updated life of mine plan technical session

83
February 21, 2018 Updated Life of Mine Plan Technical Session

Upload: others

Post on 02-Oct-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Updated Life of Mine Plan Technical Session

February 21, 2018

Updated Life of Mine Plan Technical Session

Page 2: Updated Life of Mine Plan Technical Session

www.guygold.com 2

This presentation of Guyana Goldfields Inc. (the "Company") containsstatements that constitute "forward-looking statements." Such forward-lookingstatements involve known and unknown risks, uncertainties and other factorsthat may cause our actual results, performance or achievements, ordevelopments in our industry, to differ materially from the anticipated results,performance or achievements expressed or implied by such forward-lookingstatements. Forward looking statements are statements that are not historicalfacts and are generally, but not always, identified by the words "expects,""aims," "plans," "anticipates," "believes," "intends," "estimates," "projects,""potential" and similar expressions, or that events or conditions "will," "would,""may," "could" or "should" occur. Information inferred from the interpretation ofdrilling results and information concerning mineral resource and mineral reserveestimates may also be deemed to be forward looking statements, as suchinformation constitutes a prediction of what might be found to be present whenand if a project is actually developed. Forward-looking statements this documentinclude statements regarding: the Company's expectations regarding drillingand exploration activities on properties in which the Company has an interest;and the Company's statements regarding estimates of reserves and resourceson properties in which the Company has an interest.

There can be no assurance that such statements will prove to be accurate.Actual results and future events could differ materially from those anticipated insuch statements, and readers are cautioned not to place undue reliance onthese forward-looking statements that speak only as of their respective dates.Important factors that could cause actual results to differ materially from theCompany's expectations include among others, risks related to fluctuations inmineral prices; uncertainties related to raising sufficient financing to fundplanned work in a timely manner and on acceptable terms; changes in plannedwork resulting from weather, logistical, technical or other factors; the possibilitythat results of work will not fulfill expectations and realize the perceived potentialof the Company's properties; uncertainties involved in the estimation ofresources and reserves; the possibility that required permits may not beobtained on a timely manner or at all; the possibility that capital and operatingcosts may be higher than currently estimated and may preclude commercialdevelopment or render operations uneconomic; the possibility that the estimatedrecovery rates may not be achieved; risk of accidents, equipment breakdownsand labour disputes or

other unanticipated difficulties or interruptions; the possibility of cost overrun orunanticipated expenses in the work program; the risk of environmentalcontamination or damage resulting from the Company's operations; risksassociated with title to mineral properties; and other risks and uncertaintiesdiscussed appear elsewhere in the Company's documents filed from time totime with the Toronto Stock Exchange and Canadian securities regulators.

These statements are based on a number of assumptions, includingassumptions regarding general market conditions, the availability of financing forproposed transactions and programs on reasonable terms, the cost ofexploration and development and the ability of outside service providers todeliver services in a satisfactory and timely manner. Forward-looking statementsare based on the beliefs, estimates and opinions of the Company'smanagement on the date the statements are made. Except as expresslyrequired by applicable securities laws, the Corporation undertakes no obligationto update these forward-looking statements in the event that management'sbeliefs, estimates or opinions, or other factors, should change.

This presentation uses the terms "Inferred Resource", "Indicated Resource",“Measured Resource” and "Mineral Resource". The Company advises readersthat although these terms are recognized and required by Canadian securitiesregulations (under National Instrument 43-101 "Standards of Disclosure forMineral Projects"), the US Securities and Exchange Commission does notrecognize these terms. Readers are cautioned not to assume that any part or allof the mineral deposits in these categories will ever be converted into reserves.In addition, "Inferred Resources" have a great amount of uncertainty as to theirexistence, and economic and legal feasibility. It cannot be assumed that anypart of an Indicated or Inferred Mineral Resource will ever be upgraded to ahigher category. Under Canadian rules, estimates of Inferred Mineral Resourcesmay not form the basis of feasibility or pre-feasibility studies, or economicstudies except for a Preliminary Assessment as defined and permitted underNational Instrument 43-101. Readers are cautioned not to assume that part orall of an Inferred Resource exists, or is economically or legally mineable. TheMineral Resources stated in this presentation are not Mineral Reserves and, inthe absence of a current feasibility study, do not demonstrate economic viability.The determination of Mineral Reserves can be affected by various factorsincluding environmental, permitting, legal, title, taxation, socio-political, andmarketing issues.

FORWARD LOOKING STATEMENT

Page 3: Updated Life of Mine Plan Technical Session

www.guygold.com 3

AGENDA

Time Description Presenter Company

11:00‐11:30 AM Opening Remarks Scott Caldwell GUY

11:30‐11:45 AM Reserves & Resources Scott Caldwell GUY

11:45AM ‐12:00 PM Open Pit Gord Doerksen JDS Mining

Buffet Lunch Available ‐ 5 mins Break

12:05‐12:30 PM Underground Trace Arlaud JDS Mining

12:30‐1:00 PM Metallurgy & Processing Scott Caldwell GUY

1:00‐1:30 PM Exploration Daniel Noone GUY

1:30 PM Closing Remarks Scott Caldwell GUY

Page 4: Updated Life of Mine Plan Technical Session

www.guygold.com 4

2018 Updated Mine Plan: Factors

• Eliminate RK OP stripping bubble in 2019/2020

• Limit total OP production to 70,000 t/d

• Utilize a combination of  high‐grade long hole open stoping (“LHOS”) early followed by sub level cave (“SLC”) to maximize value

