire was designed and administered to the
respondents for data collection and analysis. The questionnaire used a five-point
Likert-type scale to measure a range of issues from “Not at all” to “Very large extent”
as the case may be. The questions posed in the questionnaire were structured to limit a
range of responses and still be sufficient. For authenticity and data integrity, the
questionnaire was administered directly to the engineers and managers of the different
construction companies.
The questionnaire was delivered to the respondent by hand in August, through
the researcher himself. It was collected from the respondents after a time interval,
(November) by the researcher. This is to enable the respondents have a sufficient time
for a better appreciation of the questionnaire.
26
Table 3.1: Geographical distribution of questionnaire
Geo-Political Zone States Visited No Distributed No Returned
South West Lagos 50 15
South South Akwa Ibom, Rivers
And Cross Rives
35 10
South East Enugu 59 17
North West Kaduna Kano 23 6
North East Adamawa 15 3
North Central Abuja 44 12
TOTAL 226 63
Source: primary data
3.5 DATA ANALYSES TECHNIQUE
3.5.1: Descriptive Statistics and t-test
In analyzing the data collected, basic statistics such as simple percentages,
charts and tables were used. The analyses also used a simple statistical analysis in
which the rankings of the benchmark indices of various issues were compared. This
benchmark statistic took the view of all respondents into consideration with further
sub-group analysis. The data generated were analyzed using mean item scores to
generate ranking of the variables of interest.
27
In calculating the IT benchmark index ( ,biIT ), all the numerical scores for the
constructs where transformed to indices to assess their relative rankings (Love and
Irani 2004). The ,biIT was calculated using the following formula:
biIT 10,
biITAN
w (1)
Where
biIT IT benchmark index.
w = weighting given to each factor by the respondent, which in this ranged from 1
to 5 where 1 is “not at all” and 5 is “a very large extent”.
A = the highest weighting, which is 5, and
N = the total number of respondents.
A statistical test of difference of means called the t-test was also used in testing
the hypotheses. The t-test is a parametric statistical tool used to determine whether
two means are significantly different at a chosen level of significance. The significant
agreement or otherwise with the notion being tested was determined by adopting the
mid-point value of the index (that is 3) as the hypothesized mean (Coakes and Steed,
2001). This implies that any value significantly different from this unsure value was
assumed to be either positive or negative to the notion being tested (Pullin and Haidar,
2003). The t-test statistic for a one-sample t-test is given by;
ns
xt o
/
(2)
Where;
o = specified mean value
x = sample mean
28
S = sample standard deviation
n = sample size.
All tests were carried out at 0.05 level of significance and (n-1) degrees of freedom.
The decision rule criterion stipulates that if the calculated t-test value is grater than the
tabulated t-test value (see appendix B) the null hypothesis is rejected, and the
alternative hypothesis is accepted. On the other hand, if the calculated t-test value is
less than the tabulated t-test value, null hypothesis is accepted and the alternative
hypothesis is rejected at the chosen level of significance.
3.6 ANALYSIS OF DATA
TEST OF HYPOTHESIS
Table 3.2: Extent of Delivery of IT Benefits
Response Very large extent Moderate extent Not at all
Weight 5 4 3 2 1
Frequency 19 20 21 2 1
Source: primary data
OH o : [The benefit derived from adopting IT does not justify its investment]
OH :1 [The benefits derived from adopting IT justify its investment]
We test this hypothesis by using the response from table 3.2.
Mean 857.3x
29
Standard deviation = 94.0
Sample size 63
Specified mean 3o
Substituting in t-test formula,
202.763948.0
3857.3
ns
xt o
202.7calt
From the t-test table in appendix C at 0.05 level of significance and n – 1 degree of
freedom, we have the value of 1.999
tablet = 1.999
Decision Rule:-
Since the calculated t-test value of 7.202 is greater than the tabulated t-test value of
1.999, the null hypothesis is rejected and the alternative accepted.
Conclusion:-
It can, therefore, be concluded that the benefits derived from adopting IT for enhanced
business process justifies its investment.
30
CHAPTER FOUR
RESULT AND DISCUSSION
4.1 RESULT PRESENTATION
From the 226 questionnaires that were distributed to construction
companies, a total of 63 completed questionnaires were returned after follow-up
communications with the organizations and professionals the questionnaires were
given to. This gave a response rate of 27%. The response is very low as, according to
Ellhag and Boussabaine (1999) and Idrus and Newman (2002) a response rate of 30%
is good enough in construction studies. This is attributed to lack of adequate funding
for the research and restrictions to fieldwork in the northern part of Nigeria due to
current crisis. The results of the geographical distribution of questionnaire are
presented in, Table 3.1.
4.1.1 Number of Employees in Respondents Office.
As indicated in question 1 of the questionnaire, the responses on the number of
people currently employed in the respondent‟s offices are shown figure 4.1.
31
The result shows that 13% of the respondents have less than 10 people employed in
their offices, 40% employed from 11 to 30, 23% employed from 31 to 50, 10%
employed from 51 to 100 and 14% employ from 101 to 250. This indicates that the
respondents include small, medium, and large-sized organizations.
Table 4.1: Number of Employees
Item < 10 11 – 30 31 – 50 51 - 100 101 - 250
Number 8 25 15 6 9
Percentage 13 40 23 10 14
Source: primary data
4.1.2 Job Title
The questionnaire indicated that the respondents are professionals in the
construction industry with job titles; project manager, project Engineer; Civil
Engineer, Site Engineer, Construction Manager, Consulting Engineer, QA/QC
Engineer, Structural Engineer, Batch plant Engineer, Project Supervisor, Contract
Engineer, Geotechnical Engineer, Draftsman, and Quantity Surveyor.
