Update to LIC-500, “Topical Report Process” Public Workshop on Topical Report Transformation Process Ngola Otto Office of Nuclear Reactor Regulation October 24, 2019

Upload: others

Post on 18-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Update to LIC-500, “Topical Report Process” · 2019. 10. 24. · Phase 6 – Final SE Phase 7 – “-A” Version. Status Quo, Simplified SE, Limited SE. 4. Status Quo (nominally

Update to LIC-500, “Topical Report Process”

Public Workshop on Topical Report Transformation Process

Ngola OttoOffice of Nuclear Reactor Regulation

October 24, 2019

Page 2: Update to LIC-500, “Topical Report Process” · 2019. 10. 24. · Phase 6 – Final SE Phase 7 – “-A” Version. Status Quo, Simplified SE, Limited SE. 4. Status Quo (nominally

Agenda

2

• Topical Report (TR) Review Process• Status Quo• Simplified Safety Evaluation (SE)• Limited SE• Modified Review • Tiger Team Review • Submittal Documentation• Schedule for Revising LIC-500

Page 3: Update to LIC-500, “Topical Report Process” · 2019. 10. 24. · Phase 6 – Final SE Phase 7 – “-A” Version. Status Quo, Simplified SE, Limited SE. 4. Status Quo (nominally

TR Review Process

3

Phase 1 – SubmissionPhase 2 – Work Plan DevelopmentPhase 3 - Completeness Review & Decision LetterPhase 4 – Preliminary SE and RAIsPhase 5 – Draft SEPhase 6 – Final SEPhase 7 – “-A” Version

Page 4: Update to LIC-500, “Topical Report Process” · 2019. 10. 24. · Phase 6 – Final SE Phase 7 – “-A” Version. Status Quo, Simplified SE, Limited SE. 4. Status Quo (nominally

Status Quo, Simplified SE, Limited SE

4

Status Quo (nominally 24 months)• No revision to the LIC-500, “Topical Report Process.”

o For Topical Reports that require extensive review, the normal (Status Quo) review process described in latest revision to LIC-500 would apply.

Simplified SE (3-6 months)• Revise LIC-500 to establish a modified process for the Simplified SE.

o Use the Flow Diagram to determine the type of SE (Simplified, Limited), early (e.g. Pre-submittal) in the TR review.

o Conduct a more rigorous Completeness Review.

Limited SE (6-12 months)• Revise LIC-500 to establish a modified process for the Limited SE.

o Use the Flow Diagram to determine the type of SE (Simplified, Limited), early (e.g. Pre-submittal) in the TR review.

o Conduct a more rigorous Completeness Review.

Page 5: Update to LIC-500, “Topical Report Process” · 2019. 10. 24. · Phase 6 – Final SE Phase 7 – “-A” Version. Status Quo, Simplified SE, Limited SE. 4. Status Quo (nominally

Modified Review & Tiger Team Review

5

Modified Review (12 months)• Revise LIC-500 to establish a modified process for Modified Review.

o Issue the Draft SE with Open Items, instead of issuing Requests for Additional Information (RAIs) separately.

o Conduct a more rigorous Completeness Review.o Review could be suspended if Open Items are not resolved.

Tiger Team Review (12 months)• Revise the LIC-500 review process to conduct an audit and issue the Draft

SE with the Open items.o RAIs could be eliminated because the Draft SE from the audit includes

the Open Items.

Page 6: Update to LIC-500, “Topical Report Process” · 2019. 10. 24. · Phase 6 – Final SE Phase 7 – “-A” Version. Status Quo, Simplified SE, Limited SE. 4. Status Quo (nominally

Submittal Documentation & Schedule

6

Submittal Documentation (varies)• Revise LIC-500 to establish a modified process for Submittal Documentation

o Where appropriate, use telephone calls to discuss clarification issues and then have vendors provide the information without the need for an additional RAI.

o NRC staff could document the industry position in its Draft SE and if comments are not provided on the draft, then that position is considered endorsed by the vendor.

Schedule for Revising LIC-500• Planned: January – March 2020