• Maintain tonalite feed to the mill

Page 5: Updated Life of Mine Plan Technical Session

www.guygold.com 5

Updated Mine Plan: Highlights

1 This is a non-IFRS measure. Refer to non-IFRS Performance Measures section.

Description 2018 LOM Plan 2017 Updated FS*

Ore tonnes (Mt) 43.0 34.7

Average grade (Au oz/t) 2.87 3.00

Process recovery (%) 94.8 93.8

Payable gold (Moz) 3.8 3.1

Annual gold production (2018‐2022 koz) 270 242

Mine Life (years) 16 14

AISC ($/oz)¹ 797 745

Post‐tax NPV5% (M$) 898 821

*Adjusted to commence in 2018

Page 6: Updated Life of Mine Plan Technical Session

www.guygold.com 6

2018 Guidance

2018 Guidance

Gold production 190,000-210,000

Cost of sales (production costs, royalty and depreciation) $850-900/oz

Cash cost¹, excluding royalty $430-480/ozAll-in sustaining1 (“AISC”) $830-880/oz

(1) This is a non-GAAP measure. Refer to Non-GAAP Performance Measures section

• Production is expected to be weighted towards the second half of the year due to minesequencing and increased throughput to be available with the completion of the phase 1expansion.

• The 2018 mine plan is primarily made up of all hard rock ore from the central tonalite/diorite ore at Rory’s Knoll and East Walcott deposits.

• Costs are based on an increased stripping rate during 2018, offset by the increased and more cost-efficient production offered by the process plant expansion investments.

Page 7: Updated Life of Mine Plan Technical Session

www.guygold.com 7

MINERAL RESERVES

As at December 31, 2017

Category Quantity(kt)

Grade(g/t Au)

Ounces(k Oz)

ProvenOP Saprolite 108 0.73 3OP Rock 4,569 2.75 404Total Proven 4,677 2.70 406ProbableOP Saprolite 2,291 1.77 130OP Rock 12,959 2.81 1,172UG Rock 23,120 3.04 2,262Total Probable 38,370 2.89 3,565Total P&P 43,047 2.87 3,971

1. The CIM definitions were followed for mineral reserves.2. Mineral Reserves are based on a gold price of US$1,200 per ounce, an 8% royalty and an average

metallurgical recovery of 96.0% for saprolite and 94.0% for fresh rock material.3. Open pit saprolite and rock reserves are reported at a cut-off grade of 0.44 g/t Au and 0.42 g/t Au

for vein and upper saprolite material respectively. Open pit rock reserves are reported at a cut-offgrade of 0.76 g/t Au and 0.64 g/t Au for vein and Rory’s Knoll rock material respectively.

4. Underground fresh rock reserves are reported at a cut-off grade of 1.5 g/t Au.5. Mineral reserves are contained within mineral resources.6. All figures have been rounded to reflect the relative accuracy of the estimates. Numbers may not

add due to rounding7. The mineral reserve estimate was prepared by Tysen Hantelmann, P.Eng. and Gord Doerksen,

P.Eng of JDS Mining and both are a “qualified person” under National Instrument 43-101.

Page 8: Updated Life of Mine Plan Technical Session

www.guygold.com 8

MINERAL RESERVES – BREAKDOWN

As at Dec 31, 2017Proven & Probable

Quantity Grade Ounces Waste Strip(kt) (g/t Au) (k Oz) (kt) Ratio

OPEN PITRory's Knoll 10,407 2.85 954 88,505 8.5Aleck Hill 5,862 2.73 515 50,822 8.7Satellites 2,753 2.33 206 30,049 10.9Stockpile 905 1.16 34

OP - Total 19,927 2.67 1,709 169,376 8.9UNDERGROUNDRory's Knoll 21,368 2.92 2,003Aleck Hill 1,108 4.28 153Mad Kiss 643 5.18 107

UG - Total 23,120 3.04 2,262OP + UG -Total 43,047 2.87 3,971

1. The CIM definitions were followed for mineral reserves.2. Mineral Reserves are based on a gold price of US$1,200 per ounce, an 8% royalty and an average

metallurgical recovery of 96.0% for saprolite and 94.0% for fresh rock material.3. Open pit saprolite and rock reserves are reported at a cut-off grade of 0.44 g/t Au and 0.42 g/t Au

for vein and upper saprolite material respectively. Open pit rock reserves are reported at a cut-offgrade of 0.76 g/t Au and 0.64 g/t Au for vein and Rory’s Knoll rock material respectively.

4. Underground fresh rock reserves are reported at a cut-off grade of 1.5 g/t Au.5. Mineral reserves are contained within mineral resources.6. All figures have been rounded to reflect the relative accuracy of the estimates. Numbers may not

add due to rounding7. The mineral reserve estimate was prepared by Tysen Hantelmann, P.Eng. and Gord Doerksen,

P.Eng of JDS Mining and both are a “qualified person” under National Instrument 43-101.