32
4.13 IT Department
Figure 4.2 above elicited response on whether organization has specific IT
Department. 80% admitted that they have a specific IT department, 20% had no
specific IT department and 0% for no response. Most of the organizations surveyed
make use of computers as a tool for enhanced business process which is in line with
Oldaapo (2006) which indicated that the construction industry in Nigeria has during
the past few years increased it‟s use of ICT. The response also agreed with Oladapo
(2007), which indicated that most of the respondents were optimistic about the future
of ICT applications in the Nigerian construction industry. However, this high rate of
positive response to specific IT department is attributed to organization sampling. This
is because most of the respondents‟ organizations are foreign firms. A more reliable
result may be achieved by eliciting response from a larger sample with more local
firms.
33
Table 4.2 Response to Specific IT Department
Specific IT Department Yes No No Response
Number 50 13 0
Percentage 80 20 0
Source: primary data
4.1.4 Person Responsible for IT planning and Expenditure
Figure 4.3 above elicited response of the interviewees on persons responsible for IT
planning and expenditure. 65% of the respondents indicated that an IT specialist is
responsible for IT planning and expenditure in their organization, 15% indicated that
persons other than IT specialist are responsible for IT planning and expenditure and
20% of the respondents had nobody responsible. This implies that most of the
respondents‟ organizations understand the potential benefits of ICT applications as a
tool for improved business process in the construction sector and hence employ
34
experts for IT planning and expenditure. However, a reasonable number of the
respondents have applied ICT in their business process.
Table. 4.3: Person Responsible for IT Planning and Expenditure
Item IT Specialist Others None
Response 40 10 13
Percentage 65 15 20
Source: primary data
4.1.5 Percentage of Turnover Invested on IT
From figure 4.4 and table 4.4, 31% of the respondents invest between 1-5% and 6-
10% of turnover on IT, 27% invest 11-20% of turnover, 10% invest more than 20% of
turnover and non of the respondents invest less than 1% of turnover on IT. About 60%
does not invest more than 10% of turnover on IT, this represents a low rate of
investment on IT.
35
Table 4.4: Percentage of Turnover Invested in IT
Item < 1% 1 – 5% 6 – 10% 11 – 20% >20%
Response 0 20 20 17 6
% Response 0 31 31 27 10
Source: primary data
4.1. 6 Organization Annual Turnover
From figure 4.5 and Table 4.5, 39% of the organization has an annual turnover of
more than N250M, 31% has annual turnover of N101-250M, 17% has annual turnover
of N51-100M, 6% has annual turnover of N11-50M, 5% has annual turnover of N1-
10M and non of the organizations has an annual turnover of less than N1M. About
70% of the respondents‟ organizations record an annual turnover of up to N250M.
This indicates that most of the organizations are medium to large-scale organizations.
36
Table 4.5: Organization Annual Turnover
Item <N1M N1–10M N11-50M N51-100M N101-250M >250M
Response 0 5 4 11 20
23
Percent 0 7 6 17 31 39
Source: primary data
4.1.7 Organization Type
The respondent‟s organization types were mostly contractor representing about 96%
of response.
Table 4.6: Organization Type
Organization Type Contractor Others
Response 61 2
% Response 96 4
Source: primary data
4.1.8 Person responsible for implementing IT projects
37
From fig 4.6 above and table 4.7, 84% of the respondents admitted that an IT
specialist is responsible for implementing IT projects in their organizations, 10% of
the respondents for a Non IT Business Manager, 4% of the respondents admitted that
both are responsible and no response for others. Most of the organizations had an IT
Specialist responsible for implementing IT projects. This indicates that a majority of
the organizations appreciates the role of ICT in the construction value chain by
employing IT experts to be in charge of implementing IT projects.
Table 4.7: Person Responsible for implementing IT Projects
Response IT Specialist Non-IT Bus. Manager Both Others
Number 53 6 4 0
Percentage 84 10 6 0
Source: primary data
4.1.9 Person responsible for IT Project Justification
38
From fig 4.7 above and table 4.8, 68% of the respondents admitted that IT Department
management is responsible for IT project justification, 32% of the respondents for
Business Management and none for others. This is also a confirmation of the previous
finding that the respondent‟s organizations agree that ICT has the potential to improve
construction quality, cost efficiency and competitiveness of their organizations.
Table 4.8: Person Responsible for IT Project Justification
Response IT Dept. Management Bus. Management Others
Number 43 20 0
Percentage 68 32 0
Source: primary data
4.1.10 Issues Concerning Organization’s Approach to Implementing IT
Question 22 of the questionnaire elicited response on the most serious issues
concerning organization‟s approach to implementing IT. The most prominent issues
are cost issues such as “cost of software and hardware”, “maintenance cost”, “training
cost”, “operating cost”, and “issued regarding training and retraining of IT staff”.
“Others are issues of budgetary allocation on IT”, “consultancy and frequent policies
on updating”. This agrees with Oladapo (2007) which stressed that among the major
constraints to the use of ICT are “insufficient/irregular power supply” and “high cost
of ICT software and hardware”.
39
4.1.11 IT Application Areas
Table 4.9: Benchmark Metrics for IT Application Areas
Application Areas ITabi Rank
Engineering design 0.946 1
Communication (e.g. e-mail) 0.942 2
Construction project program 0.882 3
Cost and supply management 0.844 4
Information exchange (e.g. Drawings) 0.761 5
Web based project management (e.g. Extranet, Intranet ) 0.526 6
3D design visualization 0.473 7
E - tendering 0.469 8
Geographical information system (GIS) 0.425 9
ITabi – application benchmark index Source: primary data
Table 4.9 shows that Engineering design, Communication (e.g. e-mail) and
construction project program, are among the most common application areas and thus
are ranked 1, 2, and 3 respectively. However, advanced ICT applications (web based
project management system, 3D design visualization, e – tendering and Geographical
information systems) are not common in the local construction industry. This is in line
the findings of Oladapo (2007), which stated that the main uses of ICT in the industry
are word processing, internet communications, costing and work scheduling.
