using 3d laser scanning in limited or restricted access environments by brian a. christiano
DESCRIPTION
Some environments present a challenge to obtain and accurately document existing layouts and as-built configurations to be used in planning modifications or developing accurate drawings. Limited access to areas due to environmental or operational schedules may prevent revisiting for data gathering opportunities.TRANSCRIPT
Using 3D Laser Scanning
Brian A. Christiano, MSME, P.E.October 15, 2014
In
Limited or Restricted Access
Environments
Credentials
• Adjunct Professor
• Licensed Prof. Engr
• BSME - U of Wash
• MSME - USC
• Submarine Officer (retired)
– Nuclear Power
– Nuc/Conv Weapons
– Electrical/Comms
BC Engineering and Design
• Since August 1, 1997
• Located: Columbia, South Carolina
• Specializing in 3D scanning, reverse
engineering, and mechanical design analysis
• Use FARO® equipment
– FOCUS
– Tracker X
– Laser Edge Arm
Restricted Access Environments (RAE)
• Environmental
– Heat
• Time Restriction
• Security
• Health or Hazard
– Tank or closed compartment
– Radiation
– Chemical
– Asbestos
Restricted Access Environments
• Nuclear Power Plants
• Department of Defense – Shipboard/Submarine
RAE – Nuclear Power Plants
• Nuclear Power Plants present several challenges where 3D scanning can be used to optimum advantage
• Exposure to radiation– Alpha – low possibility
– Beta - possible
– Gamma – most common
– Neutron - unlikely
• Exposure to surface contamination
• Asbestos exposure
• Heat exposure
• Time restrictions– Radiation levels
– Operating schedules
Nuclear Power Plants (cont’d)
• Design Planning in Nuclear Power Plants is long term
– Driven by certification and design reviews
– Nuclear Regulatory Commission (NRC) compliance
• Reduction to radiation exposure is paramount
– ALARA – As Low As Reasonably Achievable
– Methods to reduce exposure
• Time• Distance
• Shielding
Nuclear Power Plants (cont’d)
• Time restrictions for planning are limited to plant “Outages” or planned shutdown and refueling periods
– Generally at 18 month periodicity or longer
– Must work around a very tight schedule for all planned maintenance
– Refueling periods during the outage restrict access and movement within the Containment Area
Nuclear Power Plants (cont’d)
• Working in the Nuclear environment requires:– Specialized training
– An understanding of the potential hazards
– An ability to work within very stringent guidelines
• Zero tolerance for deviations
– Proper background and security clearances
– Preparation of personnel and equipment
Personnel and Equipment
• Wrapping the equipment to prevent possible surface contamination
• Personnel PPE
• When completed, all equipment pieces must pass through Reactor Protection (RP) to check for contamination
• Personnel must pass through RP and be cleared
Nuclear Power Plants
• Advantages of using 3D Scanning in the nuclear power environment:– Reduce exposure time gathering valuable design data
– Documentation is accurate and can be reviewed long after the plant is back in operation
– Can be used for historical data for “as built” configurations
– Reduces the number of personnel who need to access the radiation or contaminated areas
– Data can be placed on a sharepoint for multiple departments that may have use for the data
Nuclear Power Plants
• Challenge: to get the
measurements needed in a 4
hour window
• Environment: Hot (near
100ºF)
Example: LP Turbine
Time: Planned outage
Scope: Take measurements
around the turbine to design a
work platform to fit the opening
• Controlled area
• RP login/logout
• Fall hazard
• FME – foreign
material exclusion
RAE - Submarines
• Submarines share many of the same challenges as nuclear power plants
• However, the most restrictive challenges are two-fold1. SECURITY
2. TIME
• A third challenge is SPACE
Submarines ~ SECURITY
• Submarine access and most surface ships (DOD)
require at least a SECRET clearance to go aboard
for work related visits
– Have to have or be under a DOD contract
– Background checks
• A clearance does not give carte blanche
permission to go aboard – NEED TO KNOW
Submarines ~ TIME
• Submarine operating schedules are demanding
• Deployment schedules for operations and training
are set months in advance
• In-port AVAILABILITIES are chiseled in stone
– A request to come aboard to do design planning is not
looked on as high priority
– A team will be working around the crew daily
maintenance and training routines, meetings, drills, etc.
Submarines ~ SPACE
• Unlike large surface ships, most submarines have one or two ways to go through the ship, and in some cases, only one passage going the length of the ship.
• Hence, all personnel and equipment must traverse along those passageways.– The shorter period of time you can restrict movement the better it
is for everyone concerned
– Smaller teams are easier to get aboard to work; less space occupied and less security concerns
• Submariners, by nature are cautious and questioning of outside contractors and support personnel.
Submarines ~ 3D Scan Advantages
• Before 3D scanning a team of technicians and engineers would arrange to meet the submarine in a port of opportunity.
• They would arrive a day or two ahead of the ship’s arrival date to get clearances and arrange with the port authority to get aboard
• They would spend a couple of hours briefing the crew what they hoped to accomplish and then commence work to measure, take notes, etc. No pictures were generally allowed, or limited.
• Two to three days of measuring, evening checks at the hotel to review what all was documented, drawings (if available) were marked up
Submarines ~ 3D Scan Advantages
• After return to the home office, invariably something was missed. Estimates or plans to accommodate the variations had to be made.
• 3D Scanning provides:– Positive documentation
– Accurate dimensions
– Less personnel required to complete the site checks• 1 to 2 personnel can scan most areas completely
• = cost reduction
– Direct input into CAD
– Less time spent on site to document the areas in question• = cost reduction
Restricted Access Environment
~ a comparison
Nuclear Power Plants
• Time restrictions
• Security
• Environmental
hazards
• Requires
specialized training
Submarines/shipboard
• Time restrictions
• Security
• Space Limitations
• Requires specialized
training
Restricted Access Environment
Since 9-11-2001, the environment for both
Department of Defense and nuclear power plant
access have become, by necessity, more restrictive.
Information is held as “need to know” and
background checks are conducted frequently and
at random.
Therefore, the RAE is just that, RESTRICTED
ACCESS.
Restricted Access Environment
Summary: Restricted Access Environments offer
challenges for working. If personnel are not
familiar with the hazards and restrictions they can
be unfriendly.
However, with proper training and preparations,
3D scanning can provide a significant advantage
over traditional means to do design planning and
documentation.
Need Professional Assistance?
Some environments can be unfriendly if not trained properly
Contact Information:
BC Engineering & Design, LLCP.O. Box 11315
Columbia, SC 29211-1315
Ph: (803) 796-6721 Cell: (803) 238-6768
Fax: (803) 739-8874
http://www.bcengineeringanddesign.com