Page 9: Updated Life of Mine Plan Technical Session

www.guygold.com 9

MINERAL RESOURCESAs at December 31, 2017

CategoryQuantity

(kt)Grade

(g/t Au)Ounces(k Oz)

MeasuredOP Saprolite 108 0.73 3 OP Rock 4,728 2.91 442 Total Measured 4,836 2.86 445 IndicatedOP Saprolite 1,404 0.93 42 OP Rock 20,901 2.60 1,747 UG Rock 30,060 3.91 3,780 Total Indicated 52,365 3.31 5,569 Total M + I 57,201 3.27 6,014 InferredOP Saprolite 1,939 0.91 57 OP Rock 2,581 1.93 161 UG Rock 11,810 4.12 1,560 Total Inferred 16,330 3.39 1,777

1. The CIM definitions were followed for mineral resources.2. Mineral resources are inclusive of mineral reserves. Mineral resources are not mineral reserves and do not have demonstrated economic viability.3. All figures have been rounded to reflect the relative accuracy of the estimates. Number may not add due to rounding.4. Open pit mineral resources are reported at a cut-off grade of 0.30 g/t for Saprolite and 0.40 g/t for Fresh rock respectively, and underground mineral resources are reported at a cut-off grade of 1.8 g/t. Cut-off

grades are based on a price of US$1,300 per ounce of gold and a gold recoveries of 97 percent for saprolite and 94.5 percent for fresh material.5. Mineral resources have been adjusted using the 2017 EOY topography, to account for open pit mining to date, and include ore stockpile inventories as of EOY 2017.6. The qualified person is not aware of any mining, metallurgical, infrastructure, permitting, or other factors that could materially affect the mineral resource estimates.7. The mineral resource estimate for Rory’s Knoll was prepared under the supervision of Tim Maunula, of T. Maunula & Associates Consulting Ltd. Mr. Maunula is a “qualified person” under NI 43-101 and

is independent of the Company. The mineral resource estimate for the satellites was prepared under the supervision of Daniel Noone of Guyana Goldfields Inc. Mr. Noone is a “qualified person” underNational Instrument 43-101.

Page 10: Updated Life of Mine Plan Technical Session

www.guygold.com 10

ORE PROCESSED BY SOURCE

 ‐

 0.5

 1.0

 1.5

 2.0

 2.5

 3.0

 3.5

 4.0

 ‐

 0.5

 1.0

 1.5

 2.0

 2.5

 3.0

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

Grade

 (gpt)

Ore Processed

 (Mtonn

es)

ORE Processed

UG OP SP Ave Grade

Page 11: Updated Life of Mine Plan Technical Session

www.guygold.com 11

Rory’s Knoll

Alek Hill

Alek Hill North

WalcottHill

Mad Kiss

OPEN PIT

Page 12: Updated Life of Mine Plan Technical Session

www.guygold.com 12

SITE LAYOUT: Aurora Gold Mine

Rory’s Knoll

Walcott Hill

Mad Kiss

Aleck HillNorth Aleck Hill

Page 13: Updated Life of Mine Plan Technical Session

www.guygold.com 13

Rory’s Knoll

Aleck Hill

Aleck Hill North

WalcottHill

Mad Kiss

OPEN PIT ORE SOURCES

Page 14: Updated Life of Mine Plan Technical Session

www.guygold.com 14

Rory’s Knoll

Alek Hill

Alek Hill North

WalcottHill

Mad Kiss

OPEN PIT SEQUENCING

Page 15: Updated Life of Mine Plan Technical Session

www.guygold.com 15

Rory’s Knoll

Alek Hill

WalcottHill

Mad Kiss

OPEN PIT SEQUENCING

Page 16: Updated Life of Mine Plan Technical Session

www.guygold.com 16

Rory’s Knoll

Alek Hill

WalcottHill

Mad Kiss

OPEN PIT SEQUENCING

Page 17: Updated Life of Mine Plan Technical Session

www.guygold.com 17

Rory’s Knoll

Alek Hill

WalcottHill

Mad Kiss

OPEN PIT SEQUENCING

Page 18: Updated Life of Mine Plan Technical Session

www.guygold.com 18

Rory’s Knoll

Alek Hill

WalcottHill

Mad Kiss

OPEN PIT SEQUENCING

Page 19: Updated Life of Mine Plan Technical Session

www.guygold.com 19

Rory’s Knoll

Alek Hill

WalcottHill

Mad Kiss

OPEN PIT SEQUENCING

Page 20: Updated Life of Mine Plan Technical Session

www.guygold.com 20

Rory’s Knoll

Alek Hill

WalcottHill

Mad Kiss

OPEN PIT SEQUENCING

Page 21: Updated Life of Mine Plan Technical Session

www.guygold.com 21

Rory’s Knoll

Alek Hill

WalcottHill

Mad Kiss

OPEN PIT SEQUENCING

Page 22: Updated Life of Mine Plan Technical Session

www.guygold.com 22

Source Ore(Mt)

M/H Grade(g/t)

ContainedGold(Moz)

Waste(Mt) Strip Ratio

Rory’s Knoll 10.4  2.85  0.95  88.5 8.5 

Aleck Hill 5.9 2.73  0.52  50.8 8.7 

North Aleck Hill 1.9  1.81  0.11  17.4  9.4 

Mad Kiss 0.6 4.32  0.08  9.4 16.1 

Walcott 0.3 1.53  0.02  3.3 10.3 

2018 LOM Total 19.0  2.74 1.68  169.4 8.9

OPEN PIT ORE SOURCES

Page 23: Updated Life of Mine Plan Technical Session

www.guygold.com 23

OPEN PIT ORE AND WASTE MINING

 ‐

 0.5

 1.0

 1.5

 2.0

 2.5

 3.0

 3.5

 4.0

 4.5

 ‐

 5

 10

 15

 20

 25

 30

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

Mined

 Grade

 (gpt)