40
4.1.12 Organization Justification Process for implementing IT.
Table 4.10: Benchmark metrics for justification factors
Justification Process ITjbi Rank
Limited managerial and technical knowledge 0.758 1
A multiplicity of justification and implementation paths 0.755 2
Unable to identify and manage the scope of IT\IT related costs 0.736 3
Limited company resources and resistance to technology
related changes
0.733
4
The need to show quick financial returns with little risk 0,723 5
Lack of strategic vision in long term 0.720 6
Inability to account for the “full” business benefits 0.714 7
Inability to select an appropriate IT appraisal technique 0.711 8
Unable to identify financial benefits 0.704 9
Reluctance of employees to adapt to new technology 0.641 10
ITjbi – justification benchmark index Source: primary data
Table 4.10 shows the extent of the problems encountered during the justification
process for IT implementation. “Limited managerial and technical knowledge,” “A
multiplicity of justification and implementation paths” and “Unable to identify and
manage the scope of IT/IT related costs” were among the most common problems and
thus were ranked 1, 2, and 3 respectively. However the least rank problems namely;
“Unable to identify financial benefits” and “Reluctance of employees to adapt to new
technology” which ranked 9 and 10 respectively indicate that most of the
organizations agreed that they would record substantial financial benefits as a result of
41
IT implementation for enhanced business process and are flexible in the case of
emergence of new technology.
4.1.13 Organization Motivation for Implement IT
Table 4.11: Benchmark metrics for motivation to implement IT.
Motivation Factors ITmbi Rank
Improve service quality 0.815 1
Improve the performance (ie. effectiveness) of business processes 0.787 2
Improve profitability 0.787 2
Improve the organization competitive advantage 0.780 4
Improve productivity (ie cost efficiency) of business process 0.777 5
Pressure from rivals who are implementing IT 0.746 6
Support the strategic direction of the organization 0.723 7
Improve market share 0.695 8
Seemed like the thing to do at the time 0.679 9
ITmbi – motivation benchmark index Source: primary data
Table 4.11 shows the ranking of the benchmark metrics of motivation factors to IT
implementation for an enhanced business process. “Improved service quality,”
“improved the performance (ie effectiveness) of business process” and “improved
profitability” are the major motivators and thus ranked 1, 2, and 3 respectively.
“Improved service quality” which ranked highest indicates that the respondents
indentified it as a major motivation for adopting ICT for enhanced business process in
construction organizations. Also, the least ranked items; “Improve market share” and
42
“Seemed like the thing to do at the time” shows that the construction organizations are
genuinely motivated to adopt ICT and not just because they think that it is in vogue.
4.1.14 Organization strategic benefits of IT implementation.
Table 4.12: Benchmark metrics for strategic benefits
Strategic Benefits ITsbi Rank
Enhanced competitive advantage 0.752 1
Improved customer/ supplier satisfaction 0.746 2
Improved organizational and process flexibility 0.717 3
Improved growth and success 0.704 4
Reduced marketing costs 0.692 5
Leader in new technology 0.692 6
Improve customer/ supplier relations 0.660 7
Market leadership 0.657 8
Improved market share 0.609 9
ITsbi – strategic benchmark index Source: primary data
Table 4.12 itemizes the strategic benefits of IT implementation and their
corresponding ranks. “Enhanced competitive advantage,” “improved customer/
supplier satisfaction” and “improved organization and process flexibility” were the
major strategic benefits for the respondents‟ organization and thus were ranked 1, 2
and 3 respectively. “Enhanced competitive advantage” which ranked highest shows
that most of the organizations realized that organization that implement ICT exhibits
some level of competitive edge over those that are yet to implement ICT. “Improved
customer/supplier satisfaction” which ranked a close second indicates that
organizations that implements ICT are more able to satisfy the ever increasing needs
43
of clients. However the least ranked items; “Market leadership” and “Improved
market share” indicate that organizations that adopt ICT do not automatically become
market leaders, skills are still required to harness the benefits of ICT.
4.1.15 Organization Tactical Benefits of IT Implementation.
Table 4.13: Benchmark Metrics for Tactical Benefits.
Tactical Benefits ITtbi Rank
Improved service quality 0.803 1
Improved contract administration 0.796 2
Improve teamwork 0.780 3
Improved response to changes 0.765 4
Improved integration with other business functions
(e.g. Estimating and on-site operations)
0.733
5
Reduced time to prepare cost plans 0.714 6
Reduced time to compile tenders 0.695 7
Promotes pro-active culture 0.688 8
Increased planning times 0.644 9
ITtbi – tactical benchmark index Source: primary data
Table 4.13 itemizes the tactical benefits of IT implementation and their corresponding
ranks. “Improved service quality,” “Improved contract administration” and
“Improved teamwork” were the major tactical benefits for the respondent‟s
organization and thus ranked 1, 2 and 3 respectively. This is an indication that most
organizations record marked increase in construction quality as a result of ICT
adoption. However the least ranked item “Increased planning times” was well placed
because organizations should record a reduction in planning times as a result of ICT
adoption.
44
4.1.16 Organization Operational Benefit of IT Implementation
Table 4.14: Benchmark Metrics for Operational Benefits
Operational Benefits ITobi Rank
Improved data management 0.831 1
Improved communication 0.819 2
Improved ability to exchange data 0.787 3
Improved decision making 0.746 4
Improved quality of output 0.742 5
Reduced paperwork 0.704 6
Improved control of cash-flow 0.647 7
Reduced lead times to financial reporting 0.641 8
Improved forecasting and control 0.638 9
Improved response time to queries (e.g. Request for
information)
0.609
10
Reduced rework 0.587 11
Reduced labour cost 0.587 11
ITobi – Operational benchmark index Source: primary data
In table 4.14 above, items such “improved data management,” “improved
communication” and “improved ability to exchange data” are the major operational
benefits of IT implementation for the respondents organizations which ranked 1, 2 and
3 respectively. This is an indication that the top ranked operational benefits are
essentially communication-centric support service that does not require much tacit
knowledge in business processing. This agreed with the views of Ugwu (2010). The
result generally shows that there is increased flexibility in management and transfer of
information as a result of ICT implementation.
45
4.1.17 Direct Cost of IT Implementation
Table 4.15: Benchmark for Direct Cost
Direct Costs ITdci Rank
Hardware accessories 0.749 1
Overheads (e. g. Running costs and consumables) 0.749 1
Increase in processing power 0.739 3
Maintenance cost 0.733 4
Consultancy support 0.707 5
Installation Engineers 0.701 6
Training cost 0.688 7
Networking security (e.g. firewalls) 0.666 8
Networking hardware and software 0.657 9
ITdci – Direct cost index Source: primary data
Table 4.15 itemizes the direct cost of IT implementation and their corresponding ranks
“Hardware accessories,” “Overheads,” “Increase in processing cost” and
“Maintenance cost” were the major direct cost items and thus, ranked 1, 2, 3 and 4
respectively. “Hardware accessories” which ranked highest indicates the high cost of
ICT infrastructure support system. Also, “Overheads” which ranked a close second
indicate a high operating cost which is one of the major hindrances to ICT
implementation due to such problems as lack of power supply which is a serious issue
in Nigeria.
46
4.1.18 Indirect Cost of IT Implementation
Table 4.16: Benchmark for Indirect Cost
Indirect Cost ITidi Rank
Employee training 0.739 1
Management time 0.730 2
Cost of ownership (e.g. system support, troubleshooting
cost)
0.720
3
Management and staff resources (e.g. Integrating
computerize administration and control into work
practices)
0.707
4
Management effort and dedication to exploring the
potential of the system
0.701
5
Employee motivation (eg. Maintaining employees interest
in computer aided tasks)
0.692
6
Employee time in detailing, amending and approving the
computerization
0.682
7
Changes in salaries as a result of improved employee
flexibility.
0.657 8
Strains on resources 0.644 9
Organizational restructuring 0.634 10
Staff turnover (e.g. Increases in interview costs and
training costs)
0.631
11
Productivity losses 0.596 12
ITidi – Indirect cost index Source: primary data
Table 4.16 itemizes the indirect cost of IT implementation and their corresponding
ranks. “Employee training,” “management time” and “cost of ownership” were the
major indirect cost items with ranks 1, 2, and 3 respectively. “Employee training”
which ranked highest is a confirmation of the organizations response to most serious
issues concerning organization‟s approach to implementing IT of which issues
regarding training and retraining of IT staff is one of them. However, issues of “staff
turnover” and “productivity losses” ranked the least among the indirect cost issues
with 11 and 12 respectively.
47
4.1.19 Risks Associated With IT Implementation
Table 4.17: Benchmark for Risk Factors
Risk Factors ITrbi Rank
Capital outlay with no guarantee of likely returns. 0.698 1
Uncertainty about how to measure potential benefits 0.695 2
Lack of information systems infrastructure support for
the IT investment
0.592
3
Maintenance cost 0.673 4
Uncertainty about how to measure the costs involved 0.669 5
Minimal IT expertise 0.660 6
Security issues 0.660 7
Theft of software and hardware 0.647 8
Reluctance of employees to adapt to change 0.09 9
Training expenses on staff that leave the organization 0.606 10
Technical uncertainty and lack of knowledge 0.593 11
ITrbi – Risk benchmark index Source: primary data
Table 4.17 Shows that “capital outlay with no guarantee of likely returns,”
“uncertainty about how to measure potential benefits” and “lack of information
system infrastructure support for the IT investment” were the major risk factors
associated with IT use and implementation. Among the least ranked risk factors for
the organizations is “Theft of software and hardware” which shows that theft of ICT
infrastructure is mild. “Reluctance of employees to adapt to change” which ranked 9th
, shows that the employees are not really reluctant to change but are rather optimistic
to the changes brought about by ICT implementation. “Training expenses on staff that
48
leave the organization” which ranked 10th
, shows that staff are not in the habit of
leaving their organizations after receiving training from them. This should help to
internalize the acquired knowledge.
4.1.20 Organization IT investment Evaluation Techniques.
Table 4.18: IT Evaluation Techniques
Evaluation Techniques ITetbi Rank
Return on investment (RO1) 0.904 1
Net present value (NPV) 0.847 2
Discounted cash flow and internal rate of return 0.844 3
Payback period 0.758 4
Profitability index 0.679 5
Present worth 0.666 6
Employee training 0.638 7
ITetbi – Evaluation benchmark index
Table 4.18 itemizes the IT evaluation techniques employed by the respondent‟s
organization with their corresponding ranks. “Return on investment (ROI),” “Net
present value (NPV)” and “Discounted cash flow and internal rate of return” were the
major evaluation techniques and thus ranked 1, 2 and 3 respectively. Employee
training which ranked 7th
was not a preferred evaluation technique for the most of the
construction organizations.
49
4.1.21 Organization IT Evaluation Process
Table 4.19: Benchmark Metrics for Evaluation Process.
Evaluation Process ITepbi Rank
Prepare a benefits delivery plan before approval 0.752 1
Plan organizational changes associated with the implementation
of IT during system design
0.730
2
Prepare a benefit delivery plan during the Implementation of IT 0.726 3
Prepare a benefits delivery plan during system design 0.711 4
Plan organizational changes associated with the implementation
of IT before approval.
0.701
5
Conduct reviews during the implementation of IT 0.688 6
Use it to develop future process 0.685 7
Plan organizational changes associated with the implementation
of IT during implementation
0.685
8
Plan organizational changes associated with the implementation
of IT once the technology is implemented
0.676
9
Prepare a benefits delivery plan once the technology is
implemented
0.676
10
Conduct post – implementation reviews 0.673 11
Uncertainty about how to measure the costs involved 0.644 12
ITepbi – Evaluation process benchmark index.