Material M

ined

 (Mtonn

es)

OP Material Mined

Ore Waste Grade

Page 24: Updated Life of Mine Plan Technical Session

www.guygold.com 24

OPEN PIT TONNES MINED BY SOURCE

 ‐

 10

 20

 30

 40

 50

 60

 70

 80

 ‐

 5

 10

 15

 20

 25

 30

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

Mining Ra

te (k

tpd)

Material M

ined

 (Mtonn

es)

OP Material by Source

RK AH AN WH MK tpd

Page 25: Updated Life of Mine Plan Technical Session

www.guygold.com 25

Rory’s Knoll

Alek Hill

Alek Hill North

WalcottHill

Mad Kiss

UNDERGROUND

Page 26: Updated Life of Mine Plan Technical Session

www.guygold.com 26

RK longhole stopes (LHS) are mined while the open pit is operating. 

The crown pillar between the OP and the longhole stopes is taken out after the RK pit is finished. 

Sub level cave (SLC) mining begins after the primary longhole stopes are complete.

Satellite deposits will be scheduled to fill in production gaps

RORY’S KNOLL (RK) UNDERGROUND

Page 27: Updated Life of Mine Plan Technical Session

www.guygold.com 27

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

180,000

200,000

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

1,600,000

1,800,000

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

Oun

ces

Tonn

es

RK & EW UG Production

Au (oz) Tonnes

UG PRODUCTION SUMMARY

Page 28: Updated Life of Mine Plan Technical Session

www.guygold.com 28

RESERVE BY ELEVATION

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

0

100,000

200,000

300,000

400,000

500,000

600,000

700,000

800,000

900,000

1,000,000

‐285

‐310

‐335

‐360

‐385

‐410

‐435

‐460

‐485

‐510

‐535

‐560

‐585

‐610

‐635

‐660

‐685

‐710

‐735

‐760

‐785

‐810

‐835

‐860

‐885

‐910

‐935

‐960

‐985

‐101

0‐103

5‐106

0‐108

5‐111

0‐113

5

Oun

ces

Tonn

es

Reserves by Level

Ounces Tonnes

Page 29: Updated Life of Mine Plan Technical Session

www.guygold.com 29

2018

Page 30: Updated Life of Mine Plan Technical Session

www.guygold.com 30

2019

Page 31: Updated Life of Mine Plan Technical Session

www.guygold.com 31

2020

Page 32: Updated Life of Mine Plan Technical Session

www.guygold.com 32

2021

Page 33: Updated Life of Mine Plan Technical Session

www.guygold.com 33

2022

Page 34: Updated Life of Mine Plan Technical Session

www.guygold.com 34

2023

Page 35: Updated Life of Mine Plan Technical Session

www.guygold.com 35

2024

Page 36: Updated Life of Mine Plan Technical Session

www.guygold.com 36

2025

Page 37: Updated Life of Mine Plan Technical Session

www.guygold.com 37

2026

Page 38: Updated Life of Mine Plan Technical Session

www.guygold.com 38

2027

Page 39: Updated Life of Mine Plan Technical Session

www.guygold.com 39

2028

Page 40: Updated Life of Mine Plan Technical Session

www.guygold.com 40

2029

Page 41: Updated Life of Mine Plan Technical Session

www.guygold.com 41

2030

Page 42: Updated Life of Mine Plan Technical Session

www.guygold.com 42

2031

Page 43: Updated Life of Mine Plan Technical Session

www.guygold.com 43

2032

Page 44: Updated Life of Mine Plan Technical Session

www.guygold.com 44

2033

Page 45: Updated Life of Mine Plan Technical Session

www.guygold.com 45

DRAW CONTROL

• High Grade Crown pillars and primary stopes higher grade mined and recovered prior to commencing SLC‐ SLR

• In caving finer material is preferentially draw over coarse material (in SLC‐ SLR fine fragmentation is created through blasting, with the use of both powder factor and blast timing).

• As SLC‐SLR is typically choke blasting (no free face ‐ blasting against blasted or cave material a higher powder factor is used with a tight initiation pattern). 

• In LHS a slightly lower powder factor is used compare to SLC‐SLR as there is a free face to blast too.

• In the pillar wrecking zone – lower powders factors will be used to ensure the material is more coarser than the SLC‐SLR material to ensure it will not preferentially draw over the high grade. This can also be achieved by a  more open – slower initiation pattern in the blasting and more open drill pattern.

• Material above the pillar wrecking zone will be allowed to cave naturally, thus anticipate to be the most coarse material. 