Table 4.19 shows that the following evaluation process items, “Prepare a benefit
delivery plan before approval,” “Plan organization changes associated with the
implementation of IT during system design,” and “Prepare a benefits delivery plan
during the implementation of IT” were among the most common with ranks, 1, 2 and
3 respectively
50
4.2 DISCUSSION OF FINDINGS
Compared with the conventional usage of IT such as design and programming
software, the application of advanced IT tools such as “web based project
management,” “3D design visualization,” “E-tendering” and “Geographical
information system (GIS)” have not yet had a good penetration into the
Nigerian construction industry. This finding is in line with the contribution of
Oyediran (2005) which stressed that the construction industry has been
sluggish in adoption of ICT despite the amenability of its process to IT
operation. Also, Oladapo (2007) stated that in Nigeria, the use of computers is
still at the rudimentary stage where a basic application like word processing is
the most prominent, while the other countries have advanced to the stage of
application to more technical business functions.
The foremost problems encountered during the justification process for IT
implementation are “limited managerial and technical knowledge” and “ A
multiplicity of justification and implementation paths”. However the
organizations indicated that they would record substantial financial benefits as
a result of IT implementation and are flexible in the case of adapting to new
technology.
The major motivations for the implementation of IT by the construction
organizations are “improve services quality,” “improve the performance of
business process” and improve profitability.” This is an indication that the
construction organizations are genuinely motivated to ICT and not just because
they think it is in vogue.
51
The core strategic benefits of IT implementation are “Enhanced competitive
advantage,” “improved customer/supplier satisfaction” and “improved
organizational and process flexibility.” The respondent‟s organizations
affirmed that organizations that implement ICT are more competitive than
those that are yet to implement ICT. There is also the tendency to satisfy client
needs as a result of ICT implementation. However, organizations that adopt
ICT do not automatically become the market leader as skills are still required to
harness the full benefits of ICT.
The core tactical benefits of IT implementation as indicated by the
respondent‟s organization are “improved service quality,” “improved contract
administration,” and “improved teamwork.” Most of the organizations record
marked increase in construction quality as a result of ICT adoption. Also,
organizations should record a reduction in planning times as a result of ICT
implementation.
The core operational benefits of IT implementation as indicated by the
respondent‟s organization are “improved data management,” “improved
communication” and “improve ability to exchange data.” The top ranked
operational benefits are essentially communication-centric support service that
does not require much tacit knowledge in business processing. This is in line
with Ugwu (2010)
The major direct cost implications of IT implementation are “hardware
accessories,” “overhead” and “increase in processing power.” High cost of ICT
infrastructure support system is a major issue as regards direct cost implication
52
of ICT adoption. Operating cost such as cost of power supply is one of the
major hindrances to ICT adoption in Nigerian construction industry.
The major indirect cost implications of IT implementation are “Employee
training,” “management time” and “cost of ownership.” Cost training and
retraining of IT staff is among the most serious issues concerning
organization‟s approach to implementing IT.
The major risks factors associated with IT implementation as indicated by the
respondent organizations are “capital outlay with no guarantee of likely
returns,” “uncertainty about how to measure potential benefits” and “lack of
information system infrastructure support for the IT investment.” However,
theft of ICT infrastructure is mild and employees are not really reluctant to
adapt to changes brought about as a result of ICT implementation. Also
employees are not in the habit of leaving their organizations after receiving
quality training from them. This encourages continuity and internalization of
acquired knowledge.
The most common IT investment evaluation techniques as indicated by the
respondent organizations are “Return on investment (ROI),” “Net present value
(NPV)”, “Discounted cash flow and internal rate of return.” However,
“Employee training” was not a preferred evaluation technique for most of the
construction organization.
The major organization‟s IT evaluation process are “prepare a benefits delivery
plan before approval,” “plan organizational changes associated with the
implementation of IT during system design” and “prepare a benefits delivery
plan during the implementation of IT.”
53
The benefits derived from implementing IT for enhanced business process
justifies its investment.
The adoption and implementation of ICT by the Nigerian construction industry is
being hindered by high cost of ICT infrastructure support system and high operating
cost mainly due to lack of power supply which is a serious issue in Nigeria This is in
line with (AFDB/OECD, 2004) which stressed that inadequate and erratic power
supply is way ahead of the list of obstacles as electricity supply in Nigeria has been
unreliable, leading to high production cost for companies, which are forced to procure
and run their own power generating facilities.
The study also indicated that organization record marked increase in
construction quality and a reduction in planning times as a result of ICT adoption.
These perceived benefits arguably translates into greater efficiency and seem to
support Toole‟s (2003) view that ICT is one of the most powerful process innovation
for increasing operational efficiency. However, this does not automatically mean that
these benefits have been very well achieved, but it highlights the need for the
necessary ICT infrastructure that would facilitate achieving such benefits in
construction organizations. Cases of theft of hardware and software are mild in the
Nigerian construction industry and employees are not reluctant to change but are
rather optimistic to changes brought about as a result of ICT implementation. Also
from Table 4.18, the findings show that employees are not in the habit of leaving their
organizations after receiving quality ICT training from them, which will encourage
continuity and also internalize the knowledge acquired.
54
CHAPTER FIVE
SUMMARY, CONCLUSIONS AND RECOMMENDATIONS
5.1 SUMMARY
This research work studied the level of use and adoption of ICT in the Nigerian
construction industry and also determined the prospects with respect to the benefits,
costs, and risks in the areas of research and development. It covered a review of ICT
adoptions and applications by some construction companies in Nigeria.
A comprehensive questionnaire was designed and administered to the
respondents for data collection and analysis. The questionnaire instrument was already
validated and used for other related international studies in Hong Kong and Auatralia
(Ugwu et al 2006,2007). In analyzing the data collected, distinctive statistical tools
such as simple percentages, charts and tables were used. The analysis also used a
simple statistical analysis in which the rankings of the benchmark indices of various
issues were compared. A statistical test of difference of means called the t-test was
also used in testing the hypothesis at a chosen level of significance.
The study shows that Information Communication Technology (ICT) has not
yet had a good penetration in the Nigerian construction industry. Compared with the
conventional IT usage such as design and programming software, the advanced ICT
applications such as “web based project management,” “3D design visualization,” “e-
tendering and “Geographical information systems” are not common in the local
construction industry.
The interviewees attributed this to several factors such as the fact that benefits
they bring to a company are difficult to quantify, cost of hardware and software,
55
operating cost, issues regarding training and retraining etc. The responses elicited
were also used to generate ranking of various items on issues of benefits, cost, risks
and others. However, the interviewees indicated that the benefits derived as a result of
IT adoption is sufficient to justify its investment.
Among the organization‟s justification process for implementing ICT, “limited
managerial and technical knowledge” and “A multiplicity of justification paths” were
ranked highest by the respondents. As a result, the organizations were optimistic that
they would record substantial benefits from implementing ICT.
A key motivator for implementing ICT was “improved service quality” and
was ranked first by the respondents. “improved performance ( i.e effectiveness) of
business process” was ranked second by the respondents.
Among the most common strategic benefits of implementing ICT is “enhanced
competitive advantage” which was ranked first by the organizations. “improved
customer/supplier satisfaction” was ranked a close second by the respondents. At the
tactical level, the most common benefits was “improved service quality” which ranked
first, “improved contract administration” and “improved teamwork” were ranked
second and third respectively. At the operational level, the study shows that the
organizations considered “improved data management” as a significant benefit they
have achieved to a large extent and thus, ranked it first. “improved communication”
and “improved ability to exchange data” were ranked second and third respectively.
The comparison of benchmark metrics for the direct cost of implementing ICT
show that “hardware accessories” and “overheads” were considered by the
respondents to be the most significant issues to a large extent and were both ranked
56
first by the respondents. “increase in processing power” was ranked a close second.
The rankings of the various issues of indirect cost implications of ICT adoption shows
that “employee training” was ranked first by the respondents. “management time” and
“cost of ownership” were ranked second and third respectively.
A comparison of risk factors associated with ICT implementation show that
“capital outlay with no guarantee of likely returns” was the most significant risk and
was ranked first by the organizations. “uncertainty about how to measure the potential
benefits” was ranked a close second, “lack of information system infrastructure
support for the IT investment” was ranked third.
The ICT evaluation technique mostly employed by the respondent
organizations to a large extent was “return on investment (ROI)” which was ranked
first. “net present value (NPV)” and “discounted cash flow and internal rate of return”
were ranked second and third respectively.
Among various issues regarding organizations‟ ICT evaluation process,
“prepare a benefits delivery plan before approval” was the most significant from the
study and was ranked first by the respondents. “plan organizational changes associated
with the implementation of IT during system design” and “prepare a benefit delivery
plan during the implementation of IT” were ranked second and third respectively.
The result of the t-test carried out on the null hypothesis that “the benefits
derived from adopting IT does not justify its investment” favoured the opposite. It can
therefore, be stated that the benefits derived from implementing ICT for enhanced
construction quality, cost efficiency and competitiveness justifies it‟s investment
decision.
57
The research based on a case study project discussed a wide range of
enablers and barriers to ICT application in the construction sector. Analyses of recent
applications provide basic experimental foundations and theoretical underpinning to
understand challenges that face ICT development and diffusion in emerging
economies. Like most other sectors, successful, uptake and diffusion of ICT systems
is predicated on a set of critical factors. Some of these factors may depend on specific
organization attributes (e.g. size). The study identified some fundamental critical
success factors that would act as enabler for successful implementation of ICT
projects in construction.
5.2 CONCLUSION
This study concludes that the Nigerian construction industry players have not
appreciated the uptake and utilization of ICT to global competitive thresholds. This
delay in uptake is limiting advances in construction quality, cost efficiencies and
competitiveness of local construction firms. The industry must become more flexible
in its business conduct and encourage ICT uptake and utilization. However most of
the organizations were optimistic that they would record significant benefits from
implementing ICT. The future prospects of ICT implementation by the Nigerian
construction industry is encouraging as most construction organizations are genuinely
motivated to adopt ICT.
According to the survey, the organization affirmed that implementing ICT
gives a competitive edge over those that are yet to implement it. Organizations will be
58
more able to satisfy client needs as a result of ICT adoption, however, skills are
needed to harness the full benefit of ICT.
The adoption and implementation of ICT by the Nigerian construction industry
is being hindered by high cost of ICT infrastructure support system and high operating
cost mainly due to lack of power supply which is a serious issue in Nigeria.There is
also the issue of cost of training and retraining of IT staff which is one of the most
serious issues concerning organization approach to implementing ICT.
It is expected that these results will guide policy makers in Nigeria to identify
where to concentrate their efforts to promote increased use of ICT, especially in the
construction industry. Also, for the construction in a developing country such as
Nigeria to maximize the returns on investment in ICT, it must go beyond basic
application like design and programming software to more technical business
allocations like, e-business, electronic data management, e-tendering, web base
project management, and other advanced ICT applications.
It is also hoped that this study will be repeated in the next few years to measure
any quantitative and qualitative improvements in ICT diffusion in the Nigerian
construction industry.
5.3 RECOMMENDATIONS
In a quest to increase uptake and utilization of ICTs in the Nigerian
construction sector, this study is proposing the following interventions:
Introduce rigorous sectoral ICT skills training, networking and advocacy for
involvement of industry stakeholders.
59
Engage in more regional collaboration for information exchange on
competitive bidding processes and sustainable local contractor development
programs.
Lobby for increase in Government funding for training due to the absence of
legal framework for skills development fund and perceived donor fatigue in
capacity building support.
Improve industry – schools links (e.g. construction clubs).
Increase opportunities for more private trainers to participate in ICT training
and credentialing.
Improving the attractiveness of the industry through rigorous advocacy for
construction sector Research and Development (R & Ds).
It is expected that Research and Development (R & D) will continue to drive progress
in several aspects. Examples of areas that R & D should address in the short and
medium terms are:
1. Education (teaching and learning)
2. Interoperability and systems integration
3. User requirement capture
4. Application of complexity and chaos theories as an underpinning framework to
investigate the socio-technical dimension of ICT implementation
5. Adoption and diffusion in construction organizations
6. Standardization e.g. using eXtensible Markup Language (XML) solutions.
As a general recommendation, there is need for further research on this subject to
elicit more evidence from a larger sample.