Page 46: Updated Life of Mine Plan Technical Session

www.guygold.com 46

Source Tonnes(Mt)

MH Grade(g/t)

MH Gold(koz)

Rory’s Knoll Dev 1.0 3.11 99

Rory’s Knoll LH 2.4 3.98 302

Rory’s Knoll SLC 17.2 2.76 1,525

Aleck Hill 1.1 4.28 153

Mad Kiss 0.6 5.18 107

East Walcott 0.8 2.90 78

TOTAL 23.1 3.04 2,262

UNDERGROUND ORE SOURCES

Page 47: Updated Life of Mine Plan Technical Session

www.guygold.com 47

UG MATERIAL BY SOURCE

 ‐

 1.0

 2.0

 3.0

 4.0

 5.0

 6.0

 ‐

 0.5

 1.0

 1.5

 2.0

 2.5

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

Mined

 Grade

 (gpt)

Material M

ined

 (Mtonn

es)

UG Material by Source

RK Development RK LH RK SLC MK AH RK‐EW LH Grade

Page 48: Updated Life of Mine Plan Technical Session

www.guygold.com 48

COMBINED RECOVERED GOLD

 ‐

 50

 100

 150

 200

 250

 300

 350

 ‐

 5

 10

 15

 20

 25

 30

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

Gold Re

covered (k oz)

Material M

ined

 (Mtonn

es)

Total Material Mined / Gold Recovered

Ore Processed UG Ore OP Ore Waste Recovered Oz 2017 FS Oz

Page 49: Updated Life of Mine Plan Technical Session

www.guygold.com 49

RECOVERED GOLD / COSTS

0

200

400

600

800

1,000

1,200

 ‐

 50

 100

 150

 200

 250

 300

 350

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

Costs (US$

/oz)

Recovered Oz

Gold Recovered / Costs

Recovered Oz Operating Cash Cost AISC

Page 50: Updated Life of Mine Plan Technical Session

www.guygold.com 50

OPEX

Description Unit 2018 LOM 2017 Updated FS

OP Mining $/tonne mined 2.20 2.09

RK UG Mining $/ore t mined 24.83 25.72

Satellite UG Mining $/ore t mined 48.35 50.82

Processing $/t processed 16.06 14.25

G&A $/t processed 9.12 8.67

Operating Cash Cost¹ (w/ royalty) $/oz 627 613

Operating Cash Cost¹ (excl. royalty) $/oz 531 517

AISC¹ $/oz 797 745

Page 51: Updated Life of Mine Plan Technical Session

www.guygold.com 51

CAPEX

Initial Unit LOM 2018 2019 2020UG Mining - RK US$M (88.8) (9.1) (62.6) (17.1)UG Mining - Sat US$M (61.8) (9.8) (10.4)OP Mining US$M (1.9) (1.9)Processing US$M (12.9) (12.9)On-Site Infrastructure US$M 0.0Off-Site Infrastructure US$M 0.0Owner's Costs US$M (0.7) (0.7)Initial Subtotal US$M (166.1) (34.4) (73.0) (17.1)SustainingUG Mining - RK US$M (160.0) (17.1)UG Mining - Sat US$M (47.3) (3.2) (10.8)OP Mining US$M (3.0) (3.0)Processing US$M (28.8) (0.8) (4.0) (2.0)Tailings Management US$M (18.8) (1.0) (2.8)EPCM & Indirects US$M (14.3) (2.8) (11.4)Owner's Costs - Sustaining US$M (17.1) (2.1) (1.0) (1.0)Closure US$M (6.0)Deferred Stripping US$M (138.1) (36.1) (28.0) (36.8)Sustaining Subtotal US$M (433.3) (44.8) (48.7) (70.5)

Total CAPEX US$M (599.4) (79.2) (121.8) (87.6)US$/t 13.92

Page 52: Updated Life of Mine Plan Technical Session

www.guygold.com 52

ECONOMIC PARAMETERS

Parameter Unit 2018 LOM Plan 2017 Updated FS

Gold Price $/oz 1200 1200

Electricity Cost $/kWh 0.14 0.14

Diesel Price $/L 0.55 0.55

Tax Rate % 27.5 27.5

NS Royalty % 8 8

Results

Revenue M$ 4,518 3,769

Operating Cash Flow M$ 2,158 1,837

Pre‐tax NPV5% M$ 1,142 1,035

Post‐tax NPV5% M$ 898 821

Page 53: Updated Life of Mine Plan Technical Session

www.guygold.com 53

GOLD PRICE SENSITIVITY

Financials @ 5% Discount Rate

$1,000/ozgold price*

$1,100/ozgold price

$1,300/ozgold price

$1,400/ozgold price

Pre-tax NPV ($mlns) 722 891 1,393 1,645Post-tax NPV ($mlns) 588 713 1,081 1,264

* Royalty decreases from 8% to 5% at gold prices at and below US$1,000/oz

Page 54: Updated Life of Mine Plan Technical Session

www.guygold.com 54

PLAN ADVANTAGES

• Early access to both RK and MK allows for further characterisation – geotechnical, environmental and in fill drilling.

• Underground tonnes reduces pressure on the RK Pit, smoothing production and waste profile.

• Underground high grade tonnes brought forward in plan.• High grade stopes in pit floor mass blasted almost immediately 

after pit finish. • Reduced – No dip in production profile.• More rapid production build up in SLC due to development of 

ore curtain through pillar wrecking above ‐460.• No requirement for backfill plant.• Reduced ventilation requirement over LHOS only plan.