60
Finally, in line with attaining the national vision of becoming one of the twenty
largest economics in the world by the year 2020, a viable construction sector which
utilizes ICTs to global competitive threshold is an imperative. If the construction
companies in Nigeria must hold to theirs as regards construction and also be
competitive in bidding for international construction contracts, the ICT paradigm is
inevitable.
61
REFERENCES
Adejimi A. and Iyagba R. O. (2007): Comparing E-Construction Technology for
Integrating Building Processes between Nigeria, Canada and the Nordic
Countries.
African Development Bank/Organization for Economic Cooperation and
Development (2004): African Economic Outlook.
Anumba C.J et al, Ugwu O.O et al & Ren. Z et al (Eds), (2005) – Agents and Multi-
Agent Systems in Construction.
Arif A.A and Karam A.H. (2001): Architectural Practice and their use of IT in
the Western Cape Province, South Africa, Journal of Information
Technology in Construction, 6,17-34, at http://www.itcom.org/2001/2
Barrow. C. (1999): Implementing an Executive Information System Seven
Steps for Success, Journal of Information System Management, 7 (2), p.
41-46.
Betts M. (1999): Strategic Management of IT in Constitution, Blackwell,
Oxford, UK.
Bingi P, Sharma M. K, Godle. J.K. (1999): Critical Issues Affecting and ERP
Implementation, Journal of Information System Management 16(3), p. 7-
14.
Bourque P, Dupuis R, Abran A, More J. W, Tripp L. (1999): The Guide to
Software Engineering Body of Knowledge, IEEE Software 16 (6), 1999,
p. 35-44.
Capron K. (2000): Information Technologies Applications for Construction
p.37-38.
Coakes S. J. and Steed L. G. (2001): SPSS; Analysis Without Anguish, John
Wiley sons, Milton, UK.
Dharwadker P. P (1979): Management in Construction Industry, Oxford and I.
B. H. Publishing Co., New Delhi.
Doherty J. M. (1997): A Survey of Computer use in the New Zealand Building
and Construction Industry. Electronic Journal of Information Technology
in Construction – Itcon vol 2 (http://www.litecon.org/1994).
62
Egbu C. O., Botterill K. (2002): Information Technologies for Knowledge
Management; Their Use and Effectiveness, Electronic Journal of
Information Technology in Construction –Itcon vol 7
(http://www.litcon.org/2002/81).
Elhag T. M. S. and Bousssbaine A. H. (1999): Evaluation of construction costs
and Time Attributes. Procedings of The 15th
ARCOM Conference. Vol.2,
Liverpool John Mores University, P. 473-800.
Francis M. and Ruben N. (2010): Information and Communication Technology
Uptake and Utilization in the Zambian Construction Industry.
Gann D. M. (2000): Building Innovation: Complex Constructs in a Changing World.
Thomas Telford Publishing, London.
Goh B.H (2005): IT Barometer 2003: Survey of the Singapore Construction
Industry and a Comparism of Results, Journal of Information Technolog
in Contruction, 10, p. 1-13 at http://www.itcon.org/2005/1
Henshaw N. (2010): Optimization of Material Inventory in Nigeria Construction
Company. M.ENGR Project Report, Department of Civil Engineering,
University of Nigeria, Nsukka, Nigeria.
Houdeshel G. and Waton H. J. (1990): The Management Information and
Decision Support (MIDS) System at lock head Georgia, MIS Quaterly,
11 (1), P. 127-140
Howard R, Kiviniem A, Samulason O. (1998): Surveys of IT in the Contruction
Industry and Expernince of IT Barometer in Scandinavia Electronic
Journal of Information Technology in Construction –ITCON Vol 3
(http//www./itcon.org/1989/41)
Hua G. B. (2005): IT Barometer 2003. Survey of the Singapore Construction
Industry and a Comparison of Results. Electronic Journal of Information
Technology in Construction- ITcon Vol 10
(http://www.litcon.org/2005/1)
Idrus A. B. and Newman J. B (2002). Construction Related Fact ors Influencing
Choice of Concrete Floor Systems, Construction Management and
Economics, 20 p. 13-19.
63
Life Cycle Document Management System for Construction (2010): Information
Technologies Applications for Construction. P-37 – 46.
Life Cycle Management System for contruction (1995) Information
Technologies Applications for Construction P. 42-43.
Lim Y.M et al, Rashid A.Z., Ang C.N., Wong C.Y. and Wongs .L. (2002): A
Survey of Internet Usage I the Malausian Construction Industry, Journal
of Information Technology in Construction, p.7,259-269, at
http://www.itcon.org/2002/17.
Liston K.M et al, Fischer M.A. and Kunz.J.C. (2000): Designing and evaluating
visualization techniques for construction planning, Proceedings of the 8th
international conferences on Computing in Civil and Building
Engineering (ICCBE-VIII) Stanford University, Stanford, CA, p. 1293-
3000.
Love. P. E. D, Irani Z (2004): An Exploratory Study of Information Technology
Evaluation and Benefits Management Practices of SMEs in the
Construction Industry, Information and Management, 42, p. 227-242.
Masqsood T et al, Walker D.H.T. and Finnegan A.D. (2004): An Investigation
of ICT Diffusion in an Australian Construction Company using SSM,
Proceedings of The Joint CIB-W107 and CIB0TG23 Symposium on
Globalisation and Constitution, Bangkok, Thailand, p. 485-495.
Oladapo A.A. (2007): An Investigation into the Use of ICT in Nigerian
Construction Industry.
Oladapo A. A. (2006): The Impact of ICT on Professional Practice in the
Nigerian construction Industry, The Electronic Journal of Information
System in Developing Countries, 2 24(2) , P. 1-19.
Oyediran O. S. (2005): Awareness and Adoption of Information and
Communication Technology (ICT) by Architectural, Engineering and
Construction (ACC) Industry Educations in Nigeria.
Oyediran O. S. and Odusami K. T. (2004): Whither the Nigerian Quantity
Surveyors in the Information Technology Age.