Page 55: Updated Life of Mine Plan Technical Session

www.guygold.com 55

Early UG Mining SWOT

Strengths:– Significantly reduces RK pit waste bubble– Keeps tonalite feed to the mill and 

extends RK pit life– Brings HG areas in early MK, RK and EW– Eliminates RK backfill– Allows for easy extraction of high‐grade 

crown pillar under RK pit– Reduces production dip normally 

associated with SLC start‐up– Allows more time to train crews– Provides earlier orebody characterization

Weakness: Lack of drilling at EW Resources for satellites being redone Lack of RK geotech, hydrogeological and 

heat characterization at depth

Opportunities: Storing of development waste UG (MK 

and AH) Mining MK earlier Mining MK entirely using UG methods Improved grades at MK and EW 

Threats: UG refrigeration, SLC mudrush, water 

management, geotech, mining capability

Page 56: Updated Life of Mine Plan Technical Session

www.guygold.com 56

UG Start-Up Plan

Oct 1 2018 start date for UG development with slow (4 m/d) development ramp‐up of development in Q4 2018

Significant UG equipment already purchased including:  Two LHDs One 45‐t truck One two‐boom development jumbo Service vehicles Refuge chamber Jacklegs and stoppers

Manpower plan:  Contractor mining for the first 3 years Transition to owner‐operation in 2020 Owner‐operation includes retaining a small NA expat team and a larger (50 person) 

regional expat team along with Guyanese workforce.

Page 57: Updated Life of Mine Plan Technical Session

www.guygold.com 57

TECHNICAL CONSIDERATIONS: TRANSITION PLAN

• 2018 start of underground development.• Development and production tonnes 2019 RK & MK.• Mining of primary high grade stopes between ‐460 and ‐285• Mining of two high grade crown pillar stope immediate following 

pit operations (drilled from the open pit).• Mining of East Walcott primary stopes.• East Walcott stopes directly under the pit ramp drill from RK pit, 

mined following crown pillars in the pit.

Page 58: Updated Life of Mine Plan Technical Session

www.guygold.com 58

Metallurgy & Processing

Page 59: Updated Life of Mine Plan Technical Session

www.guygold.com 59

PROPOSED MILL EXPANSION

87

88

89

90

91

92

93

94

95

96

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Current Operation Phase 1 Pre‐Crush Install Phase 2 GravityExpansion

Phase 2 Ball Mill

Recovery (%

)

Throug

hput (tpd

)

Throughput Recovery

Page 60: Updated Life of Mine Plan Technical Session

www.guygold.com 60

PROPOSED MILL EXPANSION

Revised Phase 2 Design

Original Phase 2 Design

Throughput (tpd) 7,500 8,000

LOM recoveries (%) 94.8 94.0

Pre-crush circuit 1,000 tpd N/A

Ball mill size 1,000 tpd 8,000 tpd

Power requirements 1.4 MW 6.0 MW

Capital Cost ($mlns) $6 $27

Completion date 4Q 2018 Mid-2019

Page 61: Updated Life of Mine Plan Technical Session

www.guygold.com 61

PROPOSED MILL EXPANSION

• Phase 1 Expansion: On‐time & On‐budget for completion at end of 1Q 2018

• Phase 2 Pre‐crush Expansion:– Capital cost of $3.5mln– Engineering & procurement underway– Expected completion by 3Q2018

• Phase 2 Ball Mill & Gravity Expansion:– Capital cost of $2.5mln– Scoping study completed– Ball mill (1,000 tpd) & concentrators already purchased– Expected completion by 4Q 2018

• Expected capital cost savings of ~$20mln compared to original phase two expansion while still achieving similar throughput & recovery levels

Page 62: Updated Life of Mine Plan Technical Session

www.guygold.com 62

Mill Expansion: Thickener Construction

Page 63: Updated Life of Mine Plan Technical Session

www.guygold.com 63

Mill Expansion: Leach Tank Progress

Page 64: Updated Life of Mine Plan Technical Session

www.guygold.com 64

FLOWSHEET

Page 65: Updated Life of Mine Plan Technical Session

www.guygold.com 65

PRE-CRUSH TRIAL WORK

• Pre‐crush trial work commenced in November coinciding with Aurora becoming a hard‐rock only operation

• Trial work to date has showed:– The addition of the Pre‐Crush Circuit at a blend rate of approximately 15% yields a 10% increase 

in throughput– The throughput increase, at this rate, does not adversely affect the grind or recovery

• Processing with pre‐crush material show an average recovery of ~92.0% versus an average recovery of 88.6% for the first nine months of 2017

• Pre‐crushing increases gold liberation making gold more suitable for gravity recovery resulting in increased throughput & recoveries

Page 66: Updated Life of Mine Plan Technical Session

www.guygold.com 66

PRE-CRUSH GRAVITY RECOVERIES

Page 67: Updated Life of Mine Plan Technical Session

www.guygold.com 67

PRE-CRUSH: GENERAL ARRANGEMENT

Cone crusher

Existing sap feeder

Jaw crusher

Page 68: Updated Life of Mine Plan Technical Session

www.guygold.com 68

BALL MILL & GRAVITY EXPANSION

• Addition of the ball mill will:– Provide additional fine grinding– Reduce the recirculating load on the SAG Mill 

• Installation of the 2 x KC 20 gravity concentrators will:– Reduce the recirculating gold load– Further improve overall recovery via gravity concentration vs leaching/CIP 

• ~8% reduction in Cyanide, SMBS and Copper Sulphate consumption (annualized savings of US$ 0.5M) due to higher gravity recovery & reduced gold loading in the leaching & CIP circuits

• 1,000 tpd ball mill & gravity concentrators are part of the Hope Bay mill purchase made in 2016

Page 69: Updated Life of Mine Plan Technical Session

www.guygold.com 69

ARANKA MILL EQUIPMENT PURCHASED IN 2016

Page 70: Updated Life of Mine Plan Technical Session

www.guygold.com 70

ARANKA MILL EQUIPMENT PURCHASED IN 2016

Knelson Concentrator Ball mill Concentrator Structure

Jaw crusher Structure Cone Crusher Structure Cone Crusher Cone Crusher Structure

Page 71: Updated Life of Mine Plan Technical Session

www.guygold.com 71

EXPLORATION

Page 72: Updated Life of Mine Plan Technical Session

www.guygold.com 72

EXPLORATION - GUIANA SHIELD: Known Gold Region

Page 73: Updated Life of Mine Plan Technical Session

www.guygold.com 73

CUYUNI BASIN: A TRUE MINING DISTRICT: Looking for Mine #2

• 1 Operating Aurora Gold Mine

• 1 Sulphur Rose secondary resource

• Multiple near-mine saprolite targets

• 1,200 square km land package

• Long history of artisanal mining

• Highly prospective greenstone belt

Looking for Mine #2

Arangoy

Page 74: Updated Life of Mine Plan Technical Session

www.guygold.com 74

Opportunities: Resource Additions At Depth at WH

Ultimate pit design

Page 75: Updated Life of Mine Plan Technical Session

www.guygold.com 75

BROWNFIELDS EXPLORATION:

Page 76: Updated Life of Mine Plan Technical Session

www.guygold.com 76

Iroma: Near Mine Open Pit Feed Target

• Located 10km NE of Aurora

• First-ever drilling: Nine holes have been completed to date totaling 2,000 meters of drilling. Best results shown.

• Drilling will continue to test the mineralized zones laterally and at depth. A drill rig road is currently being pushed towards Areas 2 and 3 along the 8.5km gold anomalous zone that will be drill tested.

• Gold mineralization is associated with NNW trending shear zones along an 12km central zone of anomalous gold.

• Prerequisites:• Deep plumbing• Brittle / Ductile Contrast• Source of iron• Sulphidation / Gold Event

Page 77: Updated Life of Mine Plan Technical Session

www.guygold.com 77

Wynamu: First Ever Drilling Program

• Regional NE Structure

• First ever drilling: Four drill holes have been completed totaling 500 meters. Best results shown

• Drill testing will continue towards the northeast of the drilled area to test anomalous gold in soils and trenches.

• Anomalous Gold in soil over 5 km

• Iron rich volcanic host rock

• Pervasive iron carbonate alteration

Page 78: Updated Life of Mine Plan Technical Session

www.guygold.com 78

Greater Sulphur Rose Area & Arangoy

• Arangoy is located ~ 10 km NW of Sulphur Rose • Sulphur Rose Resource:

• M&I: 277,580 oz @ 1.04 g/t AuInf: 289,250 oz @ 1.42 g/t Au

• Soil sampling conducted within the vicinity of the greenstone and intrusive lithological contact indicated a large and coherent gold anomaly in soils measuring roughly 1km by 0.5km.

• A trenching and drilling program is currently being planned to test the gold anomaly. Mobilization and resources to Arangoy commenced in February 2018.

Page 79: Updated Life of Mine Plan Technical Session

www.guygold.com 79

APPENDIX

Page 80: Updated Life of Mine Plan Technical Session

www.guygold.com 80

Annual LOM Production Profile

UnitsTotal/Avg

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

OPEN PIT MINING

Open Pit Ore ktonnes 19,022 2,579 3,078 1,553 2,317 1,976 1,098 820 684 1,039 1,096 957 822 684 320

Au Grade Mined gpt 2.74 2.62 2.90 2.89 2.80 2.74 3.09 2.61 2.86 2.03 2.93 2.44 1.78 3.99 2.20

Au Mined from Open Pit kounces 1,675 217 287 144 208 174 109 69 63 68 103 75 47 88 23

Open Pit Waste ktonnes 169,376 22,071 22,472 24,067 19,416 8,880 8,465 8,640 8,943 8,705 8,622 8,984 9,577 9,755 779

Open Pit Material Moved ktonnes 188,397 24,650 25,550 25,620 21,733 10,855 9,562 9,460 9,627 9,745 9,717 9,942 10,399 10,439 1,098Strip Ratio 8.9 8.6 7.3 15.5 8.4 4.5 7.7 10.5 13.1 8.4 7.9 9.4 11.7 14.3 2.4

UNDERGROUND MINING

Ore Mined - Rory's Knoll ktonnes 20,537 347 554 1,332 1,506 1,714 1,725 1,714 1,720 1,738 1,707 1,704 1,748 1,677 1,349

Au Grade Mined gpt 2.92 4.76 4.24 3.85 2.93 2.88 3.25 3.43 3.05 2.50 2.38 2.34 2.31 2.69 2.74Au Mined from Rory's Knoll

UG koz 1,925 53 76 165 142 159 180 189 169 140 131 128 130 145 119

Ore Mined - Satellites koz 2,583 140 420 562 285 67 165 181 209 205 205 144

Au Grade Mined gpt 4.06 3.41 4.98 3.66 3.23 2.97 4.72 4.64 3.90 4.07 3.77 4.93Au Mined from Satellites