Pamulu M. S. and Bhuta .C. (2004): Strategic Management of Information
Technology in Construction Industry; the Indonesian Perspectives, Proceedings
of the Joint CIB-W107 and CIB- TG23 Symposium on Globalization and
Construction, Bangkok, Thailand. Pg. 521-530.
64
Paulson J. (1995): Life Cycle Document Management System for Construction.
Information Technology Applications for Construction. Pg. 42-43.
Pullin L. and Haidar A. (2003). Managerial Values in Local Government-
Victoria, Australia, The International Journal of Public Sector
Management, 16 (4), p286-302.
Rivard H. (2000): A Survey on the Impact of Information Technology in the
Canadian Architecture, Engineering and Construction Industry, Journal of
Information Technologyin construction 5, p.37-56, at
http://www.item.org/2003/3
Samuelson O. (2002): IT-Barometer 2000-The use of IT in the Nordic
Construction Industry. Journal of Information Technology in
Construtction, 7, p.1-26 at http: //www.itcon.org/2002/1
Sarshar M. and Isikdag, U. (2004): A Survey of ICT use in the Turkish
Construction Industry, Engineering, Construction and Architectural
Managemtn, 119(4), p. 238-247.
Sun S.M., and Howard R. (2004): Information Technology Applications for
Construction, Life Cycle Document Management System for
Construction. P.39-44
The Financial Time Ltd – Malaysia (2007): ICT to enhance Productivity,
Efficiency in Construction Industry.
Toole T. M. (2003): Information Technology Innovation; A View of Large.
Constructors, Proceedings of the ASCE Const ruction Research Congress,
Honolulu, Hawaii, at
http://www.facstaff.bucknell.edu/ttoole/ITinnovation.doc.
Ugwu O.O et al, and Nwoji C.U. (2011): Steps in Successful Project
Actualization. Civil Engineering Practice and Entrepreneurship. P.55-56.
Ugwu O.O et al, Anumba C.J. Newnham L, Thorpe A. (1999): Agent-Based
Collaborative Design of Constructed Facilities in Artifical Intelligence in
Structural Engineering – Information Technology for Design,
Manufacturing, Maintenance, and Monitoring, Proceedings of the 6th EG-
SEA-AI Workshop, Wierxba 1999, Adam Borkowki (Ed.), p. 19- 9-208.
65
Ugwu O.O (2005B): A Service- Oriented Framework for Sustainability
Appraisal and Knowledge Management, International Journal of ICT
Construction ITcon (Electronic journal) vol. 10 (2005) p 245-263.
Ugwu O.O.(2010): Lecture Notes, Coures: “Information & Communication
Technology (ICT) Aids for Megaproject Management” The University
of Nigeria, Nsukka (UNN) MENGR Management of Construction.
Ugwu O. O et al, Kumaraswamy M. M (2007): Critical Success Factors for
Construction ICT Projects – some empirical evidence and lessons for
emerging economies.
Ugwu O. O et al, Kumaraswamy M.M., Ng T, Lee P.K.K. (2006):
Information and Communication Technology (ICT) Applications in
Construction, Repot of surveys on ICT Applications, Benchmarks, Benefits,
Cost, Barriers & Research &Development Issues in the HKSAR construction
industry.
Ugwu O. O et al, Ng S. T, Kumaraswamy M. M. (2003a): “Key Enablers in IT
Implementation- A Hong Kong Construction Industry Perspective”, in
„Towards a Vision for Information Technology in Civil Engineering‟,
Proceedings of 4th Joint International Symposium on Information
Technology in Civil Engineering (Flood I. Ed.), Nashville Tennessee
USA, 15-16 November 2003, Sponsored by ASCE‟s Technical Council
on Computing Practices and European Group for Intelligent Computing
in Engineeing (EG-ICE), ISBN 0-7844-0704-5.
Umit I., Jason U., Murat K., Jack G., and Utku A. (2009): Construction Informatics
in Turkey; Strategic Role of ICT and Future Research Directions.
Watson H.J, and Frolick M. N. (1993)
: Delivering Information Requirements for an EIS, MIS Quterly 17(3), p.
255-290.
Watson H.J, Rainer R. K and Kol C. (1991): Executive Information System; a
Framework for Development and Survey of Current Practices ERP, MIS
Quaterly 15(1), p. 13-32.
66
APPENDIX A
STUDENT’S T-TEST TABLE
Degrees of Freedom Probability, P
0.1 0.05 0.01 0.001
1 6.31 12.71 63.66 636.62
2 2.92 4.30 9.93 31.60
3 2.35 3.18 5.84 12.92
4 2.13 2.78 4.60 8.61
5 2.02 2.57 4.03 6.87
6 1.94 2.45 3.71 5.96
7 1.89 2,37 3.50 5.41
8 1.86 2.31 3.36 5.04
9 1.83 2.26 3.25 4.78
10 1.81 2.23 3.17 4.59
11 1.80 2.20 3.11 4.44
12 1.78 2.18 3.06 4.32
13 1.77 2.16 3.01 4.22
14 1.76 2.14 2.98 4.14
15 1.75 2.13 2.95 4.07
16 1.75 2.12 2.92 4.02
17 1.74 2.11 2.90 3.97
18 1.73 2.10 2.88 3.92
19 1.73 2.09 2.86 3.88
20 1.72 2.09 2.85 3.85
21 1.72 2.08 2.83 3.82
22 1.72 2.07 2.82 3.79
23 1.71 2.07 2.82 3.77
24 1.71 2.06 2.80 3.75
25 1.71 2.06 2.79 3.73
26 1.71 2.06 2.78 3.71
27 1.70 2.05 2.77 3.69
28 1.70 2.05 2.76 3.67
29 1.70 2.05 2.76 3.66
30 1.70 2.04 2.75 3.65
40 1.68 2.02 2.70 3.55
60 1.67 2.00 2.66 3.46
120 1.66 1.98 2.62 3.37
Infinity 1.65 1.96 2.58 3.29
Source: http:wikipedia.org/wiki/student‟s_t-test