UG koz 337 15 67 66 30 6 25 27 26 27 25 23

Total Au Mined koz 3,937 217 302 265 350 368 257 227 243 257 272 240 205 242 179 170 142

PROCESSING

Tonnes Milled ktonnes 43,047 2,355 2,738 2,745 2,738 2,738 2,738 2,745 2,738 2,738 2,738 2,745 2,738 2,738 2,738 2,745 2,337

Throughput Rate tpd 7,400 6,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 6,400

Mill Feed Average Grade gpt 2.87 2.91 3.12 3.30 3.48 3.70 3.01 2.87 3.12 2.95 3.07 2.70 2.37 2.83 2.14 2.15 2.11

Recovery % 94.8% 92.1% 95.4% 95.6% 95.8% 96.1% 95.2% 95.0% 95.4% 95.1% 95.3% 94.6% 93.9% 94.9% 93.3% 93.3% 93.1%

Total Au Recovered kounces 3,767 203 262 278 294 313 252 240 262 247 258 226 196 236 176 177 148

Page 81: Updated Life of Mine Plan Technical Session

www.guygold.com 81

Annual LOM Cost Profile

UnitsTotal/Avg

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

FINANCIALS

Revenue $mlns 4,508 243 314 333 352 374 302 288 313 295 309 270 235 283 211 211 177

NSR Royalty (8%) $mlns 361 19 25 27 28 30 24 23 25 24 25 22 19 23 17 17 14

Site Operating Costs $mlns 1,989 92 100 118 141 121 126 129 130 135 137 138 139 146 119 113 108

Sustaining Capital $mlns 295 9 21 34 29 16 14 19 21 16 12 15 17 26 21 16 10

Deferred Stripping $mlns 138 36 28 37 11 5 2 4 6 - - 3 4 2 - - -

Expansion Capital $mlns

Mill Expansion $mlns 13 13 - - - - - - - - - - - - - - -

UG Mining $mlns 151 19 73 17 - - - - - - 20 21 - - - - -

Other $mlns 3 3 - - - - - - - - - - - - - - -

Total Capital Costs $mlns 599 79 122 88 41 20 16 22 27 16 32 40 21 28 21 16 10 Total Site Costs $mlns 2,950 190 247 232 210 171 166 174 182 175 193 200 178 196 157 147 132AISC $mlns 3,002 170 188 229 223 185 180 188 196 188 187 192 191 210 171 160 145

Pre-tax Cash Flow $mlns 1,567 50 61 98 140 204 138 112 128 120 113 70 57 82 60 64 46 NPV (5%) (pre-tax) $mlns 1,142

Tax $mlns 348 1 7 6 24 50 33 30 35 33 32 20 14 23 14 16 11

NPV (5%) (after tax) $mlns 898

Operating Cash Cost¹ $/oz 531 455 385 425 483 389 501 540 498 551 532 614 710 618 679 645 732Operating Cash Cost (incl

Royalty)¹ $/oz 627 551 481 521 579 485 597 636 594 647 628 710 806 714 775 740 828AISC¹ $/oz 797 836 717 821 761 592 713 783 747 764 723 851 977 886 970 907 985

Page 82: Updated Life of Mine Plan Technical Session

www.guygold.com 82

Scientific and Technical InformationThe compilation of the Optimized LOM Plan was completed by Tysen Hantelmann, P.Eng. and Gord Doerksen, P.Eng of JDS Mining. Byvirtue of their education, membership to a recognized professional association and relevant work experience, Tysen Hantelmann andGord Doerksen are independent Qualified Persons as defined by National Instrument 43-101 and have reviewed, approved and verifiedthe technical content of this news release.

The mineral reserve estimates were prepared under the supervision of Tysen Hantelmann, P.Eng. and Gord Doerksen, P.Eng of JDSMining. Mr. Hantelmann and Mr. Doerksen are a “qualified person” under NI 43-101 and is independent of the Company. The mineralresource estimate for Rory’s Knoll was prepared under the supervision of Tim Maunula, of T. Maunula & Associates Consulting. Mr.Maunula is a “qualified person” under NI 43-101 and is independent of the Company. The mineral resource estimates for the satellitedeposits was prepared under the supervision of Danial Noone of Guyana Goldfields Inc. Daniel Noone is a “qualified person” underNational Instrument 43-101 and has also reviewed the contents of this press release.

Securities LawsThis presentation does not constitute an offer or solicitation to buy or sell any securities discussed herein in any jurisdiction where suchwould be prohibited. This presentation is not an offer to sell, or a solicitation of an offer to purchase, any securities in the United States.The securities referred to in this presentation will not be registered under the U.S. Securities Act of 1933 and may not be offered or sold inthe United States except pursuant to an exemption from the registration requirements of the U.S. Securities Act of 1933 and applicablestate securities laws.

The information contained in this presentation does not and is not intended to constitute a "valuation," "formal valuation," "appraisal,""prior valuation," or a "report, statement or opinion of an expert" for purposes of any securities legislation in Canada or otherwise.

CurrencyUnless otherwise indicated, all dollar values herein are in United States dollars.

SCIENTIFIC, TECHNICAL AND SECURITIES INFORMATION

Page 83: Updated Life of Mine Plan Technical Session

www.guygold.com 83

Jacqueline WagenaarVP, IR & Corporate Communications

Tel: (416) 628 5936 x.5295Email: [email protected]